POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27...
Transcript of POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27...
![Page 1: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/1.jpg)
Litthanoulok LASPHODirector of Energy Policy Division,Department of Energy and Planning, Ministry of Energy and Mines.
POWER SECTOR OF LAO PDRWorkshop on Energy Connectivity and TransboundaryPower Trade.8-9 November 2015, Suzhou, China
![Page 2: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/2.jpg)
1.AREA OF 236,800 SQ. KM• 26 people /square
kilometer;• Mountainous area with
major Tributaries of the Mekong River Covering 35% of total Mekong River basin.
2. POPULATION 2014• Total: 6.8 Millions
3. GDP in 2014• GDP/per Capital: 1,720
US$• Growth Rate GDP: 7.65%
BASIC FACTS ABOUT LAOS
![Page 3: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/3.jpg)
The 1st Power Sector Policy was formulated in 1990:
1.Earn foreign exchange through electricity export to finance the country’s economic and social programs;
2.Increase access to electricity by grid extensions and off-grid rural electrification;
3.Maintain an affordable tariff to promote economic and social development;
4.Replace dependence on imported fuels for energy generation.
![Page 4: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/4.jpg)
![Page 5: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/5.jpg)
Responsibilities and Domestic Power Market
EdL-Gen. Off-takefrom IPP(e) IPP(d) SPPs
Transmission
Distribution
DomesticConsumers
Generation
EL
EC
TR
ICIT
E D
U L
AO
S
Interconnected with neighboring gridthrough HV Transmission lines import and export
Connected with neighboring gridthrough MV Transmission lines for import
Vertical integration of EDL
![Page 6: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/6.jpg)
![Page 7: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/7.jpg)
GenerationIPP (e)
Responsibilities and exporting power market
Transmission
Distribution systems ofneighboring countries
GO
VE
RN
ME
NT
AG
EN
CIE
S
Dedicated Transmission linesto neighboring grids for export
![Page 8: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/8.jpg)
![Page 9: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/9.jpg)
Power potential in Lao PDRLAOS HAS HYDRO POWER POTENTIAL OF ABOUT 26,000 MW: Only 3,294 MW have been developed with 27 plants and
can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy output of 32,866 GWh in 44
hydro + 1 thermal (Lignite) power projects under construction;
1,642 MW with annual energy output of 7,305 GWh in 24 hydro power projects under final preparation/negotiation and F/S;
By the year 2020, Laos will have 11,121 MW and annual energy output of 56,058 GWh= 43% of the total potential.
![Page 10: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/10.jpg)
RE Policy• Increase a share of renewable energy to 30% in the total
energy mix by 2025;
![Page 11: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/11.jpg)
Solar Resource
Pakxe St.
Thakek St.
Luang Prabang
Vientiane St.
Xamnua St.
![Page 12: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/12.jpg)
Wind Resource
![Page 13: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/13.jpg)
RE projectsWIND: 600 MW (1st phase: 250MW) under
negotiation for development in Sekong Prov. 3 additional projects under field investigation
SOLAR: Only Home Solar System (SHS) (50-100W)
(25,000 HH) 100 kW demonstration project (Japan grant) 50 MW solar farm under study in Vientiane.
![Page 14: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/14.jpg)
Transmission line system in
2014
International Power Cooperation
![Page 15: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/15.jpg)
Lao PDR has set as top priority in theNational Energy Policy to develop the vasthydropower potential available in order tostimulate the regional power trade and sooptimizing the energy-mix within the ASEANCommunity.
However, this National Top Agenda requiresoptimal development of the country’shydropower resources in a sustainable wayby sharing the multifaceted benefitsdelivered.
Conclusion
![Page 16: POWER SECTOR OF LAO PDR. Litthanoulok LASPHO - Lao...Only 3,294 MW have been developed with 27 plants and can generate 15,887 GWh of electricity per annum; 6,185 MW with annual energy](https://reader035.fdocuments.in/reader035/viewer/2022081621/61243c74979b8f05940596b3/html5/thumbnails/16.jpg)
THANK YOU FOR YOUR ATTENTION