POINT OF WORK RISK ASSESSMENT Project Eco of London 30 st ... · Site Location: 30 st Mary axe,...

2
POINT OF WORK RISK ASSESSMENT Date 15 Apr 2019 Project Eco of London Site Location: 30 st Mary axe, London Task: ups startup Applicable Risk Assessments: London Before commencing work review the Task Specific Risk Assessment. If no additional hazards identified mark not applicable and signoff this form. Where Hazards/Risks are not covered in the Task Specific Risk Assessment complete the detail below. Use the back of the sheet if necessary. No. Hazard / Risk Control Measures Implemented 1 Other contractors in comms room Good communication and good housekeeping 2 Heavy parts to be lifted Correct mainsail handling techniques used and safety boots worn IF THE HAZARD / RISK CANNOT BE CONTROLLED DO NOT PROCEED Indicate Number of Persons at Risk Employees: 1 Contractor Staff: 0 Public: 0 ALL Persons must sign on to the risk assessment. It must be ensured that the contents are fully discussed, agreed and understood by all Name Signature Robert Holden C O N T R A C T O R S Name Signature Name Signature IF IT´S NOT SAFE - DON´T DO IT

Transcript of POINT OF WORK RISK ASSESSMENT Project Eco of London 30 st ... · Site Location: 30 st Mary axe,...

Page 1: POINT OF WORK RISK ASSESSMENT Project Eco of London 30 st ... · Site Location: 30 st Mary axe, London Task: ups startup Applicable Risk Assessments: London Before commencing work

POINT OF WORK RISK ASSESSMENT

Date 15 Apr 2019 Project Eco of LondonSite Location: 30 st Mary axe, LondonTask: ups startupApplicable Risk Assessments: London

Before commencing work review the Task Specific Risk Assessment. If no additional hazards identified mark notapplicable and signoff this form.

Where Hazards/Risks are not covered in the Task Specific Risk Assessment complete the detail below. Use the backof the sheet if necessary.

No. Hazard / Risk Control Measures Implemented1 Other contractors in comms room Good communication and good housekeeping2 Heavy parts to be lifted Correct mainsail handling techniques used and safety

boots worn IF THE HAZARD / RISK CANNOT BE CONTROLLED DO NOT PROCEED

Indicate Number of Persons at RiskEmployees: 1 Contractor Staff: 0 Public: 0

ALL Persons must sign on to the risk assessment. It must be ensured that the contents are fully discussed, agreed andunderstood by all

Name Signature

Robert Holden

C O N T R A C T O R SName Signature Name Signature

IF IT´S NOT SAFE - DON´T DO IT

Page 2: POINT OF WORK RISK ASSESSMENT Project Eco of London 30 st ... · Site Location: 30 st Mary axe, London Task: ups startup Applicable Risk Assessments: London Before commencing work

PHOTOGRAPHS

No. Hazard / Risk Control Measures Implemented

1 . -

2 . -