POL-001 Rev.01
-
Upload
singaravelu-subramanian -
Category
Documents
-
view
89 -
download
3
description
Transcript of POL-001 Rev.01
ABU DHABI MARINE OPERATING COMPANY
Document Ref.:
POL-001 Control Sheet
ADMA-OPCO STANDARD ENGINEERING DOCUMENTS PAGE
Page 1 of 24
D
O
C
U
M
E
N
T
DESIGNATION POL-001
MAINTENANCE POLICY TITLE
AUTHORITY NAME TITL B.UNIT/
DIV SIGNATURE DATE
TECHNICAL
CUSTODIAN Farid M. Chigara RESL
Prod./
MTD
TECHNICAL Ali Al-Hammadi RDMTL
Prod./
MTD
STANDARDS Khaled Tawfik Hendy ESQA
SL (A)
P&E/
DED
APPROVAL Salah Mubarak Ali MM Prod./
MTD
ENDORSEMENT Abdul Aziz Al-Kayoumi AGM(P) Prod.
CONTROL STAMP
The soft copy of this document on
ADMA-OPCO Web is
Controlled. When printed, it is considered
Uncontrolled
1 03-010 Issued for implementation
0 01-04 Issued for implementation
Rev.1 DATE DESCRIPTION/TEXT AFFECTED
SF / General / 001 Rev.0 sheet 1 of 1
COPYRIGHT © ABU DHABI MARINE OPERATING COMPANY - ADMA-OPCO
All rights reserved. The information contained in this document is regarded as confidential. Recipient(s) other than ADMA-
OPCO's employees undertake both during the continuance of their services to ADMA-OPCO and after termination to maintain
in safe custody and not to use any such information for any purpose other than a purpose falling within the scope of the
Agreement or Contract under which this document was supplied. Recipient(s) further agree not to dispose of, make copies, in
whole or in part of such information or permit the use or access of the same by any Third Party unless the prior written
permission of ADMA-OPCO Manager Disciplines Engineering is obtained.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
2
SF / General / 002 Rev.0 sheet 1 of 1
Liability for utilization by personnel/organizations outside ADMA-OPCO Whilst every effort has been made to ensure the accuracy of this document, neither ADMA-OPCO nor its employees will assume liability for any application or use outside ADMA-OPCO premises/assets.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
3
SF / General / 002 Rev.0 sheet 1 of 1
TABLE OF CONTENTS
1. INTRODUCTION ....................................................................................................................... 4
1.1 PREFACE ................................................................................................................................... 4 1.2 OBJECTIVE ................................................................................................................................ 4 1.3 CORPORATE VISION ............................................................................................................... 4 1.4 MAINTENANCE MISSION STATEMENT .............................................................................. 4 1.5 REFERENCES ............................................................................................................................ 5 1.6 ABBREVIATIONS ..................................................................................................................... 6 1.7 DEFINITIONS ............................................................................................................................ 6 1.8 USE OF LANGUAGE ................................................................................................................ 6 1.9 UNITS ......................................................................................................................................... 6 1.10 LESSONS LEARNT ................................................................................................................... 6 1.11 SITE CONDITIONS & DATA ................................................................................................... 6
2. QUALITY ASSURANCE .......................................................................................................... 7
2.1 QUALITY ASSURANCE SYSTEM .......................................................................................... 7 2.2 QUALITY PLAN ........................................................................................................................ 8 2.3 INSPECTION AND CERTIFICATION REQUIREMENTS ..................................................... 8
3. POLICY ........................................................................................................................................ 9
3.1 POLICY REVIEW PERIOD ....................................................................................................... 9 3.2 INTEGRITY ................................................................................................................................ 9 3.3 PEOPLE ...................................................................................................................................... 9 3.4 CODES AND STANDARDS ..................................................................................................... 9 3.5 RELIABILITY FOCUSED METHODOLOGY ....................................................................... 10 3.6 CRITICALITY .......................................................................................................................... 10 3.7 MAINTENANCE KEY PERFORMANCE INDICATOR DRIVERS ..................................... 10 3.8 MANAGEMENT OF CHANGE .............................................................................................. 10 3.9 BUDGETS ................................................................................................................................ 11 3.10 RESOURCES ............................................................................................................................ 11 3.11 AUDIT ...................................................................................................................................... 11 3.12 COST ......................................................................................................................................... 11 3.13 DESIGN .................................................................................................................................... 11 3.14 LIFE CYCLE COST MODEL .................................................................................................. 12 3.15 EQUIPMENT REPAIR OR REPLACE PHILOSOPHY .......................................................... 12 3.16 STANDARDIZATION ............................................................................................................. 12 3.17 ONSHORE WORK SCOPES ................................................................................................... 12 3.18 COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEM ....................................... 13 3.19 PLANNING .............................................................................................................................. 14 3.20 SHUTDOWNS .......................................................................................................................... 15 3.21 WELLHEAD TOWER MAINTENANCE ............................................................................... 15 3.22 BENCHMARK ......................................................................................................................... 15
APPENDIX-A: ABBREVIATIONS ................................................................................................. 16
APPENDIX-B: DEFINITIONS......................................................................................................... 17
APPENDIX-C: REFERENCED DOCUMENTS ........................................................................... 24
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
4
SF / General / 002 Rev.0 sheet 1 of 1
1. INTRODUCTION
1.1 Preface
ADMA-OPCO will conduct its maintenance activities in line with the Maintenance
Policies contained within this document to align with the corporate Vision and
Maintenance Mission.
1.2 Objective
The objective of this Policy is to provide an effective maintenance service to support
oil and gas production which meets our ADMA obligations to parent and
shareholder group requirements, while complying with all legal, safety and
environmental standards in a cost effective manner while fostering the ADMA-
OPCO corporate image.
1.3 Corporate Vision
To perform as a world class hydrocarbon producer from the offshore Concession
reserves, ensuring facilities integrity, protecting health safety and environment for the
next 50 years.
1.4 Maintenance Mission Statement
ADMA Maintenance Policy is intended to
a. Ensure that the plant and equipment operates at the required performance and
availability levels by the application of preventative maintenance and to adopt
predictive maintenance techniques where cost-effective.
b. Take action to improve reliability of plant and equipment, through Root Cause
Analysis techniques, and a process of continuous improvement.
c. Develop a highly skilled team which maximizes value for both the employee
and ADMA-OPCO”.
d. provide & highlights the minimum basic requirements of ADMA-OPCO and
shall not relieve the Contractor of his contractual obligations. Any deviation
from this document shall be identified by Contractor and shall require written
approval from ADMA-OPCO.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
5
SF / General / 002 Rev.0 sheet 1 of 1
1.5 References
1.5.1 General
The latest edition (at the time of the contract award) of the reference documentation
as listed in Appendix-C shall be read as an integral part of this document.
The latest edition/revision of ADMA-OPCO Standard Engineering Documents as
indicated in Status List SL-001 shall be utilized.
1.5.2 Equivalent Standards
Standard Documents equivalent to those referred to herein shall not be substituted
without written approval from ADMA-OPCO. Approval of equivalent Standard
Documents will not, in any way, remove responsibility from the Contractor to meet
the best practices and/or requirements of the Standard Engineering Documents
referred to herein, in the event of conflict.
Where differences and/or conflicting issues occur between the referenced documents
themselves or the requirements of this document, the requirements of this document
shall overrule unless otherwise advised by ADMA-OPCO. However major conflicts
shall be reported in writing to the ADMA-OPCO Standards Authority/Technical
Custodian appearing in the front sheet of this Procedure for arbitration/resolution.
The following hierarchy of adherence to standards shall be followed:
a. Whenever ADMA-OPCO Standard Engineering Documents (SED‟s) relevant to
the system, service and/or equipment design are available, the same shall be
utilized first.
b. Shareholder SED‟s (tailored to suit ADMA-OPCO needs) shall be utilized next in
the hierarchy, if the relevant subject is not covered by ADMA-OPCO standards.
c. National or International standards (tailored to suit ADMA-OPCO needs) shall be
utilized, if the required subject is not covered either by ADMA-OPCO or
Shareholder SED‟s.
The Contractor shall equip himself with copies of all the referenced Standard
Engineering Documents referred in Appendix-C of this document and shall make
them readily available to all ADMA-OPCO, or nominated representative, personnel
involved in the work.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
6
SF / General / 002 Rev.0 sheet 1 of 1
1.6 Abbreviations
The abbreviations used in this document are listed in Appendix-B.
1.7 Definitions
The definitions used in this document are listed in Appendix-A.
1.8 Use of Language
Throughout this document, the words „will‟, „may/can‟, „should‟ and „shall/must‟,
when used in the context of actions by ADMA-OPCO or others, have specific
meanings as follows:
a. „Will‟ is used normally in connection with an action by ADMA-OPCO and / or
nominated representative, rather than by a Contractor or Vendor.
b. „May / Can‟ is used where alternatives / action are equally acceptable.
c. „Should‟ is used where provision is preferred.
d. „Shall / Must‟ is used where a provision is mandatory / vital.
1.9 Units
Units shall be in accordance with ADMA-OPCO STD-00, Part-1.
1.10 Lessons Learnt
Upon completion of works related to the scope of this document, lessons learnt shall
be made available by the Contractors/consultants/job officer and shall be fed to
ADMA-OPCO Lessons Learnt system as appropriate.
1.11 Site Conditions & Data
Site Conditions & Data shall be in accordance with ADMA-OPCO STD-00, Part-2.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
7
SF / General / 002 Rev.0 sheet 1 of 1
2. QUALITY ASSURANCE
2.1 Quality Assurance System
2.1.1 All activities and services associated with the scope of this document shall be
performed by Contractors/Vendors approved by ADMA-OPCO.
2.1.2 The Contractor/Vendor shall operate Quality Management Systems (QMS) within his
organizations, which ensure that the requirements of this Specification are fully
achieved.
2.1.3 The Contractor/Vendor‟s quality management system shall be based on ADMA-
OPCO Specification SP-1009 or the latest issue of ISO 9001 Series and accredited by
an international certifying agency.
The Contractor‟s quality manual shall provide details for the preparation of a quality
plan, which shall include provisions for the QA/QC of services activities.
Where an approved Contractor/Vendor revises their Quality Management System that
affect the ADMA-OPCO approved Quality / Inspection and Test Plan, then the
revised Quality Plan / Inspection and Test Plan shall be submitted for ADMA-OPCO
approval before initiating any service activities.
2.1.4 The effectiveness of the Contractor‟s quality management system may be subject to
monitoring by ADMA-OPCO or its representative and may be audited following an
agreed period of notice.
2.1.5 The Contractor/Vendor shall make regular QA audits on all their Sub-
Contractors/Suppliers. Details of these audits shall be made available to ADMA-
OPCO when requested.
2.1.6 The Contractor/Vendor shall maintain sufficient Inspection and Quality Assurance
staff, independent of the service provider management, to ensure that the QMS is
correctly implemented and that all related documentation is available.
2.1.7 Using Sub-Contractors is not allowed for services/functions carried out by a
Contractor without ADMA-OPCO approval.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
8
SF / General / 002 Rev.0 sheet 1 of 1
2.2 Quality Plan
2.2.1 Contracted activities shall be performed in accordance with an approved Quality Plan
(QP).
2.2.2 The level of detail required in the Quality Plan shall be commensurate with the scope
of services provided.
2.2.3 The quality of works is an essential factor in carrying out all services & activities
covered by this Document.
2.2.4 During services/activities, quality assurance/quality control issues are the
responsibility of the Contractor, and shall be approved and certified by TPA.
2.2.5 Conflicts between Contractor & TPA shall be reported in writing to ADMA-OPCO
for resolution.
2.3 Inspection and Certification Requirements
Inspection and certification requirements for material shall be certified to ADMA-
OPCO CP-102 and BS EN 10204.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
9
SF / General / 002 Rev.0 sheet 1 of 1
3. Policy
The following subsections contain the policy statements these are the key elements in the
drive towards achieving the goals determined in the corporate Vision and Maintenance
Mission statements.
3.1 Policy Review Period
The Maintenance Policy should be reviewed every 3 years.
3.1.1 Responsible Policy Holder
The responsible person and owner of the Policy will be the Assistant General Manager
Production (AGM-P) the current holder‟s name will be contained in the Policy. The
Technical Custodian for the Policy will be the Maintenance Division.
3.1.2 Revisions, Additions and Deletions
These can be added to the Policy at any time subject to approval of the responsible person.
3.2 Integrity
Maintenance policy, procedures and tasks will be implemented such that the integrity of the
installation(s) is not compromised.
3.2.1 Independence of Integrity Division
The Integrity Division and its personnel will remain independent of the asset. To act as
“Third Party” for maintenance activities.
3.2.2 Inspection Generated Work Orders
All work scopes generated by the Inspection Engineer will be implemented by the
maintenance department in the timescale and content agreed with the Inspection Engineer.
3.3 People
All maintenance personnel will complete a role based competence assessment. This will
ensure that the correct skills and experience levels are maintained.
3.4 Codes and Standards
All work will be completed to the appropriate ADMA and shareholders codes and Standards
or applicable International Standard.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
10
SF / General / 002 Rev.0 sheet 1 of 1
3.5 Reliability Focused Methodology
All maintenance activities will be geared towards the goal of increasing the reliability and
efficiency of plant and equipment. To achieve this goal existing processes and procedures
will be reviewed or replaced as necessary.
In order to gather the data that allows the reliability and efficiency of equipment to be
calculated the main information sources for data collection is:
a. Computerised Maintenance Management System (CMMS)
b. Operator log sheets.
For dependable data from the CMMS
a. The correct configuration of the CMMS hierarchy and associated equipment data.
b. Maintenance personnel entering the data trained in the use of the CMMS and of the
importance of correct data entry.
3.6 Criticality
The maintenance requirements for each process system and equipment within the system will
be reviewed on a criticality basis recognising the 5 Year Business Plan.
Criticality is defined as a relative measure of the consequences of a failure, its mode and its
frequency of occurrence. A criticality analysis is the procedure for ranking potential failure
modes according to the combined influence of severity (the degree of damage that could
ultimately occur) and the probability of occurrence or expected loss frequency.
3.7 Maintenance Key Performance Indicator Drivers
To manage maintenance effectively and to support a continuous improvement culture, a set of
objectives must be defined. A performance management system uses Key Performance
Indicators (KPI‟s) as an effective means of summarizing key information for:
a. supporting the establishment of targets for performance
b. comparing performance with objectives
c. clearly demonstrate the cost and value of maintenance.
3.8 Management of Change
Any change as defined in the Management of Change document will be managed through the
“Plant Modification Request” (PMR) procedure.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
11
SF / General / 002 Rev.0 sheet 1 of 1
3.9 Budgets
Maintenance Budgets will be developed on an accepted frequency. This is the asset high
level cost control. Budget(s) will be the responsibility of the onshore and offshore team
leaders.
3.10 Resources
Sufficient suitably qualified and competent resources will be available on the installations
and in onshore support roles, to satisfactorily complete the maintenance activities and to
ensure the technical integrity of the installation(s) is maintained.
3.11 Audit
A maintenance Audit schedule and a maintenance Audit procedure will be developed. To
determine that the maintenance activities are being completed competently and correctly, to
the relevant maintenance standards and procedures.
Audits will be completed by both internal and independent external resources. Best practices
to be disseminated throughout all assets.
3.12 Cost
All costs associated with maintenance will be clearly transparent.
Maintenance costs will be tracked by two different integrated systems.
a. ORACLE The high level cost system used by finance department
b. MAXIMO The detail level cost control within the CMMS
3.13 Design
All engineering that is required to be completed for:
a. New Projects
b. Plant Modifications
c. Plant replacement
will comply with agreed operations and maintenance philosophy, including but not limited to
reliability, maintainability and standardisation.
3.13.1 Reliability Availability Maintainability (RAM) Model
“RAM” model generation for capital projects should be considered for development, to assist
in design decisions.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
12
SF / General / 002 Rev.0 sheet 1 of 1
3.14 Life Cycle Cost Model
A Life Cycle Cost Model will be used. All future equipment will be purchased after making
use of the model to assist in the selection process for plant and equipment. Similarly all
future project and modification scopes will use the model in the selection process for any
equipment purchased. Use of the model will be linked to the Procurement Process.
3.15 Equipment Repair or Replace Philosophy
When an item of equipment is removed from service for repair then the following formulas
will be used to determine whether the unit is to be repaired or replaced as a new item:
General Rule
a. IF (Cost of Repair 70% of Cost of new replacement) then REPAIR
b. IF (Cost of Repair ≥ 70% of Cost of new replacement) then REPLACE
However the following additional factors must be taken into consideration:
If “Lead Time” for the replacement is excessive compared to the repair time and the item is
critical to production then the item is to be REPAIRED.
This can be superseded by sanction of the Site Manager for Emergency Safety or Production
related items.
In all cases if production is directly effected then the method that has the shortest lead time
will be the method chosen regardless of cost.
3.16 Standardization
New or replacement equipment should be specified with standardisation on:
a. Type
b. Manufacturer
Providing this is supported by historical maintenance or operational evidence/experience.
Procurement strategy to be aligned with this philosophy.
3.17 Onshore Work Scopes
All scopes that can be completed onshore will be completed onshore. These are the
following:
a. Fabrication.
b. Equipment Repair/Overhaul
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
13
SF / General / 002 Rev.0 sheet 1 of 1
This will reduce the cost of repairs and the numbers of personnel onboard the installations.
This can be superseded by sanction of the Site Manager for Emergency Safety or Production
related items, and on a cost benefit analysis basis.
3.18 Computerized Maintenance Management System
All maintenance to be managed by a CMMS. All costs will be tracked by the CMMS at the:
a. Tag Level.
b. Equipment Number Level.
Responsibility for the change management of the CMMS database will be with the
Maintenance Division as single point control. This will ensure that all changes follow a
change management process. The responsibility for the day to day quality of the data will be
with the Asset Line Management.
Access to the CMMS will be by secure “LOGIN” unique to assigned individual personnel.
3.18.1 Maintenance Types
Maintenance within the CMMS will be classified into three types:
a. Planned Maintenance (see Figure 1 below)
a1. Planned Maintenance Programs (Intrusive)
a2. Predictive Maintenance Programs (Non-intrusive)
a2.1 Condition Monitoring Programs
a2.2 Performance Testing
a3. Inspections Programs
a4. Shutdown Maintenance
b. Corrective Maintenance (see Figure 1 below)
c. Breakdown Maintenance (see Figure 1 below)
These terms are defined in the definition section below
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
14
SF / General / 002 Rev.0 sheet 1 of 1
Figure 1 Maintenance types
BREAKDOWN MAINTENANCE
CORRECTIVE MAINTENANCE
Corrective Work Orders Raised as a result
of Planned Maintenance Program
Corrective Work Orders Raised as a result
of Predictive Maintenance Program
Corrective Work Orders Raised as a result
of an Inspection.
Corrective Work Order raised by Operations
during watch-keeping.
Corrective Work Order raised by other
means.
PLANNED MAINTENANCE
Planned Maintenance Programms in CMMS
Predictive Maintenance Programs in CMMS
Inspection Programs
Figure 1 shows the maintenance types and how their ratios should be, i.e. largest percentage
Planned, then Corrective, Breakdown Maintenance to be a minimum.
3.19 Planning
All maintenance works will be completed in a planned manner. This will ensure that
maintenance activities align themselves with the goal of high availability for the installations.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
15
SF / General / 002 Rev.0 sheet 1 of 1
Planning will be the responsibility of the planning department Plans will be developed for
the following timescales:
a. 5 Year Plan
b. 3 Year Plan
c. 1 Year Plan
d. 90 Day Plan.
e. 30 Day Look ahead.
Additional to the above the following will have separate plans:
a. Major Maintenance
b. Shutdowns
c. Towers Maintenance
d. Projects and Modifications(PMR‟S)
3.20 Shutdowns
Plant shutdowns will be kept to a minimum. Process safety must not be compromised.
The following guidelines will be applied to shutdowns:
a. Shutdown will be completed normally in Modular sections of plant.
b. Shutdowns will be planned in advance and agreed with all internal and external parties
concerned Value Added Processes (VAP) will be applied.
c. Shutdown work scopes will be classified as shutdown separately within CMMS.
3.21 Wellhead Tower Maintenance
The maintenance of the field well towers will be addressed on a batch/campaign basis.
This will:
a. Reduce Logistics Costs
b. Increase Resource efficiency.
3.22 Benchmark
Benchmark exercise to be carried out every three years for measurable maintenance
activities.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
16
SF / General / 002 Rev.0 sheet 1 of 1
APPENDIX-A: ABBREVIATIONS
Abbreviation Description
ADMA-OPCO Abu Dhabi Marine Operating Company
QA Quality Assurance
QAS Quality Assurance System
QC Quality Control
QMS Quality Management Systems
SI Systeme International d‟Unites
TPA Third Party Agency
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
17
SF / General / 002 Rev.0 sheet 1 of 1
APPENDIX-B: DEFINITIONS
B.1 General Definition
Term Definition
Contractor Is the Company contracted to undertake the works of a Project and is
accountable to ADMA-OPCO's or its nominated representative.
Quality
Assurance
All those planned and systematic actions (QA) necessary to ensure
quality i.e. to provide adequate confidence that a product or service will
be fit for its intended purpose.
Quality Manual A Document setting out the general quality policies, procedures and
practices of an organization.
Quality Plan A document prepared by the Contractor/Vendor setting out the specific
quality practices, resources and activities relevant to a particular project.
Quality
Management
System
The structure organization, responsibilities, activities, resources and
events that together provide organized procedures and methods of
implementation to ensure the capability of the organization to meet
quality requirements.
TPA Is the Company contracted to undertake the Third Party Inspection &
Verification Tasks (TPA) on behalf of ADMA-OPCO.
Vendor
Is the named Manufacturer or Supplier in the ADMA-OPCO Purchase
Order. The term “Vendor” as used herein includes all Manufacturers and
sub-suppliers of equipment covered by this Document.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
18
SF / General / 002 Rev.0 sheet 1 of 1
APPENDIX-B: DEFINITIONS (CONT.’D)
B.2 Special Definition
TERM DEFINITION
Asset Register The electronic list held within the CMMS of all TAG items on an installation‟s
engineering drawings:
a. P&ID‟S
b. PFD‟s
c. Cause and Effect
d. SLD‟s
e. Loop Diagrams
f. Lifting Equipment Register
Audit A systematic examination of documents, reports, accounts or quality attributes.
Confirming the stated performance.
Available The state of an item when it is capable of performing its required functions in
the defined conditions of use.
Backlog A listing unique to each installation of the outstanding work to be done.
Outstanding work is considered to be work that has not been done by its
required or requested date.
Batch Maintenance The grouping of blocks of maintenance activities into a structured plan to
minimise downtime of equipment or process and maximise productivity of
maintenance personnel.
Benchmark A reference value against which a measurement or a series of measurements
may be compared against that of a peer or competitive leader.
Benchmarking Measuring a process against that of a leader. Benchmarking may be carried out
using either:
a. A qualitative assessment of the use of management practices.
b. A quantitative assessment with specific measures, e.g. process availability.
Breakdown Failure of an item resulting in the non-availability of the item to provide its
operating function
Compliance An affirmative indication or judgement that the supplier of a product or service
has met the requirements of the relevant specifications, contract or regulation.
The state of meeting the requirements.
In terms of the maintenance programs that are issued from the CMMS 100%
compliance for any given period, would mean that all the maintenance programs
were completed for that period on or before their due date. Any that were not
completed by their due date would be entered into the backlog.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
19
SF / General / 002 Rev.0 sheet 1 of 1
APPENDIX-B: DEFINITIONS (CONT.’D)
TERM DEFINITION
Condition
Monitoring
The continuous or periodic measurement and interpretation of data to indicate
the condition of an item to determine the need for maintenance.
Conformity An affirmative indication or judgement that a product or service has met the
requirements of the relevant specifications, contract or regulation.
Deferment In terms of the maintenance programs this is the process by which relevant
management agrees that for operational reasons a maintenance program can be
deferred until next execution.
Example
Site Management can decide that a weekly maintenance program is not
completed that week for operational reasons. This means that the maintenance
program is not execute that week and not put into Backlog.
Deferment
Procedure
A system where the deferred production “loss” is collected into a database.
Example
A gas turbine generator shuts down due to fault. The Load Shedding system
cannot prevent the installation from loss of total electrical supply and production
is shut down. The deferred loss is that production that would have been
exported during the time the installations was shutdown, i.e. if in the case of
this example the generators were down for 1 hour then 1/24 of the daily
production would be the deferred loss. This and the reason for the loss would be
entered into the database.
Direct Cost Those costs that is recognisable as being attributed to maintenance. These are:
a. Manpower Cost (Internal & External)
b. Service Contract
c. Material Cost
Fail-Safe A design property of an item which prevents its failure from resulting in critical
faults, e.g. an Emergency Shutdown Valve will close in the event of loss of the
supply medium keeping it open.
Failure The termination of the ability of an item to perform a required function. Failure
is an event resulting in fault which is a state.
Failure Mechanism The physical, chemical or other process which has led to failure.
Fault The state of an item characterized by the inability to perform a required
function. A fault is often the result of a failure.
Lead Time The time taken for an item or items to be delivered from a Vendor after a valid
purchase order has been awarded. Lead time is for delivery to the onshore
stores base (Mussafah)
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
20
SF / General / 002 Rev.0 sheet 1 of 1
APPENDIX-B: DEFINITIONS (CONT.’D)
TERM DEFINITION
Life Cycle Cost The total cost of ownership of an item taking into account all the costs of
acquisition, personnel training, operation, maintenance, modification and
disposal.
Indirect Cost Those costs that is not easily recognisable as being attributed with maintenance.
These are
a. Logistics costs for manpower and materials.
b. Onshore overheads.
Insurance Spare Spares that are vital to the function of the plant or equipment. They are usually
very expensive and with long lead times and have infrequent use.
Maintenance The combination of all technical, supervisory and administrative actions,
intended to retain an item in, or restore it to, a state in which it can perform a
required function.
Maintenance Cost The total cost of retaining an item in, or restoring it to a state in which it can
perform its required function.
Maintenance Work
Order
An instruction, generated on the CMMS, detailing the work scope to be carried
out on an item or system.
Management of
Change
The process of reviewing, evaluating and controlling modifications to facilities,
procedures and organizational structure to ensure that the impact on safety,
environmental and process disruption is understood and the appropriate
safeguards are in place. Within ADMA-OPCO this is the Plant Modification
Request (PMR) procedure.
Mission Statement A timeless statement of the values by ADMA-OPCO, identifying core purpose
and tasks. Its aim is to create a unity of purpose necessary to achieve the vision.
Mothballed
Maintenance
Maintenance of equipment that is adjusted to ensure the preservation mode of
the mothballed equipment. All other maintenance normally associated with the
equipment will be suspended during the mothball period.
Obsolescent Becoming, or about to become, obsolete, out of date or unobtainable.
Obsolete An item that is no longer being manufactured or supplied.
Opportunistic
Maintenance
Maintenance of an item that is deferred or advanced in time when an unplanned
opportunity becomes available.
Overhaul A comprehensive examination and restoration of an item, or a major part
thereof, to an acceptable condition.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
21
SF / General / 002 Rev.0 sheet 1 of 1
APPENDIX-B: DEFINITIONS (CONT.’D)
TERM DEFINITION
Planned
Maintenance
The maintenance organized and carried out with forethought, control and the use
of records to a predetermined plan.
Example
The core maintenance programs that are issued by the CMMS. Corrective
maintenance arises as the result of fault detection during a planned maintenance
program, i.e. a condition monitoring program highlights the need for a
corrective work order to be raised before a failure can occur.
Predictive/Proactiv
e Maintenance
This is the maintenance completed as the applicable type of condition
monitoring where data is collected from a functioning machine from which
decisions are made. The output of these decisions could be to raise a corrective
work order. This is a non-intrusive type of maintenance, i.e. maintenance that
can be completed with the equipment remaining in service.
Preventative
Maintenance
The maintenance carried out at predetermined intervals or according to
prescribed criteria and intended to reduce the probability of failure or the
degradation of the functioning of an item. This would be the Planned
Maintenance Programs that are issued by the CMMS. This is an intrusive type
of maintenance, i.e. maintenance that would necessitate the removal from
service of the equipment.
Breakdown
Maintenance
Maintenance of an item when it is in the breakdown condition.
See Example 2 of Corrective Maintenance
Unplanned
Maintenance
This is maintenance carried out to no pre-determined timescale, e.g. breakdown
maintenance.
Redundancy In an item, the existence of more than one means for performing a required
function.
Reliability The ability of an item to perform a required function under given conditions for
a given time interval.
Reliability Centred
Maintenance
(RCM)
A systematic approach for identifying effective and efficient preventive and
condition maintenance tasks for equipment and items in accordance with a
specific set of procedures and for establishing the intervals between
maintenance tasks.
Risk Based
Inspection
Inspection intervals allocated to equipment on a calculated risk based
methodology.
Schedule The specific time when a planned event will be completed.
Shutdown
Maintenance
Maintenance that is carried out only when the plant or system is out of service.
Specification The document that prescribes the requirements to which the product or service
has to conform.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
22
SF / General / 002 Rev.0 sheet 1 of 1
APPENDIX-B: DEFINITIONS (CONT.’D)
TERM DEFINITION
Standardisation The goal of reducing the different types of equipment or manufacturer on an
installation. Standardisation can be applied on an installation by installation
basis or as a company goal for all installations.
Standby
Redundancy
That redundancy wherein a part of the means for performing a required function
are inoperative until needed.
Corrective
Maintenance
The maintenance carried out after fault recognition and intended to put an item
into a state in which it can perform a required function. Corrective maintenance
is the vehicle by which the effectiveness of the planned maintenance is
monitored.
This definition requires some examples to fully explain what is classed as
Corrective Maintenance. For this three examples will be used to clarify the
definition.
Example 1 Inspection Action Report.
A report has been issued by the integrity department that informs the
maintenance department that a pipe spool has been identified by corrosion
monitoring/NDT inspection as having a defect that is nearing retrial thickness
and the spool is to be renewed. This is a corrective work order.
1. Spool and line are still in service so although no failure has arisen the
planned maintenance has identified the corrective action needed to return
the spool to original condition.
2. The replacement spool will be ordered and fitted in a planned manner.
Example 2 A Pump fails to give any output pressure
A production operator starts a pump but the pump will not give any output
pressure. This is not corrective work, it is a breakdown work order for the
following reasons:
1. A failure has occurred, the pump cannot perform its required function, i.e. it
cannot pump.
2. The fault will be the reason that the pump cannot pump. This will be
determined by investigation.
Example 3 Increase in Vibration Trend
A condition monitoring program has informed the maintenance department that
a machine is showing signs of internal problems that are trending towards a
failure condition, and they recommend that investigative action take place. This
is a corrective work order for the following reasons:
1. Although the machine is still running performing its function, the condition
monitoring has identified that corrective action is needed.
2. No failure or fault has occurred.
The investigation and rectification will take place in a planned manner.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
23
SF / General / 002 Rev.0 sheet 1 of 1
APPENDIX-B: DEFINITIONS (CONT.’D)
TERM DEFINITION
Standby State A non-operating state when an item is available to fulfil its operating function if
required.
TAG A unique number allocated to a piece of equipment that gives the details of the
type, location and duty. The TAG number format is determined by the company
TAG number format standard.
Tender An offer, normally in writing, to supply a commodity or to execute works,
giving price and compliance with a specification.
Equipment Number A unique identification number to allow the history of maintenance and costs to
be tracked with equipment that has more than one possible location.
Example
Pressure Safety Relief valves of the same setting can be removed from a
separator and re-fitted in different locations to provide the same function, i.e
they are inter-changeable.
Work Order: A work order specifies a particular task to be accomplished, and the
labor, materials, services, and tools needed to complete the work
activities in Maintenance Management Process.
1 03-010 Issued for implementation
Rev. Date Description / Text Affected
MAINTENANCE POLICY
ADMA-OPCO POL-001 PAGE
24
SF / General / 002 Rev.0 sheet 1 of 1
APPENDIX-C: REFERENCED DOCUMENTS
Unless otherwise specified, the latest edition of the Standard Engineering Documents listed below
shall to the extent specified herein, represent part of this document.
Designation Title
ADMA-OPCO
CP-102 Third Party Inspection and Certification Requirements for New Equipment
and Materials in Manufacture.
SL-001 Status List for ADMA-OPCO Standard Engineering Documents.
SP-1009 Requirements for Contractors Quality Systems on Major Projects
STD-00 Part-1: Measurements Units
Part-2: Site Condition & Data
British Standards Institution (BSI)
BS EN 10204 Metallic Products – Types of Inspection Documents.
International Organization for Standardization (ISO)
ISO 9001 Quality Management Systems - Requirements.