PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

52
1 For the PMP® Exam using PMBOK® Guide 5 th Edition © Khaled El-Nakib, MSc, PMP, PMI-RMP 2015 PMI®, PMP®, PMBOK® Guide are registered trade marks of Project Management Institute, Inc.

Transcript of PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

Page 1: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

1

For the PMP® Exam using PMBOK® Guide 5th Edition

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

PMI®, PMP®, PMBOK® Guide are registered trade marks of Project Management Institute, Inc.

Page 2: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

2

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Contacts

• Name: Khaled El-Nakib, MSc, PMP, PMI-RMP

• URL: http://www.khaledelnakib.com

• E-mail: [email protected]

• LinkedIn: https://eg.linkedin.com/pub/khaled-el-nakib-msc-pmp-pmi-rmp/16/471/6a8

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Project Time Management

Project Time Management includes the processes required to manage timely completion of the project

Page 3: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

3

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Time Management Processes

Project Time Management

(6.1)Plan Schedule Management

(6.2)

Define Activity

(6.3)Sequence

Activity

(6.4)Estimate

Activity Resource

(6.5)Estimate

Activity Duration

(6.6)Develop

Schedule

(6.7)Control

Schedule

PlanningMonitoring and

Controlling

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Time Management Processes

Flexible combination of planning processes:

1. In simple, low risk projects all five processes can be seen as one big process.

2. In complex, high risk projects they can be seen as five distinct processes

Page 4: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

4

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.1 – Plan Schedule Management

• Plan Schedule Management is the process of establishing the policies, procedures and documentation for planning, developing, managing, executing, and controlling the project schedule.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.1 – Plan Schedule Management

Inputs:

IN-1: Project management plan

IN-2: Project charter

IN-3: Enterprise environmental factors

IN-4: organizational process assets

Page 5: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

5

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-1: Expert Judgment

• Expert judgment refers to input received from knowledge and experienced parties

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-2: Analytical Techniques

• Choosing from options such as:

• Scheduling software

• Scheduling tools

• Estimating approaches

• Formats

Page 6: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

6

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-3: Meetings

• Project team may attend project meetings to develop the schedule management plan.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-1: Schedule Management Plan

• A document that establishes criteria and the activities for developing and controlling the project schedule

It includes, but not limited to the following:

1. Scheduling tool

2. Level of accuracy

3. Rules of performance measurements

4. How schedule variances will be handled

5. Schedule change control procedures

6. Reporting format

Page 7: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

7

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.2- Define Activity

Define activities is the process of identifying the specific actions to be performed to produce the project deliverables

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.2- Define Activity

Purpose of process

Decomposing the work package into smaller components called Schedule Activities to provide a basis for estimating

Page 8: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

8

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.2- Define Activity

Inputs:

IN-1: Schedule Management Plan

IN-2: Scope Baseline

IN-3: Enterprise Environmental Factors

IN-4: Organizational Process Assets

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-1: Decomposition

• Subdivision of work packages into smaller, more manageable components called Schedule Activities

Page 9: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

9

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-2: Rolling Wave Planning

• It is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail at a low level of WBS

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-3: Expert judgment

• Project team members or other experts who are experienced and skilled in developing detailed project scope statement, WBS’s, and project schedule provide expertise in defining activities.

Page 10: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

10

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-1: Activity List

• The activity list is a comprehensive list including all schedule activities that are planned to be performed on the project.

• Activity list is a component of the project management plan.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-2: Activity Attributes

• Activity attributes are an extension of the Activity attributes in the activity list and identify the multiple attributes associated with each schedule activity.

• It may include:activity code, description, predecessor, successor, logical relationship, leads

and lags, resource requirements, imposed dates, constraints, and assumptions.

Page 11: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

11

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-3: Milestone List

• A milestone is a significant event in the project, usually completion of a major deliverable

• A milestone has duration of zero and no effort

• A list of schedule milestone identifies all milestones and indicates whether the milestone is mandatory, or optional.

• Milestone list is a component of the project management plan.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.3 - Sequence Activity

• Sequence activity involves identifying and documenting the logical relationships among project activities.

Page 12: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

12

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Inputs

IN-1: Schedule Management Plan

IN-2: Activity List

IN-3: Activity Attributes

IN-4: Milestone List

IN-5: Project Scope Statement

IN-6: Organizational process assets

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-1: Dependency Determination

• Mandatory dependencies :(i.e., hard logic): These are dependencies that cannot change

• Discretionary dependencies :(i.e., soft logic): These are dependencies that may be at the discretion of the project management team

• External dependencies:These are dependencies that may be beyond the control of the project team

• Internal dependencies:These are dependencies between project activities, and generally inside the project’s team control

Page 13: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

13

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-2:Applying Leads and Lags

• Lead

• Allows an acceleration of the successor activity

• Lag

• Directs a delay in the successor activity

Activity A

Activity B

Activity A

Activity B

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-3: Preceding Diagramming Method (PDM)

• PDM is a method of constructing a project schedule network diagram used by most project management software packages

• It is also called Activity on Node (AON)

Page 14: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

14

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Preceding Diagramming Method (PDM) (Continued)

• Finish Installing Windows in order to start installing Office

Activity A

Activity B

Finish Activity A to Start Activity B

Finish-to-Start

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Preceding Diagramming Method (PDM) (Continued)

• Start coding (Activity B) 5 days after starting design (Activity A)

Activity A

Activity B

Start Activity A to Start Activity B

Start-to-Start

Page 15: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

15

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Preceding Diagramming Method (PDM) (Continued)

• Finish buying the new truck in order to end finish ending rent contract

• Finish writing last chapter to finish writing the whole book

Activity B

Activity A

Finish Activity A to Finish Activity B

Finish-to-Finish

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Preceding Diagramming Method (PDM) (Continued)

• Theoretical, rarely used

• Start night shift to finish day shift

Activity B

Activity A

Start Activity B to Finish Activity A

Start-to-Finish

Page 16: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

16

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-1: Project Schedule Network Diagram

• Project schedule network diagrams are schematic display of the project’s schedule activities and the logical relationships among them.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-2: Project Documents Updates

• Activity List (Updates)

• Activity Attributes (Updates)

• Risk Register

Page 17: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

17

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.4 - Estimate Activity Resource

• Estimate activity resources is the process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Inputs

IN-1: Schedule Management Plan

IN-2: Activity List

IN-3: Activity Attributes

IN-4: Resource Calendars

IN-5: Risk Register

IN-6: Activity Cost Estimate

IN-7: Enterprise environmental factors

IN-8: Organizational process assets

Page 18: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

18

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-1: Expert Judgment

• Any group or person with specialized knowledge in resource planning a and estimating can provide such expertise.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-2: Alternative Analysis

• You can accomplish an activity in more than one way.

• Define the combination of:

• Resource capability and skills levels

• Machine type

• Different tools

• Resource related buy or make decision

Page 19: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

19

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-3: Published Estimating DataPublished Estimating DataPublished Estimating DataPublished Estimating Data

• Some organizations publishes production rates, unit cost for labor, materials, equipments, for different countries and geographical locations within countries

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-4: Bottom Up Estimating

• When a scheduled activity cannot be estimated with reasonable degree of confidence, the work within the schedule activity is decomposed into more detail.

Page 20: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

20

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-5: Project Management Software

• Project management software has the capability to help plan, organize, and manage resource pools and develop resource estimates.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-1: Activity Resource Requirements

• Identification and description of the types and quantities of resources required for each schedule activities in a work package

• It may include:

• Basis of estimate

• Assumptions

• Availability

• Quantity

Page 21: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

21

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-2: Resource Breakdown Structure (RBS)

• A hierarchical structure of the identified resources by resource category and resource type

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-3: Project Documents Updates

• Activity List (Updates)

• Activity Attributes (Updates)

• Resource Calendars

Page 22: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

22

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.5 - Estimate Activity Durations

• Estimating activity durations process is the process of estimating the number of work periods needed to complete individual activities with estimated resources

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Effort VS Duration

• Effort: the number of units required to complete a schedule activity or WBS component. Usually expressed as staff hours, staff days, or staff weeks.

• Duration: The total number of work periods(not including holidays or other nonworking periods) required to complete a schedule activity or WBS component.

• Elapsed Time: The amount of time that elapses between the

time the task is started and the time it is completed

Page 23: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

23

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.5 - Activity Duration Estimate Inputs

1. Schedule Management Plan

2. Activity list

3. Activity attributes

4. Activity resource requirements

5. Resource calendars

6. Project scope statement

7. Risk Register

8. Work Breakdown Structure

9. Enterprise environmental factors

10. Organizational process assets

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-1: expert judgment

• One time estimate means one estimate per activity is received.

• Disadvantages:

• Padding (providing worst-case estimates)

• Hiding information about risks and uncertainties

• Untruthfulness when activity takes less period

• Lack of experience produce risky estimates

Page 24: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

24

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-2: Analogous Estimate

• A.K.A. Top-down estimating

• Using actual duration of a previous similar schedule activity as the basis for estimating the duration of future schedule activity.

• Used when there is limited information

• Uses both historical data and expert judgment

• Useful when activities are really similar not just in appearance.

• Usually used in early planning phase

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-3: Parametric Estimating

• Multiplying the quantity of work to be performed by the productivity rate.

• Example:

• Cable installation in meters/ labor hours

• Line if code/shift

Page 25: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

25

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-4: Three-Point Estimate

• Program Evaluation and Review Technique (PERT)

• PERT uses three time estimates (optimistic, most likely, and pessimistic

• PERT is probabilistic in nature, based on a beta distribution for each activity time and a normal distribution for expected time duration

• PERT is used on those projects where percent complete is almost impossible to determine except at completed milestones (R&D)

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

PERT Calculations

• Activity Duration Estimation

• Most optimistic completion time. This time assumes that everything will go according to plan and with minimal difficulties

• Most pessimistic completion time. This time assumes that everything will not go according to plan and maximum difficulties will develop

• Most likely completion time. This is the time that, in the mind of the functional manager, would most often occur should this effort be reported over and over again

Page 26: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

26

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

PERT Calculations (continued)

Estimated activity duration =

In order to calculate the probability of completing the

project on time, the standard deviations of each activity

must be known

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-5: Group Decision Making Techniques

• Unanimity (complete agreement by everyone)

• Majority (one vote more than 50% of total votes)

• Plurality (largest number of votes)

• Dictatorship (one person makes the decision)

Page 27: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

27

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-6: Reserve Analysis

• Project team can choose to incorporate additional time referred to as contingency reserve, time reserve or buffer, into the overall project schedule as recognition of schedule risk.

• The contingency reserve can be used completely or partially, reduced or eliminated

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-1: Activity Duration Estimate

• Activity duration estimate are quantitative assessments of the likely number of work period that will be required to complete a schedule activity.

• 15days – 19days

• 17 days ± 2days

• 80% activity duration 17 days

Page 28: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

28

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-2: Project Document Updates

• Activity attributes are updated to include the durations for each schedule activity, the assumptions made in developing the activity duration estimates, and any contingency reserve.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

What do we have now?

• Activity list

• Activity scope of work

• Activities dependencies

• Required resource types

• Required resource quantities

• Resource calendars

• Resource availability

• Schedule activity duration

Page 29: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

29

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.6 - Develop Schedule

• Purpose: to determine planned start and finish dates for project activities.

• Schedule development continues throughout the project as work progresses, the project management plan changes, and anticipated risk events occur or disappear, or new risks are identified

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Inputs

1. Schedule Management Plan

2. Activity list

3. Activity attributes

4. Project schedule network diagram

5. Activity resource requirements

6. Resource calendars

7. Activity duration estimates

8. Project scope statement

• Schedule related Assumptions and Constraints

Page 30: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

30

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Inputs (continued)

9. Risk Register

10.Project staff assignments

11.Resource breakdown structure

12.Enterprise environmental factors

13.Organizational process assets

• Project calendar (working days, non working days ,shifts)

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-1: Schedule Network Analysis

• Schedule network analysis is a technique that generates the project schedule.

Page 31: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

31

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-2: Critical Path Method (CPM)

• The critical path method calculate theoretical early start and finish dates, and late start and finish dates for all schedule activities without regard for any resource limitations by performing a forward pass analysis an a backward pass analysis through the project schedule network.

• Purpose: determine schedule flexibility.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Critical Path Calculation (continued)

Page 32: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

32

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Critical Path Calculation

• Earliest start times (forward pass)

• Earliest starting time of a successor activity is the latest of the earliest finish dates of the predecessors

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Critical Path Calculation (continued)

Page 33: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

33

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Critical Path Calculation (continued)

• Latest starting times (Backward pass)

• The latest finishing time for an activity entering a node is the earliest Late starting time of the activities exiting the node

• The latest starting time can be calculated by subtracting the activity time from the latest finishing time

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Critical Path Calculation (continued)

Page 34: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

34

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Critical Path characteristics

• The longest path through the project

• Activities on the Critical Path have ZERO float

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Total Float

• The amount of time you can delay the earliest start of a task without delaying the ending of the project

Page 35: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

35

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Total Float Calculation (continued)

(10-6) or (17-13)(6-0) or (10-4) (17-13) or (22-18)

Float = LS – ES Float = LF – EF OR

(9-6) or (14-11)(14-14) or (22-22)

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Free Float

• The amount of time you can delay the start of a task without delaying the earliest start of a successor task

• Free float can only occur when two or more activities share the same successor

Page 36: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

36

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Free Float Calculation

6-4 = 2 6-6 = 0

Free Float = ES2 – EF1

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-4: Resource optimization techniques

• Resource Leveling

• Also called the resource-based method—is used when resources are limited or time constrained (especially those assigned to critical path activities) and when specific schedule dates need to be met

• Resource Leveling approach can cause the original critical path to change

Page 37: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

37

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-4: Resource optimization techniques

• Resource Smoothing

• A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed predefined resource limits.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-5: Modeling Techniques

• What-if scenario analysis is the process of evaluating scenarios in order to predict their effect, positively or negatively on project objectives

• Simulation involves calculating multiple project durations with different set of activity assumptions.

Page 38: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

38

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-6: Applying Leads and LagsApplying Leads and LagsApplying Leads and LagsApplying Leads and Lags

• Lags

• Delay successor activities and require time added either to the start date or to the finish date of the activity

• Leads

• Require time to be subtracted from the start date or the finish date of the activity

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-7: Schedule Compression

• Schedule compression shortens the project schedule without changing the project scope, to meet the schedule constraints, Imposed dates, or other schedule objectives. It includes two techniques:

1. Crashing

2. Fast tracking

Page 39: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

39

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Schedule Crashing

• A technique in which cost and time tradeoffs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Schedule Crashing (continued)

Time , weeks Costs Crashing cost per week, $Activity Normal Crash Normal Crash

A 4 2 10000 14000 2000B 6 5 30000 42500 12500C 2 1 8000 9500 1500D 2 1 12000 18000 6000E 7 5 40000 52000 6000F 6 3 20000 29000 3000

Page 40: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

40

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Fast Tracking

• Fast-tracking a project means that activities that are normally done in series are done in parallel

• Fast-tracking a job can accelerate the schedule but requires that additional risks be taken

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-8: Scheduling ToolsScheduling ToolsScheduling ToolsScheduling Tools

• Automated scheduling tools expedite the scheduling process by generating start and finish dates based on the inputs of activities, network diagram, resource and activity duration

Page 41: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

41

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-1: Project ScheduleProject ScheduleProject ScheduleProject Schedule

GANTT (BAR) Chart with relationships

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-1: Project ScheduleProject ScheduleProject ScheduleProject Schedule (Continued)

GANTT (BAR) Chart

Page 42: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

42

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-1: Project ScheduleProject ScheduleProject ScheduleProject Schedule (Continued)

Network Diagram

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-1: Project ScheduleProject ScheduleProject ScheduleProject Schedule (Continued)

Milestone Chart

Page 43: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

43

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-2: Schedule Baseline

• A schedule baseline is a specific approved version of the project schedule.

• A schedule baseline is a component of Project Management Plan, which provides the basis for measuring and reporting schedule performance.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-3: Schedule Data

• Supporting data for the schedule, this output includes but not limited to the milestones, schedule activities and activity attributes, resource histograms, alternative schedules, schedule contingency reserves, and the assumptions and constraints regarding the schedule

Page 44: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

44

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-4: Project Calendars

• A project calendar identifies working days and shifts that are available for schedule activities.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-5: Project management plan updates

• Schedule Baseline

• Schedule Management Plans

Page 45: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

45

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-6: Project Document updates

• Activity Attributes update

• Activity Resource Requirements

• Calendar

• Risk Register

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

6.7 - Schedule Control

• Objectives:

1. Determining the current status of the project schedule

2. Influencing the factors that create schedule changes

3. Determining that the project schedule has changed

4. Managing the actual changes as they occur

Page 46: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

46

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Inputs

1. Project Management Plan

2. Project Schedule

3. Work Performance Data• Provide information on schedule performance, such as which

planned dates have been met, and which have not, and alert to issues that may cause performance problems

4. Project Calendars

5. Schedule Data

6. Organizational Process Assets

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-1: Performance Reviews

• Measure, Compare and analyze schedule performance.

Page 47: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

47

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-2: Project Management Software

• Project management software is used to track the actual schedule dates against planned schedule dates.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-3: Resource optimization techniques

• Resource Smoothing

• A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed predefined resource limits.

Page 48: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

48

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

TT-4: Modeling Techniques

• What-if scenario analysis is the process of evaluating scenarios in order to predict their effect, positively or negatively on project objectives

• Simulation involves calculating multiple project durations with different set of activity assumptions.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Common Tools & Techniques

• TT-5: Adjust leads and lags

• TT-6: Schedule compression

• TT-7: Scheduling tools

Page 49: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

49

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-1: work Performance information

• The calculated schedule variance (SV) and schedule performance index (SPI) values are documented and communicated

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-2: Schedule forecasts

• Schedule forecast are estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time of the forecast.

Page 50: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

50

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Out-3: change Requests

• Schedule variance analysis, along with review of progress reports may result in requested changes to the project schedule base line.

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Common outputs

• TT-4: Project Management Plan Updates

• TT-5: Project Documents Updates

• TT-6: Organizational process asset updates

Page 51: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

51

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Activity Duration Dependent on

Start 0 -

A 3 Start

B 4 Start

C 2 Start

D 2 B

E 5 A,C

F 1 B

G 6 D,F

H 11 E

I 8 D,F

Finish 0 G,H,I

Identify the critical Path

Calculate Float of activity D

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015

Question & AnswersQuestion & Answers

Page 52: PMI®, PMP®, PMBOK® Guide are registered trade marks of ...

52

© Khaled El-Nakib, MSc, PMP, PMI-RMP 2015