POST-MORTEM ANALYSIS AFTER HIGH POWER OPERATION OF THE TD24 … · 2016. 12. 13. · 3 1....

21
CERN-ACC-2016-0337 01/08/2016 CERN – EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH POST-MORTEM ANALYSIS AFTER HIGH POWER OPERATION OF THE TD24_R05 TESTED IN XBOX_1 Alberto Degiovanni, Rolf Wegner, Nerea Mouriz Irazabal, Markus Aicheler, Ana Pérez Fontenla, Walter Wuensch, Wilfrid Farabolini CERN/Switzerland Abstract The CLIC prototype structure TD24_R05 has been high power tested in Xbox_1 in 2013. This report summarizes all examinations conducted after the high power test including bead-pull measurements, structure cutting, metrology and SEM observations. A synthesis of the various results is then made. The structure developed a hot cell progressively during operation and detuning was observed after the test was complete. The post mortem examination clearly showed a developed standing wave pattern which was explained by the physical deformation of one of the coupler iris. An elevated breakdown count through SEM imaging in the suspected hot cell however could not be confirmed. Neither any particular feature offering an explanation for the observed longitudinal breakdown distribution could be detected. Geneva, Switzerland 01.08.2016 CLIC Note 1070

Transcript of POST-MORTEM ANALYSIS AFTER HIGH POWER OPERATION OF THE TD24 … · 2016. 12. 13. · 3 1....

  • CER

    N-A

    CC

    -201

    6-03

    3701

    /08/

    2016

    CERN – EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH

    POST-MORTEM ANALYSIS AFTER HIGH POWER OPERATION OF

    THE TD24_R05 TESTED IN XBOX_1

    Alberto Degiovanni, Rolf Wegner, Nerea Mouriz Irazabal, Markus Aicheler, Ana Pérez Fontenla,

    Walter Wuensch, Wilfrid Farabolini

    CERN/Switzerland

    Abstract

    The CLIC prototype structure TD24_R05 has been high power tested in Xbox_1 in 2013. This report

    summarizes all examinations conducted after the high power test including bead-pull measurements,

    structure cutting, metrology and SEM observations. A synthesis of the various results is then made. The

    structure developed a hot cell progressively during operation and detuning was observed after the test was

    complete. The post mortem examination clearly showed a developed standing wave pattern which was

    explained by the physical deformation of one of the coupler iris. An elevated breakdown count through SEM imaging in the suspected hot cell however could not be confirmed. Neither any particular feature

    offering an explanation for the observed longitudinal breakdown distribution could be detected.

    Geneva, Switzerland

    01.08.2016

    CLIC – Note – 1070

  • 2

    Contents 1. Introduction ..................................................................................................................................... 3

    2. RF History ......................................................................................................................................... 4

    2.1. Bead-pull measurements and tuning ...................................................................................... 4

    2.2. RF high power test history ....................................................................................................... 4

    3. Sample preparation ......................................................................................................................... 7

    3.1. Cutting operations ................................................................................................................... 7

    3.2. Wire EDM cutting at CERN....................................................................................................... 8

    3.3. Chemical cleaning: Degreasing ..............................................................................................10

    4. Results of characterization ............................................................................................................10

    4.1. RF measurements before cutting ..........................................................................................10

    4.2. Metrology ..............................................................................................................................11

    4.3. Simulations ............................................................................................................................13

    4.4. Scanning Electron Microscope (SEM) observation ................................................................14

    4.4.1. Surface study .................................................................................................................14

    4.4.2. BD counting and distribution .........................................................................................15

    4.4.3. Assessment of bonding quality ......................................................................................17

    4.4.4. Presence of B-field arcs .................................................................................................18

    4.4.5. Thermal fatigue considerations .....................................................................................19

    5. Discussion ......................................................................................................................................19

    5.1. Geometrical deformation and Bead-pull ...............................................................................19

    5.2. Break down number considerations .....................................................................................19

    5.3. Bonding joint and B-field arcs comparison to T18 and TD18 ................................................20

    6. Conclusions ....................................................................................................................................20

  • 3

    1. Introduction The aim of this document is to summarize the post-mortem analysis of the TD24_R05_N1 structure

    tested in X-box1 during the first semester of 2013. This document contains links to presentations,

    detailed documents and data that are relevant for this study. It is also intended as a guideline for

    defining a common protocol for the post high power operation studies on future structures to be

    carried on at CERN and other laboratories to allow direct comparison of results.

    The structure is made of 24 regular cells and 2 matching cells (input and output couplers). The cells

    are numbered from 1 to 26, as shown in Figure 1. The mechanical drawings of the structure can be

    found in https://edms.cern.ch/file/1258457/5/12WDSDVG1.8_R05.pdf .

    Figure 1: Cells nomenclature for the TD24 structure.

    The objective of the post mortem analysis was to quantify the effect of high-gradient operation on the

    structure surface. There was also the specific objective to investigate the origin and characteristics of

    a hot cell. The analysis of the data collected during the high power tests showed a concentration of

    BDs in cell number 5 (see Figure 4 and Figure 5). The hot-cell emerged after approximately two months

    of operation. A three times higher total number of BD spots was expected in this location of the

    structure. Furthermore, the results of bead pull measurements performed after high power operation

    showed a detuning of the coupling cells, indicating a possible mechanical deformation.

    The decision to cut, open and examine the structure was taken in May 2014. The following goals for

    the post-mortem were established:

    1. metrology measurements (for better understanding the detuning effect)

    2. hot cells analysis (BD distribution)

    3. B-arc features (EDMS: 1096980, TD18 KEK/SLAC post mortem observations)

    4. samples (octant/quadrant) for various types of analysis by collaborators

    https://edms.cern.ch/file/1258457/5/12WDSDVG1.8_R05.pdf

  • 4

    More information about the structure can be found in:

    EDMS 1069239 – RF design and parameters (https://edms5.cern.ch/document/1069239/1) EDMS 1258457 – traveller of structure (https://edms.cern.ch/document/1258457/5) EDMS 1239394 – RF tuning (https://edms.cern.ch/document/1239394/1) EDMS 1306038 – first RF analysis after high power op. (https://edms.cern.ch/document/1306038/1)

    2. RF History

    2.1. Bead-pull measurements and tuning After brazing, the structure underwent low power measurements in the lab and tuning. The upper

    plot of Figure 2 shows the results of bead pull measurements performed before and after the tuning

    of the structure. The values of the longitudinal electric field (normalized to the average along the

    structure) at the centre of each accelerating cell measured before (after) tuning are reported in blue

    (red). On the top of them, the results of HFSS simulations are presented (black curve). The red curve

    and the black curve are in good agreement, meaning that the tuning was carried out successfully.

    Another way of looking at the data is the phase advance per cell (bottom plot of Figure 2). The

    structure was tuned to obtain a constant phase advance per cell of 120° (red curve).

    Figure 2: results of bead pull measurements before and after tuning in terms of accelerating field and phase advance at the centre of each cell.

    2.2. RF high power test history The structure was installed in CTF2 (CLIC Test Facility 2) in January 2013 and was tested under high

    power RF for about 5 months. The full history plot of the high power test is shown in Figure 3.

    https://edms5.cern.ch/document/1069239/1https://edms.cern.ch/document/1258457/5https://edms.cern.ch/document/1239394/1https://edms.cern.ch/document/1306038/1

  • 5

    The average accelerating gradient (green curve) calculated during the 50 ns compressed RF pulse, was

    raised smoothly by using a preliminary version of the Xbox1 conditioning algorithm to keep the BDR

    constant (for more details http://accelconf.web.cern.ch/accelconf/IPAC2014/papers/wepme016.pdf)

    Figure 3: Summary history plot of the test of the TD24_R05_N1 structure.

    After the accelerating gradient reached 105 MV/m (light blue curve in Figure 3) the pulse length was

    increased while the power was reduced in order to keep a constant BDR. The BDR evaluated on a

    sliding window of 1 Million pulses is indicated by the magenta line in Figure 3. The red curve indicates

    the cumulated number of interlocks on the structure Reflected power. About 40% of those events

    were detected within 30 seconds from the previous breakdown event (cluster). The blue curve

    indicates the cumulated number of cluster during the whole run.

    Once the conditioning was completed, the structure was tested at constant power level, in order to

    measure BDR dependence with respect to accelerating gradient. By looking at the distribution of the

    BD location inside the structure obtained by timing methods (described in

    https://cds.cern.ch/record/2025952/files/tupp029.pdf) it was noticed that towards the end of the

    conditioning period the structure started to develop a hot spot, in the vicinity of cell number 5.

    Breakdown distribution plots are shown in Figure 4 and Figure 5.

    In total the structure saw about 190 million pulses and accumulated 8000 BDs. From the cell location

    study those BD were not equally distributed along the structure but are expected to be concentrated

    in the first irises, in particular on the two irises forming cell number 5.

    http://accelconf.web.cern.ch/accelconf/IPAC2014/papers/wepme016.pdfhttps://cds.cern.ch/record/2025952/files/tupp029.pdf

  • 6

    Figure 4: Normalized measured BD distribution in the TD24_R05_N1 structure, with respect to record number (from 1 to 140). Each record corresponds to 8 hours of run at 50 Hz. The very high peak values are an artifact of the normalization (if only 2 BDs during a record these cells will result very active).

    Figure 5: BD distribution inside the structure evaluated for the run at different pulse length. The missing bin at cell number 4 is an artefact due the limited time resolution (4 ns) compared to the round trip delay time of the signals in the first cells. Breakdowns physically happening in cell 4 dilute over to the adjacent bins.

  • 7

    3. Sample preparation

    3.1.Cutting operations Different cutting methods were considered and compared, taking into account the type of features to

    be observed and the possible problems for analysis after cutting. Further details can be found in the

    presentation http://indico.cern.ch/event/281511/contribution/0/material/slides/1.pdf

    The following table summarizes the considerations for the different cutting methods.

    Table 1: Various cutting methods and their evaluations

    Cutting method

    Cutting issues Indicated for type…

    Example Metrology check

    BD distribution on iris

    SEM chemical analysis

    Detailed SEM exploration

    Saw

    High deformation High velocity chips and pollution* into the cavity (*The pollution due to cooling liquids could be reduced or even suppressed)

    damped TD18 KEK/SLAC

    no difficult difficult difficult

    2.a Milling- 2.b Turning (and ripping apart)

    Very clean method (for undamped only) Possible small deformation

    undamped T18 KEK/SLAC

    limited yes yes yes

    Wire EDM cut (Electrical Discharge Machining)

    No deformation Sparks in the cutting plane and possible oxidation; Pollution into the cavity (de-ionized water)

    Damped/ undamped

    T18 CERN yes yes no could be affected by pollution

    Abrasive saw slow cutting

    Slow rotation speed implies long time (~days) «clean» method No deformation

    Damped/ undamped

    Never done before Aquistion of suitable machine...

    yes yes maybe maybe

    Water jet cutting

    No deformation Pollution into the cavity

    Damped/ undamped

    Never done before

    yes yes no could be affected by pollution

    The Wire EDM cutting technique was chosen because of its availability at CERN and because it does

    not affect the geometry of the structure. Cutting forces are extremely low, deformation is only

    expected from the release of internal stresses. Furthermore, this method was already used

    successfully for other structures in the past.

    http://indico.cern.ch/event/281511/contribution/0/material/slides/1.pdf

  • 8

    3.2.Wire EDM cutting at CERN The scheme sketched in Figure 6 was proposed and then used for the cutting. In total 9 cuts were

    needed, 2 on the longitudinal plane and 7 on the transverse plane.

    Figure 6: Cutting scheme. The numbers indicate the cuts executed.

    Figure 7 shows the structure after the first transversal cut. The wire has a thickness of 0.35 mm and

    the cutting speed is of the order of 0.1 mm per minute. The structure was brought to the CERN main

    workshop on the 20th of May 2014. The cutting was completed in three days.

    Figure 7: Setup during EDM wire cutting.

    The distances of the cutting planes positions are shown in Figure 8. The values in the top drawing refer

    to the centre of the dimple tuners. A correction of 2.65 mm was applied in order to avoid cutting

  • 9

    through the dimple tuner. The longitudinal cuts were performed on the two perpendicular planes at

    the distances shown in the bottom right drawing.

    Figure 8: Position of the cuts. A correction of 2.65mm was applied to the number shown in order to avoid cutting through the dimple tuners.

  • 10

    3.3.Chemical cleaning: Degreasing After cutting, the different parts of the structure were degreased using the CERN standard process.

    The procedure was completed on 13th of June 2014. Figure 9 shows some pieces of the structure after

    degreasing.

    Figure 9: Pieces of the structure after degreasing.

    4. Results of characterization

    4.1.RF measurements before cutting In order to track the changes due to the RF test the structure underwent low power measurements in

    the lab after high power operations.

    The upper plot of Figure 10 shows the accelerating field value at the centre of each cell (normalized

    to the average along the structure) measured after tuning and after High Power Operation (HPO). On

    the top of these two curves, the results from the simulations with deformation of 10 um and 25 um

    are super-imposed.

    The same comparison was done for the phase advance per cell. The phase advance per cell after high

    power operation shows a strong standing wave pattern (green curve on bottom plot of Figure 10). The

  • 11

    same pattern in phase advance can be obtained in simulation by adding a 10 um tilt deformation in

    the last iris (black).

    Figure 10: measured field profile and phase advance compared to simulations results.

    4.2.Metrology Metrology measurements were performed on one of the two halves of both the input and output

    coupler. Five sections were measured on each iris face. The data obtained from the measurements

    can be found in EDMs (https://edms.cern.ch/document/1391907/3).

    Figure 11 shows the reference axis used for the measurement of the output coupler and the position

    of the five sections on the first iris surface (section A1 to A5).

    Figure 11: definition of axis and of measured section for the output coupler piece.

    https://edms.cern.ch/document/1391907/3

  • 12

    The plots of Figure 12 and Figure 13 summarize the results of the measurements on the output and

    input coupler pieces. The maximum deviation is found in section 1 and section 5 (the ones closer to

    the cutting plane, respectively at 10° and 170°) and for the first iris (named disk A). As shown in Figure

    12, the output iris tilted towards the main body of the structure with a maximum deflection at the tip

    of 0.2 mm, which corresponds to an angular deviation with respect to the vertical plane of about 35

    mrad.

    Figure 12: Output coupler deformation.

    Figure 13: Input coupler deformation.

  • 13

    4.3.Simulations In order to evaluate the effects of the deformations determined by metrology on the RF properties of

    the structure, simulations were performed with HFSS. The nominal design

    [https://edms5.cern.ch/document/1069239/1] has been modified by introducing a tilt in the last iris

    on the output coupler as shown in Figure 14. The tilt is obtained by rotating the iris around an axis

    parallel to the x axis and passing at a height of the bore radius at the centre of the last iris. It measures

    the difference in position of the tip of the iris along the z direction. A tilt of 100 micron is shown as an

    example in Figure 14.

    Figure 14: Geometry used for RF simulations of the deformed structure.

    The field profiles and phase advances of the simulations on the deformed design have been compared

    to the results of the nominal structure, giving the results shown in Figure 15. The upper plot shows

    the normalized value of the magnitude of the axial electric field for 4 different values of tilt of the last

    iris (respectively 0 um, 10 um, 25 um and 50 um). One can notice the peaks in correspondence of the

    centre of the cells. The bottom plot of Figure 15 shows only the values of the peaks.

    The presence of the tilt induces a standing wave pattern which is more evident with the increase in

    deformation.

    https://edms5.cern.ch/document/1069239/1

  • 14

    Figure 15: field profiles obtained from HFSS simulations for different values of tilt of the last iris.

    4.4.Scanning Electron Microscope (SEM) observation SEM observations were made of the samples after cutting. Special focus was put on surface

    modification in the areas affected by breakdown (BD). One aspect of the observation was to look for

    previously observed structures like craters, worm-like features (WLF), B-field arcs, but another was to

    look for new features.

    4.4.1. Surface study Cells surface presented a large variety of craters morphologies consistent with clusters of sparks or

    isolated craters observed previously in post-mortem analysis of other RF structures and DC-spark

    samples. Apart from craters, surface modifications related with breakdown activities were detected

    as brunches of molten material (that could be a prelude of crater or a form of very soft breakdown)

    and WLF. Exemplary SEM images (SE2) of the observed features are included in Figure 16

  • 15

    Figure 16: SEM (SE2) images of sites affected by BD activities at cell #4

    4.4.2. BD counting and distribution In order to compare the hot cell aspect with a “normal” cell, global images composed by thousands of

    high resolution SEM images acquired and assembled with Smart Stitch were performed in various

    neighbouring cells. Affected BD sites were marked manually on the global image highlighting areas

    with higher BD density. Additionally, the number of marks were estimated by image analysis software

    AxioVision. This procedure results in a BD number estimation lower than the real number because of

    close proximity of craters, their overlapping and various other not classified features. An example of

    overview is shown in Figure 17.

  • 16

    Figure 17: BD activity affected sites overview at cell #4 (upstream) and estimated total number (460 sites)

    The estimated number of BD sites in cells #4 and #5 with this procedure was 750 and 790 sites

    respectively. Breakdown affected regions were randomly distributed on the cells and there was not a

    clear correspondence between facing irises in terms of position and number. For cells #22 and #23 the

    extrapolated number (only one cell side counted) is 340 and 390 respectively. Figure 18 shows the BD

    distribution as in Figure 5 overlaid with the above mentioned numbers from the SEM BD counting.

    Figure 18 BD distribution inside the structure similar to Figure 5 but overlaid with SEM breakdown counting (green circles).

    In addition, an analysis of the BD radial distribution was performed as shown in Figure 19. As expected

    from field simulations, no clear relation to max E-area nor to max Sc-area could be established, since

    geometrically by design those two areas are very close. It can however be confirmed that in most

  • 17

    cases the breakdown density is diminishing with increasing distance from the iris. More statistics might

    reveal a finer substructure in radial distribution. However, at this point the analysis has been

    completed for the given accelerating structure.

    Figure 19: study of the BD radial distribution in cell #4 and cell #5

    4.4.3. Assessment of bonding quality The quality of bonding joints was investigated. Additionally, disk number 22 was cut into quadrants,

    allowing for a direct view with the microscope into the area under a better angle (perpendicular to

    the cell wall).

    Non-uniformity in the bonding joint meniscus can be seen in cell 22 as shown in Figure 20. There is

    less non-uniformity than in previous structures (T18 and TD18), possibly due to improvements in the

    bonding design (most notable, the reduced edge radius of 50um). The maximum lengths of areas

    lacking material are 10um as compared to >25um in TD18).

  • 18

    Figure 20: SEM (SE2) images of bonding contact at cell #4 and cell #22

    4.4.4. Presence of B-field arcs In previous structures (T18 and TD18) the presence of features associated to B-field arcs were

    observed. B-field arcs are called features emerging at the former joint region (meniscus) in areas

    where the magnetic fields are highest and hence electrical currents are highest, too. Those features

    form and grow as seen in Figure 21 and might evolve to a state where electrical breakdown is triggered

    in and around those sites, although electric fields are not as high here as in other regions.

    Figure 21: SEM (SE2) images of B-field sites at the bonding plane in cell #23

  • 19

    Initial features of B-field arcs were also found in the current structure TD24 R-05 as shown in Figure

    21, but only in the opened cells at the end of the structure (cell #22 and cell #23), whereas here no

    extensive arcing was associated to these sites.

    More information concerning the SEM observation on structure TD24_R05_N1 can be found in the

    EDMS document 1450676.

    4.4.5. Thermal fatigue considerations No features of thermal fatigue have been observed in the structure. The highest ∆T according to the

    RF design was 40.5K at an average unloaded gradient of 100MV/m. This result confirms the RF

    optimisation choice of lowering the max ∆T below 50K (empirically determined from the TD18 post

    mortem observation) in order to avoid any deterioration due to accumulative thermal cycling effects.

    5. Discussion

    5.1.Geometrical deformation and Bead-pull The bead-pull measurements after high power operation revealed anomalies as presented in the

    results in form of reflections at the output coupler. Simulations indicate that even small deformations

    of the geometry of the output coupler (tilts of 10-20 um) could generate measurable effects on the

    field profile and on the cell-to-cell phase advance.

    Unfortunately it was not possible to find a consistency amongst RF measurements, metrology and

    corresponding simulations. Also information is missing from intermediate steps to determine at which

    stage the changes occurred. Making all of the necessary measurements must be balanced against the

    risk of causing new problems - contamination, scratches, etc. – which could compromise high gradient

    performance. In addition the design of the CLIC baseline ‘compact coupler’ does not have the coupling

    iris which deformed, so this may not be a long term issue.

    5.2.Break down number considerations The seemingly good agreement of counted numbers of breakdowns in cell number 5 and recorded

    from RF signal (within 10% in Figure 18) does not hold true anymore after closer examination. As

    mentioned in the BD distribution plot in Figure 5 the bin of cell number 4 is supposed to be distributed

    to the adjacent bins. Hence the initial < 10% agreement cannot be true. Unfortunately, it is at this

    point impossible make a better estimation. However, the situation towards the end of the structure

    (cell #22 and #23) shows a clear underestimation of the recorded number of breakdowns with respect

    to the counted ones by a factor of 2-3.

    The discrepancy found between the recorded number of breakdowns during high power operation

    and the observed and counted number of breakdowns by microscopy confirms again the difficulty in

    defining exactly what an individual breakdown event looks like: potentially multiple sites affected by

    one recorded breakdown, surface changes without triggering the breakdown recorder or other

    unknown effects. Understanding these processes are object to current research and are key in

    understanding and operating the accelerating structures better.

    https://edms5.cern.ch/document/1450676/1

  • 20

    5.3.Bonding joint and B-field arcs comparison to T18 and TD18 The bonding joint in the current structure shows an improved aspect and a smaller meniscus with

    respect to the previously observed T18 (EDMS: 1211776) and TD18 (EDMS: 1096980) thanks to the

    improvement in the bonding design. The radius at the bonding edge was reduced to 50um and

    resulted in local areas of lack of material smaller than 10um.

    However, the current structure also shows a similar trend in developing features in the bonding joint

    as the formerly observed T18 and TD18. Early stages of features are observed which in the case of the

    TD18 led to features which could be clearly associated with significant electrical breakdown activity.

    However, in the current structure, as well as in the older T18, those features do not show any kind of

    breakdown activity due to lower local magnetic fields and hence less pronounced trigger features.

    6. Conclusions The analysis reported in this document is the last part of a long process that starts from the RF design

    and the manufacturing of the accelerating cells involving several steps that are summarized in Figure

    22.

    Figure 22: Schematic summary of lifecycle of a CLIC prototype accelerating structure

    The problems that are addressed by the proposed analysis can be summarized in two main questions:

    1- Is the geometry of the disks preserved during the bonding?

    2- Are the dimensions of the disks influenced by high power operations?

    https://edms5.cern.ch/document/1211776/1https://edms5.cern.ch/document/1096980/2

  • 21

    The use of non-destructive measurements (such as bead-pull) taken before and after high power

    operation could help in answering such question. Those results, complemented with the destructive

    analysis and microscopy of the inner part of the structure can provide with important feed-back for

    the RF design and the whole manufacturing and handling process, towards a better defined procedure

    better suited for industrialization.

    CLICcoverpage_CLIC_Note_1070Post mortem TD24_R05_N1 --- V71. Introduction2. RF History2.1. Bead-pull measurements and tuning2.2. RF high power test history

    3. Sample preparation3.1. Cutting operations3.2. Wire EDM cutting at CERN3.3. Chemical cleaning: Degreasing

    4. Results of characterization4.1. RF measurements before cutting4.2. Metrology4.3. Simulations4.4. Scanning Electron Microscope (SEM) observation4.4.1. Surface study4.4.2. BD counting and distribution4.4.3. Assessment of bonding quality4.4.4. Presence of B-field arcs4.4.5. Thermal fatigue considerations

    5. Discussion5.1. Geometrical deformation and Bead-pull5.2. Break down number considerations5.3. Bonding joint and B-field arcs comparison to T18 and TD18

    6. Conclusions