‘Plugging In’ to Hybrid Technology Milwaukee County’s PHEV Utility Trucks

9
‘Plugging In’ to Hybrid Technology Milwaukee County’s PHEV Utility Trucks Sustainability Summit Milwaukee, WI March 6, 2013 Presented by: Gordie Bennett

description

‘Plugging In’ to Hybrid Technology Milwaukee County’s PHEV Utility Trucks. Sustainability Summit Milwaukee, WI March 6, 2013 Presented by: Gordie Bennett. Fleet Management. Part of Co. Dept of Transportation Headed by Dan Goeden 27 technicians Maintain and manage: - PowerPoint PPT Presentation

Transcript of ‘Plugging In’ to Hybrid Technology Milwaukee County’s PHEV Utility Trucks

Page 1: ‘Plugging In’ to Hybrid Technology Milwaukee County’s  PHEV Utility Trucks

‘Plugging In’ to Hybrid Technology

Milwaukee County’s PHEV Utility Trucks

Sustainability SummitMilwaukee, WIMarch 6, 2013

Presented by:Gordie Bennett

Page 2: ‘Plugging In’ to Hybrid Technology Milwaukee County’s  PHEV Utility Trucks

Fleet Management

• Part of Co. Dept of Transportation• Headed by Dan Goeden• 27 technicians • Maintain and manage:

– 2700 vehicles and equipment  – 4 fueling sites @ 800K gal/yr

Milwaukee County’s PHEV Utility Trucks March 6, 2013

Page 3: ‘Plugging In’ to Hybrid Technology Milwaukee County’s  PHEV Utility Trucks

PHEV Utility Trucks

• Delivered late 2011/early 2012• 4 bucket trucks w/ cranes• Used by Highway Maintenance• Driven > 24K miles in CY12• Maintained by Fleet Mgmt

Milwaukee County’s PHEV Utility Trucks March 6, 2013

Page 4: ‘Plugging In’ to Hybrid Technology Milwaukee County’s  PHEV Utility Trucks

Our Trucks

• Made by Deuco and Odyne• Purchased 2 x 40-ft, 2 x 60-ft• Chassis by Kenworth• 35kWh Li-Ion battery system• Redundant power for hydraulics• Retro-fit capable

Milwaukee County’s PHEV Utility Trucks March 6, 2013

Page 5: ‘Plugging In’ to Hybrid Technology Milwaukee County’s  PHEV Utility Trucks

Battery Charging

• Two 208-volt chargers • Charge overnight as needed• Electricity use metered• Costs ~$2.25 per 95% charge

Milwaukee County’s PHEV Utility Trucks March 6, 2013

Page 6: ‘Plugging In’ to Hybrid Technology Milwaukee County’s  PHEV Utility Trucks

Costs & Funding

• $1.2 M total; $400K thru WCTP• Previous trucks due for replacement• County bought trucks• WCC supported hybridization:

– Batteries– Hybrid motors– Charging station

Milwaukee County’s PHEV Utility Trucks March 6, 2013

Page 7: ‘Plugging In’ to Hybrid Technology Milwaukee County’s  PHEV Utility Trucks

Benefits

• Improved fuel efficiency:– Nearly 50% higher mpg– Avoided $34K/yr in fuel costs

• Reduced idling and noise:– Engine not needed for hydraulics– Cabs heated/cooled with batteries

• Hedge against fuel cost increases• Positive buzz and PR for County

Milwaukee County’s PHEV Utility Trucks March 6, 2013

Page 8: ‘Plugging In’ to Hybrid Technology Milwaukee County’s  PHEV Utility Trucks

Lessons Learned

• Special reqs may delay delivery• Build charger costs into estimates• Techs need training on O&M• Added weight -> slower acceleration

Milwaukee County’s PHEV Utility Trucks March 6, 2013

Page 9: ‘Plugging In’ to Hybrid Technology Milwaukee County’s  PHEV Utility Trucks

Gordie BennettDirector, Office of [email protected]

Dan GoedenDirector, Fleet Management [email protected]

Contact Us

WCTP:wicleancities.org

milwaukeecounty.org/greenprint