POWERED by NATURE - SHER carries out all phases of a hydro-power project : reconnaissance study,...
Transcript of POWERED by NATURE - SHER carries out all phases of a hydro-power project : reconnaissance study,...
SHER Ingénieurs-Conseils s.a is a Belgian engi-neering consultancy set up in Brussels in 1985 providing services worldwide. The headquarters have been based in Namur (Belgium) since 1997.
The company was set up by a handful of Engi-neers, Water resources experts, Economists, Hy-drologists and Geologists. Since 15th January 2015, SHER Ingénieurs-Conseils is part of the AR-TELIA Group
SHER Ingénieurs-Conseils s.a. is multidisciplinary and active in the following sectors : hydropower, hydraulics, water supply, sanitation, building and infrastructures, irrigation and agro-industrial projects, rural development, environmental pro-tection, ESIA, geological studies, GIS (Geographical Information System). SHER has carried out more than 800 studies and pro-jects. We carry out all types of studies, from identification to the operational phase and have the necessary staff and means to implement turnkey projects. Our clients include local com-munities, private investors, governments, bilate-ral and multilateral donors and international fi-nancing organizations. Through its agencies, it utilizes its personal, national and international consultants in order to use the local capacities as well as possible and to reinforce the transfers of knowledge and technologies. Moreover, the company has been ISO 9001 certified since Sep-tember 2000.
Since 1995 SHER has been providing innovative, safe and optimized solutions for many aspects of the small hydropower delivery chain around the World. SHER carries out all phases of a hydro-power project : reconnaissance study, feasibility study, tender design study, ESIA, work supervi-sion, commissionning, etc..
Permanent staff exceeding 40 in our headquar-ters and agencies (Africa, America, Asia and Eu-rope), including 30 Engineers and graduates and 10 Technicians, Topographers, Designers and Op-erators.
Small and medium hydropower projects & Energy solutions
SHER is an international profes-sional services company part of a large engineering group
Our people deliver innovative so-lutions by combining technical skill and experience with an un-derstanding of our clients’ objec-tives.
Small and medium Hydropower SHER - Services
INVESTIGATIONS AND APPRAISALS
Site identification and topographical survey
Foundation and materials investigations and
Geotechnics
Stream gauging, flood assessment and reservoir studies
STUDIES
Hydropower Atlas and Master Plan
SHPP and MHPP Feasibility studies
Environmental Impact Assessment (EIA)
Resettlement Action Plan (RAP)
Detailed studies, tender design and Technical specifi-cations
SME restructuration and PPP development,
Concession agreement (CA) support
Power purchase agreement (PPA)
CONSTRUCTION
Construction supervision, project and technical
management
Materials management and quality control
FIDIC contrats
OPERATIONAL
Management, training and maintenance
Emergency response services
Surveillance and instrumentation
Rehabilitation works, including corrosion control,
concrete repair, spillway and freeboard improvements
and upgrades, structural adequacy and stabilisation
Asset valuations and condition assessments
Sediment deposition management, seepage analysis
and control solutions
Our Group Our Capability
SHER member of the ARTELIA Group Turnover of 405 million Euros 53 subsidiaries in 37 countries 3,500 employees.
WATER - ENERGY - MARITIME - ENVIRONMENT
RDC REHABILITATION OF INGA I AND II HPP CANALS - 1630 MW
ECUADOR DELSITANISAGUA HYDROPOWER SCHEME - 180 MW
LAOS NAM LEUK HPPS INCREASE PROJECT - 60 MW
LAOS NAM MANG HYDROPOWER SCHEME - 40 MW
Small Hydropower Mapping and Planning
The mapping project aims to improve the quality and availability of information on Vanuatu’s small hydro re-sources. The project will provide the Government of Va-nuatu and commercial developers with ground-validated maps that show the varying levels of hydro-power potential throughout the country, and highlight several sites most suited for small hydropower projects. The study includes : Stakeholders Meetings at Port-Vila, data collection and compilation / Previous studies anal-ysis and data gathering /GIS layers gathering and crea-tion / Hydrology /Hydropower spatial analysis with Site-Finder Software /Site Visit preparation / Technical data gap identification for the 20 prioritized sites Data gap identification for planning purposes / Prioriti-zation and decision workshop /Training and capacity building
Vanuatu All Islands
Name of Client:
Department of Energy
Name of Funding agency : World Bank
Completion Date :
02/2017
Key figures
Small Hydropower Atlas of Vanuatu
35 promising sites visited
20 prioritized sites
Budget : 344’450 USD
Owner’s engineer services for Obuse SHPP development & Due Diligence for Yabu SHPP
The key objectives of the study is to provide :
Owner’s engineer services for SHIZEN Energy to-wards the beginning of the Obuse SHPP develop-ment (Review of the basic planning before the de-tail design / Site visit at Obuse with the civil engi-neering company
Full-fledged due diligence for a newly identified
project (rehabilitation): Yabu site. Preliminary tech-nical and economical analysis through EconEval for Yabu site. This software developed by SHER delivers preliminary cost estimates, installed capacity and yearly power production. The final output is the Le-velized Cost Of Energy - LCOE
Japan Nagano Prefecture Hyōgo Prefecture
Name of Client: SHIZEN ENERGY
Completion Date :
12/2016
Key figures Obuse SHPP (Nagano Prefecture) Capacity 199 kW / Q=1.5 m³/s / H=16.8 m
Yabu SHPP (Hyōgo Prefecture) Min. Capacity 161 kW / Q=0.9 m³/s / H=25m
Max. Capacity 545 kW / Q=0.9 m³/s / H=85m
Feasibility study, Tender design study, ESIA and Tender document for a new SHPP (5.9 MW) - Lovua River
The main objective of the study is to provide a techni-cal, economic, financial and environmental study for a new HPP plant and power line for supplying the water pumping and treatment plant of REGIDESO of Tshikapa and to operate a Mini-grid for the city. The study includes : identification/prioritization study of the most suitable and economical site (3 sites : Lovua – Lungudi II – Pogge Amont), Feasibility study, the Ten-der design study, the Technical specifications and the Tender documents including confidential cost estimates for infrastructure, equipment and transmission line, an economical and financial study and the ESIA / RAP.
Democratic Re-public of Congo — Tshikapa—Kasai
Name of Client: Projet PRISE / REGIDESO
Name of Funding agency : AfDB
Completion Date :
11/2016
Key figures Discharge : 50 m³/s - Kaplan Turbines
Design flood : 1370 m³/s
Gross head : 13.5 m
Concrete Ogee spillway / Embankment Earthfill Dam with Sheet pile cut off
Installed capacity : 5.9 MW
Energy production : 43 GWh/y
Storage capacity : 3 hm³ - Daily peaking plant
Due diligence of 3 potential micro-hydro projects in Oita and Nagano Prefectures
The main objective of the study is to provide a technical and economical due diligence for three new SHPP plants for SHIZEN ENERGY. SHER managed a bibliographical and on-line review of three micro-hydro projects in two prefectures of Japan (Oita and Nagano). SHER conducted a full-fledged due diligence for this projects as a hopeful potential project. SHER carried out a preliminary technical and economical analysis through EconEval, our analytical tool for prelimi-nary investigation. "EconEval" is fed with data gathered during site visit, by hydrological modeling, by benchmark-defined price re-gression and with an updated price list. After processing, EconEval delivers preliminary cost estimates, installed capacity and yearly power production. The final output is the Levelized Cost Of Energy (LCOE).
Japan Oita and Nagano
Name of Client: SHIZEN ENERGY
Completion Date :
10/2015
Key figures Yufu#1 Project (Oita Prefecture) :
Capacity : 35 kW / Q=0.1 m³/s / H=25 m
Yufu#2 Project (Oita Prefecture) on an exis-ting dam:
Capacity : 130 kW / Q=1.5 m³/s / H=12 m
Obuse Project (Nagano Prefecture),
Capacity 350 kW / Q=2.2 m³/s / H=22 m
Update of the prefeasibility study of the Bétérou Amont multipurpose scheme in Benin
For 20 years, Benin faces recurring energy crises. Current-ly, combined Benin and Togo capacity are sufficient their needs. To this end, CEB (Communaté Electrique du Bénin) in association with the UE launched a contract to update a prefeasibility study conducted in 1992.
Services delivered :
Review and Collection of the existing literature
Critical review of the initial study (1992)
Topographical survey of the main structures extents (spillways, stilling basin, intake, powerhouse) - 270 ha
High level environmental and social impact assessment
Economic and financial analysis of the project alterna-tives
Analysis of the energy performance
Consultations at national level (CEB, Ministry of Energy) and regional (WAPP) to agree upon a roadmap
Preparation of terms of reference for the recruitment of the Consulting Engineer.
Benin
Ouemé River Name of Client: The European Union CEB Execution Period : 01/2015 - 08/2015
Key figures Dam: 35m high concrete dam and approx. 8km earthfill embankment Reservoir storage: 1.5 km³ 6 alternatives up to 23 MW , equipped with up to 4 Kaplan turbines
Support to FUNAE / BTC in study of rehabilitation of Majaua micro-hydro (585 kW) after floodings
The Majaua micro-hydro plant is located on the Ruo river on the border of Mozambique and Malawi (Milange Dis-trict) has an installed capacity of 585 kW. It was initially built during the 1950s. The rehabilitated plant was built between 2012-2014 by FUNAE and financed by FUNAE and the European Union and BTC. The plant was opera-tional from June 2014 and managed by FUNAE up to a flooding event caused by intense rain on 15 January 2015. The power plant was heavily damaged by the flooding. The objective of SHER is to obtain : a) Technical feasibility b) Risk analysis c) Site specific flood risk analysis, of the proposed re-
pair and mitigation works for the Majaua hydro po-wer plant for supplying the Majaua Mini-grid
Mozambique Ruo River
Name of Client: FU-NAE
Name of Funding agency : European
Union / BTC
Completion Date :
10/2015
Key figures Discharge : 4.5 m³/s
Gross head : 18 m
Installed capacity : 584 kW
Renewable Energy Mapping: Small Hydro - Madagascar
The study will provide a thorough understanding of the potential small-hydro resources and their geographical distribution at the country level, overlaid with other key enabling factors and constraints, will inform land plan-ning decisions and contribute to the enhancement of the existing policy framework. An adequate policy fra-mework for RE combined with reliable and publicly-available resource data, are crucial ingredients in provi-ding commercial RE developers with the certainty they seek. Guidance on where RE development is both com-mercially viable and endorsed or encouraged by the res-pective regulatory authorities can help attract deve-lopers by highlighting investment opportunities, and can potentially save time by avoiding protracted, project-specific negotiations.
Madagascar Name of the Client: The World Bank Gouvernement de Madagascar (Ministère de l’Energie et des Mines) Date de début/fin : 2014-2016
Key Figures
Small Hydropower Atlas of Madagascar
40 promising sites visited
20 prioritized sites investigated
6 gauging stations installed
2 prefeasibility studies
Budget : 1.308.190 USD
Dibwangui hydropower scheme (10.8 MW): hydrologi-cal study and review of the detailed design
SHER and Mhylab provided consultancy services to Eran-ove and The Gabonese Strategic Investment Fund to pro-gress in the development the Dibwangui hydropower scheme on the Louesti River in South Gabon. More pre-cisely, SHER and Mhylab reviewed the existing detailed design and performed the following services : Site visit and data collection New hydrological study
Spatial and temporal data analysis of rainfall and streamflows
Flow duration analysis Flood study (flood frequency analysis) Ecological flow
Review of the electromechanical equipments Energy and power outputs performance analysis
Gabon Client: Eranove and Fonds Gabonais d’Investissement Stratégique
Completion Date : 09/2015
Key Figures Design flow : 60 m³/s Gross Head : 20.9 m Turbines : 2 Kaplan saxo (2 x 30 m³/s) Dam : 5m high rockfill dam with concrete central core Design flood: 800 m³/s ungated spillway Expected energy generation : 65.1 GWh/y
Tender design, tender document & Works supervision of the Hydropower scheme on the Giciye River – 4MW
Upon request of Rwanda Mountain Tea and financially backed by Bio-Invest, SHER and Mhylab drafted the tender design and the tender documents for the civil works and hydro-electrical equipment of the hydropo-wer plant located in Giciye. The project is based in the West province. It aims at catching the Giciye river close to the bridge crossing the River and the road Ruhengueri-Gitarama, then con-veying the water to a forebay tank using a 2.5km con-crete canal. The scheme is designed to supply to the national elec-trical company (EWSA).
Rwanda
Giciye – Western Province
Name of Client: Rwanda Mountain Tea
Completion Date (Month/Year):
07/2014
Key figures Discharge : 4 m³/s
Gross Head : 130 m; 350m long and 1m welded steel penstock Turbines : 2 Pelton turbines (2 x 2 m³/s) Gravity concrete dam of 6.5 m height Estimated power generation : 18.3 GWh/y
Preparation of prefeasibility study of 4 sites for potential mini hydropower plants located in the Lofa basin
The World Bank has awarded SHER to carry out the pre-feasibility study of 4 sites for potential mini hydropower plants located in the Lofa basin. Tasks carried out by SHER:
Review of the existing data and GIS information
Site visits of each site and main load centers / national grid connection
Identify any major environmental and social impact that needs to be addressed at feasibility level
Simplified Topographic Survey and Preliminary Surface Geological Report
Update and verification of the hydrological data
Preparation of a Schematic Layout of Hydro Power Plant, Dam and Transmission & Distribution Lines to the main load centers / national grid
Preparation of a Budgetary Cost Estimate and Electricity Generation Estimate
Training with national stakeholders
Liberia Lofa River Name of Client: The World Bank Government of Liberia (Ministry of Lands, Mines and Energy) Completion Date (Month/Year): 05/2015
Key Figures Zoi : Discharge : 240 m³/s, Head : 11 m; Installed capacity : 21.0 MW, Investment: 193 MUSD
Lofa 2 : Discharge : 265 m³/s, Head : 20 m; Installed capacity : 42 MW, Investment : 217 MUSD
Nufata : Discharge : 25 m³/s, Head : 4.2 m; Installed capacity : 0.61MW, Investment : 5.8 MUSD
Barkedu South : Discharge : 10 m³/s, Head : 3.9 m; Installed capacity : 0.57 MW, Investment : 4.9 MUSD
St. John River Hydropower Reconnaissance Study
The project starts by conducting an assessment of the St John River Hydropower Development Project, in com-pliance with the Hydropower Sustainability Assessment Protocol (IHA). Through the performance of the as-sessment, SHER has established a diagnosis of all identi-fied existing previous studies performed on the subject as well as domains where additional studies and surveys are needed for the further design stage of the projects on the cascade. The second phase focuses on the definition of the St. John River Hydropower Development Project and as-sesses various aspects in order to define and select the most appropriate alternative.
Liberia Name of Client:
Ministry of Lands, Mines and Energy / European Commis-sion
Completion Date (Month/Year): 03/2014
Key Figures Yanata : Discharge : 400 m³/s; Head : 30 m; Capacity : 105 MW; Energy production : 555 GWh/y; Storage volume : 800 hm³
St John Falls : Discharge : 400 m³/s; Head : 30 m; Installed capacity : 105 MW; Energy production : 599 GWh/y; Run-off River
Nubli : Discharge : 550 m³/s; Head : 19 m; Installed capacity : 90 MW; Energy production : 535 GWh/y; Storage volume : 5 hm³
Renewable Energy Mapping: Small Hydro - Tanzania
The study will provide a thorough understanding of the potential small-hydro resources and their geographical distribution at the country level, overlaid with other key enabling factors and constraints, will inform land planning decisions and contribute to the enhancement of the exis-ting policy framework. Objectives : To improve the quality and availability of information on Tanzania’s small hydropower resources. The project will provide the GoT (Client) and commercial developers with ground-validated maps (75 sites up to 10 MW) To contribute to a detailed comprehensive assessment of small-hydro resources in Tanzania; To verify the potential for the most promising sites (20 prioritized sites).
Tanzania Name of Client: Ministry of Energy and Mines Fund raisers : World Bank / ESMAP
Completion Date (Month/Year):
2015
Key figures Phase 1 – Initial scoping and mapping 455 potential sites identified and located 75 potential sites visited Phase 2 - Data collection and validation Phase 3 - Production of validated Small Hydro Atlas
Feasibility study, tender study and supervision of works for the reinforcement of the natural dam of Lake NYOS
The global objective of the project is to contribute to securing the area of Lake Nyos, within the framework of a broad programme involving the Cameroonian go-vernment and other funders, in order to allow the dis-placed populations to re-establish themselves in their place of origin. The specific objective is to eliminate the risks asso-ciated with the possible failure of the natural dam re-taining the water of the greater Lake Nyos. The tasks achieved by SHER are: Feasibility study, tender study and technical speci-
fication Hydropower prefeasibility study Supervision of works ; Techical assistance to the Contracting Authority
(technical, administrative, regulatory, financial, economic and construction deadlines);
Development of technical alternatives.
Cameroon
Lake Nyos
Name of Client: IRGM
Name of Funding agency : / European Union
Completion Date (Month/Year):
07/2013
Key figures Construction of an impermeable barrier by means of a double curtain of approximately 260 jet grouting for a total length of 90 m and a depth of approximately 20 to 50 m Hydropower plant : Discharge : 350 l/s Gross Head : 45 m Installed capacity : 115 kW
Feasibility study / Tender design / Supervision of works
for the Rukarara II Hydropower plant (2MW)
The Belgian Technical Cooperation and the European Un-ion entrusted SHER, in Kigali, with the engineering re-lating to the creation of the small hydro-electric power plant in Rukarara and the MV electrical line intercon-necting to the national network which runs nearby. Rwanda's energy policy was aimed at developing rural centers by improving the accessibility of electrical energy to rural populations whilst developing the country’s nat-ural resources as much as possible. This being the case, the Rukarara II site offers interesting prospects from the point of view of both hydro-electric potential (~2MW) and national network interconnection possibilities.
Rwanda Nyamagabe – South-ern Province
Name of Client: Minis-try of Infrastructure
Completion Date :
08/2012
Key figures 1 Bailey Bridge 2 masonry derivation dams on Rubyiro and Rukarara rivers, each equipped with an in-take and a flushing canal (for gravels) 2 GRP pipes DN1500 to 1200 (1515m and 400 m) 1 GRP Penstock DN 1600 (385 m) Two buildings for guards Water flow : 5.6 m³/s Gross Head : 45 m Turbines : 2 Francis (2 x .2.8 m³/s) installed capacity of 2 MW. Estimated eletricity generation : 11.8 GWh/y
Identification of 3 Small Hydropower projects : Galabodawatta (4.2 MW) - Loggaloya (1.6 MW) - Pindeniya (1.6 MW)
JINADASA, a fully Sri Lankan owned company who plays a leading role in garment industry, is presently speciali-zing in renewable energy. The fact finding mission has been ordered by Jinadasa to SHER in the frame of an investment project of 3 Small hydropower projects sub-mitted to Belgian Investment Organization (BIO):
clarify technically the project with the promoter, and implement a field visit of the 3 sites;
collect and review the pre-feasibility documents as well as the drawings ;
evaluate local engineering resources for further studies;
evaluate the existing and potential available data (topographical, geological, hydrological);
and define further steps for the implementation of the project.
Sri Lanka Location :
Central Province
Name of Client:
JINADASA Group
Funding agency : BIO-Invest
Completion Date : 01/2012
Key figures Loggaloya: 1.6 MW - 14 m³/s - Gross Head 14 m
Pindeniya: 1.6 MW - 5 m³/s - Gross Head 38 m
Galabodawatta: 4.2 MW - 13m³/s - Gross Head 39m
Technical due diligence of the Tara Bintang project (12 MW)
The objective of the assignement includes a technical due diligence of the Tara Bintang existing civil infras-tructure, an analysis of the existing technical studies and on-site field visit.
Technical studies review: situation and general characteristics of the site, appraisal of the hydro-logical potential, civil engineering works (water catchment, inlet channel, pressure pipeline, po-wer station building, access roads, etc.)
Design and technical document review
Evaluation of the human and technical capacity of the civil contractor
Evaluation of the gap between the initial design and the existing activities
Conclusion and proposal of alternatives
Indonesia Location : Sumatra Utara
Name of Client: VELCAN
Completion Date :
08/2011
Key figures Discharge : 24 m³/s
Gross head : 64 m
Installed capacity : 12 MW
Feasibility Study for the Hydropower project KAGU006 6.4 MW / 8.7 MW alternatives
Our client has signed a concession agreement with the Ministry of Energy and Mines to develop a new hydropo-wer plant on the Kagunuzi River, downstream of the Rwegura hydropower plant. SHER has been selected to realize the feasibility study, the legal due diligence, the review of the Concession agreement and the Power Purchase Agreement (PPA) study. Complete environmental Impact assessment and Reloca-tion action plan (RAP), detailed studies, tender docu-ments and works supervision are also foreseen if the re-sult of previous studies is positive.
Burundi Province of Cibitoke
Name of Client: Private
Completion Date (Month/Year): 09/2012
Key figures Water flow : 10 m³/s for run-off-the-river alternative 12 m³/s for peak power alternative Gross Head : 79 m for run-off-the-river alternative 89 m for peak power alternative Turbines : 3 Francis (3 x 3.33 m³/s or 3 x 4.0 m³/s) ins-talled capacity of 6.4 MW (run-off-the-river alternative) and 8.7 MW (peak power alter-native) Dam : Gravity concrete dam of height of 8 m for run-off-the-river alternative 18 m for peak power alternative Estimated power generation :
Pre-feasibility of the Suka Rame mini hydro power scheme (4 MW) - Sumatra
Pre-feasibility of a 4 MW (~13 m3/s @ ~45 m) hydropo-wer project: hydrology study and model, topographical survey treatment, pre-design of the concrete dam (~5 m high - seg-
ment gate), intake, power canal and tunnel, pens-tock, power house, access road,
costing and rentability analysis. preparation of terms of reference for additional to-
po and geotechnical surveys
Indonesia Sumatra
Name of Client: VELCAN
Completion Date (Month/Year): 12/2012
Key figures Water flow : 13 m³/s run-off-the-river Gross Head :45 m Turbines : Installed capacity : 4 MW
Control and supervision of works of the Keya hydropow-er scheme (2.2 MW)
Rwanda's energy policy aims at developing rural centers by improving the accessibility of electric energy to rural populations whilst developing the country’s natural re-sources as much as possible. The site of Keya has subs-tantial hydropower potential, making it an interesting location that can also easily be connected to the national grid. This interconnection aspect makes the project even more relevant as it is in line with the wider approach of interconnecting micro and mini hydropower plants, by connecting them to the national grid, boosting return on investment at the same time.
Rwanda Pfunda Name of client : Ministry of Infra-structures - Elec-trogaz Completion Date : 06/2011
Key Figures Discharge : 3 m³/s
Gross Head : 92 m; 1130 m long and 1.2m steel penstock Turbines : 1 Crossflow 2.2 MW Dam : Gravity concrete weir of height of 2 m Estimated power generation : 11.5 GWh/y
Feasibility study for the SHPP of UVIRA
Feasibility study for the micro hydropower plant of UVI-RA, DRC, with a view to supplying the pumping and wa-ter treatment plant of REGIDESO. The aim of the feasibility study is to draft a technical fea-sibility report with preliminary design plans and set up a budget so that the Veolia Foundation is able to deter-mine the financial and technical viability of the project.
Geotechnical and geological study Topographical survey Civil engineering and hydraulic calculation and de-
sign Recommendations on grid stability of the treatment
plant of Uvira Electro-mechanical equipment / technical specifica-
tions Draft bill of quantities Draft cost estimate Preliminary terms of reference for detailed studies
DR Congo Uvira
Name of Client: REGIDE-SO
Funding agency : VEOLIA
Completion Date (Month/Year): 04/2015
Key figures Water flow : 1.7 m³/s run-off-the-river Gross Head :22.4 m Turbines : Installed capacity : 270 kW Kaplan turbine S-Type
Contact
Pierre Smits
SHER Engineering & Hydropower development [email protected]
www.sher.be
Our capability
Hydrology / hydraulics / flood risk and flood mana-
gement
Topography
Design of hydraulic infrastructures : dam, weir, in-
take, spillway, desilting basin, waterways and pens-
tocks, surge tank, powerhouse, river protection, fish
ladders, etc.
Geology / geotechnical investigation
Design of hydro mechanical equipments
Electricity & grid connection
Socio-environmental studies
Economical, financial and institutional studies
Offices
Burkina Faso Laos Rwanda
Belgium - SHER HQ