Portland Cement NESHAP - Cemtek Environmental · Portland Cement NESHAP ... Quick review of PC MACT...
Transcript of Portland Cement NESHAP - Cemtek Environmental · Portland Cement NESHAP ... Quick review of PC MACT...
Portland Cement NESHAP Emissions Testing / Monitoring
Erick Mirabella
October 1, 2014
General Overview
Acronyms, Definitions, Omissions
Quick review of PC MACT Regulation
Pollutants and Limitations
Source Test Preparation
Engineering & Compliance Tests
Procedures and Methodologies
Opacity Monitoring
Process Data
Questions
Acronyms
NESHAP – National Emissions Standards for Hazardous Air Pollutants
MACT – Maximum Achievable Control Technology
CISWI - Commercial & Industrial Solid Waste Incinerator
NHSM – Non-Hazardous Secondary Materials
CPMS – Continuous Parametric Monitoring System
CEMS – Continuous Emissions Monitoring System
RATA – Relative Accuracy Test Audit
HAP – Hazardous Air Pollutants
Definitions Operating day - any 24-hour period beginning
at 12:00 A.M. during which the kiln operates for any length of time
Open clinker storage pile – any non-enclosed pile left on the ground for more than 3 days
Startup – the time when a kiln first starts firing fuel until it begins producing clinker (feed is introduced into the kiln for 120 minutes or when the feed rate exceeds 60% of capacity)
Shutdown - the cessation of kiln operation that begins when feed to the kiln is halted (when continuous kiln rotation ceases)
Definitions (continued) New source – any source where construction /
reconstruction commenced after May 6, 2009
Malfunction – a condition that is infrequent, sudden, or not reasonably preventable (cannot be caused by poor maintenance or careless operation)
Kiln - a device (including any associated preheater or precalciner devices, inline raw mills, inline coal mills or alkali bypasses) that produces clinker by heating limestone and other materials for subsequent production of Portland cement
Omissions
This presentation does not specifically detail the following areas of the NESHAP: o Specific test locations
Preheater or precalciner devices Inline raw mills & coal mills Clinker coolers Alkali bypasses Commingled sources Open clinker storage piles
o Related regulations & rules CISWI (40 CFR 60, Subparts CCCC & DDDD) Boiler MACT (40 CFR 63, Subpart DDDDD) NSPS (40 CFR Part 60, Subpart F)
Review
NESHAPS - stationary standards covering 187 hazardous air pollutants (40 CFR 63)
Requires use of Maximum Achievable Control Technology (MACT)
Applies to "major sources" that emit or have the potential to emit 10 ton/yr of any single HAP or 25 ton/yr of multiple HAPs.
Minimum stringency requirements are referred to as “floor” standards based on the average emissions from the best performing 12% of existing sources
Chronology
Original rule – June 14, 1999
New rule issued – September 9, 2010
PCA vs. EPA – December 9, 2011
Proposed amendments - July 18, 2012
Final rule effective - February 12, 2013
Implementation (compliance) for existing sources - September 9, 2015
Plants may seek a 1-year extension through the relevant authority, under General Provisions, Section 63.6 (4)(i)(A)
Changes to NESHAP Recent amendments
o Compliance date extension o Revised MACT floor (select limitations) o Reduced testing requirements and change
in monitoring requirements o Sets work practices for clinker piles and
startup / shutdown o Adds other affected sources units such as
clinker coolers & raw material dryers o Clarifies NHSM rule
23 cement units have now been re-classified as CISWI units
Pollutants of Concern
Total Hydrocarbons (THC)
Organic Hazardous Air Pollutants (oHAP)
Particulate Matter (PM)
Hydrochloric Acid (HCl)
Mercury (Hg)
Dioxins & Furans (PCDD/PCDF or D/F)
Total PM and PM10/2.5 - condensible analysis (local permit)
Various surrogates such as SO2
Emissions Limitations
Pollutant Existing Source
Standards New Source Standards
Mercury 55 lb/MM tons clinker a 21 lb/MM tons clinker a
PM 0.07 lb/ton clinker b 0.07 lb/ton clinker b
THC 24 ppmvd @ 7% O2 a, c 24 ppmvd @ 7% O2
a, c
HCl 3 ppmvd @ 7% O2 a 3 ppmvd @ 7% O2 a
Organic HAP (alternative to THC)
12 ppmvd @ 7% O2 d 12 ppmvd @ 7% O2
d
PCDD/PCDF 0.2 ng/dscm @ 7% O2 (TEQ) e 0.2 ng/dscm @ 7% O2 (TEQ) e
a Standards based on a 30 day rolling average.
b Standards based on 3-run test average. c Measured as propane d If the source opts to comply with the THC limit, this standard does not apply. e If the average inlet temperature to the first PM control device during the D/F performance test is 400 °F or less, the limit is changed to 0.4 ng/dscm @ 7% O2 (TEQ)
Preparing for a Source Test Requirements?
Review test schedule & unit conditions (operators must be involved)
Plan for standby (should a contingency day be part of scope?)
No surprise engineering tests
Pre-establish T&M rates
Ensure safety orientation / instructor is pre-scheduled
Plant liaison must be available
Preparation (continued)
Work permits in place
Plant analyzers must be calibrated
Uninterrupted/dedicated circuits available (who is responsible?)
Elevators (proposal probably based on them working, T&M if they’re not)
Ports clean, caps/flanges loosened
Scaffolding / man-lift in place
Communication!!!
Engineering Tests Why are they important?
Compliance dress rehearsal BEFORE the compliance/performance test
Determine effectiveness of new controls
Allows for adjustment
Compares emissions to the new limits
Uncovers unforeseen obstacles
Stratification testing important
Multiple engineering tests may be required
Compliance / RATA Tests
Know the scope of work!
Should you worry? (generally not if engineering tests were performed)
What can go wrong? (everything/nothing)
Timely maintenance and good work practices very important
Qualified contractor with method experience (complicated methods)
Calibrate plant CEMS and ensure gas calibrations are current
Annual RATAs
RATAs for Part 75 must be performed by accredited firm
Nine to twelve RM test runs conducted for direct comparison with plant CEMS o NOx and SO2 RATA (PS 2) o THC RATA (PS 8A) o Flow RATA (PS 6) o HCl RATA (PS-15 or PS-18) o Hg RATA (PS-12A or PS-12B)
RATAs may also be required by 40 CFR 60 and operating permit
Hydrogen Chloride (HCl) Reference method - EPA 321 (FTIR)
3.0 ppmvd @ 7% O2 limit (30-day rolling average following performance testing)
Performance testing every 30 months, RATA every year (when applicable)
Testing on mill on and off conditions
Continuous monitoring required for new and existing kilns (major & minor sources)
HCl alternatives available for sources utilizing scrubbers
HCl RATA
If the facility has an inline raw mill, a RATA test under PS-15 or PS-18 must be conducted with the raw mill on
Span for HCl CEMS is two times the emission standard
Must have a second span for expected higher emissions during “mill off” operation
EPA protocol gases are not yet available for low-level HCl
HCl Alternatives Alternative compliance method for
units that utilize wet scrubbers, dry scrubbers and tray towers o Establish site specific operating
parameters during performance test o Continuously monitor established
operating parameters o Continuous SO2 monitoring possible
Performance testing required every 30 months for resetting all parameters
HCl Alternatives (continued)
Wet scrubbers o Continuously measure and record pressure
drop across the scrubber, liquid flow rate, and pH in ≤ 15-minute intervals
Dry scrubbers (sorbent injection) o Continuously measure and record sorbent
injection rate in ≤ 15-minute intervals
Both scrubber types o Sulfur dioxide (SO2) may be used as an
operating parameter o Annual SO2 RATA requirement
HCl by FTIR (current)
Fourier Transform Infrared Spectroscopy
Hot/wet analyzer with real-time data collection (continuous monitoring)
Can simultaneously measure multiple gases from a single sample stream
Sub-ppm resolution possible
Sample collection – Hot temperatures are critical!
Can replace several CEMS analyzers
Inside an HCl by FTIR
Interferometer
I/O Module
Gas Cell
Temperature Control
Power Brick
Pump
Power Supply
O2 Sensor
Purge Flow Meter
Network Switch
CAI 600 SC Series - Picture curtesy of California Analytical Instruments
Total Hydrocarbons (THC)
Reference method - EPA Method 25A
24 ppmvd @ 7% O2 limit (as propane) based on 30-day rolling average
Initial compliance based on first 30 kiln operating days after rule implementation
Annual testing required on mill & bypass, RATA every year (PS-8A)
Tests at both mill on and off conditions
Flame ionization detection (FID) with continuous monitoring (THC CEMS)
Organic HAP* Alternative Meet oHAP standard by monitoring THC
EPA Methods 18 and/or 320 (FTIR), plus simultaneous EPA 25A tests (FID)
12 ppmvd @ 7% O2 limit (organic HAP)
Triplicate test runs (≥60 minutes) at both mill on and off conditions
Testing required every 30 months for resetting THC monitoring parameter
* Formaldehyde, benzene, toluene, styrene, m-xylene, p-xylene, o-xylene, acetaldehyde, and naphthalene
oHAP (continued) Test run durations can be extended to
adequately capture THC variability over time
Compliance shown as average of 3 test runs performed at both mill on and off conditions based on ratio of time at each operating condition
THC will then be considered a surrogate to oHAP and it must be monitored continuously
oHAP Scaling When oHAP is measured in compliance
at over 75% of the limit: o The site-specific THC parameter will be set
according to average THC measured during the test runs or 75% of standard, whichever is greater
When oHAP is measured at 75% or less of the limit: o Scaling factor for best performers o THC operating parameter is then set
to max 75% of HAP limit (ratio up)
oHAP Scaling Example
HAP test measurement is 6 ppm (value < 9 ppm or 75% of 12-ppm HAP limit)
Plant THC CEMS measures 30 ppm at the same time (concurrent test runs)
Facility can now ratio THC operating parameter up to corresponding HAP limit o 9 ppm * 30 ppm = 6 ppm (X) = 270 ppm o Solve for “X” (270 ppm / 6 ppm) = 45 ppm
45 ppm THC is now the new facility operating limit for oHAP
Particulate Matter (PM) Reference Methods - EPA 5 or 5i (both
measure front-half (filterable) PM only
0.07 lb/ton clinker (existing sources) 0.02 lb/ton clinker (new sources)
Annual compliance based on average of three 60-minute isokinetic test runs
Testing during mill on or off conditions (one dust concentration condition only)
Permit may require PM10/2.5 and/or condensibles (EPA 201A/202)
PM CPMS Continuous “parametric” monitoring
(CPMS) system now required
CPMS uses same PM CEMS hardware, but output measured in milliamps (mA) – antiquated!
Testing every 12 months required to determine and reset CPMS operating limit (based on either mill on or off condition)
30-day rolling average established by identifying average CPMS response based on highest 1-hr PM test
PM Scaling Example PM source test results are 0.03 lb/ton
(value is below 0.0525 lb/ton or 75% of the 0.07-lb/ton limit)
PM CPMS measures 6 mA with a zero instrument air reading of 4 mA the same time
Facility can scale mA operating parameter up to the corresponding reading o 4 + (0.0525 / (0.03 / (6-4))) = 7.5 mA
o 7.5 mA is new facility operating limit for PM
Mercury (Hg)
Reference method - EPA 30B (paired sorbent traps) or EPA 29 (wet-isokinetic)
55 lb/MM ton clinker (existing sources) 21 lb/MM ton clinker (new sources)
Limits based on 30-day rolling average following initial performance testing
Testing required annually until Hg levels are below MDL for 2 consecutive years (moved to every 30 months after that)
Testing during mill on condition only
Hg (continued)
Hg CEMS - CVAFS or sorbent trap-based system (must include flow rate monitor)
Hg protocol gases not yet available, but Hg generators are available now
Hg typically higher during mill-off conditions due to reduced adsorption capacity of raw mill particles in the mill
Efficient PM controls can remove some particle-bound Hg, but most Hg is emitted in vapor form
Hg RATA
Annual RATA – mill on condition only
Hg CEMS required for: o New and existing kilns o Major sources
Two CEMS options: • Continuous mercury CEMS – PS 12A • Sorbent trap CEMS – PS 12B
If the facility has an inline raw mill, RATA testing under PS12A, PS12B, or Procedure 5 must be conducted with the raw mill on
Hg RATA (continued) Span for Mercury CEMS is two times the
emission standard
Must have a second span for expected higher emissions with “mill off” operation.
A RATA is not required for “mill off” operation
Speciation of Hg Emissions
45%
40%
10% 5%
Raw Materials / Fuel Hg Contribution
Limestone Ash Coal Other
6%
36% 58%
Raw Mill On
Particlebound
Oxidized
Elemental
6%
78%
16%
Raw Mill Off
Mercury Analysis On-site vs. Off-site
On-site Hg analysis o Same-day turnaround for RATA determination o Higher DLs could mean longer test runs o Thermal analysis destroys sample (a bad
analysis means a re-test)
Off-site Hg analysis o 1 or 2-day turnaround (best case) o Must ship samples (time & expense) o Lower DLs could mean shorter test runs o Better QA/QC, especially for speciation
Hg Sorbent Train (new) EPA 30B Hg (schematic)
Stack Wall Note: FAMS speciation train is optional.
Heated Probe Assembly
Teflon tubing to control boxTeflon tubing to control box
Teflon tubing to control box
Control Box
RotameterTeflon impinger
with desiccant Exhaust
Dry Gas MeterPump
FAMS
TOTAL Hg
TOTAL Hg
TOTALIZER
Dioxin/Furan (PCDD/PCDF)
Reference Method - EPA 23 (isokinetic)
0.20 ng/dscm @ 7% O2 emissions limit TEQ (APCD above 400 °F)
0.40 ng/dscm @ 7% O2 emissions limit TEQ (APCD 400 °F and below)
Testing required every 30 months
Triplicate test runs required on both mill on and mill off conditions
Can be combined with EPA Method 5 PM sampling train
PCDD/PCDF (continued)
With careful planning/approval, results can be used to update California AB2588 emissions inventory
Concentrations generally based on chlorine, organic precursor (from raw feed), residence time at temperature
Note: Lower APCD temps do not always lower PCDD/PCDF emissions since the concentrations of chlorinated VOC still play a role
Opacity Monitoring
Requirement removed for kilns and clinker coolers at major sources after Sept. 9, 2015
10% Opacity limit for raw material areas, finished product storage bins, conveying system transfer points, bagging systems, bulk loading/unloading systems, raw and finish mills, and raw materials dryers
The Rule allows for demonstration of continuous compliance with either a COMS or Method 22 observations
Opacity (continued)
If Visible Emissions (VE) are observed during any EPA Method 22 performance test, a 30-minute Method 9 must be completed, beginning within 1 hour of the observance of the VE (63.150 (iν))
Any totally enclosed conveying system transfer point, regardless of the location of the transfer, is NOT required to conduct a Method 22 (63.150 (ν))
Process Data
APCD temperatures
Various feed rates
COMS, CMS & CPMS data
CEMS data including criteria pollutants (if necessary), Hg, THC and HCl
Other possibilities – SO2, scrubber solution pH, pressure drop across scrubber, flow rates, sorbent injection rates, etc.