PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps...

66
Footer Text Date ENV125 Basics of Traffic Noise and TxDOT’s Policy 9/12/18

Transcript of PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps...

Page 1: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

ENV125 Basics of Traffic Noise and TxDOT’s

Policy

9/12/18

Page 2: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Agenda

Introduction and Overview

– Traffic Noise Toolkit

Fundamentals of Noise

Traffic Noise Analysis Process

– Regulations and Guidance

• The major objectives of a traffic noise analysis

2

Page 4: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Traffic Noise Guidance and Policy

TxDOT’s Traffic Noise

Policy (2018)

PROPOSED

4

Page 5: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Sound/Noise

Noise Analyses

Sound/Noise

O

V

E

R

V

I

E

W

Page 6: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Highway Traffic Sound

Source Receiver < Propagation Medium >

Page 7: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Decibel

A-weighting

Equivalent Level

Decibel

Page 8: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Rock Band

Pneumatic Hammer

Food Blender

Downtown

Vacuum Cleaner

Air Conditioning Unit

Dishwasher

Library

6,324,555

2,000,000

632,456

200,000

63,246

20,000

6,325

2,000

110

100

90

80

70

60

50

40

PRESSURE micro Pascals

SOURCES

LEVEL decibels

L 10log (P )

(P ) 10log

(P )

(P )

D

D (St)

2

ref

2

o

2

ref

2

o

2

2 2

Page 9: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

SOURCES

Rock Band

Pneumatic Hammer

Food Blender

Downtown

Vacuum Cleaner

Air Conditioning Unit

Dishwasher

Library

LEVEL decibels

110

100

90

80

70

60

50

40

x2

120

63

Page 10: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

A-weighting

Decibel

A-weighting

Equivalent Level

Page 11: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

6,300 1,000 7 8 9 >

4 5 6 <

1 2 3 /

DIS PRO OUT SEC

ENT NEX CLR SFT

0 + - %

SOUND ANALYZER

MIKEE-LECTRONICS

65 70 75 85 75 70 65

-weighting

Page 12: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Decibel

Equivalent Level

A-weighting

Equivalent Level

Page 13: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

L = 10log 1T

10 L10

eq 10t

t=1

N

time

sound level

Page 14: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

SOUND LEVEL

-1 dBA Not perceptible

-3 dBA Barely perceptible

-5 dBA Readily perceptible

Change Loudness Subjective

Page 15: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

O

V

E

R

V

I

E

W

Sound/Noise

Noise Analyses Noise Analyses

Page 16: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Traffic Noise Guidance and Policy

TxDOT guidelines

conform to federal rule

(regardless of funding)

–23 CFR 772

TxDOT’s Guidelines for

the Analysis and

Abatement of Roadway

Traffic Noise (2011)

16

Page 17: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Determine if a Type I project

The construction of a highway on new location; or,

The physical alteration of an existing highway where there is either:

– Substantial Horizontal Alteration

– Substantial Vertical Alteration

The addition of a through-traffic lane(s)

The addition of an auxiliary lane, except for when the auxiliary lane is a turn lane; or,

The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or,

Restriping existing pavement for the purpose of adding a through-traffic lane or an auxiliary lane; or,

The addition of a new or substantial alteration of a weigh station, rest stop, ride-share facility, or toll plaza.

17

Page 18: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

TRAFFIC DATA!!!!

First thing to do when you know you have a Type I analysis

GET TRAFFIC DATA!!!!

18

Traffic Information

Existing

Predicted

Speed Limits

Collect Data

Page 19: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

TRAFFIC DATA!!!!

19

Receiver < Propagation Medium > Source

- Future -- 20 years

- Existing Traffic

Traffic Data

- Future Traffic

- Worse-Case

- Full Speed

- Predicted dBA

Page 20: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Traffic Data Request

20

When requesting Traffic Data use

TPP Form 2124

Make sure to check Box 1 (Basic

Highway Traffic Data), 2 (Vehicle

Classification for Environmental

Studies), 3 (Line Diagram Analysis)

ALL TRAFFIC MUST BE FROM TPP

OR APPROVED BY TPP

Page 21: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Traffic Data

21

Page 22: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Traffic Data: Line Diagram with Turning Movements

22

Light Duty Vehicles

Medium Duty Vehicles

Heavy Duty Vehicles

% of ADT % of DHV

91.0 92.8

6.0 4.2

3.0 3.0

% of ADT % of DHV

97.0 98.3

2.0 1.7

1.0 0.0

Frontage Roads

and

Streets

Mainlanes

K-factor: 10.5%

31800

21700

3600

1600

4700

3000

33900

22600 31800

21700

35200

23500

6200

4100

1300

900

1000

500

1000

500

3400

1500 800

400

800

400 4900

3200

AVERAGE DAILY TRAFFIC (ADT) VOLUMES

SH 123

DHV = ADT (x) K-factor

65 SPEED

LIMIT

40 SPEED

LIMIT

LEGEND

1000 - 2015 ADT

1000 - 2035 ADT

Projects that involve more than

mainlanes and frontage roads typically

with require a depiction of turning

movements - - from TPP.

Page 23: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Determine Need for Traffic Noise

Analysis of a Highway Project

- New Location, or

- Substantial Realignment, or

- Addition of Through-Traffic Lane

Analysis not

required

Traffic

Information

Design

Information

Measure/Model

Noise Levels

Existing Levels Predicted Levels

Predicted levels exceed

existing by more than 10 dBA

Predicted levels approach,

equal, or exceed the NACOR

Consider/Evaluate

Abatement Measures

Traffic

Management

Alteration of

Alignment

Acquisition of

Buffer Zone

Construction of

Noise Barriers

Insulation of

Public Buildings

Construction

Noise

Information for

Local Officials

NOYES

IF

IF

NO

YES

Determine Impact

Additional

Topics

Collect Data

Abatement not

required

Project

Reevaluation

Collect Data Design

Information

Roadways

Receivers

Site Characteristics

Source of Sound

Receiver of Sound

Propagation Path

Page 24: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Roadway Design and Site Characteristics

Electronic CAD files with Roadway Design

– Striping

– Edge of Pavement

– Any other relevant design information

Adjacent Topography if available

– Other sources would be GIS, Google Earth, Surveys

ELEVATIONS ARE CRITICAL TO BARRIER DESIGN

24

Page 25: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

A Brief Overview of the Traffic Noise Process

The major objectives of a traffic noise analysis are to:

– Identify areas where possible noise impacts may occur for each project

alternative.

– Consider and evaluate abatement measures to mitigate these impacts.

– Propose implementation of feasible and reasonable abatement measures.

– Communicate the results to the public and local officials.

Important: it is never too early to discuss possible noise abatement

25

Page 26: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

A Brief Overview of the Traffic Noise Process

Identify adjacent land uses

for noise sensitive areas

(residences, schools,

churches, parks, etc)

INCLUDES PERMITTED

DEVELOPMENT

26

Page 27: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Noise Receiver Selection Criteria

27

Page 28: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

A Brief Overview of the Traffic Noise Process

FHWA’s Traffic Noise Model

(TNM) is used to model all

impacts

28

Page 29: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Table 6: NOISE ABATEMENT CRITERIA

Activity

Category

FHWA

(dB(A)

Leq)

TxDOT

(dB(A)

Leq)

Description of Land Use Activity Areas

A 57

(exterior)

56

(exterior)

Lands on which serenity and quiet are of extra-

ordinary significance and serve an important public

need and where the preservation of those qualities is

essential if the area is to continue to serve its

intended purpose.

B 67

(exterior)

66

(exterior)

Residential

C 67

(exterior)

66

(exterior)

Active sport areas, amphitheaters, auditoriums,

campgrounds, cemeteries, day care centers,

hospitals, libraries, medical facilities, parks, picnic

areas, places of worship, playgrounds, public

meeting rooms, public or nonprofit institutional

structures, radio studios, recording studios,

recreation areas, Section 4(f) sites, schools ,

television studios, trails, and trail crossings

D 52

(interior)

51

(interior)

Auditoriums, day care centers, hospitals, libraries,

medical facilities, places of worship, public

meeting rooms, public or nonprofit institutional

structures, radio studios, recording studios,

schools, and television studios

E 72

(exterior)

71

(exterior)

Hotels, motels, offices, restaurants/bars, and other

developed lands, properties, or activities not included

in A-D or F.

F -- -- Agricultural, airports, bus yards, emergency services,

industrial, logging, maintenance facilities,

manufacturing, mining, rail yards, retail facilities,

shipyards, utilities (water resources, water treatment,

electrical), and warehousing.

G -- -- Undeveloped lands that are not permitted.

Page 30: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Determine Need for Traffic Noise

Analysis of a Highway Project

- New Location, or

- Substantial Realignment, or

- Addition of Through-Traffic Lane

Analysis not

required

Traffic

Information

Design

Information

Measure/Model

Noise Levels

Existing Levels Predicted Levels

Predicted levels exceed

existing by more than 10 dBA

Predicted levels approach,

equal, or exceed the NACOR

Consider/Evaluate

Abatement Measures

Traffic

Management

Alteration of

Alignment

Acquisition of

Buffer Zone

Construction of

Noise Barriers

Insulation of

Public Buildings

Construction

Noise

Information for

Local Officials

NOYES

IF

IF

NO

YES

Determine Impact

Additional

Topics

Collect Data

Abatement not

required

Project

Reevaluation

Determine Impact

Predicted levels approach,

equal, or exceed the NAC

ABSOLUTE CRITERION

Predicted levels exceed

existing by more than 10 dBA

RELATIVE CRITERION

OR

IF

Page 31: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Table 6: NOISE ABATEMENT CRITERIA

Activity

Category

FHWA

(dB(A)

Leq)

TxDOT

(dB(A)

Leq)

Description of Land Use Activity Areas

A 57

(exterior)

56

(exterior)

Lands on which serenity and quiet are of extra-

ordinary significance and serve an important public

need and where the preservation of those qualities is

essential if the area is to continue to serve its

intended purpose.

B 67

(exterior)

66

(exterior)

Residential

C 67

(exterior)

66

(exterior)

Active sport areas, amphitheaters, auditoriums,

campgrounds, cemeteries, day care centers,

hospitals, libraries, medical facilities, parks, picnic

areas, places of worship, playgrounds, public

meeting rooms, public or nonprofit institutional

structures, radio studios, recording studios,

recreation areas, Section 4(f) sites, schools ,

television studios, trails, and trail crossings

D 52

(interior)

51

(interior)

Auditoriums, day care centers, hospitals, libraries,

medical facilities, places of worship, public

meeting rooms, public or nonprofit institutional

structures, radio studios, recording studios,

schools, and television studios

E 72

(exterior)

71

(exterior)

Hotels, motels, offices, restaurants/bars, and other

developed lands, properties, or activities not included

in A-D or F.

F -- -- Agricultural, airports, bus yards, emergency services,

industrial, logging, maintenance facilities,

manufacturing, mining, rail yards, retail facilities,

shipyards, utilities (water resources, water treatment,

electrical), and warehousing.

G -- -- Undeveloped lands that are not permitted.

I M P A C T ? ABSOLUTE CRITERION RELATIVE

OR, if predicted levels exceed

existing by more than 10 dBA

“approach, equal or exceed”

FHWA Noise Abatement Criteria

” ……1 dBA below

Page 32: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Determine Need for Traffic Noise

Analysis of a Highway Project

- New Location, or

- Substantial Realignment, or

- Addition of Through-Traffic Lane

Analysis not

required

Traffic

Information

Design

Information

Measure/Model

Noise Levels

Existing Levels Predicted Levels

Predicted levels exceed

existing by more than 10 dBA

Predicted levels approach,

equal, or exceed the NACOR

Consider/Evaluate

Abatement Measures

Traffic

Management

Alteration of

Alignment

Acquisition of

Buffer Zone

Construction of

Noise Barriers

Insulation of

Public Buildings

Construction

Noise

Information for

Local Officials

NOYES

IF

IF

NO

YES

Determine Impact

Additional

Topics

Collect Data

Abatement not

required

Project

Reevaluation

Determine

Noise Levels

Existing Levels Predicted Levels

Measured by

Sound Meter

Modeled by

Computer

OR Modeled

Page 33: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

A Brief Overview of the Traffic Noise Process

The major objectives of a traffic noise analysis are to:

– Identify areas where possible noise impacts may occur for each project

alternative.

– Consider and evaluate abatement measures to mitigate these impacts.

– Propose implementation of feasible and reasonable abatement measures.

– Communicate the results to the public and local officials.

Important: it is never too early to discuss possible noise abatement

33

Page 34: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Noise Barrier

Source Receiver - Propagation Path -

Noise Abatement

Page 35: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

A Brief Overview of the Traffic Noise Process

35

Page 36: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Determine Need for Traffic Noise

Analysis of a Highway Project

- New Location, or

- Substantial Realignment, or

- Addition of Through-Traffic Lane

Analysis not

required

Traffic

Information

Design

Information

Measure/Model

Noise Levels

Existing Levels Predicted Levels

Predicted levels exceed

existing by more than 10 dBA

Predicted levels approach,

equal, or exceed the NACOR

Consider/Evaluate

Abatement Measures

Traffic

Management

Alteration of

Alignment

Acquisition of

Buffer Zone

Construction of

Noise Barriers

Insulation of

Public Buildings

Construction

Noise

Information for

Local Officials

NOYES

IF

IF

NO

YES

Determine Impact

Additional

Topics

Collect Data

Abatement not

required

Project

Reevaluation

Reasonable AND

Propose

Abatement

Evaluate

Abatement Measures

Feasible

Page 37: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Cost Reasonableness

37

2018

2011 • Less than 1388 square feet per

benefiting receiver

• ($18 square foot/$25k per benefiter)

• Less than 1500 square feet

per benefiting receiver

• $35 square foot

• $52.5k per benefiter

Page 38: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Cost Reasonableness

38

• Less than 1500 square feet per

benefiting receiver

• ($35 square foot/$52.5k per

benefiter)

Page 39: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Cost Reasonableness

39

• Less than 1500 square feet per

benefiting receiver

• ($35 square foot/$52.5k per

benefiter)

12’

375’

Page 40: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Feasible

effective reduction in noise -?

Page 41: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Feasible

-? -5 (or more)

Page 42: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Feasible

-? -5 (or more)

Reasonable

Cost-reasonableness

Criterion

Size for each

Benefited Receiver

1500 square feet (or less)

Page 43: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Reasonable

1500 sq ft (or less)

-? (or more)

AND

Feasible

-5

-4 -4 -5 -5 -5 -7 -5 -5

? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? NOISE BARRIER ? ? ? ? ? ? ? ? ? ? ? ? ? ? ?

For Example

Page 44: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

-? -5 (or more)

Feasible

(or less)

Reasonable

AND

Total Cost 6,000 total sq ft

-4 -4 -5 -5 -5 -7 -5 -5 ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? NOISE BARRIER ? ? ? ? ? ? ? ? ? ? ? ? ? ? ?

6 benefiters

= 1,000 sq ft

Sq Ft for each

Benefited Receiver

Total Sq Ft

#Benefited =

1,500 sq ft

Page 45: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

A Brief Overview of the Traffic Noise Process

The major objectives of a traffic noise analysis are to:

– Identify areas where possible noise impacts may occur for each project

alternative.

– Consider and evaluate abatement measures to mitigate these impacts.

– Propose implementation of feasible and reasonable abatement measures.

– Communicate the results to the public and local officials.

Important: it is never too early to discuss possible noise abatement

45

Page 46: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

A Brief Overview of the Traffic Noise Process

Noise Barrier

AKA Sound Walls

46

Page 47: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

A Brief Overview of the Traffic Noise Process

Why not pavement or vegetation?

47

Page 48: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

15 feet

Vegetation

100 feet = perceptible

reduction

Page 49: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Vegetation

- dense enough that it cannot be seen through

- coverage: floor to canopy

- evergreen

Page 50: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

- dense enough that it cannot be seen through

- coverage: floor to canopy

- evergreen

Vegetation

Page 51: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Vegetation

“... provides only psychological benefits”

“... may be provided for visual, privacy or

aesthetic treatment”

“... not a noise abatement measure”

Page 52: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Pavement

Page 53: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

PRIORITIES NOISE SAFETY DURABILITY

*FHWA: “should never be jeopardized”

* *

Page 54: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

FHWA Concern ….. can “quiet”

pavement continue to effectively

reduce noise levels over the life

of the pavement?

FHWA

Traffic Noise

Policy

“The use of specific pavement

types or surface textures must

not be considered as a noise

abatement measure.”

Page 55: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

FHWA Concern ….. can “quiet”

pavement continue to effectively

reduce noise levels over the life

of the pavement?

FHWA

Traffic Noise

Policy

“The use of specific pavement

types or surface textures must

not be considered as a noise

abatement measure.”

“Additional research is needed to

determine to what extent different

types of pavements contribute to

traffic noise.”

research

Page 56: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Page 57: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

A Brief Overview of the Traffic Noise Process

The major objectives of a traffic noise analysis are to:

– Identify areas where possible noise impacts may occur for each project

alternative.

– Consider and evaluate abatement measures to mitigate these impacts.

– Propose implementation of feasible and reasonable abatement measures.

– Communicate the results to the public and local officials.

57

Page 59: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Noise Workshop

59

??????????????????????? SOUND WALL ??????????????????????

Consent of a Majority of BENEFITING AND ABUTTING Property Owners

Benefiting receivers can be on the second (or any row)!!!

Page 60: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Noise Workshop

Purpose: to provide sufficient information to owners of property benefiting

and abutting a proposed noise barrier(s) that will allow these owners to make

an informed vote for or against the proposed noise barrier(s).

Timing: after the public hearing has occurred

INFORMAL PUBLIC INVOLVEMENT CAN HAPPEN AT ANY TIME IN THE

PROJECT’S DEVELOPMENT.

60

Page 61: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Noise Workshop: Sample Ballot

61

NOISE BARRIER BALLOT SH 286 EXPANSION and SH 358 INTERCHANGE PROJECT

NOISE WORKSHOP, May 23, 2000

In conjunction with the SH 286 expansion and SH 358 interchange project, the Texas Department of Transportation proposes to construct a noise barrier within the right-of-way west of SH 286 between Gollihar Road and Mansheim Drive. However, the proposed noise barrier cannot be constructed without the approval, by majority vote, of adjacent property owners. 1. Do you own property adjacent to the right-of-way west of SH 286 between Gollihar

Road and Mansheim Drive? YES ______ NO ______

2. FULL NAME (please print)

ADDRESS TELEPHONE NO. _____________________________

3. Are you for or against the construction of the proposed noise barrier within the right-of-way west of SH 286 between Gollihar Road and Mansheim Drive? Only one vote is allowed for each property.

FOR _____ AGAINST _____ This vote is final.

4. Comments (use reverse if necessary):

SIGNATURE (required) __________________________________ DATE

The ballot must be completed and signed by the property owner of record.

If possible, please bring your completed and signed ballot to the Noise Workshop.

If you are not able to attend the Noise Workshop, please send your completed and signed ballot (must be postmarked no later than ……………) to: Texas Department of Transportation, Attention: …………..P.O. Box 9907, Corpus Christi, TX, 78469-9907.

1) Adjacent property owners will be notified of the results of the vote for or against the proposed noise barrier after all ballots have been received and counted.

Page 62: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Noise Workshop: Mailing

Mailing preferably by prestamped/preaddressed return envelope

include a description of the noise barrier and the noise effects with and

without the barrier.

Include a description of the decision making process that TxDOT will follow to

assess the survey/ballot results and make a decision on whether to build the

barrier.

Include an invitation to the meeting with the location and time

62

Page 63: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Letters to Local Officials

Used to inform local officials regarding the department’s responsibilities

regarding noise abatement for new development once an environmental

decision has been made.

Required for all projects adjacent to undeveloped lands

Cannot occur before document has been signed

Minimal notification:

– Urban area is the Mayor’s Office

– Rural or suburban area, the County Judge’s Office.

Template letter found in Traffic Noise Toolkit

Notice of Availability Template found in Public Involvement Toolkit

63

Page 64: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

ECOS Documentation

Noise Workshop Summary

– Documentation of the completed traffic noise workshops shall include:

• a summary of the materials presented

• comments from the public and associated responses, and

• the results of the ballots for each proposed barrier.

Noise Analysis Technical Reports

Super 2 correspondence

64

Page 65: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

ECOS Documentation – TNM model

TNM model

65

Page 66: PowerPoint Presentation · 2018-10-29 · The addition or relocation of interchange lanes or ramps added to a quadrant to complete an existing partial interchange; or, Restriping

Footer Text Date

Noise Workshop

66