Transcript of Power generation and energy - Electricity Issues in Indonesia
![Page 1: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/1.jpg)
power generation
& energy electricity issues in
Indonesia
Iwan Agung Firstantara
GM PT PLN (Persero) Unit Pembangkitan Jawa Bali
Thermofluid VI 2014
Yogyakarta, April 29, 2014
Gajah Mada University
![Page 2: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/2.jpg)
About
Speaker
@ GM_UPJB
Iwan Agung Firstantara was born in Jogjakarta, on October 1969. He
graduated from Gajah Mada University with a major in Mechanical
Engineering in 1993, and Master of Management also in the same
University.
Iwan is a General Manager of PT PLN (Persero) Unit Pembangkitan
Jawa Bali, one of PLN’s Strategic Business Unit that respondsible for
the Operation & Maintenance of 14 Power Generation Unit across
Java-Bali Interconecting System (making it the biggest total asset
compared to IP, PJB &IPP)
![Page 3: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/3.jpg)
1
2
3
4
Macro Economic PerspectiveFacts of Indonesia’s Economic Situation
Indonesia’s Energy OutlookEnergy current Trends and Challenge
Power Generation issuesFast Track Program, Energy Mix, & Environment-Efficiency
How technology solve Eletricity’s IssueDeal with Capacity & Efficiency matters
![Page 4: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/4.jpg)
Macro Economic’s PerspectiveFacts of Indonesia’s Economic Situations
Images taken from http://hqwide.com/
#Jakarta View #Wisma46
#BNITower
![Page 5: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/5.jpg)
comes to your mind
Indonesia?Wh
at when you think of
Images taken from http:// globe-walls .com/
#HelloJakarta #Monas
#Istiqlalmosque
![Page 6: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/6.jpg)
Images taken from http://listofimages/
Biggest Countryi n S o u t h E a s t A s i a
1 7 . 0 0 0 i s l a n d s3 . 1 m i l l i o n s q . k m o f s e a1 . 9 m i l l i o n s q . k m o f l a n d2 4 7 m i l l i o n i n h a b i t a n t s ( 2 0 1 2 )
#RajaAmpat #Beach
#BeautifulIndonesia
![Page 7: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/7.jpg)
Images taken from http://wallpapersus
Biggest Economyi n S o u t h E a s t A s i a
G D P $ 8 7 8 b i l l i o n ( 2 0 1 2 )
G D P g r o w t h 6 , 2 % ( 2 0 1 2 )
I n f l a t i o n 4 , 3 % ( 2 0 1 2 )
#Jakarta@Night #Pancoran
#Patung Dirgantara
![Page 8: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/8.jpg)
![Page 9: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/9.jpg)
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012* 2013**
6,7
8
7,8
6
8,5
6
9,3
3
10
,48
12
,48
14
,82
17
,29 21
,36
23
,88
27
,03 30
,66 33
,53 37
,54
GDP
Source : BPS
Capita( m i l l i o n r u p i a h )
![Page 10: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/10.jpg)
GDP
Source : BPS
Consumption
Government
Investment
Stat Discrepancy
X - M -2 %
5 %
32 %
9 %
54 %
o f 2 0 1 3
The BIG growth of Indonesia’s GDP was
driven primarily by domestic consumption“
![Page 11: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/11.jpg)
Emerging middle class in
Indonesia
Middle- & High- class inIndonesia has rose 5times higher in the last25 years
Source : BI (2013) Images taken from http://teropongbisnis.com/
![Page 12: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/12.jpg)
Indonesia’s middle-class
proportion:
Yellow: $ 2-4/ day
Source : BI (2013)
![Page 13: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/13.jpg)
![Page 14: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/14.jpg)
Indonesia’s Energy OutlookEnergy Current Trends & Challenge
Images taken from http://wallsave.com/
![Page 15: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/15.jpg)
Primary
Source : BP Statistical Review of World Energy 2011 & World Economic Outlook Database April 2011, IMF
in Some Country
Intensity
![Page 16: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/16.jpg)
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
Energy Consumption
Capita( B O E / C a p i t a )
3,4
6
Source : BPS
3,3
4
2,9
8
2,5
8
2,5
6
2,4
3
2,4
7
2,4
8
2,4
1
2,2
7
2,3
2
2,2
8
![Page 17: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/17.jpg)
11 11 12 13 15
17 18 21
23 25
27 28
34 36 37 36
40 42 44
46 48
46
51 55
31 33 34
36 39
41 44
47 50
55
60
65
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
Business Industry Household
Electricity
Consumption(in TWh)
Source : EMRPLN divided its customer into 5 segments: (1) Business, (2) Industry, (3) Household, (4) Social, (5) Government
![Page 18: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/18.jpg)
Images taken from http://globeimages.net/
#JakartaView #BunderanHI
#MonumenSelamatDatang
Since 2007Household has outreach the electricity
consumption among other PLN’s customer segments
![Page 19: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/19.jpg)
Energy demandhas been increasing faster than economic development and population growth
Images taken from natgeo society
![Page 20: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/20.jpg)
Electricity Shortage More than 70-80 million people
lack access to electricity
Images taken from http://phototony.com/
![Page 21: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/21.jpg)
1980 1985 1990 2000 2005 2006 2007 2008 2009 2010 2011 2012
Electrification Ratio( p e r c e n t )
73 76
67
66
65
63
62
57
43
28
16
8
Source : EMR
Highest : Jakarta (99,99%)Lowest : Papua (35,89%)
![Page 22: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/22.jpg)
Electricity is heaviliy subsidisedand currently customers pay forelectricity at far below marketprice.
Reliance on Subsidies
Images taken from natgeo
![Page 23: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/23.jpg)
Their estimated cost to government in 2013 is Rp 284 trillion and increasing to Rp 328,7 in 2014 (state budget plan).
subsidies have created a massive burden on the state budget.
Fuel &
Images taken from http:// 3.bp.blogspot.com/
Electricity
Source : Ministry of Finance
![Page 24: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/24.jpg)
60 57 57 53 57 55 51 50 49 48 47 48
13 15 15 19 17 19 23 27 23 23 24 27
23 22 24 24 21 21 22 19 24 25 23 21
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
Oil Coal Gas Hydropower Geothermal Biofuel
Primary Energy SupplyExclude Biomass
(in percent)
Source :CDI-EMR
![Page 25: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/25.jpg)
Driven by three main things:
1. Electrification programTo support government program to accelerate electrification ratio
2. Economic growthTo support manufacturing and service companies to produce products and services
3. Captive taking overMeet large consumer demand, to take over captive and to meet large customer demand
Demand of electricity is expected to grow fast
Images taken from http://touristrack.com/
![Page 26: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/26.jpg)
Power Generation IssuesFast Track Program, Energy Mix, & Environment-Efficiency
#LabuanCFSPP
#FTP-1 #2x300MW
![Page 27: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/27.jpg)
PLN P3B as “System Owner”and “Market Operator”
DistributionPower Generation (PLN or IPP)P3B as Transmission Provider
Primary Energy
Power Generation
Transmisi DistributionEnd
Customer
Availability of Primary Energy: quality, quantity,time, cost
Availability: reliable, safe, efficient, quality
Availability: reliable, safe, efficient, quality;Economic
optimisation;
Availability: reliable, safe, efficient, Sufficiency &
quality of supply
Services: simple, easy, quick, quality;
StandardService
StandardService
StandardService
StandardService
Standard of Public
Service
Electricity Supply Chain
![Page 28: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/28.jpg)
To meet Indonesia’s growing demand
Issue#1
#RembangCFSPP #FTP-1
#SubcriticalPulverized
PLN is mandated to implement Fast Track Program (FTP) for capacity expansion
![Page 29: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/29.jpg)
FTP Phase 1 :
42 Coal-Fired Steam Power Plants of PLN’s Project• 10 power plants with capacity of 6.900 MW in Java-Bali • 32 power plants with 2.252 MW outside Java-Bali
FTP Phase 2 :
93 power plants (Hydro, Geothermal, & Coal-Fired Power Plant)• 21 power plants of PLN’s Project • 72 power plants of Partnership Project
#TjAwar-awarCFSPP
#CoalHandling #StackerReclaimer
Issue#1
![Page 30: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/30.jpg)
Chinese’s Power Plants (FTP-1)
are cheaper than Japanese’s PP, but the quality has likely not yet proven.
PLN also suffer from project completion delay.
#PalabuanRatuProject
#Construction #FTP-1
Issue#1
![Page 31: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/31.jpg)
Even though
The FTP has improved thecompany's internal cash flowsand meet the 9% of electricitydemand growth.
It has also minimize the Fuelcontribution in PLN Fuel Mixfrom 22% in 2009 to 12% in2013.
Images taken from http://dl.bizhi.sogou.com/
Issue#1
![Page 32: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/32.jpg)
2%
58%18%
6%
16%
2019
Fuel Coal Gas Hydro Geo
36%
35%
17%
9%
3%
2008
Fuel Coal Gas Hydro Geo
Source :RUPTL 2010-2019
Fuel Mix
Issue#2
1% replacement of Fuel into Coal will generate financial efficiency up to Rp 1,74 T (in 2012) .
![Page 33: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/33.jpg)
Indonesia’s electricity is still rely on coal-based power plants
Contribute approximately 58% of the total electricity generated
Issue#2
Images taken from http:// ncealliance.com/
![Page 34: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/34.jpg)
Environment
Efficiency
Issue#3
Reciprocal Relationship in
coal power plant
![Page 35: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/35.jpg)
Images taken from http://ak2.picdn.net /
Clean Coal Technology
Every option capable of reducing emissions upstream, downstream, or within the power generation (energy conversion) process
Issue#3
![Page 36: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/36.jpg)
For new power plants
Images taken from http:// saistrip2010.webatu.com /
Could consider this following options:
#IGCC #CleanCoalTech
Supercritical & Ultra-supercritical (USC) pulverized coal technology
Circulating fluidized bed combustion (CFB)
Integrated gasification combined cycle (IGCC)
Issue#3
![Page 37: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/37.jpg)
For existing power plants
Could initiate rehabilitation & recondition, to:
Improve efficiency
Decrease hidden capacity
#MuaraKarang #CCPP
Issue#3
![Page 38: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/38.jpg)
How Technology Solve Electricity IssuesDeal with Capacity and Efficiency matters
Images taken from http:// www.iorise.com /
![Page 39: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/39.jpg)
Efficiency(%)
39
37
35
33
1 2 3 4 5 6 7 8
Lifetime(Years)
Annual Inspection
SI SI SI SIME SE MERehabilitationRecondition
Restore
New Technology
Improve
100
75
50
25
Capacity
(%)
Efficiency & capacity degradation
![Page 40: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/40.jpg)
How to deal with Capacity & Efficiency matters?
Capacity:• Coal Mixing• Coal Drying
Efficiency:• Tiny-oil Burner
• Heat Balance modelling
#PalabuanRatu #Construction
#FastTrackProgram
![Page 41: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/41.jpg)
Coal mixing
the process of blending two different typesof coal (low & medium range coal) to obtaina desired efficiency/ load profile.
Heating valueLow Range Coal = + 4.200 kCal/kgMedium Range Coal = + 4.900 kal/kg
Coal layering
The process of placing the med range coalat specific boiler burner layer to obtain adesired efficiency/ load profile.
![Page 42: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/42.jpg)
Coal dryingThe process of heating the coal feed to get a dry coal feed and
increase coal quality
Is being constructed at Labuan & Lontar CFSPP
Expected to increase coal quality up to 1000 kCal/kg
Images taken from http:// carzz.co /
![Page 43: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/43.jpg)
Tiny-oil burner
A modified boiler burner to obtainless fuel oil consumption.
Could reduce the fuel consumptionup to 85% (@Labuan CFSPP).
Original
burner
Tiny burner
![Page 44: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/44.jpg)
Heat balance
modellingImplemented through a Gatecycle, heat balance modelling discover all
of plant’s main equipment and predict the modelling.
The modelling help the management to develop more accurate Root Cause
Failure Analysis (RCFA).
Images taken from http:// st.gdefon.ru /
![Page 45: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/45.jpg)
PLN Generation Challenges
![Page 46: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/46.jpg)
Heat Rate Comparison in 2013( i n k C a l / k W h ) )
Tech challenge
Challenge#1
TJB (Non-FTP)
IMY(FTP)
2.732
2.403
![Page 47: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/47.jpg)
Turbine
efficiency
improvement
There has been no significant breakthrough on turbine efficiency improvement
Challenge#2
Images taken from http://deltatest.de /
![Page 48: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/48.jpg)
Heat Balance
Modelling
Challenge on:• Accuration• HR Competency• Alternative model
Challenge#3
Images taken from http:// img0.mxstatic.com /
![Page 49: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/49.jpg)
Source :World Bank TeamPBR (Performance Based Regulation) is given by the Government to determine PLN Allowed Revenue.
Challenge#4
![Page 50: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/50.jpg)
EpilogueEfficiency improvement in Power Generation represent the
largest opportunities in reducing subsidies, where thermofluid takes the most improtant role.
#Sunset #Fisherman
#BeautifulIndonesia Images taken from natgeo
![Page 51: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/51.jpg)
![Page 52: Power generation and energy - Electricity Issues in Indonesia](https://reader034.fdocuments.in/reader034/viewer/2022051515/554c5b95b4c905282a8b52c5/html5/thumbnails/52.jpg)
An institution to bridge the interest between business (power generation) and universities has not yet established.
Images taken from http://austinareaphoto.com /