Power Converters and DC cables Slide 1/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Water cooledcables
warm bus bars
powerconverter
Energy Extraction
Power Converters and DC cables Slide 2/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
IntroductionIntroduction
1. Power converter reception tests and installation2. DC cable reception tests and installation3. Warm power tests without superconducting magnets4. Cold power tests with superconducting magnets5. Conclusion
Power Converters and DC cables Slide 3/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
LHC Power ConvertersLHC Power Converters
TI 2
TI 8
SPS
Injection
Injection
Beam dump
SR1BA7
BA4
RR13RR17
UJ14UJ16
UA23
UA27
SR2
UJ33
SR3
UA47UA43
SR4 RR53 SR5
SM18
RR57
USC55UJ56
UA63
UA67
RR73SR7
RR77
SR8
UA83
UA87
SR6Point 5
Point 4
Point 2
Point 3
Point 6
Point 7
Point 1
Point 8
SR: Thyristor PCs forthe warm magnets
ARC: 60A corrector PCs
UA: 3.25kA and 2kA PCs600A and 120A PCsMB PCs
RR: 2kA PCs600A PCs
•1700 converters with 98% underground
• 750*60A corrector converters (0.5kW)
• 740*120A&600A converters• 220*2kA&3.25kA converters• 8*13kA MB converters (2.6MW)
Power Converters and DC cables Slide 4/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
LHC Power Converter
DcctFGC
Vref
Magnet
Power Part(Voltage Source)
AC Mains Supply
DC cables
Power Interlock Controller
Cooling System
WorldFIP(Iref)
DC cables Intk
LHC Power ConvertersLHC Power Converters
Power Converters and DC cables Slide 5/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Power converter tests before installation
Power Part(Voltage source)
FGC
Dcct
Individual Testsat CERN
Surface Halls
Individual Testsat manufacturer
premises
Power Part(Voltage source)
FGC
Dcct
Power Part
FGC Dcct
Converter Integrationat CERN
Surface Halls
LHC Power Converter(Current source) :
Performance validation
Power converter reception testsPower converter reception tests
Power Converters and DC cables Slide 6/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
PC installationPC installation
Power converters installation
•the power converters are transported and installed in the tunnel without to be dismantled…
Power Converters and DC cables Slide 7/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
PC installationPC installation
… except the main dipole power converter
11 m
2.2 m
Installation tests
40 t
- By the specialists- In parallel with the short circuit tests
Power converters installation
Power Converters and DC cables Slide 8/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
DC cables Installation and testsDC cables Installation and tests
Water cooled cable tests and installation
•The water cooled cables are not tested at CERN before their installation
•After their installation, the water cooled cables are only tested
•in pressure : 24 bars, 10 minutes
•in insulation : 3 kV DC with current leakage measurement
Power Converters and DC cables Slide 9/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Powering circuitPowering circuit
Energy Extraction
PowerConverter
Magnet
Intksyst
CtrlRoom
DC cables
ACMain
supply
DC cable intk
Cooling system
Warm power tests (EDMS 464458 & 573115)
Cold power tests (EDMS 519716)
Power Converters and DC cables Slide 10/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Warm power testsWarm power tests
8 hours heat run tests for superconducting circuits•The objectives of this test are to valid
• AC connexion of the power converter• Installation of power converter• Cooling of the DC cables• DC connexions between power converter, DC cables and
discharge system
•The magnet is replaced by a short circuit piece
Hardware commissioning procedureEDMS 575406
Power Converters and DC cables Slide 11/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Warm power testsWarm power tests
8 hours heat run tests for superconducting circuits
•Requests• AC distribution• UPS• Water cooling system• Ventilation system• Short circuit pieces
• Energy extraction system for the 13kA and 600A with EE• PIC for the 13kA
Power Converters and DC cables Slide 12/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Warm power testsWarm power tests
8 hours heat run tests for warm magnets
•The objectives of this test are to valid• AC connexion of the power converter• Installation of power converter• DC connexions between power converter, DC cables and
magnet• Set up of the current loop• Power converter performance
•For transfer line power converters, the TI8 procedure is used
Power Converters and DC cables Slide 13/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Warm power testsWarm power tests
•Requests• AC network• Interlock system• Magnet
8 hours heat run tests for warm magnets
Power Converters and DC cables Slide 14/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Warm power testsWarm power tests
Interlock tests
•The objectives of this test are to valid•Connexion between the interlock system and the power
converter•Comportment of the different system (power converter,
interlock system and energy extraction system)
Control Test
•The objectives of this test are to valid• The WorldFIP (MUGEF for TL-PC)• The Field Control Room softwares• The Alarm system, Logging system and Post Mortem system
Power Converters and DC cables Slide 15/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
24 hours heat run test for superconducting circuits
•The objectives of this tests are to valid• Global water cooling system• Global air conditioning system• Global AC distribution• Global control of power converters by the FCR
Warm power testsWarm power tests
Power Converters and DC cables Slide 16/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Warm power testsWarm power testsID Task Name Duration
1 Power Converter Short Circuit Tests 58 days
2 UA83 40 days
3 Water connection 1 day
4 400V and UPS connection 1 day
5 RB 14 days
6 Converter reception tests 8 days
7 18kV connection 1 day
8 PIC connection & Discharge system verification1 day
9 Converter setting 1 day
10 8H Heat run 1 day
11 DCCT calibration tests 2 days
12 RQD, RQF 7 days
13 PIC connection & Discharge system verification1 day
14 Converter setting 1 day
15 8H Heat run 1 day
16 DCCT calibration tests 4 days
17 Other converters 6 days
18 Converter setting 1 day
19 8H Heat Run sector D2C 1 day
20 Test des systemes de decharge secteur C2B1 day
21 Converters setting sector C2B 1 day
22 8H Heat Run sector C2B 1 day
23 Converters setting sector B2A 1 day
24 8H Heat run sector B2A 1 day
25 PIC connection 1 day
26 Inner Triplet 8 days
27 Converters reception tests 3 days
28 Converter setting 1 day
29 8H Heat run 1 day
30 DCCT calibration tests 2 days
31 PIC connection 1 day
32 WorldFIP connection for the UA83 2 days
33 24H Heat Run for the UA83 1 day
34
35 RR77 8 days
36 Water connection 1 day
37 400V connection 1 day
38 Discharge system tests 1 day
39 Converter setting 1 day
40 8H Heat Run 1 day
41 PIC connection 1 day
42 WorldFIP connection 1 day
43 24H Heat Run 1 day
44
45 Tunnel machine sector 7-8 10 days
46 400V connection 2 days
47 Converter setting 3 days
48 WorldFIP connection 4 days
49 8H Heat Run 1 day
AB-PO
AB-PO,TS-EL
AB-PO,AB-CO,AT-MEL
AB-PO
AB-PO,TS-EL,AT-MEL
AB-PO
AB-PO,AB-CO,AT-MEL
AB-PO
AB-PO,TS-EL,AT-MEL
AB-PO
AB-PO
AB-PO,TS-EL
AB-PO,AB-CO,AT-MEL
AB-PO
AB-PO,TS-EL,AT-MEL
AB-PO
AB-PO,TS-EL
AB-PO,AB-CO
AB-PO
AB-PO
AB-PO,TS-EL
AB-PO
AB-PO,AB-CO
AB-PO,AB-CO
AB-PO,TS-CV,TS-EL,AT-MEL,AB-CO
AB-PO,TS-CV
AB-PO,TS-EL
AB-PO,AT-MEL
AB-PO
AB-PO,TS-CV,AT-MEL
AB-PO,AB-CO,AT-MEL
AB-PO,AB-CO
AB-PO,AB-CO,AT-MEL,TS-CV
AB-PO,TS-EL
AB-PO
AB-PO,AB-CO
AB-PO
3 6 9 12 15 18 21 24 27 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24February 2004 March 2004 April 2004 May 2004
10 weeks for a sector- 5 weeks for an UA- 3 weeks for a RR- 2 weeks for an arc
Sector 78
Power Converters and DC cables Slide 17/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Circuit type tests (60A, 120A, etc…)
•First Powering tests (at minimum stable current)• Check the start of the power converter• Set up of current loop and verify the stability• Safety system
•Intermediate current• Verify the current loop stability• Safety system
• Nominal current
• Power converter performance in current source
Cold power tests Cold power tests (EDMS 519716)(EDMS 519716)
Power Converters and DC cables Slide 18/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Main dipole circuits
•Main issues with the RB circuits• Starting of the power converter (> 20 s to go to the
minimum current)• Setting current loop (noise of the current measurement) • Discharge system in the odd point• Recuperation mode• Safety system• Power converter performance in current source
Cold power testsCold power tests
Power Converters and DC cables Slide 19/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
MQM circuits
•Main issues with the MQM circuits•Starting of the 2 power converters•Setting current loop and verify the performance
(resistive coupling) •Safety system
6 kA 6 kA
Cold power testsCold power tests
Power Converters and DC cables Slide 20/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Inner Triplet main quadrupole circuits (EDMS 531773)
RST-
Iref1
Ipc1
RST-
Iref2
RST-
Iref3
Ipc3
Ipc2
Deco
uplin
g s
yst
em
4.7 kA±600 A
7 kA Ipc1
Ipc2Ipc3
Vref1
Vref2
Vref3
7 kA
7 kA
Cold power testsCold power tests
Power Converters and DC cables Slide 21/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
•Test strategy•Test the 5 kA circuit alone (inner power converter)•Test the 7 kA circuit alone (outer power converter)•Test the 5 kA + 7 kA with decoupling loop•Test the 5 kA + 7 kA + 0.6 kA with decoupling loop•Set up of the current loops
Inner Triplet main quadrupole circuits
4.7 kA±600 A
7 kA
7 kA
7 kA
Cold power testsCold power tests
Power Converters and DC cables Slide 22/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
Cold power testsCold power tests
7R 8L 8R 1L 1R 2L 2R 3L 3R 4L 4R 5L 5R 6L 6R 7L
Main Circuits (RB, QF and QD)
Low current loop setting 2 1 1 1 1 1 1 1Low current FW test 2 1 1 1 1 1 1 1Intermediate current FW 2 1 1 1 1 1 1 1Nominal current FW tests 2 1 1 1 1 1 1 1DCCT Calibration 6 3 3 3 3 3 3 3
Inner Triplet Quadrupoles System
Tests at low current 10 5 5 5 5 5 5 5Intermediate current discharge tests 2 1 1 1 1 1 1 1Nominal current discharge tests 2 1 1 1 1 1 1 1DCCT Calibration 2 1 1 1 1 1 1 1
Inner Triplet Correctors + D1
Low current loop setting 3 1.5 1.5 1.5 1.5 1.5 1.5 1.54, 6 and 8 kA converter
Low current loop setting 1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5600 A without Energy Extraction
Low current loop setting 1 1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5600 A with Energy Extraction
Low current loop setting 1 1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5120 A Orbit correctors
Current loop setting 1 1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.560 A Orbit correctors
Current loop setting 1 1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5Total de jours de 16H par point et secteur 4 38 19 12 12 19 19 2 2 9.5 9.5 12 12 9.5 9.5 2Total de jours de 16H par secteur
sector 7-8 sector 8-1 sector 2-3sector 1-2 sector 3-4 sector 4-5 sector 6-7sector 5-6
11.5 21.5 21.5 11.521 31 31 21
Other sector:7 days for the 3 main circuits8 days for the IT circuits4 days for the other circuits
First sector:14 days for the 3 main circuits16 days for the IT circuits8 days for the other circuits
Power Converters and DC cables Slide 23/..LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005
ConclusionsConclusions
1. The power converters are tested before their installation but theses tests are limited
not real load not real environment not with the other systems (PIC and WorldFIP)
2. The DC cables are not tested before their installation not tests in power
3. The main circuits (RB and RQ) and Inner Triplet request a special attention