Pow Apo Island (Elec) - Final

download Pow Apo Island (Elec) - Final

of 7

description

program of works

Transcript of Pow Apo Island (Elec) - Final

  • OFFICE OF THE BRGY SUB-PROJECT MANAGEMENT COMMITTEE (BSPMC)Barangay of Apo Island

    Municipality of DauinProvince of Negros Oriental, Region VII

    SUB- PROJECT PROGRAM OF WORK

    Sub-Project Tile : ACQUISITION OF GENERATOR SET 60KVACategory : Public EnterprisePhysical Target : 1 unitTotal Sub-Project Cost Php995,300.00Mode of Implementation : By Community Force Account (CFA)PROJECT DESCRIPTION : Sub-Project Duration 45 Calendar Days (CD)

    Acquisition of GenSet 60KVA w/ Complete Accessories with Freight and Handling Equipment/ Tools Needed None

    Sub-Project Location:Technical Personnel

    DAC/ME

    Sub-Project Site Location is witan Island Brgy. 15KM fromtown proper Electrician

    Item no. Scope of Work ( Direct Cost ) % Wt. Quantity Unit Unit Price Total Amount

    1 98.83% 1.00 Unit 804,500.00 804,500.00

    2 Signages (Project Billboard) 1.17% 1.00 Unit 9,000.00 9,500.00

    Total Direct Cost 100.00 814,000.00

    Breakdown of Estimated Project CostSource of Fund

    TotalKALAHI- Community BLGU MLGU

    CIDSS Grant In-Kind Cash In-Kind Cash In-Kind

    A. Direct CostMaterials 674,583.33 - 10,000.00 - 124,916.67 - 809,500.00 Labor - - 1) Skilled 1,750.00 - - - - - 1,750.00 2) Labor 2,000.00 750.00 - - - - 2,750.00

    Sub-Total ( A ) 678,333.33 750.00 10,000.00 - 124,916.67 - 814,000.00 B. Indirect Cost1. Overhead Cost2. Handtools3 .Pre-engineering4. Engineering Supervision5. Permits & Licenses6. Administrative Cost 15,000.00 - - - 3,000.00 - 18,000.00 7. Material Testing - 8. Treasurer's Bond - - ### - 3,750.00 - 3,750.00

    Sub-Total ( B ) 15,000.00 - - - 6,750.00 - 21,750.00 TOTAL (A + B ) 693,333.33 750.00 10,000.00 - 131,666.67 - 835,750.00

    ADD: Contingency 33,764.67 - - - 6,935.33 - 40,700.00 TOTAL ESTIMATED PROJECT COST 727,098.00 750.00 10,000.00 - 138,602.00 - 876,450.00

    Cost Sharing to TEPC MCC Grant 727,098.00 82.96%

    100.00%LCC Cash 148,602.00 16.95%LCC Inkind 750.00 0.09%

    Add: O and M (Barangay Subsidy yearly) - GRAND TOTAL 727,098.00 750.00 10,000.00 - 138,602.00 - 876,450.00

    Prepared by : Approved by :

    ELSA M. TRUNO FELIX G. SUANService Provider BSPMC Chairperson

    Checked by: Concurred by :

    RODSON R. ESCORA HON. LIBERTY P. RHODESDeputy Area Coordinator Barangay Captain

    Recommending Approval:

    CARMEN A. GAUDIANO HON. NEIL B. CREDOMunicipal Engineer - MCT DAC Noted by: Municipal Mayor

    GEORGE S. ISULATRegional Community Infrastructure Specialist

    Acquisition of GENSET 60 KVA w/ complete accessories with Freight and Handling

  • Republic of the PhilippinesDepartment of Social Welfare and Development

    KALAHI-CIDSS : MCC PROJECTProvince of Negros Oriental

    Municipality of DauinBarangay Apo Island

    : ACQUISITION OF GENERATOR SET 60KVABILL OF QUANTITIES

    DESCRIPTION QUANTITY Unit UNIT COST

    Acquisition of GENSET 60 KVA w/ complete accessories.A. Materials

    1.00 unit 800,000.00

    Sub-TotalB. Labor Electrician 5.00 days 1.00 350.00

    Laborer 5.00 days 2.00 275.00 Sub-Total

    TOTAL FOR ACQUISITION OF GENSET 60 KVA W/ COMPLETE ACCESSORIESSIGNAGES (PROJECT BILLBOARD)A. MaterialsProject Billboard 1.00 UNIT 9,500.00

    TOTAL FOR PROJECT BILLBOARDTOTAL DIRECT COST

    Direct Cost Summary Materials Labor : Skilled Laborer

    Sub-Total ( A )Indirect Cost

    1. ADMINISTRATIVE COSTTOTAL INDIRECT COST FOR ADMINISTRATIVE COST

    2. TREASURER'S BONDTOTAL INDIRECT COST FOR TREASURER'S BOND

    3. CONTINGENCY (5% of DC) TOTAL FOR CONTINGENCY

    TOTAL INDIRECT COSTTOTAL CONSTRUCTION COST

    Prepared by: Checked & Reviewed by:

    ELSA A. TRUNO RODSON R. ESCORA

    No. of Crew/ Labor UNIT RATE /

    RATE PER DAY

    Generator Set 60 KVA w/ complete accessories with Freight Handling

  • MEO Staff Deputy Area Coordinator

  • Republic of the PhilippinesDepartment of Social Welfare and Development

    KALAHI-CIDSS : MCC PROJECTProvince of Negros Oriental

    Municipality of DauinBarangay Apo Island

    : ACQUISITION OF GENERATOR SET 60KVABILL OF QUANTITIES

    UNIT COST TOTAL

    COST SHARINGBLGU

    CASH INKIND

    800,000.00 800,000.00 666,666.67 10,000.00

    800,000.00 666,666.67 - 10,000.00 -

    350.00 1,750.00 1,750.00

    275.00 2,750.00 2,000.00 750.00 4,500.00 3,750.00 750.00 - - 804,500.00 670,416.67 750.00 10,000.00 -

    9,500.00 9,500.00 7,916.67 9,500.00 7,916.67 - - - 814,000.00 678,333.33 750.00 10,000.00 -

    809,500.00 674,583.33 - 10,000.00 -

    1,750.00 1,750.00 - - - 2,750.00 2,000.00 750.00 - -

    814,000.00 678,333.33 750.00 10,000.00 -

    18,000.00 15,000.00 18,000.00 15,000.00 - - - 3,750.00 3,750.00 - - - -

    82.96% 40,700.00 33,764.67 40,700.00 33,764.67 - - - 62,450.00 48,764.67 - - - 876,450.00 727,098.00 750.00 10,000.00 -

    Approved by:

    RODSON R. ESCORA CARMEN A. GAUDIANO FELIX G. SUAN

    TOTAL UNIT COST ADD: FREIGHT AND HANDLING

    COST

    KALAHI GRANT

    COMMUNITY INKIND

  • Deputy Area Coordinator Municipal Engineer BSPMC Chairperson

  • Republic of the PhilippinesDepartment of Social Welfare and Development

    KALAHI-CIDSS : MCC PROJECTProvince of Negros Oriental

    Municipality of DauinBarangay Apo Island

    : ACQUISITION OF GENERATOR SET 60KVABILL OF QUANTITIES

    COST SHARINGSUB-TOTAL LCC

    TOTALMLGUCASH INKIND CASH INKIND

    123,333.33 133,333.33 - 133,333.33 750,000.00

    123,333.33 - 133,333.33 - 133,333.33 750,000.00

    - - 1,750.00

    750.00 750.00 2,750.00 - - - 750.00 750.00 4,500.00 123,333.33 - 133,333.33 750.00 134,083.33 754,500.00

    1,583.33 1,583.33 - 1,583.33 9,500.00 1,583.33 - 1,583.33 - 1,583.33 9,500.00 124,916.67 - 134,916.67 750.00 135,666.67 764,000.00

    124,916.67 - 134,916.67 - 134,916.67 809,500.00 -

    - - - - - 1,750.00 - - - 750.00 750.00 2,750.00

    124,916.67 - 134,916.67 750.00 135,666.67 814,000.00

    3,000.00 18,000.00 3,000.00 - - - - 18,000.00 3,750.00 3,750.00 - 3,750.00 3,750.00 3,750.00 - 3,750.00 - 3,750.00 3,750.00 6,935.33 6,935.33 - 6,935.33 40,700.00 6,935.33 - 6,935.33 - 6,935.33 40,700.00 13,685.33 - 10,685.33 - 10,685.33 62,450.00 138,602.00 - 145,602.00 750.00 146,352.00 876,450.00

    Noted by:

    FELIX G. SUAN GEORGE S. ISULAT

    TOTAL LCC(CASH & INKIND)

  • BSPMC Chairperson RCIS

    POWBOQ