Pollution Prevention Control Act 1999 Wales) … Regulations 2010 (as amended) ... cement products...

21
Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 (as amended) REF 08_00014_PPCB Operator Besblock Ltd Installation Address Site 1 Halesfield 22 Telford Shropshire TF7 4NF Grid Reference NGR SJ 712 052 Registered Office Heslop Halesfield 21 Telford Shropshire TF7 4NF Company Number 1059042 Besblock Ltd is hereby permitted by Telford & Wrekin Council to carry on a cement products activity under Section 3.1 of Schedule 1 Part 2 the Environmental Permitting (England & Wales) Regulations 2010 (as amended), and other activities as listed and described below within the installation boundary marked red on the attached plan on page 12, and in accordance with the following conditions. Provenance Relevant Dates Date Application Made (Deemed application) 1 st April 2003 Date ‘Duly Made’ 27 th May 2003 Date Permit First Issued 1 st August 2003 Date of Variations 13/12/2010 Date of Latest Variation 13/12/2010 This permit consists of 14 numbered pages

Transcript of Pollution Prevention Control Act 1999 Wales) … Regulations 2010 (as amended) ... cement products...

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Operator Besblock Ltd Installation Address

Site 1 Halesfield 22 Telford Shropshire TF7 4NF

Grid Reference NGR SJ 712 052 Registered Office Heslop

Halesfield 21 Telford Shropshire TF7 4NF

Company Number 1059042 Besblock Ltd is hereby permitted by Telford & Wrekin Council to carry on a cement products activity under Section 3.1 of Schedule 1 Part 2 the Environmental Permitting (England & Wales) Regulations 2010 (as amended), and other activities as listed and described below within the installation boundary marked red on the attached plan on page 12, and in accordance with the following conditions. Provenance Relevant Dates Date Application Made (Deemed application)

1st April 2003

Date ‘Duly Made’ 27th May 2003 Date Permit First Issued 1st August 2003 Date of Variations 13/12/2010 Date of Latest Variation 13/12/2010

This permit consists of 14 numbered pages

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Description of the Installation The site manufactures concrete building products, using an automated batching plant at the location noted in the site location plan in the Appendix. Cementitious materials are delivered by bulk road tankers which blow air entrained material into one of two storage silos. Aggregates are delivered in bulk by lorry and tipped into storage bays. Aggregates are transferred as necessary from the storage bays to the load hopper by mechanical loading shovel. The aggregates are then transferred by an inclined and enclosed conveyor to the respective storage bins within the main process building. Aggregates are proportioned into a weigh hopper sited underneath the storage bins and taken by skip hoist to high level for discharge into the enclosed mixer. Cementitious materials are transferred by enclosed screw conveyor to the cement weigh batcher. Cementitious materials and aggregates are discharged into the mixer along with water. The concrete batch is transferred into a wet storage hopper and from there into the feed drawer of the block press. The products are vibrated and, by hydraulic and pneumatic actions, the “green” blocks are formed. The blocks are transported to the curing ovens and are subjected to overnight steam curing and are then placed into open yard storage. The curing ovens at site 1 are fired by oil. Once blocks are cured, some of them are subjected to further processing, called ‘splitting’, in order to create a decorative rough finish to the product. The splitting activity can also involve the use of grit blasting and size reduction techniques to achieve the desired end. Curing blocks are packaged and stored in the open yard storage areas.

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Raw Materials used: The following table lists the quantities of raw materials used on an annual basis within the permitted installation. Any increases of more than 25% in materials would constitute a substantial change to the permitted activities and the operator would be required to notify the regulator and apply for a variation to the permit. Table 1 – raw material usage Raw Material Quantity

(tonnes/ annum)

Storage Type Abatement

Sand 14000 bunker Water suppression Aggregates (Inc bottom Ash)

41000 bunker Water suppression

Cement 3750 silo Bagfilter Water 4851 mains Not Required Additives 12 IBC containers Not Required

Activity 1 – Concrete Block Formation For the avoidance of doubt, Schedule 1, section 3.1 of the Environmental Permitting (England & Wales) Regulations 2010 (as amended) lists use of bulk cement and the creation of cement products under Part B of that section. The activity of creating concrete blocks incorporates: the storage of raw materials, (namely sand, aggregate, cement, PFA), the transportation and loading/unloading of any of these materials, the mixing and batching of these materials, the formation into finished products, the curing of these products, the storage and disposal of any wastes arising from the activity, any plant, machinery, or equipment designed to prevent pollutant

emissions to the environment. Activity 2 – Block Splitting For the avoidance of doubt, Schedule 1, section 3.5 of the Environmental Permitting (England & Wales) Regulations 2010 (as amended) lists the size reduction of brick or concrete products under Part B of that section. The activity of block splitting incorporates: the handling, movement and storage of cured concrete blocks, the use of the block splitting machinery, grit blasting of the concrete blocks,

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

handling, storage and transportation of any wastes arising from the activity,

any plant, machinery, or equipment designed to prevent pollutant emissions to the environment.

For the purpose of the issue of this permit, Activity 1 – Concrete Block formation and Activity 2 – Block Splitting are noted to be both directly associated and technically connected and, for the purpose of regulation, both activities are regulated under this permit. List of machinery within the Installation The following Table 2 contains a list of all machinery used within the installation along with the identified emission points to atmosphere: Table 2 – Machinery used within the installation

Machinery Machinery reference number

Pollutants Abatement plant

Block Press Columbia 16

particulate Not Applicable

Cuber None particulate Not Applicable

Curing Oven None steam Not Applicable

Splitting Machine 1-88997-05-96 particulate Bagfilter

Shotblast Machine 100228 particulate Bagfilter

Silo Storage 45396 particulate Bagfilter

Silo Storage 45397 particulate Bagfilter

Masonry Saw H01367/YO3 particulate Not Applicable

Oil Fired Boiler A/JTC/4/2760 By products of combustion (NOX & COX)

Not Applicable

Clamp Trucks/ Forklift trucks

Lansing 1 Lansing 2

Diesel exhaust(NOX, COX and SOX)

regular maintenance as per manufacturers recommendations

Hermetically sealed Trichloroethylene degreasing unit

Full Hermetic Containment

Degreasing Tank

Fugitive emissions only

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Table 3 below identifies the abatement plant or production equipment that discharges to atmosphere via an emission stack. Emission stacks that emit direct to atmosphere are unabated emission points. Emissions that are vented internally to the installation are not listed and should be assumed to be fugitive emissions.

Table 3 Abatement plant and Emissions

Plant or Equipment used

Abatement Type

Machine reference numbers

Emission Points

Pollutants

Retort furnaces No’s F11 to F16, F20, F21

Water Trap Exhaust Odour Trap

1 Ammonia, TPM

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Permit Conditions Permitted Plant and Machinery 1 The permissible plant or equipment to be used within the installation shall be that mentioned in Table 2. No other plant or equipment shall be utilised without the written consent of the regulator. 1.2 Plant or equipment concerned with the prevention of emissions to atmosphere shall consist of that mentioned in Table 2 & 3. No other abatement plant shall be used except where a formal application, in writing, has been submitted to, and approved by, the regulator. 1.3 If there is any intention to change any aspect of the prescribed process from the description of the process at the beginning of this authorisation, or any other aspect which may affect the substances or concentration of substances being emitted to air, the enforcing authority shall be notified of the proposed changes at least 4 weeks before the changes take place. Emission Limits 2.0 There shall be no visible emissions of dust from the installation that cross the designated installation boundary marked on plan 08_00014_PPCB /1 in the Appendix. 2.1 There shall be no visible emission of dust from any part of any silo or transfer line during bulk delivery. 2.2 There shall be no visible emission of dust from aggregate stockpiles and storage bays nor from the handling or transport of aggregates. There shall be no visible emission of dust from any yard surface. 2.3 Emissions from the installation, other than steam or condensed water vapour, shall be free from persistent mist and free from persistent fume. 2.4 Emissions from any combustion processes including forklift and clamp

truck vehicles shall not exceed the equivalent of Ringlemann shade 1 as described in British Standard B.S.2742:1969 at any time.

2.5 The operator shall prepare a list of all emission points, and related pollutant emissions to atmosphere based on Table 2 (above). The operator shall provide details (where known) of the emissions of those pollutants to atmosphere as a result of any sampling that may be carried out (see condition 3.10). Where sampling is not carried out, the operator shall prepare an estimate of the emissions to atmosphere using data collected, based on the following criteria:

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Bagfilters are emitting particulate at a rate of 10mgm-3 during hours of

operation No correction for atmospheric pressure or water vapour need be made The results shall be tabulated and submitted in Microsoft Excel format and shall be sent to the following email address (or another to be specified by the regulator): [email protected] Such information shall be submitted as and when requested by the regulator. 2.6 The final efflux velocity of all emissions to air from any contained source must not be less than 15 m/sec. 2.7 Emission stacks shall discharge vertically upwards without restriction from caps cowls or other restrictive plates. Emission Control 3.1 The installation shall be observed for dust emissions at least once per day, or more often as may be prescribed in writing by the enforcing authority, from a point providing an unimpeded view of the emission points listed in Table 2 (above). In the event of one or more visible emissions being observed, immediate action shall be taken to determine the cause of the emission, and action shall be taken to abate the emission. The results of the observations shall be recorded in the logbook (required to be kept by condition (3.6), along with details of remedial action taken. The observations shall be undertaken whilst the activity is in operation. 3.2 Visual assessments of emissions from arrestment plant serving both silos shall be undertaken during bulk deliveries to silos during the initial and final 5 minutes of delivery to each silo. The results of the assessment, and the start and finish times of deliveries shall be recorded in the logbook in accordance with Condition (3.6). The following additional details are required to be recorded for each delivery to storage silos: Driver details Vehicle details (registration number) Amount of material delivered 3.3 In the event of emissions of dust being visible beyond the installation boundary, the process shall be stopped and remedial action carried out immediately. The regulator shall be notified as soon as is reasonably practicable and informed of the remedial action to be carried out. The process shall not be restarted until the proposed remedial action has been completed.

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

3.4 Any visible emission of dust from any part of any silo or transfer line during bulk delivery shall be recorded in accordance with Condition (3.6). The cause of the emission shall be investigated immediately and be rectified before further deliveries to the silos take place. 3.5 External hard surfaced roadways, yards and aggregate storage bays shall be inspected daily and the results of the inspection shall be recorded in the logbook in accordance with Condition (3.6). Where build-up of dusty or cementitious materials is noted these shall be removed in accordance with the cleaning schedule required to be supplied by condition 4.6). Any damage to the hard surface roadways, yards, or storage bays shall be repaired within 7 days and the details of the repair recorded in the logbook in accordance with Condition (3.6). 3.6 A logbook shall be established and maintained which contains a record of all observations made in accordance with conditions (3.1), (3.2), (3.4), (3.5), (3.7), and (3.8). The records shall include the time and date of the observations, the location from which the observations were made, the wind direction, the weather conditions, the likely source of the emissions to air, details of any corrective action taken, and the name and position within the Company of the person undertaking the observations. The logbook shall also hold details required by other permit conditions where noted. The logbook shall be kept available for inspection by the regulator at installation, and the records shall be retained for at least two years. 3.7 The bagfilter units listed in Table 2 shall be visually inspected on the following schedule of inspection: For reverse air jet filters once per month For mechanical shakers once per week For manual shakers once per day The visual inspection shall include inspection of the filter medium, the pressure relief valve and the point of outlet. The outlet shall be checked for signs that emissions have occurred. The equipment shall also be checked for defects in the air flow or the cam shakers. If emissions or defects are detected then corrective action shall be taken promptly and before another delivery takes place. Any failure of the silo management system (e.g. high level alarms, filter, pressure relief valve) shall lead to full investigation of the operation of the plant and equipment.

Details of the inspections shall be recorded in the logbook required to be kept in accordance with condition (3.6)

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

3.8 Upon receipt, in writing, of a written request from the enforcing authority, the operator shall arrange for deposition monitoring to be carried out at locations to be agreed with the enforcing authority. The duration, methodology, and extent of such monitoring to be agreed with the enforcing authority prior to undertaking the work. This condition remains suspended until such time as the enforcing authority activates it by the issue of a request in writing. Details of any such monitoring shall be submitted to the regulator within 2 weeks of completion of the monitoring and recorded within the logbook required to be kept under condition (3.6). 3.9 The operator shall prepare a written plan for dealing with failure of key abatement plant listed in Table 2. The plan shall deal with the emergency procedures to be undertaken in order to prevent emissions to atmosphere, spillage containment procedures, and repair activities likely to be required. The plan shall be submitted to the regulator within 3 months of issue of this permit and shall be updated from time to time as may be necessary to account for changes in procedure or changes to arrestment plant. Note, arrestment plant cannot be changed without prior notification of the regulator as required by condition (1.1). 3.10 Emissions from the curing oven shall be monitored for concentrations of the following substances: (i) Total Particulate Matter (ii) Oxides of Nitrogen (iii) Oxides of Sulphur All sampling to be carried out to be a recognised method of sampling to be agreed with the regulator prior to sampling takes place. All results to be quoted in terms of mgm-3 and annual mass emission in kg. Results for all substances to be corrected to 101.4kPa and 273K without correction for water vapour. Sampling shall not be required where the quantity of fuel used and a certified fuel analysis certificate is submitted to the regulator that includes the sulphur content of the fuel used. 3.11 Any malfunction which results in emissions to atmosphere which are likely to cause an adverse effect on the local community shall be reported to the enforcing authority immediately, and a record shall be made of the incident within the logbook required by condition (3.6). 3.12 Spillages of finely divided materials outside the designated storage area shall be cleaned up immediately.

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Spillages of finely divided or powdery materials shall be removed by means of vacuum cleaning using an industrial grade vacuum cleaner or by wet cleaning methods, dry sweeping methods shall not be permitted. Waste collected shall be placed in sealed containers or a covered skip to prevent wind entrainment. Bulk Materials Storage & Handling 4.0 The aggregate conveyor shall be fully enclosed. The conveyor shall be fitted with a cleaning device at the head drum return and shall deposit scraped material back into the aggregate bin. 4.1 Aggregates shall be delivered only into the storage bay areas marked on the plan 08_00014_PPCB/1 and nowhere else within the installation. Aggregate noted to be outside the storage bay areas shall be considered a spillage and shall be dealt with in accordance with condition (4.6). 4.2 The aggregate storage area shall be served by a water suppression system capable of dampening the entire storage area as noted in condition (4.1) above. The water suppression system shall be tested at least once per week to determine effective operation, and the results recorded in the logbook required to be kept by condition (3.6). In the event that the test indicates a fault with the water suppression system, this shall be noted in the logbook and repaired within 7 days. 4.3 All cementitious materials shall only be delivered to the silos and only then using the procedure for silo delivery outlined in condition (4.5) below. 4.4 A locking device shall be securely attached to each coupling of every silo supply pipe such that delivery cannot take place without removal of the device. The unlocking mechanism shall be held by named person or persons who shall be responsible for securely locking and unlocking the device before and after each delivery.

Each supply pipe shall be clearly marked with the silo details and the nature of the material contained therein.

No discharge shall take place to any silo without the express permission of the named person (mentioned above) and discharge shall only take place when the driver of the vehicle discharging to the silo has been advised of the procedure to be followed.

4.5 The following procedure shall be used for the delivery of materials to silo: (a) The named person (noted in condition (4.4) above) shall be notified on the arrival of a bulk delivery.

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

(b) The named person shall confirm that there is sufficient capacity in the silo to accept the quantity to be delivered.

(c) The named person shall bring to the attention of the delivery driver a sign clearly displayed and legible at the point of delivery stating the delivery procedure. A copy of the procedure shall be forwarded to the regulator within one month of the date of this permit.

(d) Only the named person shall remove the locking device to the cement transfer line. (e) The named person shall start the fan assisted reverse air jet filters running in accordance with the manufacturer’s instructions. (f) The driver and the named person shall inspect the delivery lines and check them for signs of damage or wear, the driver shall connect the delivery lines and the driver and the named person shall check the connections are properly made.

(g) Only after conditions (d) to (f) have been complied with shall delivery commence.

(h) Air flows into the silo during delivery from tankers shall be such as to prevent venting of air to silos at a rate that is likely to result in over pressurisation of the silos or cause a dust emission.

(i) Where any emissions of particulate matter are visible from ducting, pipework, the pressure relief valve, dust arrestment plant or any other part of the plant, or the delivery vehicle during silo filling, the operation shall cease; and the cause of the problem shall be rectified prior to any delivery taking place.

(j) Where any alarm sounds, or the level indicator on the silo suggests the silo is full, delivery shall cease immediately.

4.6 Deliveries to silos from road vehicles shall only be made using tankers with an on-board (truck mounted) relief valve and filtration system.

4.7 Waste products likely to produce dust arising from the activities within the installation shall be placed into covered containers. Any waste materials not placed within covered containers shall be considered to be spillages and shall be dealt with as per condition (4.7) above. 4.8 The installation buildings shall be maintained in a dust tight condition, holes or breaks within the fabric of the building shall be repaired as soon as is practicable such that visible emissions of dust are not noticeable from the building. Cleaning & Maintenance 5.0 Regular cleaning and effective preventative maintenance in accordance with the manufacturer's instructions shall be employed on all plant

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

and equipment concerned with the emission, capture, transport and control of emissions to atmosphere. The cleaning and maintenance schedule shall also include the hard surfaced areas and the installation buildings. Cleaning and maintenance schedules shall be submitted to the enforcing authority before 31.10.03. Such cleaning and maintenance procedures shall be updated from time to time as may be necessary to account for changes in working practice or plant and machinery or solvents used. If the schedules change, a copy of the new schedules shall submitted to the enforcing authority within 7 working days from changes being made.

Spares and consumables for authorised plant, in particular, those subject to continual wear, shall be held on site, or shall be available at short notice. Authorised plant and equipment shall not be used unless that plant is capable of working in accordance with the conditions of this permit. Training 5.1 Staff at all levels shall receive the necessary formal training and instruction in their duties relating to control of the process and emissions to air. Records shall be kept which detail all relevant training provided to staff, the records shall be made available for inspection by an authorised officer from the enforcing authority. Records of training shall be retained for two years. In relation to this permit, any reference to the ‘Local Authority’ or ‘the regulator’ shall mean the Borough of Telford Wrekin. Any information required by this authorisation to be sent to the Local Authority shall be sent to: Public Protection Borough of Telford and Wrekin Darby House P.O. Box 214 Telford, TF3 4LE Signed....................................... Date.................................................. SCIENTIFIC OFFICER Authorised by the Borough of Telford and Wrekin to sign in that behalf Public Protection Borough of Telford and Wrekin P.O. Box 214 Civic Offices Telford TF3 4LE

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Plan 08/0014/PPCB/1 – Installation Boundary

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Plan 08/00014/PPCB/2 – Raw material and waste storage areas

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Glossary of Terms/Definitions: Activity One or more stationary technical units falling within the

defined sections of the Schedule 1 of the Environmental Permitting (England and Wales) Regulations 2007

Coating Means a preparation, including all the organic solvents or

preparations containing organic solvents necessary for its proper application, which is used in a vehicle refinishing activity to spray onto a motor vehicle.

ELV Emission Limit Values, those values stipulated in the SED

or in guidance for emission of particular pollutants to atmosphere.

Halogenated shall mean an organic solvent which contains at least one Organic solvent atom of bromine, chlorine, fluorine or iodine per molecule Installation One or more stationary technical units comprising at least

one activity or activities falling within the description of Schedule 1 of the Environmental Permitting (England and Wales) Regulations 2007 within a defined area.

LEV Local Exhaust Ventilation – ducting and hoods normally

associated with small uncontained plant or equipment. Organic solvent Means any VOC which is used alone or in combination

with other agents, and without undergoing a chemical change, to dissolve raw materials, products or waste materials, or is used as a cleaning agent to dissolve contaminants, or as a dissolver, or as a dispersion medium, or as a viscosity adjuster, or as a surface tension adjuster, or a plasticiser, or as a preservative.

Organic compound Means any compound containing at least the element

carbon and one or more of hydrogen, halogens, oxygen, sulphur, phosphorus, silicon or nitrogen, with the exception of carbon oxides and inorganic carbonates and bicarbonates.

EPR Environmental Permitting Regulations , the new pollution

control regime replacing that under PPC. Regulator Means the Environment Team of the Telford & Wrekin

Council. When contacting the regulator it is not sufficient to contact any other part of the council other

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

than the Pollution Control Section at the address

specified in the additional notes or at the telephone numbers provided.

R-Phrase Means the same as in Directive 67/548/EEC as follows:

Designated risk phrase the designation or label given to a coating or preparation (as a whole). The mere fact that a preparation or coating contains r-phase chemicals does not in itself always make a material r-phrase.

SED Solvent Emissions Directive or ‘COUNCIL DIRECTIVE

1999/13/EC of 11 March 1999 on the limitation of emissions of volatile organic compounds due to the use of organic solvents in certain activities and installations’.

STU Stationary Technical Unit shall have the same meaning

as in the Pollution Prevention and Control Regulations, but in summary shall mean, one machine used for the purpose of printing on flexible packaging or one machine used in connection with that activity, e.g. an RTO. There must be at least 1 STU per activity, but it is possible to have multiple STU’s still comprising only one activity.

Volatile Organic Shall mean any organic compound having at 293,15 K a Compound (VOC) vapour pressure of 0.01 kPa or more, or having a

corresponding volatility under the particular conditions of use. For the purpose of the Solvents Emissions Directive, the fraction of creosote which exceeds this value of vapour pressure at 293.15 K shall be considered as a VOC.

Cyclone An inertial gas cleaning device, which separates dust

from the gas stream when the direction of the gas flow is changed and the dust continues in the original direction

R Phrases Definition

R40 Limited evidence of carcinogenic effects

R45 May cause cancer

R46 May cause heritable genetic damage

R49 May cause cancer by inhalation

R60 May impair fertility

R61 May cause harm to the unborn

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

by virtue of its inertia and is deposited on a collection

surface / catch pot. The inlet gas is channeled into a spiral flow. Centripetal forces operating in the spiral provide the change of direction and the larger particles

above a critical mass will be deposited on the cyclone

walls. Bag filter These are fabric filters and are comprised of a filter

medium, usually manufactured in the form of bags, through which material over a certain size cannot pass. There are three types: mechanical shakedown, reverse air jet and pulse jet. Bags are capable of filtration of finer particles than cyclones, but do not perform well with wet particulate such as wood with a moisture content > 20% (i.e. they clog up).

Indicative Monitoring Monitoring which measures the performance of the

abatement plant, rather than the quantity of dust etc emitted. In the case of bag filtration, this is normally achieved by alarming the pressure drop across the abatement plant, so that an alarm is set off should a bag / sleeve split.

Ringelmann Chart A chart set by British Standard B.S.2742:1969 which

divides smoke into 4 shades by colour. Shades 2 to 3 are dark and 4 is black.

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

ADDITONAL NOTES

These notes do not comprise part of the permit, but contain guidance relevant to it. Inspections Regular inspections will be made by officers of Telford & Wrekin Council (without prior notice), in order to check and ensure full compliance with this permit. BAT (Best Available Techniques) Article 2(11) of the IPPC Directive defines “best available techniques” as follows: “the most effective and advanced stage in the development of activities and their methods of operation which indicates the practical suitability of particular techniques for providing in principle the basis for emission limit values designed to prevent, and where that is not practicable, generally to reduce emissions and the impact on the environment as a whole”.

- “techniques” shall include both the technology used and the way in which the installation is designed, built, maintained, operated and decommissioned,

- “available” techniques shall mean those developed on a scale which allows implementation in the relevant industrial sector , under economically and technically viable conditions, taking into consideration the costs and advantages, whether or not the techniques are used or produced inside the Member State in question, as long as they are reasonably accessible to the operator,

- “best” shall mean most effective in achieving a high general level of protection if the environment as a whole.

In determining the best available techniques, special consideration should be given to the items listed in Annex IV of the Directive. Health and Safety at Work and Other Statutory Requirements Compliance with this permit does not necessarily infer compliance with any other legislation.

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Other Statutory requirements This permit, in that it regulated only air pollution matters, does not absolve you of the responsibility of any other statutory requirement, such as any need to obtain planning permission, hazardous substances consent or Building Regulations approval from the Council. Discharge consents from the local sewerage undertaker or a waste disposal licence from the Environment Agency may still be required as will compliance with health and safety legislation. Notification of Operation Changes The operator may be liable to prosecution if they operate otherwise than in accordance with the conditions and plant described in this permit. The operator should contact the regulator to discuss any proposed changes.

Enforcement The operator will be liable to enforcement action where: - 1. the operator fails to comply with or contravenes any permit condition; 2. a change is made to the installation operation without prior notification of

the change to the regulator; 3. intentional false entries are made in any record required to be kept under

the conditions of the permit;

4. a false or misleading statement is made. Any enforcement action is taken in accordance with the regulator’s enforcement policy. http://www.telford.gov.uk/NR/rdonlyres/240C3F4A-8E36-4C12-8311-E4E57A3DF8CC/26214/MicrosoftWordEnvironmentalHealthandWellbeingEnforc.pdf Annual Subsistence Charge A subsistence charge is payable on the 1st April each year. An invoice will be issued by the regulator providing further details of how to pay. The charges are based on a risk based system. Details of the risk assessment can be found at http://www.defra.gov.uk/environment/ppc/localauth/fees-risk/risk.htm

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Appeal against Regulatory Action The operator can appeal against regulatory action by the regulator to the Secretary of State for Environment, Food & Rural Affairs. Appeals must be sent to the Secretary of State on a form found at http://www.planning-inspectorate.gov.uk/pins/environment/environment/environmental_appeals/environmental_permitting_appeal_form.pdf Guidance on the appeal procedure can be found at http://www.planning-inspectorate.gov.uk/pins/environment/environment/environmental_appeals/environmental_permitting_guidance_notes.pdf There are time limits for making an appeal as follows: a) in relation to an appeal against a revocation notice, before the notice takes

effect; b) in relation to the withdrawal of a duly-made application under paragraph

4(2) of Schedule 5, not later than 15 working days from the date of the notice served under that paragraph;

c) in relation to a variation notification, a suspension notice, an enforcement notice or a landfill closure notice, not later than 2 months from the date of the notification or notice;

d) in any other case not later than 6 months from the date of the decision or deemed decision.

Please note: An appeal will not suspend the effect of the conditions appealed against; the conditions must still be complied with. In determining an appeal against one or more conditions, the Act allows the Secretary of State in addition to quash any of the other conditions not subject to the appeal and to direct the local authority either to vary any of these other conditions or to add new conditions.

Pollution Prevention Control Act 1999

Environmental Permitting (England & Wales) Regulations 2010 (as amended)

REF 08_00014_PPCB

Contact Numbers for the Regulator The Regulator is the Environment Team of Telford & Wrekin Council. They can be contacted on 01952 381818. You may also contact them by email at any time. [email protected] Correspondence Address All correspondence to Telford & Wrekin Council relating to this information shall be addressed to: Environment Team Public Protection Telford & Wrekin Council Darby House P.O. Box 214 Telford TF3 4JA