PM592 Week 3 Discussion

download PM592 Week 3 Discussion

of 11

Transcript of PM592 Week 3 Discussion

  • 7/27/2019 PM592 Week 3 Discussion

    1/11

    7/11/13 Topic Print View

    threadcontent.next.ecollege.com/(NEXT(c2554bec91))/Main/CourseMode/Topic/TopicPrintView.ed?topicID=29456095&sortBy=Title&sortOrder=Ascending&i

    Week 3: Scheduling Networks - Discussion

    Project Schedules (graded)

    Forget about cost est imation and budgets this week; now we get to play with the third and greatest element of our triple constraint -- TIME. Project scheduling follows one ofParkinson's laws: "Everything takes as long as it takes." W e will explore the elements and functions we must consider when developing the project schedule?

    We have developed a complete WBS that we feel truly defines the scope of the project, and it is well organized. We have reviewed some available resources, including someoutside sources; however we must first build a schedule baseline.

    How do you get started? What methods help in scheduling?Is there the same kind of team process involved as in building the WBS?What are your most important considerations when building a project schedule?Must you first consider deadlines? What kinds of scheduling constraints are common?

    Remember, you each don't need to address all the questions. Use them to build a discuss ion amongst all of us.

    Responses

    Response Author Date/Time

    How to Estimate an Accurate Schedule Professor Orr 5/18/2013 1:21:54 PM

    There is a lot of talk about the process f or developing cost es timates but the schedule process is not as w ell defined. What are your thoughts on how to estimate an accurate schedule?

    Regards,

    Susan

    RE: How to Estimate an Accurate Schedule Varune Ramoutar5/19/2013 1:38:14 PM

    In my opinion the elements to creating a good schedule are:

    1. Know all the activities that must be accomplished in order to achieve the project objective.

    2. Once all the activities are known durations for each activity can be estimated.

    3. It is very critical to know the dependencies of each of the activities and how they fit in to accomplishing the project. This can be established by

    creating a network diagram. This must be done before the schedule is properly established.

    4. The critical path of the activities is another very important element in scheduling because this is the longest duration of tasks that must be

    accomplished for the project. Once this is established the project schedule can be well estimated.

    5. Slack times of activities must also be determined. This is the amount of time an activity that starts at its earliest start time can be delayed without

    delaying the project. Thus slack times for activities can help manage the scheduling of resource requirements.

    6. The schedule must also take into consideration management issues such as resource constraints, cash flow, change risks, logistics etc.

    7. The schedule must also take into consideration ofmanagement reserve which is additional time that is placed in the schedule to help with

    uncertainties that may occur in the project.

    Ref: Nicholas, John M.; Steyn, Herman (2012-09-10). Project Management for Engineering, Business, and Technology (Kindle Location 5840). Taylorand Francis. Kindle Edition

    RE: How to Estimate an Accurate Schedule Cauretta Bell 5/20/2013 8:26:39 PM

    Project scheduling involves more than just estimating cost or simplying displaying taks on a Gantt chart. An integral part of project planning, and often involves a trail and error

    process of adjusting w ork tasks to meet the cintraints of limited resources w hile trying to meet project deadline. First, getting the WBS structure accurate and the start date a

    finish date for the project. Once you have allocated a duration for the activities for the AON understanding the critical path for the netw ork w ill assist the PM in understanding

    the LS/ES and ES/EL for each activity. The best w ay to s tart the project off is have an accurately placed WBS.

    RE: How to Estimate an Accurate Schedule Chukie Okunzua5/20/2013 8:54:42 PM

    I agree with you Varune that Know the project activities, their interdependencies are critical to developing an accurateschedule. Activities relationship to each other are at the heart of scheduling. It is very critical to know which activities arepredecessors and which are successor to each other. We also need to know which activities can be done at the same tim

    Activity duration must be determined and effect of resource limitation understood. The network diagram is a great tool inschedule planning and management.The WBS provides us the building blocks for starting as the work packages are the activities that are to be scheduled andtheir predecessor - successor relationship outlined

  • 7/27/2019 PM592 Week 3 Discussion

    2/11

    7/11/13 Topic Print View

    threadcontent.next.ecollege.com/(NEXT(c2554bec91))/Main/CourseMode/Topic/TopicPrintView.ed?topicID=29456095&sortBy=Title&sortOrder=Ascending&i 2

    RE: How to Estimate an Accurate Schedule Esperanca Rosa 5/19/2013 2:22:53 PM

    Hi class,

    Using a set of proactive estimating techniques to scope, plan, and constrain your project conditions, you can dramatically improve your estimatingpractices, reduce and mitigate risks, and greatly increase your project success rate.

    According to the website projectsmart.co.uk there are twelve (12) methods for boosting the accuracy of your estimates:

    1. Maintain an ongoing "actual hours" database of the recorded time spent on each aspect of your projects. Use the data to help estimate futu

    projects and identify the historically accurate buffer time needed to realistically perform the work.

    2. Create and use planning documents, such as specifications and project plans.

    3. Perform a detailed task analysis of the work to be performed.

    4. Use a "complexity factor" as a multiplier to determine whether a pending project is more or less complex than a previous one.

    5. Use more than one method to arrive at an estimate, and look for a midpoint among all of them.

    6. Identify a set of caveats, constraints, and assumptions to accompany your calculations, which would bound the conditions under which yo

    estimates would be meaningful. (Anything that occurs outside of those constraints would be considered out of scope.)

    7. If the proposed budget or schedule seems inadequate to do the work, propose adjusting upward or downward one or more of the four proje

    scoping criteria: cost, schedule, quality, and features.

    8. Consider simpler or more efficient ways to organize and perform the work.

    9. Plan and estimate the project rollout from the very beginning so that the rollout won't become a chaotic scramble at the end. For instance, yocould propose using a minimally disruptive approach, such as a pilot programme or a phased implementation.

    10. In really nebulous situations, consider a phase-based approach, where the first phase focuses primarily on requirements gathering an

    estimating.

    11. Develop contingency plans by prioritizing the deliverables right from the start into "must-have" and "nice-to-have" categories.

    12. Refer to your lessons-learned database for "20:20 foresight" on new projects, and incorporate your best practices into future estimates.

    Retrieved from:

    http://ww w .projectsmart.co.uk/12-tips-for-accurate-project-estimating.html

    Best Regards,

    Esperanca

    RE: How to Estimate an Accurate Schedule Maria Ventura 5/19/2013 7:29:57 PM

    Modified:5/19/2013 7:32 PM

    Hello class,

    When thinking on how to estimate an accurate schedule, we expect to know what does each activity requires or represent in order to complete aproject within the expected time frame. In other words, the team uses the W BS to generate an activity list where items are then reviewed toestimate the duration and cost of each one. In order to estimate an accurate schedule, it is necessary to create three duration estimates for eachactivity.

    1- best case (optimistic)

    2- worst case (pessimistic)3- the most likely (realistic) duration.

    At the minimum, three-point estimates should be created for any activity or deliverable that is unique, risky, or relatively new to the team.Ordinarily, the most likely estimates are used for most activities in developing the project schedule. Or the project manager may elect to use aweighted average of the three-point estimates for selected activities. The three duration estimates allow the project manager to perform simplesensitivity analysis on the project schedule.By changing key durations, the project manager can model the overall schedule impact of possible scenarios.

    Source: http://www.techrepublic.com/blog/tech-manager/how-to-accurately-estimate-and-forecast-in-project-management/618

    Thank you//

    RE: How to Estimate an Accurate Schedule Tanika Thomas 5/20/2013 6:44:59 PM

    http://www.techrepublic.com/blog/tech-manager/how-to-accurately-estimate-and-forecast-in-project-management/618http://www.projectsmart.co.uk/12-tips-for-accurate-project-estimating.html
  • 7/27/2019 PM592 Week 3 Discussion

    3/11

    7/11/13 Topic Print View

    threadcontent.next.ecollege.com/(NEXT(c2554bec91))/Main/CourseMode/Topic/TopicPrintView.ed?topicID=29456095&sortBy=Title&sortOrder=Ascending&i 3

    I think both 3 point estimate and the WBS identifying the critical paths, dependencies and slack time wouldgenerate close to accurate estimate. Once all the key steps and time durations are addresses like Varune mentionthen take and apply the 3 point strategy of best, worst and most likely case to the finding. I think that each oneschedule would compliment the other and show how closely the results are; if not then something is off with theestimates, paths or dependencies, etc.

    RE: How to Estimate an Accurate Schedule Philip Effiong5/20/2013 6:44:44 AM

    Accurate time est imation is a crucial sk ill in project management. Without it, you won't know how long your project will take, and you won't be able to getcommitment from the people who need to sign it off.

    These steps can be use to make accurate time estimates:

    Step 1: Understand What's Required

    Start by identifying all of the work that needs to be done within the project. Use tools such as Business Requirement Analysis, Work Break Down StructurGap Analysis and Drill Analysis to help you do this in sufficient detail.

    Step 2: Order These Act ivities

    Now, list all of the activities you identified in the order in which they need to happen.

    At this stage, you don't need to add in how long you think activities are going to take. However, you might want to note any important deadlines.

    Step 3: Decide Who You Need to Involve

    You can do the estimates yourself, brainstorm them as a group, or ask others to contribute.

    RE: How to Estimate an Accurate Schedule Cauretta Bell 5/24/2013 9:00:21 PM

    In order to know w hat is required the project manager need to have a developed a detailed WBS based on the project sc ope. The budget needs to be set w hether it be top

    down or bottom up approach. It is also important for the managers to know the resources available for the project. It w ould be beneficial f or the PM to locate other similar

    archive to s ee w hat the major risks that arise during the project so it can be planned for improvement or other alternatives.

    RE: How to Estimate an Accurate Schedule Joel Khan5/20/2013 6:45:46 AM

    From experience and the talk we had in class on w eek 1 I think that keeping an accurate schedule w orks w ell if you can:

    Continuing to use the same mechanism for es timating and scheduling will result in continued inability to meet schedules.

    The organization needs to f ind an estimatingand scheduling process that w orks.

    People who w ill be doing the work are best able to estimate how long the work w ill take.

    The organization needs training in good estimating and scheduling practices.

    People doing the work need the ability to set the schedule and then need to be held accountable for meeting it.

    Also, it w orks like a schedule for softw are development, there is alw ays more to it then it seems once you dive into the project.

    Reference:http://ww w .sw qual.com/images/Creating.pdf

    RE: How to Estimate an Accurate Schedule Nishan Ragoonanan 5/20/2013 1:36:47 PM

    When I think accurate schedule, I think critical path and netw ork diagram. We take the low level tasks f rom the WBS and put them into a networ k diagram that w ill show us the

    dependencies betw een tasks, i.e. w hich ones come first, w hat needs to happen before a certain task can begin etc. We assign the estimates of all these tasks and the longest path

    through the network diagram gives us our schedule. This is of c ourse all dependent upon the time estimates f or the tasks, w hich could in actuality be shorter or longer causing errors in

    the estimate.

    RE: How to Estimate an Accurate Schedule Serge Ndongo5/20/2013 6:38:32 PM

    The three point estimates should be good enough to estimate an accurate sc hedule as it leans on three duration estimates f or each activity: best case (optimistic), w orst c as

    (pess imistic), and the most likely (realistic ) duration. On the other hand we can apply the lessons learned f rom the other projects to make a fair est imation. For example, if the

    plan on your desk show s that the business r equirements w ill be documented and accepted in 15 w orking days, and your last three projects took at least 20 w orking days

    each, to get accepted requirements, you should be able to explain w hy your estimates are only 15 days.

    RE: How to Estimate an Accurate Schedule Herminio Dionisio 5/21/2013 6:53:28 PM

    Estimation is one area w here most project teams have trouble. For one thing, there is no consistency. One person might be optimistic, another pessimistic, and w e w on't know w hich

    unless w e have had prior substantiating evidence of one or the other. Before w e can estimate duration, w e need to make sure everyone is w orking from a common definition. The

    duration of a project is the elapsed time in business w orking days, not including w eekends, holidays, or other non w ork days. There are some variances also that w e must consider w h

    http://www.swqual.com/images/Creating.pdf
  • 7/27/2019 PM592 Week 3 Discussion

    4/11

    7/11/13 Topic Print View

    threadcontent.next.ecollege.com/(NEXT(c2554bec91))/Main/CourseMode/Topic/TopicPrintView.ed?topicID=29456095&sortBy=Title&sortOrder=Ascending&i 4

    developing our sc hedule that may be a c ause of actual duration to vary from planned duration. Some of these are the v arying skill level, unexpected events that w ill cause interruption, a

    sometimes despite of clearly and concisely describing the task to be performed, mistakes and misunderstanding still happened.

    RE: How to Estimate an Accurate Schedule Dwayne Grant 5/22/2013 6:53:15 PM

    All business professions have critical skills and cost estimates for scheduling just happens to be one of those skills. If you were an EMT one of the criticalskills of a paramedic is to perform triage on a injured person. One type of estimate is a time estimate, and it lays the foundation setting deadlines andplanning projects. Another reason a time estimate is important is that if you have a detailed list you can accurately predict how long it will take to completea task.

    RE: How to Estimate an Accurate Schedule Bruce Foley5/23/2013 9:20:02 AM

    Another step-by-step process that is used in Project Time Management is to evaluate the project time needs in this order:

    1. 1.ACTIVITY DEFINITION

    2. 2. ACTIVITY SEQUENCING

    3. 3. ACTIVITY RESOURCE ESTIMATING

    4. 4. ACTIVITY DURATION ESTIMATING

    5. 5. SCHEDULE DEVELOPMENT

    6. 6. SCHEDULE CONTROL

    http://leadershipchamps.w ordpress.com/2008/09/03/brief-overv iew- on-project-time-management-processes/

    RE: How to Estimate an Accurate Schedule Mary Hart 5/23/2013 10:10:02 AM

    Modified:5/23/2013 10:11 AM

    The step-by-step precess of Project Time Management presented by Bruce is aligned with concepts presented in the PMBOK Guide 3rd

    edition as follow:

    Activity Duration Estimating: In this process, est imation of required time is done to carry out a defined activity based on the scope & resource

    availability. Accuracy of

    this process leads to exact schedule development of whole project & cost estimation of resources (Planning Process Group)

    Schedule Development: Coming up with planned start and end dates for every activity & also for the entire project happens in this process. This

    process uses activity sequences, duration estimation, resource estimation & project schedule constraints to arrive the project schedule. Few we

    established techniques are already available. Output of this process is approved and used as schedule baseline against which project progress is

    tracked (Planning Process Group)

    Schedule Control: This process explains project status monitoring, finding changes in the schedule(early you find lesser the impact !) and

    controlling schedule changes to meet planned schedule. Communication is more important in this process (Monitoring & Controlling Process

    Group)

    Here we can observe the high interdependency between time management processes. When a project has smaller scope then all time

    management processes can be combined in a single process.

    Ref: PMBOK Guide 3rd edition

    RE: How to Estimate an Accurate Schedule Huyen Bui 5/23/2013 7:18:47 PM

    For estimating an accurate schedule, i think the PM can refer to the previous s imilar projects duration plan / actual duration. Utilize the WBS to estimate schedule to the bottom level (w ork

    package)

    It also has to align w ith the resource allocation, budget, and the given project durat ion.

    In order to keep the schedule deliverable, using the expertise from the team to have the overall idea

    Sensitivity Analysis Professor Orr 5/20/2013 11:38:06 AM

    http://leadershipchamps.wordpress.com/2008/09/03/brief-overview-on-project-time-management-processes/
  • 7/27/2019 PM592 Week 3 Discussion

    5/11

    7/11/13 Topic Print View

    threadcontent.next.ecollege.com/(NEXT(c2554bec91))/Main/CourseMode/Topic/TopicPrintView.ed?topicID=29456095&sortBy=Title&sortOrder=Ascending&i 5

    Include in your answ ers the constants and variables that w ere included in any calculations of s ensitivity a sample calculation would be excellent!

    Regards,

    Susan

    RE: Sensitivity Analysis Varune Ramoutar 5/20/2013 2:22:33 PM

    I think a simple example of this would be linear regression statistical modeling. Here a linear relationship is formulated between 2 variables that have a

    relationship where the value of one is dependent on the other when a constant regression coefficient applied to the other e.g. if we have a sample of

    housing prices in the same neighborhood and we want to find out how the cost of a house varies depending on the number of fireplaces we may find

    that the mean price is $100,000 and for each increase in fireplace the price increases by an applied coefficient of $100 this gives us a linear

    relationship of Estimated Price of house = $100,000 + $100 x # of fireplaces.So if a house has no fire place the estimated price = $100,000 x $100(0) = $100,000

    For 2 fireplaces estimated price = $100,000 + $100(2) = $100,200

    The key here is the regression coefficient which is determined by plotting a sample of variables against each other and then determining the linear

    rerelationship that exists between them form the standard linear equation y = c + m(x).Ref: GM 533 Week 1 lecture.

    RE: Sensitivity Analysis Esperanca Rosa 5/20/2013 8:29:49 PM

    Hi Varune!

    I strongly agree with your comments. They are elucidative for the reason that they are giving a great insight of how can we apply variables andconstants in a model to calculate the sensitivity. Adding to that, the statistic class (GM 533) was great because we could learn how to make therelationship between two variables in a particular case.

    In our industry, we can use and apply the sensit ivity analys is in several cases. For instance, we have been using models to calculate the flow ofreservoir and how the sensitivity study will be helpful for that model. The calculation of permeability (K) and porosity () of a reservoir, we need toidentify their relationship to apply in the model. In this model, variables have a s trong relationship between them. We characterize porosity andpermeability distribution in the reservoir to demonstrate the feasibility of our approach for large-scale field applications.

    Please, find the figure in the attachment to see their relationship.

    Source

    Marine and Petroleum Geology, Volume 27, Issue 8, September 2010, Pages 1692-1697

    Retrieved from:

    http://www.sciencedirect.com/science/article/pii/S0264817209001196

    PorPerm-Variable Relationship.pptx

    RE: Sensitivity Analysis Maria Ventura 5/21/2013 7:37:47 AM

    Modified:5/21/2013 7:38 AM

    Hello class,

    Great posts!! According to our text book, using the model a sensitivity analysis can be performed to see what happens when costs arevaried up or down; also to show best-case, most-likely, and worst-case scenarios. The model can also be used to determine by howmuch and in what combination the costs must vary before the project becomes lucrative or disastrous. In addition to that, when usingconstants and variables that were included in any calculations of sensitivity at least one of the variables must be fixed or constrained;in order to provide a basis for planning the project. It is possible to constrain two of the variables, again within certain limits, if the thirdvariable is unconstrained. If all three are constrained, there is probably no feasible way to accomplish anything meaningful; your project in trouble from the very start. Meaning that at least one of the variables has to be flexible in order for a project to be successful.

    Source: http://www.jamesaward.com/key%20project%20constraints.htm

    Thank you//

    RE: Sensitivity Analysis Philip Eff iong 5/22/2013 7:39:17 AM

    According to our lecture notes, sensitivity analysis determines which parameters (both cash and non-cash variables such as project life) are the mostsensitive to a project's economic feasibility. As such, sensitivity analysis forms a bridge between economic analysis and risk analysis. Highlighting thesesensitive factors allows further analysis and closer examination, with the goal of improving relevant cash-flow estimates by gathering additional data tonarrow the range of accuracy.

    Sensitivity analysis can be undertaken on single project variables such as break-even point, life of equipment (replacement analysis), rate of return, or onmultiple variables such as that performed in scenario analysis.

    For example, an analyst might create a financial model that will value a company's equity (the dependent variable) given the amount of earnings per share(an independent variable) the company reports at the end of the year and the company's price-to-earnings multiple (another independent variable) at thattime. The analyst can create a table of predicted price-to-earnings multiples and a corresponding value of the company's equity based on different values fo

    http://www.jamesaward.com/key%20project%20constraints.htmhttp://www.sciencedirect.com/science/article/pii/S0264817209001196
  • 7/27/2019 PM592 Week 3 Discussion

    6/11

    7/11/13 Topic Print View

    threadcontent.next.ecollege.com/(NEXT(c2554bec91))/Main/CourseMode/Topic/TopicPrintView.ed?topicID=29456095&sortBy=Title&sortOrder=Ascending&i 6

    each of the independent variables.

    http://www.investopedia.com/terms/s/sensitivityanalysis.asp

    RE: Sensit ivity Analysis Serge Ndongo 5/22/2013 11:34:16 AM

    Sensibility analysis is a procedure to determine the sens itivity of the outcomes of a model based upon changes to its parameters. Th

    would no t usually include changes in its environment. If a small change in a parameter (input factor) results in relatively large chang

    in the model outcome, the outcome is said to be sensitive to that pa rameter. If this is the case, either the input factor will need

    accurate control or the process will need redesign to reduce the sensitivity. That is, sensitivity analysis is used to assess how robust

    the results a re to uncertain decisions or assumptions in the model. A process can be investigated using a mathematical model. Themodel can comprise a series of equations, input factors, parameters, and variables w hich aim to characterize the process.

    http://w w w .project-management-basics.com/project_management_176_Project_management_systems_part_13_Sensitivity_analysis .shtml

    RE: Sensit ivity Analysis Herminio Dionisio 5/23/2013 6:51:41 PM

    Sensitivity A nalysis helps to determine and examines the extent to w hich the uncertainty of each project elements af fects the objective being examined w hen all other uncertain element

    are held at their baseline values. By using a model for exper imentation and tests , it permits var ious alternatives that w ill help and guide in making critical decision. One form of sensitivity

    analysis is determining a break even point, usually w ith respect to sales. If the break even figure is c learly w ithin reach, it provides a sense of comfort that the project w ill not lose mone

    even if it may not have the desired rate of return on investment.

    A good sample of a Break Even Point calculation: If a company sells 400 units of its product at $500 per unit, what w ill be its Net Operating Income w ith the follow ing given variables?

    Total Per Unit

    Sales (400 units) $200,000 $500Less: Variable Expenses 120,000 300

    Contribution Margin 80,000 200

    Less: Fixed Expenses 80,000

    Net Operating Income $ 0

    Note: Remember that w hen Contribution Margin is equal to Fixed Expenses, this is your Break Even Point because the difference betw een these tw o which is your Net Operating Income

    "zero". In this case, you now know that you need to have a sale of 400 units firs t and anything above w ill be your profit.

    Determining "Sensitivity" to Specific Items Professor Orr 5/21/2013 9:51:47 AM

    Class, how do you determine if the project is "sensitive" to the specific items? What are the criteria for selecting items f or analysis?

    Regards,

    Susan

    RE: Determining "Sensitivity" to Specific Items Mary Hart 5/21/2013 3:30:37 PM

    Modified:5/21/2013 3:33 PM

    "A sensitivity analysis helps to determine which r isks have the most potential impact on the project. It examines the extent to w hich the uncertainty of each project elements af fects the

    objective being examined when all other uncertain elements are held at their bas eline values." ( PMBOX Guide, 4th Edition,pg 298)

    Based on the information given by the PMBOX Guide I would cons ider that firs t a list of risk item should be established, then w e should identify the uncertainties that most influence

    estimates of baseline values.

    RE: Determining "Sensitivity" to Specific Items Maria Ventura 5/22/2013 9:03:18 PM

    Hello class,

    Sensitivity analysis, also defined as what-if analysis is a brainstorming technique used to determine how projected performance is affected bychanges in the assumptions that those projections are based upon. In other words, it allows a reviewer to assess the impact that changes in acertain parameter will have on the models conclusions.It also helps the reviewer to determine which parameters are the key drivers of a modelsresults.

    Sources: http://www.medicine.ox.ac.uk/bandolier/painres/download/whatis/What_is_sens_analy.pdfhttp://www.iplanner.net/business-financial/online/how-to-articles.aspx?article_id=what-if-analysis

    Thank you//

    RE: Determining "Sensitivity" to Specific Items Nishan Ragoonanan 5/21/2013 8:39:44 PM

    I would think we w ould look at the items f or w hich w e expect the greatest variance or those for w hich w e have the least information or present the most risk to perform a sensitivity

    http://www.iplanner.net/business-financial/online/how-to-articles.aspx?article_id=what-if-analysishttp://www.medicine.ox.ac.uk/bandolier/painres/download/whatis/What_is_sens_analy.pdfhttp://www.project-management-basics.com/project_management_176_Project_management_systems_part_13_Sensitivity_analysis.shtmlhttp://www.investopedia.com/terms/s/sensitivityanalysis.asp
  • 7/27/2019 PM592 Week 3 Discussion

    7/11

    7/11/13 Topic Print View

    threadcontent.next.ecollege.com/(NEXT(c2554bec91))/Main/CourseMode/Topic/TopicPrintView.ed?topicID=29456095&sortBy=Title&sortOrder=Ascending&i 7

    analysis upon. We can then quantify the effect on our project by 'simulating' the effect of change on these variables and the result of the project say in terms of cost or schedule or

    scope.

    RE: Determining "Sensitivity" to Specific Items Esperanca Rosa 5/22/2013 12:39:15 AM

    Hi class,

    Sensitivity analysis is a subject that has brought our attention. Sensitivity analysis is one such method. It is implemented to analyze the variousrisks to the project by looking at all aspects of the project and their potential impact on the overall goal. Knowing the level of impact variouselements have on a project can assist management with setting priorities to more quickly achieve the end result. Project management can easilconvey the results of a sensitivity analysis through the use of a tornado diagram. The differences among the risks can be easily seen since theanalysis is a quantitive value. Rather than qualifiers desc ribing the risks, the impact of each is quantified in a numerical value. This facilitates

    comparisons between the various elements to quickly discern which risks are worth taking. Project management can use the sensit ivity analys isto create priorities in dealing with elements risk to the project.

    Retrieved from:

    http://project-management-knowledge.com/definitions/s/sensitivity-analysis/

    Regards,

    Esperanca

    RE: Determining "Sensitivity" to Specific Items Chukie Okunzua 5/22/2013 10:42:25 PM

    Sensitivity analysis examines the effect of change of a variable on the project plan and is the simplest form of riskanalysis. this methos has it pros and cons.

    "Some of the advantages of sensitivity analysis include impressing management that there is a range of possibleoutcomes, decision making is more realistic, though perhaps more complex. And the relative importance of eachvariable examined is readily apparent. Some weaknesses are that variables are treated individually, limiting theextent to which combinations of variables can be assessed, and a sensitivity diagram gives no indication ofanticipated probability of occurrence"

    http://certifedpmp.wordpress.com/2008/09/17/risk-analysis-techniques/

    RE: Determining "Sensitivity" to Specific Items Philip Eff iong 5/23/2013 6:14:12 AM

    Sensitivity analysis helps a business estimate what will happen to the project if the assumptions and est imates turn out to be unreliable. Sensitivity analys

    involves changing the assumptions or estimates in a calculation to see the impact on the project's finances. In this way, it prepares the business 's

    managers in case the project doesn't generate the expected results, so they can better analyse the project before making an investment.

    In capital budgeting calculations, sensitivity analysis changes one assumption or estimate at a time to see how the results change. For example, abusiness may expect to earn $500, $1,000 and $1,000 in the first three years of a project. If the business makes an initial investment of $2,500, it will

    recoup its expenses in three years. However, the project may perform better than expected, generating $2,000 yearly in its second and third year. The

    business will then break even in two years.

    http://smallbusiness.chron.com/sensitivity-analysis-c apital-budgeting-10153.html

    RE: Determining "Sensitivity" to Specific Items Herminio Dionisio 5/23/2013 7:28:30 PM

    It is very useful to do a s ensitivity analysis on one or more of the key estimates. This is done by sys tematically varying one of the parameters in the calculations to determine its eff ect on

    the final outcome. If it is found that the ultimate decision is highly sensitive to a particular estimate, it may be w orthw hile to devote additional time and eff ort to ref ining that number. One

    good example of this is w hen you are applying the parametric method employing the per unit area or per linear foot in your c ost estimation. Adjusting your unit rate to different degrees w

    help and assist you on w hich is the most ideal rate to use, and you w ill be aware that this es timate has risk associated w ith it. My analysis point of concentration w ill be on the triple

    constraint w hich are time, cost, and scope, and they have its individual criteria and respective priorities.

    RE: Determining "Sensitivity" to Specific Items Dwayne Grant5/25/2013 5:05:09 PM

    If, I had to select specific items for a sensitivity analys is it would include items from the risk analysis , and also from the critical path. The reason why thecritical path was selected is because each day that tasks are delayed on the critical path will add additional days to the project end date. I would then usethe risk matrix to determine which risk would effect items on the critical path. Once these items have been identified it would be a good it to do a s tatisticacalculation, and concept called null hypothesis comes to mind. So, we can create a scenario and do hypothesis testing to predict the outcome, andaccording to the data will accept the hypothesis or fail to reject the null hypothesis.

    RE: Determining "Sensitivity" to Specific Items Bruce Foley 5/25/2013 7:12:19 PM

    A project is "sensitive" to specific items mainly if the item is on the critical path to completion. This is the main criteria, in my opinion that dictates if an item is sensitive to a specific item.

    Critical path item can potentially stop a project in it's path.

    http://smallbusiness.chron.com/sensitivity-analysis-capital-budgeting-10153.htmlhttp://certifedpmp.wordpress.com/2008/09/17/risk-analysis-techniques/http://project-management-knowledge.com/definitions/s/sensitivity-analysis/
  • 7/27/2019 PM592 Week 3 Discussion

    8/11

    7/11/13 Topic Print View

    threadcontent.next.ecollege.com/(NEXT(c2554bec91))/Main/CourseMode/Topic/TopicPrintView.ed?topicID=29456095&sortBy=Title&sortOrder=Ascending&i 8

    Calculations of Sensitivity: Constants and Variables Professor Orr 5/22/2013 11:34:23 AM

    This is a good start. Include in your answ ers the constants and variables that w ere included in any calculations of s ensitivity a sample calculation would be excellent!

    Regards,

    Susan

    RE: Calculations of Sensitivity: Constants and Variables Varune Ramoutar 5/22/2013 7:25:40 PM

    To build on my example used earlier on calculating the cost of a house based on the number of fireplaces i.e. Cost = $100,000 + $100(x):

    The constant is the mean price of a house in the neighborhood i.e. $100,000.

    The variable is the number of fireplaces - x.

    The rate by which the house price increases based on the number of fireplaces i.e. the gradient of the linear relationship is $100

    RE: Calculations of Sensitivity: Constants and Variables Nishan Ragoonanan 5/23/2013 1:14:17 PM

    An example of sensitivity analysis that might be performed could be the cost of a manufacturing plant that is dependent on refinery components that are coming from Germany. In this ca

    if the cost of the components are quoted as 5 million in Euros, and w e are paying our German manufacturer in Euros then w e are sensitive to exchange rate fluctuations so

    Final Plant cost = US to EuroExchange rate x Cost of Refinery Components

    We can measure using this equation how even a 1% f luctuation in exchange rate can influence our f inal plant cost.

    RE: Calculations of Sensitivity: Constants and Variables Esperanca Rosa 5/24/2013 1:26:17 PM

    Modified:5/24/2013 1:31 PM

    Dr. Susan,

    The variables that I could include while doing calculations on sensitivity analysis would depend on what we are analyzing. Depending on the type of the project, the variableor constant would vary according to the analytical study. A great example is when we have a construct ion or builder company and want to build new houses orcondominiums. What are the major aspects or variables we need to take into consideration? For a seller perspective, I would say location, school zones, security, futuremonthly expenses, and price. For the buyer perspective, one of the first variables to analyze would be price, location, school zone, and security.

    All these variables would be relevant in our sensitivity analysis because if one fails it will affect the other ones. Consequently, it will affect our final decision. Whether theprice is high, we would have to analyze the other variables and check if it would compensate to be in that house.

    I have found a great website to share with you that has good explanation of it.

    One goal of a housing suitability model might be to identify the most desired locations to build a house based on specified criteria. In the following housing suitability modsensitivity analysis was used to explore how the output housing preference locations changed with slight variations in the input criteria parameters.

    The suitability surface using the base parameters.

    The suitability surface is shown above using the base parameters. Green is the most preferred, while red is the least preferred. Purple defines areas that were removed fromconsideration.

    The housing suitability model is a s imple model built in ArcGIS Spatial Analyst using four criteria:

    The lower the slope, the more preferred because of lower building costs.

    Since the study site is in northern Vermont in the United States (a cold climate), the more southerly the exposure the better.

    To reduce the cost of access to the infrastructure (for example, electricity ) and reduce driveway costs , the c loser to a road, the better.

    Because you cannot build on exis ting houses or s tructures or in conservation areas, these areas were removed from consideration.

    Sensitivity analysis was performed by changing each of the input criteria by 5 percent increments. Only the three most preferred classes were altered for each criteria,since only the best locations for a house are of interest.

    The following table represents the total number of cells in the top two c lassifications relative to the change in parameter scenarios (values 30 and 29 being the mostpreferred locations). Base is the output using the base parameters, Roads 5 percent changed the distance to roads parameters by 5 percent, and so forth. The percentchange is also provided for the most preferred locations. The total number of cells in the top two c lassifications is provided (30+29). Note that a 5 percent change in distancfrom roads provided no change, but a 10 percent change provided the greatest change. Small changes in both the slope and aspect parameters (5 percent) resulted in largechanges but leveled out at greater changes (10 percent).

  • 7/27/2019 PM592 Week 3 Discussion

    9/11

    7/11/13 Topic Print View

    threadcontent.next.ecollege.com/(NEXT(c2554bec91))/Main/CourseMode/Topic/TopicPrintView.ed?topicID=29456095&sortBy=Title&sortOrder=Ascending&i 9

    Val/Sc Base Roads 5% Roads 10% Slope 5% Slope 10% Aspect 5% Aspect 10%

    30 163 163 (0%) 205 (1.26%) 177 (1.09%) 195 (1.20%) 178 (1.10%) 189 (1.16%)

    29 811 825 927 911 999 889 958

    30+29 974 988 1132 1088 1194 1067 1147

    The following table shows the total cell change from the changes in values from the base surface to the changed surface. The value changes on the y-axis are identified bytwo values. The first is the value from the suitability model using the base parameters and the second number is what they changed to with the parameter change. Note thanone of the most preferred locations (value 30) changed in any of the change scenarios. However, when more locations were assigned to the most preferred class (value 30in a change scenario, those locations generally came from the base model's second most preferred locations. The exception to this is with the changes to aspect wheresome of the third most preferred locations on the base suitability model (value 28) became the most preferred (value 30).

    Retrieved from:

    http://resources.esri.com/help/9.3/arcgisdesktop/com/gp_toolref/process_simulations_sensitivity_analysis_and_error_analysis_modeling/performing_sensitivity_analysis.h

    Find please the map in the attactment.

    Thanks,

    Esperanca

    One goal of a housing suitability model might-Erosa.pptx

    Changes betw een Prototype and Full Production Professor Orr 5/23/2013 10:08:28 AM

    Good discussion. What factors might change betw een a prototype run and f ull production, w hich might make data gathered during the prototype run inaccurate? How w ould you adjust estimates?

    Regards,Susan

    RE: Changes betw een Prototype and Full Production Huyen Bui 5/23/2013 7:26:26 PM

    In my FMCG industry , in order to launch the NPD (new product dev elopment), it has to pass a certain type of test f rom the R&D.

    For example, I w as developed the new bottle of f loor cleaning product. The manufacture w ill develop the mock-up bottle and w e had to test the durable of the bottle base on temperature

    does the liquid chemical react to the bottle, etc.

    The plastic of the bottle was too thick that it made the bottle not f lexible and easy to break so they have to f ix and it aff ected to the duration of a w hole project.

    So in order to lkeep the project on time, w e had to schedule tasks parallel, and ask the R&D w hether they can speed up the process of tes ting.

    RE: Changes be twe en Prototype and Full Production Cauretta Bell5/26/2013 3:00:30 PM

    you are corr ect! w e have to cr eate a prototype before full production is in place. Prototypes are c reated to see w hat kinks need to be examine in order for thefull production

    take effec t. In the examp.e above it w ould have been a was te of money for tne w ater bottles to go into full production wthout know ing the major or minor issues. once inproduction it is more costly to make the corrdctions and the start again.

    RE: Changes be twe en Prototype and Full Production Dwayne Grant 5/26/2013 7:11:42 PM

    That is great point Huyen and we can't underestimate the importance of using a prototype. There is a reason for that, and w e talked about this topic at length in our class. On

    class mate use the example of the carrier catapult that malfunctioned that cause hundreds of those of dollars in rew orks cost. Most of the class agreed the preventing this

    w ould have been better, and this should of been in the form of a scaled dow n version or a speed test prior to acc eptance. I also remember fr om a quality class it is easier to

    it right the first time than to do it over.

    RE: Changes be twe en Prototype and Full Production Serge Ndongo 5/23/2013 9:18:00 PM

    A prototype is a model of a product w hich is used for testing before a manufacturing run is ordered. Many companies run through several prototypes w hen developing a new product, a

    they learn more about the manufacturing process, how people w ill use it, and how it c an be handle.

    The factors that might change between a prototype run and a f ull production are the size, the quantity, the design, the quality of material used, and the features of the product. Surveys

    might make data gathered during the prototype run inaccurate. The best w ay to adjust estimates is through evaluation and testing.

    RE: Changes be twe en Prototype and Full Production Tanika Thomas5/23/2013 10:05:27 PM

    Excellent point Serge. Prototype run is where all errors should be worked out to which is similar to R&D. Making adjustmeprior to full production would reduce the cost of liabili ty on production/company.

    When I think of prototype, I always go back to the notion buying new technology on the market is not for me because it wasonly tested in a selected market and once the product hits full production and all users began to explore and truly test theproduct, this is when the real results are discovered. Prime example would be iPhone 4 and the location of the antenna wanot discovered until after hitting the market. This caused increase in fixing the problem, inconvenience to customers, etc.Please correct me i f I'm wrong in my understanding of prototype and full production.

    http://resources.esri.com/help/9.3/arcgisdesktop/com/gp_toolref/process_simulations_sensitivity_analysis_and_error_analysis_modeling/performing_sensitivity_analysis.htm
  • 7/27/2019 PM592 Week 3 Discussion

    10/11

    7/11/13 Topic Print View

    threadcontent.next.ecollege.com/(NEXT(c2554bec91))/Main/CourseMode/Topic/TopicPrintView.ed?topicID=29456095&sortBy=Title&sortOrder=Ascending& 1

    RE: Changes be twee n Prototype and Full Production Joel Khan 5/24/2013 9:57:46 AM

    Tanika, That makes sense.

    As as example of prototype and production I can also suggest an example of an application that is being developed. Although we are suppose to test all the

    functions in development some of the functions like server load, bandw idth is not uncovered till the applications is in production which makes changing the

    application at that point very difficult so w e try to get as many users to test at the s ame time as poss ible since the most of the queries on the database have to w o

    w ith database locks so everyone can do their job.

    RE: Changes be twe en Prototype and Full Production Nishan Ragoonanan5/24/2013 12:44:40 PM

    During a prototype run, chances are w e are w orking the kinks out of the system and w e are not building or producing production / releasable products for the public consumption. This

    can aff ect our costs greatly, funny enough on a prototype sys tem, since it's not for public use, s imply internal, the costs can be quite low as w e take shortcuts on quality that w e w ould

    not take on a final system. If this is the case then w e w ould need to inflate our cost and schedule to properly estimate the production run. We would also be a lot more tolerant of f ailures

    in the sys tem and the process w hich w e could not tolerate on the production run requiring more personnel and supervision to reduce the likelihood of failures or the investment in

    machinery and quality process checks to guarantee we meet the quality standards. This all comes w ith associated costs and schedule ramp up time to sw itch over to a production run.

    RE: Changes be twe en Prototype and Full Production Varune Ramoutar 5/25/2013 1:49:06 PM

    Great post Nishan,

    During prototype testing there could be results that come up that were not expected this could cause some re-design of the prototype which

    would of course adjust the production run e.g. in testing the prototype for a new cell phone it may be found that the casing becomes hot wh

    the phone is on this would mean that either a new casing would have to be designed or insulation be installed so that the heat is not

    experienced by the user. In either case the full production run would be changed from the prototype.Also if we subject the prototype to limited tests then the data gathered from it would be limited and the prototype may not be well tested in

    the real situations it would encounter in the real world e.g. the cell phone may not be tested to see if it would still work if it was used by a

    person with wet hands.

    There should be adequate contingencies placed from the prototype model and the final production model. This would be an order of

    magnitude contingency because you really don't know what could happen during the prototype testing.

    RE: Changes be twe en Prototype and Full Production Mary Hart5/24/2013 4:15:38 PM

    Product prototype and full production are phases of a product life cycle.

    An example of a product life cycle would be as follow:

    Concept: An idea is developed in this conceptual phase. Here the client defines the deliverables.

    Design: In this s tage the outline of the idea is developed, samples or samples called prototypes are built, test , evaluated, redesigned as needed andapproved for production. At the end of this phase the design and specifications are completed.

    Development/pilot: In this stage the process of "production" is established based on product technical specifications. At the end of this stage, the design,process, production plan and cost estimates are reviewed and approved upon for production.

    Full Production: In this s tage the product is mass produced using defined design and process. The final product is then called "production- products.

    RE: Changes be twe en Prototype and Full Production Chukie Okunzua 5/25/2013 9:17:16 PM

    Prototypes differ from production in materials, processes and fidelity.Production materials tend to require manufacuring processes that involve higher capital cost than is practical for prototype. Prototype tend to usesubstitute materials that simulate the final material.

    Production process tend to require expensive and time comsuming unique tools to fabricate a custom design while prototype compromise byusing variable processes.Final design often require extensive effort to capture high volume manufacturing detail that is not required in prototype. Final production often use

    statistical process control and rigorous testing .

    http://www.en.wikipedia.org/wiki/prototype

    RE: Changes be twe en Prototype and Full Production Herminio Dionisio 5/25/2013 6:47:19 PM

    Many clients cannot relate to a narrative description of a sys tem but they can relate to a visual representation of that sys tem. Its purpose is to help clients define w hat they w anted. By

    show ing them a mock up solution, they could comment on it and give the developers more insight into w hat constitutes an acceptable solution. It should be obvious that the meaningful

    involvement of the c lient is c ritical to the success of this approach. The client w orks w ith a version of the solution and provides feedback to the project team as they envision further

    enhancement and changes until all requirements are s atisfied and met. Prototype support the c oncept of progressive elaboration because they are used in iterative cycles of mock up

    creation, users experimentation, and feedback generation.

    http://www.en.wikipedia.org/wiki/prototype
  • 7/27/2019 PM592 Week 3 Discussion

    11/11