POINT OF WORK RISK ASSESSMENT
Date 15 Apr 2019 Project Eco of LondonSite Location: 30 st Mary axe, LondonTask: ups startupApplicable Risk Assessments: London
Before commencing work review the Task Specific Risk Assessment. If no additional hazards identified mark notapplicable and signoff this form.
Where Hazards/Risks are not covered in the Task Specific Risk Assessment complete the detail below. Use the backof the sheet if necessary.
No. Hazard / Risk Control Measures Implemented1 Other contractors in comms room Good communication and good housekeeping2 Heavy parts to be lifted Correct mainsail handling techniques used and safety
boots worn IF THE HAZARD / RISK CANNOT BE CONTROLLED DO NOT PROCEED
Indicate Number of Persons at RiskEmployees: 1 Contractor Staff: 0 Public: 0
ALL Persons must sign on to the risk assessment. It must be ensured that the contents are fully discussed, agreed andunderstood by all
Name Signature
Robert Holden
C O N T R A C T O R SName Signature Name Signature
IF IT´S NOT SAFE - DON´T DO IT
PHOTOGRAPHS
No. Hazard / Risk Control Measures Implemented
1 . -
2 . -