Portable Classroom Controls Project Chuck Collins RCM Meeting April 27, 2007.
-
Upload
kathryn-buckley -
Category
Documents
-
view
217 -
download
3
Transcript of Portable Classroom Controls Project Chuck Collins RCM Meeting April 27, 2007.
The portable classroom
Time clock
User control
Electric heating
No scheduling capability
Electric heat pumps
No A/C
Exhaust fans
Limited windows
No demand charges
Part of PSE rebate program for schools
• List of eligible equipment• Variable rebate amounts
depending on which pieces of equipment installed
• Application for rebate• Rebate amount is close to
cost of controller
Portable classroom control project process
• Project research (cost/benefits, other data)• Make pitch to organization• Rebate application, work with PSE early• Find a contractor to do the work• Commence with project• Set up temperature set-points, times, etc• Verify avoided costs, consumption• Receive rebate
The Project
• 127 portable classrooms• Upgraded thermostat controller• Connected to District DDC through
network• Control setpoints via DDC system• Can verify temps, setpoints, trends, etc• Ability to remotely shut down all portables• Scheduling, snow day, etc
Avoided electricity calculations
• Mar 2005– Cost - $75.22– kWh – 942.26
• Mar 2006– Cost - $182.72– kWh – 2,391.50
• Mar 2007– Cost - $62.97– kWh – 766.45
942.26 + 2391.50 2
= 1,666.9 – 766.45 =
900 kWh per yearor 54%
Avoided cost calculations
• Mar 2005– Cost - $75.22– kWh – 942.26
• Mar 2006– Cost - $182.72– kWh – 2,391.50
• Mar 2007– Cost - $62.97– kWh – 766.45
$75.22 + $182.72 2
= $128.97 - $62.97 =
$66.00 per yearor 51%!
Avoided cost survey• 18 portables at various sites (14% of total)• Used PSE’s Energy Interval Service for data• Total electricity cost March 2006: $2,468.39 • Total electricity cost March 2007: $1,854.49• Avoided monthly cost for sample: $613.90• x 10 months: $6,139.00 annual avoided cost• / 18 portables = $341.05 per portable, per year• x 127 portables = $43,314.05 (estimated annual
avoided cost, based on survey)
Total cost/benefit
• Estimated annual savings: $43,314
• Total project cost: $110,642
• Simple payback (no rebate): 2.6 years
• PSE rebate: $29,750
• Actual project cost: $110,642 - $29,750 =$80,892
• Simple payback (with rebate): 1.9 years