Funding Received under North Dakota Century Code Section
57-51-15
3/7/2014 1
![Page 2: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/2.jpg)
The funds received under § 57-51-15 have been used to finance infrastructure related to growth.
None of these funds have been deployed to flood recovery.
3/7/2014 2
![Page 3: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/3.jpg)
Hub City Funding from Three Sources in Gross Production 5% Tax Distribution: ◦ 1. Mining Employment Formula
◦ 2. Energy Impact Grant Funding Infrastructure
Airport
◦ 3. Production Formula
3/7/2014 3
![Page 4: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/4.jpg)
3/7/2014 4
![Page 5: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/5.jpg)
Legislative Estimated Amount = $1.5 million per fiscal year ◦ Received through February - $1.125 million
Formula base on percent of mining employment as determined by Job Service
Sanitary Lift Station Upgrades – Six Upgraded ◦ Lift Stations at Capacity Because of Minot’s Growth
◦ Total Project Cost - $11,949,916
◦ Provides added capacity until new trunk sewer line is constructed (total estimated cost $30 million)
3/7/2014 5
![Page 6: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/6.jpg)
3/7/2014 6
![Page 7: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/7.jpg)
Amount Received - $5 million (Minot is capped at this amount for the biennium)
Southwest Sewer Improvements Phase I ◦ Installation of 24” Sewer Main
◦ Total Project Cost - $6,400,900
3/7/2014 7
![Page 8: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/8.jpg)
Amount Received - $21,218,395
Total Project Costs - $100,075,161 ◦ Terminal $18,500,000
◦ SRE Building 163,395
◦ Furniture 100,000
◦ Terminal Apron 805,000
◦ Access Roads & Parking 1,650,000
$21,218,395
3/7/2014 8
![Page 9: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/9.jpg)
3/7/2014 9
![Page 10: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/10.jpg)
Legislative Estimate Amount to be Received - $4.570 million
Amount Received To-date - $1,719,603.87
Total Project Costs – ◦ BNSF Sewer Relocation $1,670,597
◦ Puppy Dog Sewer Phase IV $3,372,610
3/7/2014 10
![Page 11: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/11.jpg)
2014 Capital Improvements Plan ◦ Water & Sewer $ 32,824,408
◦ Street Improvements $ 21,787,346
◦ Airport $ 43,844,118
◦ Fire, Landfill, Cemetery, Other $ 29,921,471
$128,377,343
3/7/2014 11
![Page 12: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/12.jpg)
Servicing a Population in excess of 50,000
Water & Sewer Rates1 ◦ Minot $66.73 ◦ Fargo $56.05 ◦ Mandan $55.09 ◦ Dickinson$54.00 ◦ Bismarck $47.96 ◦ Williston $33.47
South Minot – Retail, Residential, and New Hospital
North Minot – Retail, Residential, New School
Regional Service Area
City Goals: Keep Property Tax Reasonable, Debt Load Manageable, and Water and Sewer Rates Affordable
1SOURCE: AE2S Annual Water Rate Study 2013 – For Cities with population over 5,000
3/7/2014 12
![Page 13: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/13.jpg)
Current debt bonded long-term for 10, 15, and 20 years
3/7/2014 13
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
$1,800
$2,000
2008 2009 2010 2011 2012 2013
Total Debt Per Capita
Total Debt Per Capita
![Page 14: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM](https://reader035.fdocuments.in/reader035/viewer/2022071008/5fc601c2a3fc933aac77ed3c/html5/thumbnails/14.jpg)
The funds received under § 57-51-15 have been used to finance infrastructure related to growth.
None of these funds have been deployed to flood recovery.
3/7/2014 14