Project Management InstitutePractice Standard for Project Estimating
Asep Nurul Haq, S.T., PMPProposal Coordinator
© 2010 McDermott International, Inc. All rights reserved.
Month, YearP.T. McDermott Indonesia
![Page 2: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/2.jpg)
Preface
This presentation is prepared as reading notes prepared as backup for PDU claim required to maintain writer’s PMP
Writer also wish that this reading notes be useful to others interested in understanding estimating from PMI’s perspective
Content is extracted from PMI Practice Standard for Project Estimating (here forth referred to as “The Book”). All rights reserved.
![Page 3: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/3.jpg)
The Book’s Table of Content
1. Introduction
2. Principles & Concepts
3. Prepare to Estimate
4. Create Estimate
5. Manage Estimate
6. Improve Estimating Process
![Page 4: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/4.jpg)
1. Introduction - Definition
Estimate – A quantitative assessment of the likely amount or outcome.
Project Estimating – The act of creating a quantitative assessment of the likely amount or outcome. It is usually applied to:. Activity Resource
Activity Duration
Costs
Baseline – An approved plan for a project, will be compared to the actual performance.
Continue improving/ detailing a plan or estimate as more information is received is called “Progressive Elaboration”
![Page 5: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/5.jpg)
2. Principles & Concept
Continue improving/ detailing a plan or estimate as more information is received is called “Progressive Elaboration”
![Page 6: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/6.jpg)
Estimating Life Cycle
![Page 7: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/7.jpg)
Causes of Estimating Variances
Variance is the difference between baseline vsactual cost
The causes are: Evolution of requirements
Approved change request
Operational Problems
Faulty Estimating
![Page 8: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/8.jpg)
Basic Characteristics of a Good Estimate
Clear identification of task
Broad participation in preparing estimates
Availability of valid data
Standardized structure for the estimate
Provision for uncertainties
Recognition of inflation
Recognition of excluded cost
Independent review of estimates
Revision of estimates for significant project changes
![Page 9: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/9.jpg)
3. Prepare to Estimate
1. Inputs:1) Project Documents
Requirements documentation
Scope baseline
Activity list
Risk Register
Resource Calendar
2) Experts
3) Estimating Techniques (analogous/ parametric/ bottom up)
4) Constraints and Assumptions (scope/ duration/ cost)
5) Additional Influences (organization process assets/ enterprise environmental factors)
6) Historical Project Information (past project effort/ schedule/ cost/ resources/ documentation)
![Page 10: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/10.jpg)
3. Prepare to Estimate (Cont..)
2. Activities: Create Project Estimating Approach1) Scope of Estimate
2) Organizational Process Assets
3) Project Work Information
4) Estimating Assumptions
5) Constraints
6) Estimation Techniques
7) Resources Needed to Estimate
8) Estimate Confidence
9) Contingency Reserve Planning
![Page 11: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/11.jpg)
3. Prepare to Estimate (Cont..)
3. Outputs: Estimating Approach & Estimating Information
4. Considerations: Allocate appropriate time to plan
Proper Stakeholder Expectations Management
False perception of level of accuracy (round numbers to avoid this!)
![Page 12: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/12.jpg)
4. Create Estimates
1. Inputs1. Project Estimating Approach
2. Estimating Information
3. Estimators
4. Enterprise Environmental Factors
5. Organizational Process Assets
2. Activities1. Analogous/ top down estimating -> little info, less precise, faster
2. Parametric -> more info, more precise estimate, slower
3. Bottom Up -> complete info, most precise estimate, slowest
3. Outputs: Completed Estimate and Basis of Estimates
![Page 13: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/13.jpg)
4. Create Estimates
4. Considerations1. Optimism in Estimates
best man best day?/ no rework?
2. Progressive elaboration of estimates
fine tune as more detail is available
3. Cost-Schedule interrelationship
change in schedule = change in cost
4. Normalization of historical data
time/ location/ different type of project?
5. Accounting for time
inflation/ escalation?
5. Expert Judgment
consult the expert to validate estimate
![Page 14: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/14.jpg)
Estimating Techniques
1. Analogous EstimateUsually used to develop early and rough estimates of the project, appropriate when there’s significant similarity between proposed project and historical data
1. Ratio Estimating -> project cost = n x cost of deliverable (i.e. material, equipment, manpower, etc)
2. Power-Series Estimating -> project cost = (ratio of deliverable)n x cost
3. Range Estimating -> $$ < project cost < $$$
4. Three-Point Estimating -> cost = (low + 4 x mid estimate + high)/6
2. Parametric Estimate ->
Cost = vol of work x unit rate
3. Bottom Up EstimateEstimating to lowest level element of WBS, known as work package and then rolled up to project level.
![Page 15: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/15.jpg)
5. Manage Estimates
1. Inputs1. Baseline Estimates (project cost, schedule and resource histogram)
2. Approved Changes (approved change order)
3. Resource Plan (human / facilities/ equipment resource plan)
4. Work Performance Information (compare to actual cost)
5. Organizational Process Assets (company project control procedure?)
6. Project Estimating Approach
2. Activities: Manage estimates
3. Outputs1. Updated Estimates
2. Updated Forecast
3. Updated Change Request Log
4. Reporting and Communication
![Page 16: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/16.jpg)
6. Improve Estimating Process
Build up benchmarking from: Competitor’s price
Project historical data
Lessons learned from: Miss bids
Estimating process
![Page 17: PMI Project Estimating](https://reader030.fdocuments.in/reader030/viewer/2022020206/545fe4d6b1af9f04598b4ffe/html5/thumbnails/17.jpg)
Q&A