PO-115Determination of Clearance Criteria … µg/m3 to >260 µg/m3 – Highest concentrations near...
Transcript of PO-115Determination of Clearance Criteria … µg/m3 to >260 µg/m3 – Highest concentrations near...
1
Determination of Clearance Determination of Clearance
Criteria Following Mercury Criteria Following Mercury
Decontamination ProjectsDecontamination ProjectsPOPO--115115
American Industrial Hygiene Conference and Exposition
May 13-16, 2006
Chicago, IllinoisDavid Regelbrugge, CIH, CSPGary N. Crawford, CIHBrad Caddick Win WilliamsPH: 847-692-4700E-Mail: [email protected]
2
BackgroundBackground• How do you go about clearing a
mercury clean-up site?– Few established methods for
identification, decontamination and/or clearance of remediated areas.
3
BackgroundBackground• Spills & Releases
– Most often seen in educational facilities and hospitals.
• Spills may be from years of abuse or a single careless incident
– For example, laboratory use vs. a student finding or bring mercury from home to school to show to fellow students.
– Rare but occasionally seen in homes.
4
Exposure ValuesExposure Values
• Occupational Exposure Values– OSHA
• Ceiling limit of 100 µg/m3
– ACGIH®
• TLV® of 25 µg/m3
• Also carries a “Skin” notation
5
Exposure ValuesExposure Values• Environmental Values
– Values vary between agencies• EPA Reference Concentration 0.3 µg/m3
• Agency for Toxic Substances and Disease Registry (ATSDR)
– 0.2 µg/m3 minimal risk level– 3 µg/m3 for Industrial/commercial clearance
» For an 8 hr day – <1 µg/m3 for residential clearance
» For a 24 hr day
– Which value should be used?
6
Exposure ValuesExposure Values• Environmental Values
– Illinois gas regulators spills• Began in July of 2000• Older gas regulators (installed prior to
1961) contained approximately 135 grams (two teaspoons) of liquid mercury.
• Located inside homes• Mercury was spilled during replacement• Approximately 200,000 homes affected
7
Exposure ValuesExposure Values
• Illinois environmental values– Illinois Department of Public Health
(IDPH), the ATSDR, EPA and other local agencies agreed upon acceptable environmental levels.
8
Illinois ReIllinois Re--occupancy occupancy Environmental LevelsEnvironmental Levels
3 µg/m3Industrial-Commercial
<1 µg/m3Residential
Indoor Air Concentration
Level Acceptable for Re-occupancy
9
Exposure ValuesExposure Values
• Since there had been a consensus between the IDPH, ATSDR, EPA and other agencies in the Illinois case, we decided to used the ATSDR industrial-commercial clearance level of 3 µg/m3.
10
Assessment StrategyAssessment Strategy• Use direct reading instrument to survey
areas and identify potential areas of concern.
– Two instruments available • Instrument “A”
– Detection minimum detection level of 3 µg/m3
• Instrument “B”– Detection minimum detection level of 0.002 µg/m3
– Instrument “B” was used due to the increased sensitivity.
11
Assessment StrategyAssessment Strategy• Any area with visible mercury or
measurements above the Illinois industrial/commercial clearance levels (3 µg/m3) was considered contaminated.– Contour map developed or highlighted
photograph used to identify where contamination was found.
12
Remediation StrategyRemediation Strategy
• All contaminated areas were cleaned by a contractor with mercury remediation experience.
14
Case StudiesCase Studies•• Case 1:Case 1:
Laboratory where mercury had been used in experiments for years. Lab was scheduled for a major renovation. Lab officials wanted the area checked for asbestos and mercury prior to demolition/renovation.
15
Case Study 1Case Study 1• Initial assessment:
– Mercury concentrations ranged from 0.3 µg/m3 to >260 µg/m3
– Highest concentrations near a fume hood
– Elevated concentrations also observed above asbestos floor tile located near the fume hood.
16
Case Study 1 Case Study 1 • Asbestos and mercury remediation
was recommended• Contractor with asbestos and
mercury abatement experience was hired to perform the remediation.
17
Case Study 1 Case Study 1 • Removal techniques
– Containment with decontamination chamber (DCU)
– Workers wore disposable clothing and respirators equipped with HEPA/mercury filters.
– Vacuums and negative air machine equipped with HEPA/mercury filters.
18
Case Study 1 Case Study 1 • Remediation techniques
– Asbestos materials removed first• Increase in airborne mercury (Hg) vapors
seen when tile was removed– Possible contamination under the tile?
– Following the asbestos removal• Hg Sorb®, a mercury absorbent was used
on floor and other contaminated areas. This was followed by a through cleaning of the areas with Red Devil TSP/90®
19
Case Study 1 Case Study 1 • Air samples collected during
remediation– Samples for both asbestos and mercury
collected during removal.– Asbestos samples collected in
accordance with NIOSH 7400– Mercury concentrations measured with
the direct reading instrument
20
Case Study 1Case Study 1• Multiple cleanings were conducted
– Cleaning process repeated for mercury until area measurements indicated that airborne mercury concentrations were below 3 µg/m3 (ATSDR commercial level)
• Cleanings performed 6 times over four days
21
Case Study 1 Case Study 1 • Waste
– All asbestos waste double bagged– All waste bags tested for mercury
contamination prior to disposal with the direct reading instrument
• Waste > 1 µg/m3 (the residential clearance criteria) considered potentially contaminated and TCLP analysis performed.
• If TCLP analysis indicated levels > 0.2 mg/L (EPA limit) the material was disposed of as mercury waste.
22
Case Study 1 Case Study 1 • Waste (Continued)
– Any elemental mercury or known mercury contaminated wastes were placed into plastic drums or buckets.
– This waste was sent to a licensed metal disposal/recycling facility.
23
Case Study 1 Case Study 1 • Final mercury air samples (continued)
– When direct reading instrument indicated that mercury concentrations in the remediated area were below 3 ug/m3 final air samples were collected.
– Final air sampling methodology • Five (5) samples collected throughout the lab• NIOSH Method 6005 on SKC® Hydrar® sorbent
tubes• seven to eight hours sampling duration • Ambient temperature kept above 75oF during
collection
24
Case Study 1 Case Study 1 • Final mercury air samples (continued)
– Area was released when air samples indicated the mercury concentrations were at or below the ATSDR industrial/commercial level of 3 µg/m3.
26
Case Study 2Case Study 2•• Case 2:Case 2:
Three story college science hall scheduled for sale and possible demolition. Mercury use in building was unknown but suspected. Limited visible mercury observed in a couple of areas.
27
Case Study 2Case Study 2• Mercury survey completed with the
direct reading instrument• Same criteria used as in Case 1• Isolated areas of mercury
contamination identified.• Highlighted digital photographs used
to indicate contaminated areas.
29
Case Study 2Case Study 2• Mercury remediation of contaminated
areas recommended.• Remediation performed, similar to
that used in Case 1.– Regulated areas were used instead of
full containment.• Limiting access to contaminated areas• Full PPE for remediation crew.• Disposable foot coverings used to prevent
potential tracking of mercury.
30
Case Study 2Case Study 2• Direct reading instrument used to evaluate
remediation progress.• Findings during remediation
– Visible mercury found underneath cabinets and ceramic tiles near cabinets.
– Mercury detected in some of the drain pipes.• Horizontal pipes removed• Vertical pipes flushed with mercury surfactant
31
Case Study 2Case Study 2• Main catch basin for the building was
tested for mercury.– Water & sludge tested
• Water results compared Local Sanitary Districts discharge limits for mercury
• Sludge sent for TCLP analysis.– Water and sludge were contaminated.– Test performed prior to pipe cleaning.
32
Case Study 2Case Study 2• On-site sewer system tested
– Same environmental criteria applied to manholes as the catch basin.
– Mixed results• Sludge contaminated in three of the four
manholes tested.• Water in most manholes was not
contaminated.
33
Case Study 2Case Study 2• On-site sewer system cleaned
– Cleaning performed by a licensed hazardous waste/remediation
• Sewer vacuum/cleaning truck utilized.• All sludge & water removed
– Direct reading instrument was used to evaluate sewer cleaning
• Considered clean when measurements below the ATSDR level of 3 µg/m3.
35
Case Study 2Case Study 2Bottom of cabinet and floor tile removed to access
mercury contamination.
37
Case Study 2Case Study 2• Final air samples (continued)
– When direct reading instrument indicated that mercury concentrations were below 3 µg/m3
final air samples were collected.– Final air sampling methodology
• Eight (8) samples collected on each floor of the building.
• NIOSH Method 6005 on SKC® Hydrar® sorbent tubes.
• Seven to eight hour sample duration. • Ambient temperature kept above 75oF during
collection
38
Case Study 2Case Study 2• Final air samples (continued)
– Area was released when air samples indicated the mercury levels were at or below the ATSDR industrial/commercial clearance level of 3 µg/m3.
39
Lessons LearnedLessons Learned1. Instrument “B” was an excellent instrument
to use for the initial inspection, monitoring of remediation and for use prior to final air sampling.
2. Mercury contamination can be worse than it originally appears.
3. The ATSDR’s recommended industrial/commercial clearance level of 3 ug/m3 was achievable.
40
Speaker Contact Information:Speaker Contact Information:
David C. Regelbrugge, CIH, CSPDirector, Environmental Health & SafetyBoelter & Yates, Inc.847/[email protected]