Power converters implications for Booster Energy Upgrade

21
Power converters implications for Booster Energy Upgrade Jean-Paul Burnet, Serge Pittet LIU day, 01.12.2010 TE EPC

description

TE EPC. Power converters implications for Booster Energy Upgrade. Jean-Paul Burnet, Serge Pittet LIU day, 01.12.2010. MPS load characteristic. TE EPC. 16 periods, 4 rings. 1.4 GeV Booster MPS (1/2). TE EPC. TRIM A 1900V 50A pk 30A RMS. Load: 0.5 Ohms / 0.18 H 1.4GeV margins: - PowerPoint PPT Presentation

Transcript of Power converters implications for Booster Energy Upgrade

Page 1: Power converters implications for Booster Energy Upgrade

Power converters implications for Booster Energy Upgrade

Jean-Paul Burnet, Serge PittetLIU day, 01.12.2010

TE EPC

Page 2: Power converters implications for Booster Energy Upgrade

MPS load characteristic

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 2

TE EPC

Magnets quantity

Total resistance [mOhms]

Total inductance [mH]

Dipoles outer ring 64 172 64

Focusing quadrupoles 128 74 8

Reference magnet 4 10 4

Defocusing quadrupoles 64 51 6

Dipoles inner ring 64 172 64

Total 324 479 146

16 periods, 4 rings

Page 3: Power converters implications for Booster Energy Upgrade

1.4 GeV Booster MPS (1/2)

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 3

TE EPC

BHZ Ring 1&4

Reference magnet

GND

QFO

QDE

BHZ Ring 2&3

MPS3600V4000Apk

2300ARMS

TRIM A1900V50Apk

30ARMS

QFO520V300Apk

200ARMS

QDE520V300Apk

200ARMS

Load: 0.5 Ohms / 0.18 H1.4GeV margins:• MPS voltage: -2%• MPS peak current: -2%• MPS rms current: 3%• TRIM A peak current: 40%• TRIM Q peak current: 0%

Page 4: Power converters implications for Booster Energy Upgrade

1.4 GeV Booster MPS (2/2)

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 4

TE EPC

• From 4000A to 5500A, the current on the Trim A must be increased by a factor 4 to compensate the Outer rings saturation.

%

• The existing MPS can run faster but cannot provide more peak current

Page 5: Power converters implications for Booster Energy Upgrade

2 GeV Booster MPS

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 5

TE EPC

64 BHZ Ring 1&4

Reference magnet

GND

128 QFO Ring 1-4

64 QDE Ring 1-4

64 BHZ Ring 2&3

MPS3600V5300Apk

TRIM A1900V270Apk

QFO520V420Apk

QDE520V420Apk

Upgrade scaling on one cycle• MPS peak current: +30%• MPS rms current: +35%• 18kV apparent power: +77%• 18kV peak power: +45%• TRIM A peak current: +540%• TRIM Q peak current: +40%

Page 6: Power converters implications for Booster Energy Upgrade

18kV network

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 6

TE EPC

0 0.2 0.4 0.6 0.8 1 1.2 1.40

0.5

1

1.5

2

2.5x 10

7

X: 0.8475Y: 2.081e+007

Reactive Power

X: 0.8676Y: 1.582e+007

1.4GeV

2.0GeV

0 0.2 0.4 0.6 0.8 1 1.2 1.4-1

-0.5

0

0.5

1

1.5

2

2.5x 10

7 Active Power

X: 0.6925Y: 1.368e+007

X: 0.742Y: 2.053e+007

1.4GeV

2.0GeV

Fast transients with 2GeV cycle which can not be compensated by Meyrin SVC.

50% increase of active power, 30% increase of reactive power

Page 7: Power converters implications for Booster Energy Upgrade

Upgrading existing supply

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 7

• All power components must be upgraded to the new peak current (Thyristors, transformers, filters,…)

• Four consecutive 2GeV cycles has to be considered as a DC value for power semiconductors.

• Replace the existing TRIM A (+ 1 spare).• Replace the existing QFO and QDE (+1 spare).

Side effects:• Major upgrade of magnets cooling circuit

needed.• Power DC cables section must be increased.• 18kV average power capability to be checked.• 18kV network will probably not be able to

absorb the new peak power pulse. Flickers to be foreseen!

TE EPC

POPS MPSB existing

MPSB 2Gev Hyp

Imax 6kA 4kA 6kA

Vmax 10kV 3.6kV 3.6kV

Irms (dc side) 3.2kA 2.3kA 3.1kA

Plossrms 4MW 2.9MW 5.2MW

Emagpeak 12MJ 1.5MJ 2.5MJ

Page 8: Power converters implications for Booster Energy Upgrade

“POPS” basic principles

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 8

The energy to be transferred to the magnets is stored in capacitors.

• DC/DC converters transfer the power from the storage capacitors to the magnets.• Four flying capacitors banks are not connected directly to the mains. They are charged via the magnets.• Only two AC/DC converters (called chargers) are connected to the mains and supply the losses of the

system.

TE EPC

DC3

DC

DC +

-

DC1

DC

DC

DC5

DC

DC +

-

DC4

DC

DC-

+

DC2

DC

DC-

+

DC6

DC

DC

MAGNETS

+

-

+

-

CF11

CF12

CF1

CF21

CF22

CF2

AC

CC1

DC

MV7308

AC AC

CC2

DC

MV7308

AC

18KV ACScc=600MVA

OF1 OF2

RF1 RF2

TW2

Crwb2

TW1

Lw1

Crwb1

Lw2

MAGNETS

AC/DC converter - AFE

DC/DC converter - charger module

DC/DC converter - flying module

Chargers

Flying capacitors

Active power of the magnets

-60000000

-40000000

-20000000

0

20000000

40000000

60000000

0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8

Time [s]

Po

wer

[W

]

.

Power to the magnets:

+50MW peak

Resistive Losses and charger power

0

2000000

4000000

6000000

8000000

10000000

12000000

0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8

Time [s]

Po

we

r [W

] .

Power from the mains

10MW

Page 9: Power converters implications for Booster Energy Upgrade

POPS based proposal (1/2)Benefits• Overall voltage available increases and would

allow a reduction of the RMS current using a faster ramping.

• The capacitor bank totally absorbs the peak power on the 18kV network. Meyrin SVC would then become optional.

• Spare sharing between MPS A and B and eventually with POPS.

• Only a few new cables needed between the reference magnet (BCER) and the MPS.

• New B-field regulation to minimize eddy currents and saturation effects impact at higher current and acceleration rate.

Drawbacks• Cost estimation 14MCHF using POPS module.• RF acceleration has to be increased.

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 9

TE EPC

Reference magnet

Ring 2&3

GND

MPS B2500V5500A

QFO600V450A

QDE600V450A

GND

MPS A2500V5500A

64 BHZ Rings 1&4

128 QFO Rings 1,2,3&4

64 QDE Rings 1,2,3&4

64 BHZ Rings 2&3

Reference magnet

Ring 1&4

Ring 1 B-filedmeasurement

Ring 2 B-filedmeasurement

Page 10: Power converters implications for Booster Energy Upgrade

POPS based proposal (2/2)

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 10

TE EPC

Upgrade scaling on one cycle• MPS peak current: +30%• MPS rms current: +3%• 18kV apparent power: -26%• 18kV peak power: -78%

DC3

DC

DC +

-

MAGNETS

V_F3

UdcF3

AC

CC1

AC

MV7308

DC

DIP+QF+REF

DC3

DC

DC +

-

V_F3

UdcF3

AC

CC1

AC

MV7308

DC

DIP+QD+REF

DC3

DC

DC +

-

UdcF3

AC

CC1

AC

MV7308

DC

Page 11: Power converters implications for Booster Energy Upgrade

Layout of new building

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 11

TE EPC

New

MPSB

(2 GeV)

(26m x 16m)

TT

6

Cap bank #1 Cap bank #2 Cap bank #3

Control roomLocal for Cooling& Air Conditioning

AC/DC3 spare (1.2m x 10m) DC/DC3 floating (1.2m x 10m)

AC/DC1 (1.2m x 10m) AC/DC2 (1.2m x 10m)

DC/DC1 (1.2m x 10m) DC/DC2 (1.2m x 10m)

Out

put c

ubic

le

QF QD QS16

m

26m

4m4m

• 420m2 required, only 190m2 available in bdg. 271 ground floor.• Only 200kg/m2 allowed in bdg. 271 first floor.• No space left in bdg. 361.

With this new building:• We can install and commission during Booster operation.• We have a backup power supply during the first years.• Easy connection to existing cables and cooling services.

Page 12: Power converters implications for Booster Energy Upgrade

Effect of idle cycles

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 12

TE EPC

RMS current can also be reduced keeping RF acceleration used today (3.6kV on the MPS) and providing 2GeV cycles to LHC only:

Only 10% RMS current increase if ZERO cycles are inserted. ZERO 12 and 18 would allow a slow setting up of the transfer line:

No increase of the RMS current (compared to all cycles at 1.4GeV) if Isolde has no physics during LHC proton filling:

PSB LHC25A LHC25B ISO LHC25A LHC25B ISO LHC25A LHC25B ISO LHC25A LHC25B ISO EASTB ISO ISO TOF TOF ISO

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Energy 2GeV 2GeV 1.4GeV 2GeV 2GeV 1.4GeV 2GeV 2GeV 1.4GeV 2GeV 2GeV 1.4GeV 1.4GeV 1.4GeV 1.4GeV 1.4GeV 1.4GeV 1.4GeV

RMS partial 2822 ARMS 2822 ARMS 2822 ARMS 2822 ARMS 2267 ARMS 2267 ARMS

RMS total 2650 ARMS

PSB LHC25A LHC25B ZERO LHC25A LHC25B ZERO LHC25A LHC25B ZERO LHC25A LHC25B ZERO EASTB ISO ISO TOF TOF ZERO

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Energy 2GeV 2GeV 2GeV 2GeV 2GeV 2GeV 2GeV 2GeV 1.4GeV 1.4GeV 1.4GeV 1.4GeV 1.4GeV

RMS partial 2517 ARMS 2517 ARMS 2517 ARMS 2517 ARMS 2267 ARMS 1873 ARMS

RMS total 2380 ARMS

PSB LHC25A LHC25B ZERO LHC25A LHC25B ZERO LHC25A LHC25B ZERO LHC25A LHC25B ZERO EASTB ZERO ZERO TOF TOF ZERO

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Energy 2GeV 2GeV 2GeV 2GeV 2GeV 2GeV 2GeV 2GeV 1.4GeV 1.4GeV 1.4GeV

RMS partial 2517 ARMS 2517 ARMS 2517 ARMS 2517 ARMS 1371 ARMS 1873 ARMS

RMS total 2263 ARMS

Page 13: Power converters implications for Booster Energy Upgrade

Existing supply with idle cycles

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 13

• All power components must be upgraded to the new peak current (Thyristors, transformers, filters,…)

• Four consecutive 2GeV cycles has to be considered as a DC value for power semiconductors.

• Replace the existing TRIM A (+ 1 spare).• Replace the existing QFO and QDE (+1 spare).

Side effects:• Major upgrade of magnets cooling circuit

needed.• Power DC cables section must be increased.• 18kV average power capability to be checked.• 18kV network will probably not be able to

absorb the new peak power pulse. Flickers to be foreseen!

TE EPC

POPS MPSB existing

MPSB 2Gev Hyp

Imax 6kA 4kA 6kA

Vmax 10kV 3.6kV 3.6kV

Irms (dc side) 3.2kA 2.3kA 2.5kA

Plossrms 4MW 2.9MW 3.2MW

Emagpeak 12MJ 1.5MJ 2.5MJ

Page 14: Power converters implications for Booster Energy Upgrade

New magnet requirementsIn order to be powered by the existing power supply 4kA/3.6kV, magnet coil

copper cross section must increase• By 30% to increase the number of turns and provide the additional field

with the MPS rated current.• By 30% to compensate the additional coil length.• By 400% to compensate the increasing inductance (L n2) and keep

enough voltage margin for the desired acceleration (U = RI + L dI/dt).

Resistive losses divided by 4but

Copper weight multiplied by 7

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 14

TE EPC

Page 15: Power converters implications for Booster Energy Upgrade

And what if… (1/2)

… we increase reasonably the amperes-turns and the section on all magnets:• Existing current rating would be sufficient.• Additional voltage needed to compensate the increasing magnets

inductance.• Reactive power still increases and the Meyrin SVC capability would be an

issue within 1.2s cycle.• At the end a POPS based supply would be needed.

…we increase the amperes-turns and/or the section on the bending only:• Existing supply could be used to power the quadrupoles.• A smaller POPS based supply could be used for the bending magnets.

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 15

TE EPC

Page 16: Power converters implications for Booster Energy Upgrade

And what if… (2/2)

…we decrease the magnet gap (and vacuum chamber size) by 30%• Existing power supply can be used. The magnetic cycle would have to be

adapted to compensate for the 30% increase in load inductance.

…we install a new MPS adapted to the existing magnets and they fail after a few years of operation (they were designed for 0.8GeV).

In any cases several MCHF would be saved on the new supply and/or on electricity consumption with new magnets:

15GWh per year at 1.4GeV → 18 MCHF over 25 years10% increase in current → 21% increase in power → 3.8MCHF

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 16

TE EPC

Page 17: Power converters implications for Booster Energy Upgrade

Booster Ring (others)

• Dipoles correctors and multipoles are mainly used at low energy and have enough margin. They will be consolidated during the shutdown 2011-2012.

• The Qstrips are only used at injection. Any upgrade would be part of the linac 4 project and not of the Booster energy upgrade.

• BDLs are used at ejection but have enough margin.

• The DBS are dedicated to destructive beam measurement and will probably not be used at 2GeV.

• The shavers are only used at injection. Any upgrade would be part of the linac 4 project and not of the Booster energy upgrade.

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 17

TE EPC

Page 18: Power converters implications for Booster Energy Upgrade

PSB Ejection

• BE.SMH:2GeV setting not exactely defined yet. The capacitor bank size will have to be adapted to provide the additional energy and a new capacitor charger may have to be foreseen.

• BE1 to 4.DHZ 11L1, BE1 to 4.DHZ 4L1, BE1 to 4.DVT 11L1 and BE1 to 4.DVT 4L1:Even approaching their rated limits, these converters will not need to be upgraded for 2GeV operation.

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 18

TE EPC

Page 19: Power converters implications for Booster Energy Upgrade

BT and BTM transfer

• The transfer line includes some huge bendings (RL load similar to MPS!). An important power transfer is needed for PPM operation.

• The BT and BTM transfer lines will have to provide PPM operation between 1GeV or 1.4GeV Isolde and 2GeV PS.

• The natural discharge of the magnet is estimated by the current reached after 0.9s starting from 2GeV current.

• The capacitor bank size of ALG-1 model will have to be adapted to provide the additional energy.

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 19

TE EPC

Page 20: Power converters implications for Booster Energy Upgrade

BTP transfer

• The BTP transfer is not used by Isolde. PS cycles only will go through.• It is a non-PPM only line and quadrupoles should be redesigned for PPM

operation, allowing optics flexibility on various beams.

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 20

TE EPC

Page 21: Power converters implications for Booster Energy Upgrade

EPC Conclusions

01/12/2010 TE-EPC - Serge Pittet - EDMS 1106116 21

MPS:• The existing supply can not endorse the additional RMS and peak current, even

for one single pulse.• An increase of peak power, using traditional thyristor technology, would have a

significant negative effect on power quality of the Meyrin network 18 kV.• The solution will probably be a design similar to the new POPS for the PS, using

DC capacitors to store the energy for the pulsating load (civil engineering work required, but less demanding on resources, procurement and commissioning).

• A higher voltage ratings on each magnet would allow to limit the increasing RMS current, pushing RF acceleration to their limits. Impact of the upgrade on magnets, DC cables, 18kV average power could then be notably reduced. The alternatives would be to reduce Isolde physics program.

Transfer lines:• Pulse option must be studied with TE-MSC to reduce the overall RMS current

(many magnets could then stay in place).

TE EPC