S# Inputs Tools & Techniques Outputs 12 1. Scope Baseline 1. Decomposition DERT 1. Activity List 2. EEF (MI) 2. Rolling Wave Planning 2. Activity Attributes  3. 3. Milestone list 4. E J 13 1. Activity List 1. PDM ( D M) 1. Project Schedule Network Diagrams 2. Activity Attributes   AN (AN) 2. D 3. Milestone List 2. Dependency Determination 4. Project Scope Statement 3. Applying Leads and Lags  4. N 14 1. Activity list  1. A A 1. Activity Resource Requirements 2. Activity Attributes 2. Bottom-up Estimating 2. Resource Breakdown Structure   3. Resource Calendars  (A / C ) 3. E D 3. D 4. EEF 4. M  5. E J 15 1. Activity List  1. E J PETRA 1. Activity Duration Estimates 2. Activity Attributes 2. Analogous Estimating ( D / G ) 3. Activity Resource Requirements 3. Parametric Estimating ( ) 4. Resource Calendars  (A / C ) 4. Three-point Estimates  2. D 5. Project Scope Statement 6. EEF 16 1. Activity List 1. Critical Path Method CCS SWARS 2. Activity Attributes 2. Critical Chain Method 3. Project Schedule Network Diagrams 3. Schedule Compression (C & F ) 2. Schedule Baseline 4. Activity Resource Requirements 4. Resource Leveling 3. Schedule Data 5. Activity Duration Estimates 5. Applying Leads and Lags  4. D 6. Resource Calendars  (A / C ) 6. What-if Scenario Analysis (MC A) 7. Project Scope Statement  7. 8. EEF 8. N A ( C) 17 1. Project Management Plan 1. PPV SWARS 1. Work Performance Measurements ( / I) 2. Project Schedule 2. Variance Analysis (/I)  2. C 3. Work Performance Information (D&M E) 3. Schedule Compression (C & F ) 3. M 4. Resource Leveling  4. D 5. Adjusting Leads and Lags  5. A 6. A 7. 8. M #   . . # : E . .         &     # : F , , . 1. Project Schedule (F 1. M C, 2. B C, 3. N D) (6)    5 & 1 &   . # B , C .   .   >> A ( ). # . # A . # ( A/ & )   . # # F (F): A ( ; ). # (): A . # FF (FF): A . # F (F) : A ( ). # M (H ), D ( , , ), & E ( / )   , , , . # C HEN H LNG .   . # 2 ( ) :   . .   . I H &  . I , , & . I . # 3 / : I HIICAL DAA HE AIABLE (E: ) , , , . I . C = . # 4 3 : C , , , M L () = (++)/3 # E ( E & )/B / 3 E = (+4+)/6 # D σ = ()/6 # = ()/62. # E: B . , , . ( : E J, C, L, & E) . # D: ( & ) B . . ( D : A & C) . # E : . # H: (A ) . & .   , , , . I . # 1  I E /F , & L /F , , F/B . C & . C E NEGAIE F. # F// F: A . F C 0. (C ) = . # F F: . # F: /. # 2   . . I 1. , 2. , 3. , 4. 5. . CCM . I CCM; 2 : 1. B ( C C), 2. F B ( C C FC). # 4  L & . I & , # . I  . I . # 5 & # LEAD: A (: ). # LAG: / (E: 3 ). # 3  C . I . C . F  . I                                                                                                 (I ' LAG. I . E., 2 +/ 2 )                                                                 5. Reserve Analysis (A , , , E).

description

uil;;

Transcript of PMP Notes Chowdary Anil - Time

  • S# Inputs Tools & Techniques Outputs

    12

    1. Scope Baseline 1. Decomposition DERT 1. Activity List

    2. EEF (PMIS) 2. Rolling Wave Planning 2. Activity Attributes

    3. OPA 3. Templates 3. Milestone list

    4. Expert Judgment

    13

    1. Activity List 1. PDM (Precedence Diagramming Method) 1. Project Schedule Network Diagrams

    2. Activity Attributes or AON (Activity-on-Node) 2. Project Document Updates

    3. Milestone List 2. Dependency Determination

    4. Project Scope Statement 3. Applying Leads and Lags

    5. OPA 4. Schedule Network Templates

    14

    1. Activity list 1. Alternatives Analysis 1. Activity Resource Requirements

    2. Activity Attributes 2. Bottom-up Estimating 2. Resource Breakdown Structure ^^

    3. Resource Calendars ^^ (Acq Proj Team / Cond Proc) 3. Published Estimating Data 3. Project Document Updates

    4. EEF 4. Project Management Software

    5. OPA 5. Expert Judgment

    15

    1. Activity List 1. Expert Judgment PETRA 1. Activity Duration Estimates

    2. Activity Attributes 2. Analogous Estimating (Top Down / Gross Value)

    3. Activity Resource Requirements 3. Parametric Estimating (uses statistical relationship)

    4. Resource Calendars ^^ (Acq Proj Team / Cond Proc) 4. Three-point Estimates 2. Project Document Updates

    5. Project Scope Statement

    6. EEF

    7. OPA

    16

    1. Activity List 1. Critical Path Method CCS SWARS

    2. Activity Attributes 2. Critical Chain Method

    3. Project Schedule Network Diagrams 3. Schedule Compression (Crashing & Fast Tracking) 2. Schedule Baseline

    4. Activity Resource Requirements 4. Resource Leveling 3. Schedule Data

    5. Activity Duration Estimates 5. Applying Leads and Lags 4. Project Document Updates

    6. Resource Calendars ^^ (Acq Proj Team / Cond Proc) 6. What-if Scenario Analysis (Monte-Carlo Analysis)

    7. Project Scope Statement 7. Scheduling Tool

    8. EEF 8. Schedule Network Analysis

    9. OPA (Project Calendar)

    17

    1. Project Management Plan 1. Performance Reviews PPV SWARS 1. Work Performance Measurements (SV / SPI)

    2. Project Schedule 2. Variance Analysis (SV/SPI) 2. Change Requests

    3. Work Performance Information (Dir&Mng P Exec) 3. Schedule Compression (Crashing & Fast Tracking) 3. Project Management Plan Updates

    4. OPA 4. Resource Leveling 4. Project Document Updates

    5. Adjusting Leads and Lags 5. OPA Updates

    6. What-if Scenario Analysis

    7. Scheduling Tool

    8. Project Management Software

    # Path Convergence: The merging or joining parallel schedule network paths into the same node in a project schedule network diagram. Path convergence is characterized by a schedule

    activity with more than one predecessor activity. # Path Divergence: Extending or generating parallel schedule network paths from the same node in a project shedule network diagram.

    Path devergence is characterized by a schedule activity with more than one successor activity.

    M &

    C

    # HAMMOCK Activity: For control and mangement communication, the broader, more comprehensive summary activity.

    1. Project Schedule (Formats 1. Milestone Charts, 2. Bar

    Charts, and 3. Project Schedule Network Diagrams)

    TI (6) ME 5 Planning & 1 Monitoring&Controlling

    Control Schedule: The process of monitoring the status of the project to update project progress and managing changes to the schedule baseline.

    # Schedule Baseline is updated, whenever the Customer requests a significant change and when original estimates were wrong.

    Define Activities: The process of identifying the specific actions to be performed to produce the project deliverables. WPs >> Activities (work necessary to complete the WP).

    # Rolling wave planning lets you plan as you go. # Projects using Agile methodologies use a form of RWP. # Planning Package (placeholder put between control A/cs & WPs)

    Sequence Activities: The process of identifying and documenting relationships among the project activities. # PDM - # Finish-to-Start (FS): An activity must finish before the successor

    can start (dig hole; plant tree). # Start-to-Start (SS): An activity must start before the successor can start. # Finish-to-Finish (FF): An activity must finish before the successor can finish.

    # Start-to-Finish (SF): An activity must start before the successor can finish (rarely used). # Types of Dependencies - Mandatory (Hard logic), Discretionary (Preferred logic, Preferential

    logic, Soft logic), & External (relationship b/w proj and non-proj activities)

    Estimating Activity Resource: The process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity.

    # Resource Calendars specify WHEN and HOW LONG identified project resource will be available during the project.

    Estimating Activity Duration: The process of approximating the number of work periods needed to complete individual activities with estimted resources.

    # TT2 - Analogous (top down): look at activities from previous similar activities . The degree of similarity affects accuracy. This technique should be used early in estimating cycle when

    there is not much detail known about the activity. It uses Historical information & expert judgement . It is less costly, less time consuming than others, & less accurate . It can be

    applied to a total project or to segments of a project and may be used in conjunction with other estimating methods. # TT3 - Parametric/Quantitately - Based Estimating: It uses a

    statistical relationsip between HISTORICAL DATA and OTHER VARIABLES (Ex: Square footage in construction) to calculate an estimate for activity parameters, such as cost, budget, and

    duration. It can be applied to a total project or to segments of a project and may be used in conjunction with other estimating methods. Cost = Qty in units X Unit Rate. # TT4 - 3-Point

    Estimate or Triangular Distribution: Come up with three points, Optimistic, Pessimistic, and Most Likely (Realistic) = (P+R+O)/3 # PERT (Program Evaluation & Review

    Technique)/Beta/Weighted 3-Point Estimate = (P+4R+O)/6 #Standard Deviation = (P-O)/6 #Variance v = [(P-O)/6]^2.

    # Effort: The number of labour units required to complete a schedule activity or WBS component. Usually expressed as staff hours, staff days, or staff weeks. (Requirements for effort

    estimation: The Expert Judgement, Task Complexity, Skill Level, & Expectations). # Duration: The total number of work periods (not including holidays & non-working periods)

    required to complete a schedule activity or WBS component. Usually expressed as workdays or workweeks. (Requirements for Duration estimation: Resource Availability & Resource

    Capability). # Elapsed Time: Waiting periods. # Heuristics: Rules (A rule of thumb) for which no formula exists. Usually derived through trial & error.

    Develop Schedule: The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. It determines the planned

    start and finish dates for project activities and milestones. # TT1 Critical Path Method: It calculates the theoretical Early Start/Finish dates, & Late Start/Finish dates, for all activities

    without regard for any resource limitations, by performing a Forward/Backward pass analysis through the schedule network. Critical Path is the longest duration path through a

    network diagram & determines min time required to complete the proj. CPs have either ZERO or NEGATIVE Total Float. # Float/Slack/Total Float: Amt of time an activity can slip

    before it causes delay in proj. Float for activities on CP is 0. (CP - next longest path) = float. # Free Float: amt of time an activity can be delayed without affecting the early start date of

    subsequent dependent activities. # Proj Float: amt of time a proj can be delayed without delaying externally imposed proj completion date required by customer/mgmt. # TT2 Critical

    Chain Method: The resource-constrained critical path is known as the Critical Chain . The longest sequence of resource-leveled tasks is the critical chain. It tries to adjust for problems

    in estimating and managing tasks that result from 1. poor multi-tasking, 2. estimates with too much contingency for uncertainty, 3. work that expands to fill the available time, 4.

    waiting until the latest possible time to start and 5. lack of prioritization. CCM focuses on managing remaining buffer durations against the remaining durations of task chains. In CCM;

    buffers are 2 types: 1. Project Buffer (Protects the target finish date from slippage along the Critical Chain), and 2. Feed Buffer (Protects the Critical Chain from slippage along the

    Feeding Chains). # TT4 Resource Leveling: Leveling lets the schedule slip & the cost increase in order to deal with resource constraints. It allows to level the peaks & valleys of

    resource use, resulting in more stable # of resources used in the proj. It can be used when shared or critical required resources are only available at certain times, are only available in

    limited quantities, or to keep resource usage at a constant level . It can often cause the original critical path to change. # TT5 Leads & Lags: # LEAD: A lead can be added to start an

    activity before completion of the predecessor (eg: start writing the training material before completion of the testing). # LAG: is inserted waiting time b/w activities (Ex: needing to

    wait 3 days after pouring concrete before constructing the frame of house). # TT3 Schedule Compression: Crashing involves adding extra resources to reduce proj duration. Over

    Time is considered as Crashing. It almost always increases cost. Cheapest task has to be crashed first. Fast-Tracking involves doing critical path activities in parallel . It often results in

    rework & usually increases risk.

    PLA

    NN

    ING

    PLA

    NN

    ING

    PLA

    NN

    ING

    (It doesn't include LAGs. It may include some indication of

    the range of possible results. Eg., 2 weeks +/- 2 days)

    PLA

    NN

    ING

    PLA

    NN

    ING

    5. Reserve Analysis (As more precise information about

    the project becomes available, the Contingency Reserve

    may be Used, Reduced, or Eliminated).