32451 Project Management– MASC Training Consultants Case Study for Assignment 1 Faculty of Engineering and IT ASSIGNMENT SUBMISSION SHEET - Individual Subject Name: Project Management Subject No.: 32541 Family Name: Chen Given Name: Maojie Student No.: 10924633 Email : [email protected] u.au Tutor: Alan Sixsmith Tutorial Day: Wednesday Time : 7.30pm Room No.: 10.02.32 0. Lecturer: Alan Sixsmith Assignment No.: 1 Topic: MASC Training Consultants - Case Study Due Date: 6pm, 13 th September 2010 If not submitted on time give details of approved extension or attach approval: I have carefully read, understood, and have taken into account all the requirements and guidelines for assessment and referencing in the subject outline. I affirm that this assignment is my own work; that it has not been previously submitted for assessment; that all material which is quoted is accurately indicated as such; and that I have acknowledged all sources used fully and accurately according to the requirements. I am fully aware that failure to comply with these requirements is a form of cheating and could result in disciplinary action. Signature: ___________________________________Date:_______________________ Subject Number: 32541 Subject Name: Project Management Lecturer: Alan Sixsmith Topic: MASC Training Consultants - Case Study Assignment No.: 1 Due Date: 6pm, 13 th September 2010 Student Name: Maojie Chen Student ID: 10924633 Office Use Only Received (stamp and initial) Office Use Only Received (Tutor’s Signature) RECEIPT

Transcript of PM Assignment 1_Maojie CHen_10924633

Page 1: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

Faculty of Engineering and IT

ASSIGNMENT SUBMISSION SHEET - Individual

Subject Name: Project Management Subject No.: 32541

Family Name: Chen Given Name: Maojie

Student No.: 10924633 Email:

[email protected]

u

Tutor: Alan Sixsmith

Tutorial Day: Wednesday Time: 7.30pm Room No.: 10.02.320.

Lecturer: Alan Sixsmith Assignment No.: 1

Topic: MASC Training Consultants - Case Study

Due Date: 6pm, 13th September 2010

If not submitted on time give details of approved extension or attach approval:

I have carefully read, understood, and have taken into account all the requirements and guidelines for

assessment and referencing in the subject outline. I affirm that this assignment is my own work; that it

has not been previously submitted for assessment; that all material which is quoted is accurately

indicated as such; and that I have acknowledged all sources used fully and accurately according to the

requirements. I am fully aware that failure to comply with these requirements is a form of cheating and

could result in disciplinary action.

Signature: ___________________________________Date:_______________________

Subject Number: 32541

Subject Name: Project Management

Lecturer: Alan Sixsmith

Topic:MASC Training Consultants - Case Study

Assignment No.: 1

Due Date: 6pm, 13th September 2010

Student Name: Maojie Chen

Student ID: 10924633

Office Use OnlyReceived

(stamp and initial)

Office Use OnlyReceived

(Tutor’s Signature)

RECEIP

T

Page 2: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

32541 – Project Management

Assignment 1 :

MASC Training Consultants – Case Study

Due: 09/13/2010

Report by:

Maojie Chen 10924633

Tutor: Alan Sixsmith

Lecture: Alan Sixsmith

Page 3: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

Signatory Page

Project Charter Statement Approval / Signatures

In signing this paper I confirm I have read through the document contents and agree

with the information detailed in all pages.

Name Role Signature Date

Any subsequent changes to the scope of this document are subject to change control and

appropriate sign off.

Page 4: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

Executive Summary

As the current limitation of resource like software and hardware, does not meet

increasing the demand for corporate training, a new training centre will need to

be built to secure major clients over the last 2 years and develop new clients. In

addition, the new technique in education and management will be implemented

in new centre. The purpose for this project charter is to provide essential

contents as a guide line for project management, and describe how the project

team will provide MASC Training Consultants with management program about

new training centre.

The project chart presents how the project will be conducted; having a clear

scope and MOV, providing a well organized Work Breakdown Structure to

implement the project, and detailed analyzing risks. However, time and budget

estimation given from project plan is rough. The time and budget based events

will not be accurate to some extent, such as the implementation of some

deliverable may change because of the variation of time and budget. Therefore,

more detailed and accurate time and budge estimation should be completed in

the later process.

In addition, this project charter does not consider the other unexpected issues

which may happen during the process of implementing the project; as a result,

more reliable implementation strategies need to be investigated as the program

goes on.

Page 5: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

Table of Content

1. Background...................................................................................................1

2. The project’s Measurable Organization Value...............................................1

3. The project stakeholders...............................................................................1

4. The project’s scope:......................................................................................2

4.1 In scope..................................................................................................2

4.2 Out of scope...........................................................................................3

5. Three level Work Breakdown Structure.........................................................3

6. High Level Risk Analysis...............................................................................5

7. Success Criteria............................................................................................7

8. Recommendations........................................................................................7

Appendices...................................................................................................8

Page 6: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

1. Background

As a well developed organization in the training area, MASC Training

Consultants (MTC) offers diverse courses like training technical skills,

management skills, and executive skills etc. While some of the courses are

designed based on the specific customers’ requirement, the others are standard

courses which provide service for trainees from different organizations.

In the past two years, MTC have established tight relationship with several

important clients. Due to the increasing demand for the corporate training, MTC

made a decision to expand a new training centre and offer the first training

course on Monday June 6th, 2011.

The technology components sub-project needed for the new training centre

includes the technology using in the training equipments and the additional

support systems. This coves all the aspects related to training software and

hardware, network infrastructure and security and so on.

2. The project’s Measurable Organization Value

In order to secured several major clients and meet the increasing the

demand for corporate training, a new training centre based new training

system that allows MASC Training Consultants (MTC) to handle 50%

more customers within 2 years of implementation.

Provide technology components in actual training and manage systems

that increase customer satisfaction 50% through customer satisfaction

survey and improve the efficiency and effectiveness of management

through a new system.

1

Page 7: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

3. The project stakeholders

The stakeholders for this project are:

Name Role Contact Details

Simone Forde CEO [email protected]

Stuart Johns CIO [email protected]

Brad Miller CFO Brad . Miller @masc.com.au

Fabrice Simpson CNO Fabrice. [email protected]

Maojie Chen Project Manager [email protected]

Shane Battier IT Operations Manager Shane . [email protected]

Chase Budinger The head of Customer

Service

Chase . [email protected]

Mike Harris The head of Sales &

Marketing

Mike . [email protected]

Jordan Hill The head of Financial

Planning

Jordan [email protected]

Luis Scola The Training Manager Luis . Scola @masc.com.au

Jared Jeffries Trainer Jared [email protected]

Courtney Lee Trainer [email protected]

Ben Stanley Trainer [email protected]

Dina lock Trainer [email protected]

Quistis Trepe Trainer [email protected]

Kyle Lowry Trainer KyleLowry@ masc.com.au

4. The project’s scope:

1.1 In scope

1. Sign a contract with Broadway Construction

2. Purchase software to handle all business function

2

Page 8: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

3. Purchase hardware, network infrastructure and security solutions

via an RFP

4. Migrate application and data to new training building

5. Determine training room and breakout room

6. Design wireless internet access

7. Train staff

8. Contract management for Refurbishment, software, hardware,

network infrastructure and security solutions

9. Develop IT architecture

10.Develop test plan for new system

11. Implement new system

12.Conduct request for proposal process for Refurbishment, software,

hardware, network and security solutions

1.2 Out of scope

1. Maintenance of new software, hardware, network infrastructure

and security solutions

2. Find and hire trainers for training MTC staffs

3. Find and hire new staffs

4. Building refurbishment

5. Three level Work Breakdown Structure

MASC Training Consultants Project

1. Sign a contract with Broadway Construction

1.1 Present requirement

1.2 Negotiation

Milestone: The contract signed

2. Purchase software to handle all business function

2.1 Present requirement

2.2 Negotiation

Milestone: Sign a contract with software company

3

Page 9: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

3. Purchase hardware, network infrastructure and security solutions via an

RFP

3.1 Selection criteria

3.2 Select vendors

3.3 Run the RFP

3.4 Vendors selected

Milestone: Sign contracts with vendors

4. Migrate applications and data to new training building

4.1 Identify applications and data to be migrated

4.2 Implement migration

Milestone: Application and data migration completed

5. Determine training rooms and breakout rooms

5.1 Analyse requirements

5.2 Select appropriate training rooms and breakout rooms

Milestone: Rooms determined

6. Determine wireless internet access

6.1 Design a plan

6.2 Implement the plan

Milestone: wireless internet access determined

7. Train staff

7.1 Design a training plan

7.2 Implement the training plan

Milestone: Staff trained

8. Contract management for refurbishment, software, hardware, network

infrastructure and security solutions

8.1 Design RFPs

8.2 Select and monitor third-party

8.3 Review upon completion

Milestone: Contract management completed

9. Develop IT architecture

4

Page 10: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

9.1 Review the existing architecture

9.2 Technologies to be used

9.3 Various individual architecture plans (Network, communication,

data, security architecture plans etc.)

Milestone: Architecture plan documented

10.Testing new system

10.1 Test plan

10.2 Test result report

Milestone: Testing completed

11. Implement new system

11.1 New system configuration

11.2 New system maintenance

Milestone: New system implemented

12.Conduct RFPs process for software, hardware, network infrastructure

and security solutions

12.1 Business requirements

12.2 RFP preparation and response

12.3 Evaluation and selection

Milestone: RFPs process completed

6. High Level Risk Analysis

It is important to realize that this project may confront many different

unexpected issues which can impact the project progress. Therefore, analysing

and identifying risk in advance is very necessary in project management. When

the project starts, we can prepare for the potential threats and minimize or

eliminate the chance of risk occurring.

Here is a detailed as risk analysis shown bellow:

5

Page 11: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

# RiskLikelihoo

dImpact

Mitigation/Contingency

Strategy

1

Staffs do not

support new

project

H HHighlight the benefit of the

new product

2 Software bugs H MAsk software company to

fix the bugs

3

Business

requirement

change

H H

Convene a meeting with

stakeholders to discuss the

plan

4Misunderstanding

the requirementsH H

Make sure all stakeholders

clearly understand the

requirements and signoff

the documents

5Lose data when

migratingM H

Ensure the data safely

migrate

6

Refurbishment do

not match the

company

standards

M HTrack the refurbishment

regularly

7Refurbishment

delaysM H

Track the refurbishment

regularly

8

Staff turnover or

key member

leaves

M HShare key information to

other members

9 Increasing cost M M Cost control

10

Test plan do not

meet all the

requirements

M MReview test plan and revise

the test plan

6

Page 12: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

11

Poor materials and

grogram for

training staffs

M MReview the training plan

and revise the training plan

12

Staffs lack

technical

knowledge

M LProvide an extensive

training to staffs

13

New security

issues have been

identified

L H

Ask the selected vendors to

fulfill the new security

issues

14

Software is not

user interface-

friendly

L H

Give staffs’ feedback to

software company and ask

to update software

15Ineffective training

programL H Review training program

16 Poor team skills L M Assessments

Legend for Likelihood & Impact: H: High; M: Medium; L: Low

7. Success Criteria

1. The number of trainees and clients increases significantly. Not only

MTC secures old clients but also develops new clients.

2. Expand business. MTC initiate several new courses to meet the

requirement of market.

3. The cost of project is within the expectations of MTC.

4. The project is finished within the prescribed time. The first training

course starts on schedule.

5. The quality of education is improved. Customer complaints reduce, and

increase customer satisfaction through customer satisfaction survey.

6. Reduce the cost and time consumption on training centre management

by using new system.

7

Page 13: PM Assignment 1_Maojie CHen_10924633

32451 Project Management– MASC Training Consultants Case Study for Assignment 1

7. MTC can earn $3 million return on investment from new training centre

with in 3 years

8. Recommendations

Although the project plan about creating the new training centre and the

technology components sub-project provides timely and useful estimation for

the entire project, it still has some deficiency. The actual progress may not fit the

plan such as the time and budget completely because of the rough estimation.

Therefore, more detailed and accurate time and budge estimation should be

completed in the later process. In addition, this project plan does not consider

the other unexpected issues which may happen during the process of

implementing the project; as a result, more reliable implementation strategies

need to be investigated as the program goes on.

Appendices

The Budget components are as follows:

Budget Component $A(millions)

Software (purchase & implementation) 0.2Database (purchase & implementation) 0.2Training (MTC staff) 1.5Hardware and network infrastructure (purchase & implementation)

1.8

Security components (purchase & implementation)

0.5

Project staff costs (MTC staff only) 0.8Training Centre Refurbishment 2.5Contingency 2.5Total 10

8