PLC SCADA report Paras Singhal

56
1 A Report On Industrial Automation Based On PLC & SCADA DH+ AUTOMATION PVT. LTD. From: 1 JUNE 2014 to 15 TH JULY 2014 Submitted in partial fulfillment for the award of Degree of Bachelor of Technology in Electrical Engineering Session: 2014-15 Submitted to: Seminar Incharge : Submitted by: Mr. Kapil Parikh Vikas Jain Paras Head of Department Assistant Professor VII th B.Tech Electrical (Electrical Engineering) Department of Electrical Engineering Shrinathji Institute of Technology & Engineering (Affiliated To RTU Kota, Rajasthan)

Transcript of PLC SCADA report Paras Singhal

Page 1: PLC SCADA report Paras Singhal

1

A

Report On

Industrial Automation

Based On PLC & SCADA

DH+ AUTOMATION PVT. LTD.

From: 1 JUNE 2014 to 15TH JULY 2014

Submitted in partial fulfillment for the award of Degree of

Bachelor of Technology in Electrical Engineering

Session: 2014-15

Submitted to: Seminar Incharge : Submitted by:

Mr. Kapil Parikh Vikas Jain Paras

Head of Department Assistant Professor VIIth B.Tech Electrical

(Electrical Engineering)

Department of Electrical Engineering

Shrinathji Institute of Technology & Engineering

(Affiliated To RTU Kota, Rajasthan)

Page 2: PLC SCADA report Paras Singhal

2

ACKNOWLEDGEMENT

I am very pleasure to express my deep sense of gratitude to my esteem guide “Mr.Vikas

jain” (Assistant Professor in EE Dept.) for his valuable guidance, encouragement and

facilities provided during the training.

We wish to offer our gratitude to the management of “DH+ Automatiom Pvt.Ltd. “for

providing us with this opportunity to undergo Vocational Training at Jaipur. We would also

like to give our sincere thanks to the staff of learning Centre for their efforts in monitoring

our training activities.

We owe my gratitude to Mr. Head of Electrical Dept. of the DH+ Automation

Pvt.Ltd.company, and his team of engineers who shared their valuable experience of

working in the captive power plan.

I am also heartily thanks to Mr. Kapil Parikh (Head, Dept. of EE) for his cooperation in

providing all the facilities at every stage of the training. I extend my sincere thanks to my

friends who are there with me directly or in directly during the training.

Paras

VIIth B.Tech Electrical

Page 3: PLC SCADA report Paras Singhal

3

Chapter- 1

INTRODUCTION

1.1 INDUSTRIAL AUTOMATION:

Automation or industrial automation is the use of control systems such as computers,

controllers to control industrial machinery and processes, to optimize productivity in the

production of goods and delivery of services. Automation is a step beyond mechanization.

Mechanization provides human operators with machinery to assist them with the muscular

requirements of work, while automation greatly decreases the need for human sensory and

mental requirements while increasing load capacity, speed, and repeatability.

Automation is basically the delegation of human control Function to technical equipment for

Increasing Productivity

Increasing Quality

Reducing Cost

Increasing Safety in working conditions

1.2 AUTOMATION IMPACTS:

It increases productivity and reduce cost.

It gives emphasis on flexibility and convertibility of manufacturing process. Hence gives

manufacturers the ability to easily switch from manufacturing Product A to

manufacturing product B without completely rebuilt the existing system/produc t lines.

Automation is now often applied primarily to increase quality in the manufacturing

process, where automation can increase quality substantially.

Replacing humans in task done in dangerous environment .

1.3 DEVELOPMENT STAGES OF AUTOMATION:

1. Manual Control

2. Pneumatic Control

3. Hard wired logic Control

4. Electronic Control using Logic Gates

5. Programmable Logic Controller

Page 4: PLC SCADA report Paras Singhal

4

1.3.1 Manual Control:

All the actions related to process control are taken by the operators .

Drawbacks:

Likely human errors and consequently its effect on quality of final product

The production, safety, energy consumption and usage of raw material are all subject to

the correctness and accuracy of human action.

1.3.2 Pneumatic Control:

Industrial automation, with its machine and process control, had its origin in the 1920s

with the advent of "Pneumatic Controllers".

Actions were controlled by a simple manipulation of pneumatic valves, which in turn

were controlled by relays and switches.

Drawbacks:

Bulky and Complex System

Involves lot of rework to implement control logic

Longer project time

1.3.3 Hard wired logic control:

The contactor and Relays together with hardware timers and counters were used in achieving

the desired level of automation.

Drawbacks

Bulky panels

Complex wiring

Longer project time

Difficult maintenance and troubleshooting.

1.3.4 Electronic Control using Logic Gates:

In 1960s with the advent of electronics, the logic gates started replacing the relays and

auxiliary contactors in the control circuits. The hardware timers & counters were replaced by

electronic timers.

Advantages:

Reduced space requirements

Energy saving

Less maintenance & greater reliability

Page 5: PLC SCADA report Paras Singhal

5

Drawbacks:

Changes in control logic not possible

More project time

1.3.5 Programmable Logic Controllers:

In 1970s with the coming of microprocessors and associated peripheral chips, the whole

process of control and automation underwent a radical change.

Instead of achieving the desired control or automation through physical wiring of control

devices, in PLC it is achieved through a program or say software.

It can be effectively used in applications ranging from simple control like replacing small

number of relays to complex automation problems

Page 6: PLC SCADA report Paras Singhal

6

Chapter- 2

PROGRAMMABLE LOGIC CONTROLLER

2.1 HISTORY OF PLC’S:

In the 1960's Programmable Logic Controllers were first developed to replace relays and

relay control systems. Relays, while very useful in some applications, also have some

problems. The primary reason for designing such a device was eliminating the large cost

involved in replacing the complicated relay based machine control systems for major U.S. car

manufacturers. These controllers eliminated the need of rewiring and adding additional

hardware for every new configuration of logic. These, along with other considerations, led to

the development of PLCs. plc was more improved in 1970’s. In 1973 the ability to

communicate between PLCs was added. This also made it possible to have the controlling

circuit quite a ways away from the machine it was controlling. However, at this time the lack

of standardization in PLCs created other problems. This was improved in the 1980's.The size

of PLCs was also reduced then, thus using space even more efficiently. The 90's increased the

collection of ways in which a PLC could be programmed (block diagrams, instruction list, C,

etc.).

2.2 INTRODUCTION OF PLC’S:

A programmable logic controller (PLC) is an industrial computer control system that

continuously monitors the state of input devices and makes decisions based upon a

custom program to control the state of output devices.

It is designed for multiple inputs and output arrangements, extended temperature ranges,

immunity to electrical noise, and resistance to vibration and impact.

They are used in many industries such as oil refineries, manufacturing lines, conveyor

systems and so on, wherever there is a need to control devices the PLC provides a flexible

way to "soft wire" the components together.

The basic units have a CPU (a computer processor) that is dedicated to run one program

that monitors a series of different inputs and logically manipulates the outputs for the

desired control. They are meant to be very flexible in how they can be programmed while

Page 7: PLC SCADA report Paras Singhal

7

also providing the advantages of high reliability (no program crashes or mechanical

failures), compact and economical over traditional control systems.

In simple words, Programmable Logic Controllers are relay control systems put in a very

small package. This means that one PLC acts basically like a bunch of relays, counters,

timers, places for data storage, and a few various other things, all in one small package.

2.3 ARCITECTURE AND TERMINOLOGY OF PLC’S:

The PLC give output in order to switch things on or off. The PLC’s output is proportionally

activated according on the status of the system’s feedback sensors and input terminal which is

connected to PLC’s. The decision to activate output are based on logic programmes. The

logic programme stored in RAM or ROM memory. The PLC’s also have same as computer, a

CPU, data bus and address bus.

Fig 2.1: PLC’s internal architecture

The next diagram shows a simplified diagram of PLC’s structure. The central processing unit

control everything according to a programme stored in a memory (RAM/ROM ).Everything

is interconnected by two buses ,the address bus and data bus . The system must be able to

communicate with external devices such as programmers,display moniter and a/d converter.

Page 8: PLC SCADA report Paras Singhal

8

Fig 2.2: Simplified PLC’s structure

Fig 2.3: Basic plc sections

Page 9: PLC SCADA report Paras Singhal

9

PLCs contain three basic sections:

1. Central processing unit (CPU)

2. Memory: RAM, and ROM

3. Input/output module

4. Power supply

2.3.1 Central processing unit (C.P.U):

Like other computerized devices, there is a Central Processing Unit (CPU) in a PLC. The

CPU, which is the “brain” of a PLC, does the following operations:

Updating inputs and outputs. This function allows a PLC to read the status of its input

terminals and energize or de-energize its output terminals.

Performing logic and arithmetic operations. A CPU conducts all the mathematic and

logic operations involved in a PLC.

Communicating with memory. The PLC’s programs and data are stored in memory.

When a PLC is operating, its CPU may read or change the contents of memory

locations.

Scanning application programs. An application program, which is called a ladder logic

program, is a set of instructions written by a PLC programmer. The scanning function

allows the PLC to execute the application program as specified by the programmer.

Communicating with a programming terminal. The CPU transfers program and data

between itself and the programming terminal.

A PLC’s CPU is controlled by operating system software. The operating system software is a

group of supervisory programs that are loaded and stored permanently in the PLC’s memory

by the PLC manufacturer.

2.3.2 Input/ Output module:

2.3.2.1 Input module:

In smaller PLCs the inputs are normally built in and are specified when purchasing the PLC.

For larger PLCs the inputs are purchased as modules, or cards, with 8 or 16 inputs of the

same type on each card.The list below shows typical ranges for input voltages.

Page 10: PLC SCADA report Paras Singhal

10

12-24 Vdc

100-120 Vac

10-60 Vdc

12-24 Vac/dc

5 Vdc (TTL)

200-240 Vac

48 Vdc

24 Vac

PLC input cards rarely supply power, this means that an external power supply is needed to

supply power for the inputs and sensors. The example in See An AC Input Card shows how

to connect an AC input card.

Fig 2.4: Input card connect with external power supply

In the example there are two inputs, one is a normally open push button, and the second is a

temperature switch, or thermal relay. Both of the switches are powered by the hot output of

the 24Vac power supply - this is like the positive terminal on a DC supply. Power is supplied

to the left side of both of the switches. When the switches are open there is no voltage passed

to the input card. If either of the switches are closed power will be supplied to the input.

Page 11: PLC SCADA report Paras Singhal

11

Fig 2.5: Input side internal circuit

Plc input must convert a variety of logic level to the 5Vdc logic levels used on the data

bus.This can be done with the circuit which is shiwn in fig (2.5).This circuit is ouptocoupler

circuit.This circuit ellectrically isolate the external electrical circuitry from internal

circuitry.Other circuit componant guard to reverse voltage polarity.

2.3.2.2 Output module:

As with input modules, output modules rarely supply any power, but instead act as switches.

External power supplies are connected to the output card and the card will switch the power

on or off for each output. Typical output voltages are listed below

120 Vac

24 Vdc

12-48 Vac

12-48 Vdc

5Vdc (TTL)

230 Vac

These cards typically have 8 to 16 outputs of the same type and can be purchased with

different current ratings. A common choice when purchasing output cards is relays,

transistors or triacs. Relays are the most flexible output devices. They are capable of

switching both AC and DC outputs. But, they are slower (about 10ms switching is typical),

they are bulkier and costly.

Page 12: PLC SCADA report Paras Singhal

12

Fig 2.6: output card connected with verious load

In this example the outputs are connected to a low current light bulb (lamp) and a relay coil.

Consider the circuit through the lamp, starting at the 24Vdc supply. When the output 07 is on,

current can flow in 07 to the COM, thus completing the circuit, and allowing the light to turn

on. If the output is off the current cannot flow, and the light will not turn on. The output 03

for the relay is connected in a similar way. When the output 03 is on, current will flow

through the relay coil to close the contacts and supply 120Vac to the motor.

Fig 2.7: Ouput side internal circuit

Plc output must convert the 5Vdc logic levels on the plc data bus to external voltage levels.

This can be done with the circuit which is shown in fig( 2.7).In this circuit the relay coil is

enerzied by 5Vdc and close the relay contect and the output circuit is complete.

Page 13: PLC SCADA report Paras Singhal

13

2.3.3 Memory:

The memory unit of a PLC is the registry where the programs are stored. The fundamental

unit of memory is the word. Words are made up of bits. A bit is a single piece of data. It

contains information on only two states (ON/OFF or YES/NO). Longer words contain more

information within. Programs are combination of words that produce control logic.

To operate the PLC system there is a need for it to access the data to be processed and

instructions, that is, the program, which informs it how the data is to be processed. Both are

stored in the PLC memory for access during processing.

Plc memory has following types:

2.3.3.1 ROM(read only memory ):

ROMstores programs and data and cannot be changed after the memory chip has been

manufactured. ROM memory is non-volatile, meaning that its contents will not be lost if

power is lost. ROM is used by the PLC for the operating system.

2.3.3.2 RAM(random access memory):

RAM is designed so that information can be written into or read from the memory. RAM is

used as a temporary storage area of data that may need to be quickly changed. RAM is

volatile, meaning that the data stored in RAM will be lost if power is lost. A battery backup is

required to avoid losing data in the event of a power loss.

2.3.3.3 EPROM (Erasable Programmable Read Only Memory):

This is memory that can be programmed to behave like ROM, but it can be erased with

ultraviolet light and reprogrammed.

2.3.3.4 EEPROM (Electronically Erasable Programmable Read Only Memory):

This memory can store programs like ROM. It can be programmed and erased using a

voltage, so it is becoming more popular than EPROMs.

2.3.4 Power supply:

PLCs and their constituting modules are equipped with power generated from a power

supply. The power supply converts power line voltages into those required by the solid-state

components. It may be integral or separately mounted . It drives the Central Processor Unit,

I/O logic signals, memory unit and some peripheral devices. The expansion of I/O has led to

increased power requirement of some PLCs.

Page 14: PLC SCADA report Paras Singhal

14

2.4 Scan cycle and scan time:

2.4.1 Scan cycle :

PLC operates by continually scanning the program and acting upon the instructions , one at a

time, to switch on or off the various outputs. In order to do this PLC first scans all the inputs

and stores their states in memory. Then it carries out program scan and decides which outputs

should be high according to the program logic. Then finally it updates these values to the

output table, making the required outputs go high. At this point PLC checks its own operating

system and if everything is ok, it goes back to scanning inputs all over again.

Fig 2.8: PLC scan cycle

Whenever a programe is executed in a plc,before changing any output state,the processor

scan the input table and the entire programe,which gives rise to state of the output device

according to the program logic.These value are then updated to the output table making the

devices connected to the output module on or off. Hence PLC scan cycle consist of three step

shown in a block diagram.

2.4.2 Scan time:

Time taken by PLC to execute these three step (checking input status,executing

program,updating output status)is denoted by scan time.

Page 15: PLC SCADA report Paras Singhal

15

2.5 PROGRAMMING LANGAUGE USED TO PROGRAM PLC:

While Ladder Logic is the most commonly used PLC programming language, but it is not the

only one. Following table lists some of the Languages that are used to program a PLC.

Instruction List (IL)/Statement List(SL)

Structured Text(ST)

Sequential Functional Chart (SFC)

Ladder Diagram(LD).

Functional block Diagram (FBD)

2.5.1 Instruction List (IL)/Statement List(SL):

An instruction list (IL) consists of a series of instructions. Each instruction begins in a new

line and contains an operator and, depending on the type of operation, one or more operands

separated by commas.

In front of an instruction there can be an identification mark (label) followed by a colon (:).

A comment must be the last element in a line. Empty lines can be inserted between

instructions.

Example:

LD 17

ST lint (* Kommentar *)

GE 5

JMPC next

LD idword

EQ istruct.sdword

STN test

next:

2.5.2 Structured Text (ST):

The Structured Text consists of a series of instructions which, as determined in high level

languages, ("IF..THEN..ELSE") or in loops (WHILE..DO) can be executed.

Example:

IF value < 7 THEN

WHILE value < 8 DO

Page 16: PLC SCADA report Paras Singhal

16

value:=value+1;

END_WHILE;

END_IF;

2.5.3 Sequential Function Chart (SFC):

The Sequential Function Chart (SFC) is a graphically oriented language which makes it

possible to describe the chronological order of different actions within a program. For this the

actions are assigned to step elements and the sequence of processing is controlled by

transition elements.

Fig 2.9: Sequential Function Chart

2.5.4 Function Block Diagram (FBD):

The Function Block Diagram is a graphically oriented programming language. It works with

a list of networks whereby each network contains a structure which represents either a logical

or arithmetic expression, the call of a function block, a jump, or a return instruction.

Fig 2.9: Function Block Diagram

Page 17: PLC SCADA report Paras Singhal

17

2.5.5 Ladder Diagram (LD):

The Ladder Diagram is also a graphics oriented programming language which approaches the

structure of an electric circuit. Ladder Diagram consists of a series of networks. Each network

consists on the left side of a series of contacts which pass on from left to right the condition

"ON" or "OFF" which correspond to the Boolean values TRUE and FALSE. To each contact

belongs a Boolean variable. If this variable is TRUE, then condition pass from left to right.

Fig 2.10: ladder diagram

Page 18: PLC SCADA report Paras Singhal

18

Chapter- 3

COMMUNICATION/PROGRAMMING WITH SOFTWARE RSLINX

This chapter explains how to program the PLC. It describes how to write a program, how the

program is structured and representation of the programming language.

3.1 PROGRAMING BY LADDER DIAGRAM:

Ladder logic is a method of drawing electrical logic schematics. It is now a graphical

language very popular for programming Programmable Logic Controllers (PLCs). It was

originally invented to describe logic made from relays. The name is based on the observation

that programs in this language resemble ladders, with two vertical "rails "and a series of

horizontal "rungs" between them. A program in the ladder logic, also called ladder diagram is

similar to a schematic for a set of relay circuits.

The Ladder Diagram is also a graphics oriented programming language which approaches the

structure of an electric circuit. The Ladder Diagram consists of a series of networks. A

network is limited on the left and right sides by a left and right vertical current line. In the

middle is a circuit diagram made up of contacts, coils, and connecting lines.

Each network consists on the left side of a series of contacts which pass on from left to right

the condition "ON" or "OFF" which correspond to the Boolean values TRUE and FALSE. To

each contact belongs a Boolean variable. If this variable is TRUE, then the condition is

passed from left to right along the connecting line. Otherwise the right connection receives

the value OFF.

INPUT represented by I

OUTPUT represented by O.

Page 19: PLC SCADA report Paras Singhal

19

3.2 Addressing method:

1 slot=32 bit=2 word (1 char./word=2 byte=16 bit)

3.2.1 Input addressing:

File letter:Slot number.Word number/Bit number

For example I:2.1/1

3.2.2 Output addressing:

File letter:Slot number.Word number/Bit number

For example O:2.1/1

3.3 GENERALLY USED INSTRUCTIONS & SYMBOL FOR PLC

PROGRAMMING:

3.3.1 Input Instruction:

1. --[ ]-- This Instruction is Called XIC or Examine If Closed.

ie; If a NO switch is actuated then only this instruction will be true. If a NC switch is

actuated then this instruction will not be true and hence output will not be generated.

2. --[\]-- This Instruction is Called XIO or Examine If Open

ie; If a NC switch is actuated then only this instruction will be true. If a NC switch is

actuated then this instruction will not be true and hence output will not be generated.

3.3.2 Output Instruction:

1. --( )-- This Instruction Shows the States of Output(called OTE).

ie; If any instruction either XIO or XIC is true then output will be high. Due to high

output a 24 volt signal is generated from PLC processor.

2. --(L)-- Output Latch (OTL)

OTL turns a bit on when the rung is executed, and this bit retains its state when the rung is

not executed or a power cycle occurs.

3. --(U)-- Output Unlatch(OTU)

Page 20: PLC SCADA report Paras Singhal

20

OTU turns a bit off when the rung is executed, and this bit retains its state when the rung

is not executed or when power cycle occurs.

3.3.3 Rung:

Rung is a simple line on which instruction are placed and logics are created

E.g.; ---------------------------------------------

3.3.4 Timer:

Timer has three bit:

EN:Enable bit :

The Timer Enable (EN) bit is set immediately when the rung goes true. It stays set until

the rung goes false.

TT:Timer timing bit :

The Timer Timing (TT) bit is set when the rung goes true. It stays set until the rung goes

false or the Timer Done (DN) bit is set (i.e. when accumulated value equals preset value).

DN:Done bit:

The Timer Done (DN) bit is not set until the accumulated value is equal to the preset

value. It stays set until the rung goes false.

Timer is three type:

1. TON 2. TOF 3. RTO

3.3.4.1 TON: Timer On

Counts time base intervals when the instruction is true.

Fig 3.1: Timer on

3.3.4.2 TOF: Timer off

Delay Counts time base intervals when the instruction is false.

Page 21: PLC SCADA report Paras Singhal

21

Fig 3.2: Timer off

3.3.4.3 RTO: Retentive Timer

This type of timer does NOT reset the accumulated time when the input condition goes false.

Rather, it keeps the last accumulated time in memory, and (if/when the input goes true again)

continues timing from that point.

Fig 3.3: Retentive Timer

Addressing of timer:

Fig 3.4: Addressing of timer

Page 22: PLC SCADA report Paras Singhal

22

Table 3.1: Status of bits in timer

3.3.5 Counter:

Counter has three bit:

Count Up bit (CU):

Set When Rung conditions are true and remains set till rung conditions go false or a RES

instruction that has the same address as the CTD instruction is enabled.

Done bit ( DN):

Set When The accumulated value is => the preset value and remains set till The

accumulated value becomes less than the preset value.

Overflow ( OV):

Set When Accumulated value wraps around to +32,768 (from: 32 767) and continues

counting from there and remains set till a RES instruction that has same address as the

CTD instruction is executed or the count is incremented greater than or equal to +32,767

with a CTU instruction.

Page 23: PLC SCADA report Paras Singhal

23

Counter is two type :

1. CTU

2. CTD

3.3.5.1 CTU: Count Up

Increments the accumulated value at each false-to true transition and retains the accumulated

value when the instruction goes false or when power cycle occurs.

Fig 3.4: Count Up

3.3.5.2 CTD: Count Down

Decrements the accumulate value at each false-to true transition and retains the accumulated

value when the instruction goes false or when power cycle occurs.

Fig 3.5: Count Down

Addresing of counter:

Fig 3.4: Addressing of timer

Page 24: PLC SCADA report Paras Singhal

24

3.3.7 RESET: --(RES)--

Resets the accumulated value and status bits of a timer or counter.

A C5:0

-------[ ]---------------------(RES)--------------------------

When A is true than counter C5:0 is reset.

3.4 BOOLEAN LOGIC DESIGN BY LADDER DIAGRAM:

3.4.1 AND logic:

Y0=X0.X1

Fig 3.5: AND logic ladder diagram

3.4.2 OR logic:

Y1=X0+X1

Fig 3.6: OR logic ladder diagram

3.4.3 NOT logic:

Y3=X0

Fig 3.7: NOT logic ladder diagram

Page 25: PLC SCADA report Paras Singhal

25

3.4.4 NAND logic:

Y0=X0.X1

Fig 3.8: NAND logic ladder diagram

3.4.5 NOR logic:

Y1=X0+X1

Fig 3.9: NOR logic ladder diagram

3.4.6 X-OR logic:

Y2=X0 X1

Fig 3.10: XOR logic ladder diagram

3.4.7 X-NOR logic:

Y2=X0 X1

Fig 3.11: X-NOR logic ladder diagram

Page 26: PLC SCADA report Paras Singhal

26

3.5 PROGRAMING AND OPERATIONS IN PLC:

To understannding the programing and operation we consider a example .

We have a car parking place which has five car parking capacity and we want to control the

parking gate/light. We have one input sensor, one exit sensor,for power supply start stop push

button,and for indication LED light

3.5.1 Making programme:

STEP: 1

Making start stop push button logic:

Fig 3.12: Push button logic ladder diagram

Here button a is start push button and b is stop push button and x is binary type output.

STEP: 2

Making input side sensor logic:

Fig 3.13: Input sensor logic ladder diagram

Here we use one input sensor and one counter which is CTU (counter up) and take CTU

preset value 5.

STEP: 3

Making exit side sensor logic:

Page 27: PLC SCADA report Paras Singhal

27

Fig 3.14: Output sensor logic ladder diagram

Here we use one Exit sensor and one counter which is CTD (counter down) and take CTD

preset value 5.

STEP: 4

Making parking light (LED) control logic:

Fig 3.15: led light logic ladder diagram

Here we take done bit (DN) of counter for controlling the led light .

Operation:

After program making ,it is download in plc.This program store in plc memory.

When we push the start button than plc scan the input means input condition of button A is

true(1).so the binary output is also true(1).

Fig 3.16: operation of Push button logic(on pressing NO switch)

When start button release than input condition of button A is false.

Page 28: PLC SCADA report Paras Singhal

28

But the start button and binary input both are in parellel .The address of binary output and

binary input are same so we get continuous supply.

Fig 3.17: operation of Push button logic (on releasing NO switch)

Binary output we can use as a input in next step ,its status is true.for sense the entering car we

use a input sensor and for counting the car we use a CTU .

CTU address is C5:0 and take its preset value 5 because parking place capacity is 5. When

first car enter then input sensor status goes true . Due to this CTU count one in it’s

accumulator value .but counter done bit does not true because accumulator value less than

preset value.

Similarly when fifth car enter than CTU count it’s accumulator value .Now counter done bit

is true because accumlator value equal to preset value.

Fig 3.18: operation of input sensor logic

When done bit goes true than LED output is true so parking light is on.

Fig 3.19: operation of led with input sensor logic

Page 29: PLC SCADA report Paras Singhal

29

At exit side, one car is goes outside form parking place.Now four car is present in the parking

place but CTU done bit is on so LED light is on.To remove this interlocking problem we use

same address for both counter (CTU and CTD).

Both counter have same address so CTU accumulator value and CTD accumulator value both

are same.

Fig 3.20: operation of exit sensor logic

At exit side for sense the car we use a exit sensor .when one car is exit. Than exit sensor

status is true and CTD count and update the accumulator value .

Now both counter’s accumulator value less than preset value so done bit goes false and

parking light off .

Fig 3.21: programme on window

Page 30: PLC SCADA report Paras Singhal

30

Chapter -4

COMMUNICATION NETWORK ND APPLICATION

4.1 COMMUNICATION NETWORK OF PLC:

A proper interaction between devices, communication interfaces physical media and

connecting products is possible only if correct network is chosen for communication.

The most commonly used network solutions are:

1. EtherNet/IP

2. ControlNet

3. DeviceNet

4. DH-485

5. DH+

Table 4.1: Communication network of plc

Use this network If your application requires

EtherNet/IP network • Plant management (material handling)

• Configuration, data collection, and

control on a single, high-speed

network

• Time-critical applications with no

established schedule

• Internet connection

ControlNet network • High-speed transfer of time-critical

data between controllers and I/O

devices

• Deterministic and repeatable data

delivery

• Media redundancy

• Intrinsic safety

DeviceNet network • Connections of low-level devices

directly to plant floor controllers,

Page 31: PLC SCADA report Paras Singhal

31

without interfacing them through I/O

modules

• Data sent as needed

• More diagnostics for improved data

collection and fault detection

• Less wiring and reduced start-up time

than a traditional, hard-wired system

DH-485 network • Connections to existing DH-485

networks

• The DH-485 connection does support

remote programming and monitoring

via RSLogix 5000 software

Data Highway Plus

network

• Plant-wide and cell-level data sharing

with program maintenance

• Data sent regularly

• Transfer of information(messaging)

between controllers

4.2 TOPOLOGY:

The structure of a network is called the topology. The basic network topologies shown in

fig(4.1). The Bus and Ring topologies both share the same network wire. In the Star

configuration each computer has a single wire for connection.

Fig 4.1: Network Topologies

Page 32: PLC SCADA report Paras Singhal

32

In the Ring and Bus topologies the network control is distributed between all of the

computers on the network. The wiring only uses a single loop or run of wire. But, because

there is only one wire, the network will slow down significantly as traffic increases.

The Star topology requires more wire overall to connect each computer to an intelligent hub.

But, the network interfaces in the computer become simpler, and the network becomes more

reliable.

For a factory environment the bus topology is popular. The large number of wires required

for a star configuration can be expensive and confusing. The loop of wire required for a ring

topology is also difficult to connect.

Fig 4.2: Topology with repeater

Repeaters are used to boost the signal strength and allow the network to be larger.

Table 4.2: Comparision between communication protocols:

S.N. Network Max. No. node Speed Network

length

1. Ethernet 1024 10-

1000Gbps

85m coax,

100m twisted

pair, 400m-

50km fiber

2. Controlnet 99 5Mbps 250m-1000m

wire,3-30km

Page 33: PLC SCADA report Paras Singhal

33

fiber

3. Devicenet 64 125-

500Kbps

500m

4. DH485 32 19.2kbps 1.2 km

5. DH+ 64 230kbps 3.048km

4.3 APPLICATIONS OF PLC:

In the present industrial world, a flexible system that can be controlled by user at

site is preferred. Systems, whose logic can be modified but still, used without disturbing its

connection to external world, is achieved by PLC. Utilizing the industrial sensors such as

limit switches, ON-OFF switches, timer contact, counter contact etc., PLC controls the total

system. The drive to the solenoid valves, motors, indicators, enunciators, etc are controlled

by the PLCs.

The above said controlling elements (normally called as inputs of PLCs) and

controlled elements (called as outputs of PLCs) exist abundantly in any industry. These

inputs, outputs, timers, counters, auxiliary contacts are integral parts of all industries. As

such, it is difficult to define where a PLC cannot be used.

Proper application of a PLC begins with conversion of information into

convenient parameters to save money, time and effort and hence easy operation in plants and

laboratories.

The areas where PLC is used maximum are as follows:

1. The batch processes in chemical, cement, food and paper industries which are sequential

in nature, requiring time of event based decisions is controlled by PLCs.

2. In large process plants PLCs are being increasingly used for automatic start up and shut

down of critical equipment. A PLC ensures that equipment cannot be started unless all

the permissive conditions for safe start have seen established. It also monitors the

conditions necessary for safe running of the equipment and trips the equipment whenever

any abnormality in the system is detected.

3. The PLC can be programmed to function as an energy management system for boiler

control for maximum efficiency and safety.

4. In automation of blender recliners

5. In automation of bulk material handling system at ports.

Page 34: PLC SCADA report Paras Singhal

34

6. In automation for a ship unloaded.

7. Automation for wagon loaders.

8. For blast furnace charging controls in steel plants.

9. In automation of brick molding press in refractory.

10. In automation for galvanizing unit.

11. For chemical plants process control automation.

12. In automation of a rock phosphate drying and grinding system.

13. Modernization of boiler and turbo generator set.

14. Process visualization for mining application.

15. Criteria display system for power station.

16. As stored programmed automation unit for the operation of diesel generator sets.

17. In Dairy automation and food processing.

18. For a highly modernized pulp paper factory.

19. In automation system for the printing industry.

20. In automation of container transfer crane.

21. In automation of High-speed elevators.

22. In plastic molding process.

23. In automation of machine tools and transfer lines.

24. In Mixing operations and automation of packaging plants.

25. In compressed air plants and gas handling plants.

26. In fuel oil processing plants and water classification plants.

27. To control the conveyor/classifying system.

Thus PLC is ideal for application where plant machine interlock requirements are

finalized at a later stage and need changes during engineering trial runs, commissioning or

normal use.

Page 35: PLC SCADA report Paras Singhal

35

Chapter- 5

SCADA

(SUPERVISORY CONTROL AND DATA ACQUISITION)

5.1 INTRODUCTION

SCADA stands for Supervisory Control And Data Acquisition. As the name indicates, it is

not a full control system, but rather focuses on the supervisory level. As such, it is a purely

software package that is positioned on top of hardware to which it is interfaced, in general via

Programmable Logic Controllers (PLCs), or other commercial hardware modules.

SCADA systems are used to monitor and control a plant or equipment in

industries such as telecommunications, water and waste control, energy, oil and gas refining

and transportation. These systems encompass the transfer of data between a SCADA central

host computer and a number of Remote Terminal Units (RTUs) and/or Programmable Logic

Controllers (PLCs), and the central host and the operator terminals. A SCADA system

gathers information (such as where a leak on a pipeline has occurred), transfers the

information back to a central site, then alerts the home station that a leak has occurred,

carrying out necessary analysis and control, such as determining if the leak is critical, and

displaying the information in a logical and organized fashion.

SCADA systems consist of:

1. One or more field data interface devices, usually RTUs, or PLCs, which interface to field

sensing devices and local control switchboxes and valve actuators

2. A communications system used to transfer data between field data interface devices and

control units and the computers in the SCADA central host. The system can be radio,

telephone, cable, satellite, etc., or any combination of these.

3. A central host computer server or servers (sometimes called a SCADA Center, master

station, or Master Terminal Unit (MTU)

4. A collection of standard and/or custom software [sometimes called Human Machine

Interface (HMI) software or Man Machine Interface (MMI) software] systems used to

provide the SCADA central host and operator terminal application, support the

communications system, and monitor and control remotely located field data interface

devices.

Page 36: PLC SCADA report Paras Singhal

36

Fig 5.1: Typical SCADA System

5.2 Types of SCADA:

1. D+R+N (Development +Run + Networking)

2. R+N (Run +Networking)

3. Factory focus (Networking)

5.3 Basic Features of SCADA:

1. Dynamic process Graphic

2. Alarm summery

3. Alarm history

4. Real time trend

5. Historical time trend

6. Security (Application Security)

7. Data base connectivity

8. Device connectivity

9. Scripts

10. Recipe management

Page 37: PLC SCADA report Paras Singhal

37

11. Web Browser Client to View and Control

12. Web Browser based engineering

5.3.1 Dynamic process Graphic:

These graphics are commonly called as “SCREENS” and represent pictorial real time data of

the process/plant/machine. Having no limitation on the number of screens for application is

big advantage of SCADA.

5.3.2 Alarms Summery:

This is inbuilt graphic screen of SCADA which gives you consolidated alarm list with

details like time, area, description, level and status.

5.3.3 Alarm history:

SCADA alarm history can be used for detail analysis. Alarms can be stored for data validity

upto years together.

5.3.4 Real time trend:

These are graphical forms for analog or digital values with respect to time. Time can vary

between few second to years.

5.3.5 Historical time trend:

Historical time trends are trends use history data for graphics. SCADA can help you get

data in graphical format saved for many years.

5.3.6 Security:

This feature is nothing but access control of SCADA. SCADA can be used by many persons

from many organization. So to control & limit access of everyone to every data of the

process, we can have security levels designed.

5.3.7 Database connectivity:

SCADA stores the data in its own format depending of manufacturer. But user may require

using this data in various formats like Microsoft Access, Excel Etc. This definitely calls for

database connectivity between two different databases.

5.3.8 Device connectivity:

This can be used through communication protocols.

5.3.9 Scripts:

Backend of SCADA can be VB or C for which new block can be designed and complex

calculations can be done using Scripting.

Page 38: PLC SCADA report Paras Singhal

38

5.3.10 Recipe management:

For Batch process, you can have multiple recipes predefined in SCADA. For complex or

more no of recipes you can use special batch software’s available.

5.3.11 Web browser client for monitor and control:

Today in this internet based generation we always need access of our data at any point and

any location. Web browser makes your SCADA available on internet where as per access

granted and license purchased either you can monitor or control the SCADA

5.4 GENERATIONS OF SCADA SYSTEMS:

SCADA systems have evolved in parallel with the growth and sophistication of modern

Computing technology. The following sections will provide a description of the following

three generations of SCADA systems:

• First Generation – Monolithic

• Second Generation – Distributed

• Third Generation – Networked

5.4.1 Monolithic SCADA Systems:

When SCADA systems were first developed, the concept of computing in general centered

on “mainframe” systems. Networks were generally non-existent, and each centralized system

stood alone. As a result, SCADA systems were standalone systems with virtually no

connectivity to other systems. The Wide Area Networks (WANs) that were implemented to

communicate with remote terminal units (RTUs) were designed with a single purpose in

mind–that of communicating with RTUs in the field and nothing else. In addition, WAN

protocols in use today were largely unknown at the time. The communication protocols in use

on SCADA networks were developed by vendors of RTU equipment and were often

proprietary. In addition, these protocols were generally very “lean”, supporting virtually no

functionality beyond that required scanning and controlling points within the remote device.

Also, it was generally not feasible to intermingle other types of data traffic with RTU

communications on the network.

Connectivity to the SCADA master station itself was very limited by the system vendor.

Connections to the master typically were done at the bus level via a proprietary adapter or

controller plugged into the Central Processing Unit (CPU) backplane. Redundancy in these

Page 39: PLC SCADA report Paras Singhal

39

first generation systems was accomplished by the use of two identically equipped mainframe

systems, a primary and a backup, connected at the bus level.

Fig 5.2: First Generation SCADA Architecture

The stand by system’s primary function was to monitor the primary and take over in the event

of a detected failure. This type of standby operation meant that little or no processing was

done on the standby system. Figure 3.1 shows a typical first generation SCADA architecture.

5.4.2 Distributed SCADA Systems:

The next generation of SCADA systems took advantage of developments and improvement

in system miniaturization and Local Area Networking (LAN) technology to distribute the

processing across multiple systems. Multiple stations, each with a specific function, were

connected to a LAN and shared information with each other in real-time. These stations were

typically of the mini-computer class, smaller and less expensive than their first generation

processors. Some of these distributed stations served as communications processors,

primarily communicating with field devices such as RTUs. Some served as operator

interfaces, providing the human-machine interface (HMI) for system operators. Still others

served as calculation processors or database servers. The distribution of individual SCADA

Page 40: PLC SCADA report Paras Singhal

40

system functions across multiple systems provided more processing power for the system as a

whole than would have been available in a single processor.

The networks that connected these individual systems were generally based on

LAN protocols and were not capable of reaching beyond the limits of the local environment.

Some of the LAN protocols that were used were of a proprietary nature, where the vendor

created its own network protocol or version thereof rather than pulling an existing one off the

shelf. This allowed a vendor to optimize its LAN protocol for real-time traffic, but it limited

(or effectively eliminated) the connection of network from other vendors to the SCADA

LAN. Figure 11.2 depicts typical second generation SCADA architecture. Distribution of

system functionality across network-connected systems served not only to increase

processing power, but also to improve the redundancy and reliability of the system as a

whole. Rather than the simple primary/standby failover scheme that was utilized in many first

generation systems, the distributed architecture often kept all stations on the LAN in an

online state all of the time.

For example, if an HMI station were to fail, another HMI station could be used

to operate the system, without waiting for failover from the primary system to the secondary.

The WAN used to communicate with devices in the field were largely unchanged by the

development of LAN connectivity between local stations at the SCADA master. These

external communications networks were still limited to RTU protocols and were not available

for other types of network traffic. As was the case with the first generation of systems, the

second generation of SCADA systems was also limited to hardware, software, and peripheral

devices that were provided or at least selected by the vendor.

Page 41: PLC SCADA report Paras Singhal

41

Fig 5.3: Second Generation SCADA Architecture

5.4.3 Networked SCADA Systems:

The current generation of SCADA master station architecture is closely related to that of the

second generation, with the primary difference being that of open system architecture rather

than a vendor controlled, proprietary environment. There are still multiple networked

systems, sharing master station functions. There are still RTUs utilizing protocols that are

vendor-proprietary. The major improvement in the third generation is that of opening the

system architecture, utilizing open standards and protocols and making it possible to

distribute SCADA functionality across a WAN and not just a LAN. Open standards eliminate

a number of the limitations of previous generations of SCADA systems. The utilization of

off-the-shelf systems makes it easier for the user to connect third party peripheral devices

(such as monitors, printers, disk drives, tape drives, etc.) to the system and/or the network. As

they have moved to “open” or “off-the-shelf” systems, SCADA vendors have gradually

gotten out of the hardware development business. These vendors have looked to system

vendors such as Compaq, Hewlett-Packard, and Sun Microsystems for their expertise in

Page 42: PLC SCADA report Paras Singhal

42

developing the basic computer platforms and operating system software. This allows SCADA

vendors to concentrate their development in an area where they can add specific value to the

system–that of SCADA master station software.

The major improvement in third generation SCADA systems comes from the use

of WAN protocols such as the Internet Protocol (IP) for communication between the master

station and communications equipment. This allows the portion of the master station that is

responsible for communications with the field devices to be separated from the master station

“proper” across a WAN. Vendors are now producing RTUs that can communicate with the

master station using an Ethernet connection. Figure 5.4represents a networked SCADA

system. Another advantage brought about by the distribution of SCADA functionality over a

WAN is that of disaster survivability. The distribution of SCADA processing across a LAN

in second-generation systems improves reliability, but in the event of a total loss of the

facility housing the SCADA master, the entire system could be lost as well. By distributing

the processing across physically separate locations, it becomes possible to build a SCADA

system that can survive a total loss of any one location. For some organizations that see

SCADA as a super-critical function, this is a real benefit.

Fig 5.4: Third Generation SCADA Architecture

Page 43: PLC SCADA report Paras Singhal

43

5.5 ARCHITECTURE:

Generally SCADA system is a centralized system which monitors and controls entire area. It

is purely software package that is positioned on top of hardware. A supervisory system

gathers data on the process and sends the commands control to the process. For example, in

the thermal power plant the water flow can be set to specific value or it can be changed

according to the requirement. The SCADA system allows operators to change the set point

for the flow, and enable alarm conditions incase of loss of flow and high temperature and the

condition is displayed and recorded. The SCADA system monitors the overall performance

of the loop. The SCADA system is a centralized system to communicate with both wire and

wireless technology to Clint devices. The SCADA system controls can run completely all

kinds of industrial process.

EX: If too much pressure in building up in a gas pipe line the SCADA system can

automatically open a release valve.

5.5.1 Hardware Architecture:

The generally SCADA system can be classified into two parts:

Clint layer

Data server layer

The Clint layer which caters for the man machine interaction. The data server layer which

handles most of the process data activities. The SCADA station refers to the servers and it is

composed of a single PC. The data servers communicate with devices in the field through

process controllers like PLCs or RTUs. The PLCs are connected to the data servers either

directly or via networks or buses. The SCADA system utilizes a WAN and LAN networks,

the WAN and LAN consists of internet protocols used for communication between the master

station and devices. The physical equipments like sensors connected to the PLCs or RTUs.

The RTUs convert the sensor signals to digital data and sends digital data to master unit.

Page 44: PLC SCADA report Paras Singhal

44

Fig 5.5: Hardware Architecture

5.5.2 Software Architecture:

Most of the servers are used for multitasking and real time database. The servers are

responsible for data gathering and handling. The SCADA system consists of a software

program to provide trending, diagnostic data, and manage information such as scheduled

maintenance procedure, logistic information, detailed schematics for a particular sensor or

machine and expert system troubleshooting guides. This means the operator can sea a

schematic representation of the plant being controlled.

EX: alarm checking, calculations, logging and archiving; polling controllers on a set of

parameter, those are typically connected to the server.

5.6 WORKING PROCEDURE OF SCADA SYSTEM:

The SCADA system performs the following functions:

Data Acquisitions

Data Communication

Information/Data presentation

Monitoring/Control

These functions are performed by sensors, RTUs, controller, communication network. The

sensors are used to collect the important information and RTUs are used to send this

Page 45: PLC SCADA report Paras Singhal

45

information to controller and display the status of the system. According to the status of the

system, the user can give command to other system components. This operation is done by

the communication network.

5.6.1 Data Acquisitions:

Real time system consists of thousand of components and sensors. It is very important to

know the status of particular components and sensors. For example, some sensors measure

the water flow from the reservoir to water tank and some sensors measure the value pressure

as the water is release from the reservoir.

5.6.2 Data Communication:

The SCADA system uses wired network to communicate between user and devices. The real

time applications use lot of sensors and components which should be control remotely. The

SCADA system uses internet communications. All information is transmitted through

internet using specific protocols. Sensor and relays are not able to communicate with the

network protocols so RTUs used to communicate sensors and network interface.

5.6.3 Information/Data presentation:

The normal circuit networks have some indicators which can be visible to control but in the

real time SCADA system, there are thousand of sensors and alarm which are impossible to be

handled simultaneously. The SCADA system uses human machine interface (HMI) to

provide all of the information gathered from the various sensors.

5.6.3.1 Human machine interface:

The SCADA system uses human machine interface. The information is displayed and

monitored to be processed by the human. HMI provides the access of multiple control units

which can be PLCs and RTUs. The HMI provides the graphical presentation of the system.

For example, it provides the graphical picture of the pump connected to the tank. The user

can see the flow of the water and pressure of the water. The important part of the HMI is an

alarm system which is activated according to the predefined values.

Page 46: PLC SCADA report Paras Singhal

46

Fig 5.5: Human machine interface

For example: The tank water level alarm is set 60% and 70% values. If the water level

reaches above 60% the alarm gives normal warning and if the water level reach above 70%

the alarm gives critical warning.

5.6.4 Monitoring/Control:

The SCADA system uses different switches to operate each device and displays the status at

the control area. Any part of the process can be turned ON/OFF from the control station using

these switches. SCADA system is implemented to work automatically without human

intervention but at critical situations it is handled by man power.

5.7 SCADA FOR REMOTE INDUSTRIAL PLANT:

In large industrial establishments many process occur simultaneously and each needs to be

monitored, which is actually a complex task. The SCADA systems are used to monitor and

control the equipments in the industrial processes which include water distribution, oil

distribution and power distribution. The main aim of this project is to process the real time

data and control the large scale remote industrial environment. For an example the

temperature sensors are connected to the plc , which is connected to the PC at the front end

and software is loaded on the computer. The data is collected from the temperature sensors.

The temperature sensors continuously send the signal to the plc which accordingly displays

these values on its front panel. One can set the parameters like low limit and high limit on the

computer screen. When the temperature of a sensor goes above set point ,the plc send a

command to the corresponding relay. The heaters connected through relay contacts are turned

OFF and ON.

Page 47: PLC SCADA report Paras Singhal

47

Chapter- 6

DESIGN SCADA WITH INTOUCH WONDERWARE SOFTWARE AND

APPLICATION

SCADA is main interface between your control system and Operator. Maximum data and

features available on SCADA give you better control and clarity about the system. SCADA

needs to read data from various devices like:-

PLC/Controllers

RTU

Energy meters/Load managers/Data loggers

Field instruments like Flow meters and postioners

Each of above data communicates with SCADA on various protocols . SCADA reads or

writes the data in format of tags.

6.1 TAG:

Tag can be data representation of bit, byte, word or any array which is read from source

through communication protocol. Tag can be representation of digital or analog value

depending upon TAG configuration.

6.2 INTOUCH WONDERWARE SCADA SOFTWARE:

First we crate the animated object from “Wizard Selection” tool than specify tag name as

require. We can create almost any screen animation effect imaginable. We can make objects

change color, size, location, visibility, fill level, and so on.

Animation link selection dialog box are shown in fig (6.1)

Page 48: PLC SCADA report Paras Singhal

48

Fig 6.1: Animation Link Selection Dialog Box

6.2.1 TOUCH LINK

A. User Input touch links:

Discrete: Used to control the value of a discrete tagname.

Analog: Used to input the value of an analog (integer or real) tagname.

String: Used to create an object into which a string message may be input.

B. Sliders touch links:

Vertical& Horizontal:

we can move the slider position horizontally or vertically.

C. Touch Pushbutton links:

Discrete Value:

Used to make any object or symbol into a pushbutton that controls the state of a discrete

tagname. Pushbutton actions can be set, reset, toggle, momentary on (direct) and momentary

off (reverse) types.

Action:

Allows any object, symbol or button to have up to three different action scripts linked to it;

On Down, While Down and On Up.

Page 49: PLC SCADA report Paras Singhal

49

Show Window:

Used to make an object or symbol into a button that opens one or more windows when it is

clicked or touched.

Hide Window:

Used to make an object or symbol into a button that closes one or more windows when it is

clicked or touched.

Fig 6.2: push button dialog box

6.2.2 COLOR LINKS:

Discrete:

Used to control the fill, line and text colors attributes of an object or symbol that is linked to

the value of a discrete expression.

Analog:

The line, fill, and text color of an object or symbol can be linked to the value of an analog

tagname (integer or real) or an analog expression. Five value ranges are defined by specifying

four breakpoints. Five different colors can be selected which will be displayed as the value

range changes.

Discrete Alarm:

The text, line, and fill color of an object can all be linked to the alarm state of a tagname,

Alarm Group, or Group Variable. This color link allows a choice of two colors; one for the

normal state and one for the alarm state of the tagname. This link can be used for both analog

and discrete tagnames. If it is used with an analog tagname, it responds to any alarm

condition of the tagname

Analog Alarm:

Page 50: PLC SCADA report Paras Singhal

50

The text, line, and fill color of an object can all be linked to the alarm state of an analog

tagname, Alarm Group, or Group Variable. Allows a specific color to be set for the normal

state as well as a separate color for each alarm condition defined for the tagname.

Fig 6.3: Fill color dialog box

6.2.3 OBJECT SIZE LINKS:

We use Object Size links to vary the height and/or width of an object according to the value

of an analog (integer or real) tagname or analog expression. Size links provide the ability to

control the direction in which the object enlarges in height and/or width by setting the

"anchor" for the link. Both height and width links can be attached to the same object.

Fig 6.4: object height dialog box

6.2.4 PERCENT FILL LINKS:

We use Percent Fill Links to provide the ability to vary the fill level of a filled shape (or a

symbol containing filled shapes) according to the value of an analog tagname or an

expression that computes to an analog value. For example, this link may be used to show the

level of liquids in a vessel. An object or symbol may have a horizontal fill link, a vertical fill

link, or both.

Page 51: PLC SCADA report Paras Singhal

51

Fig 6.5: vertical fill dialog box

6.2.5 LOCATION LINKS:

We use Location Links to make an object automatically move horizontally, vertically, or in

both directions in response to changes in the value of an analog tagname or expression

Fig 6.6: horizontal location dialog box

6.2.6 MISCELLANEOUS LINKS:

There are four type of miscellaneous links.

Visibility:

Use to control the visibility of an object based on the value of a discrete tagname or

expression.

Blink:

Used to make an object blink based on the value of a discrete tagname or expression.

Orientation:

Used to make an object rotate based on the value of a tagname or expression.

Disable:

Used to disable the touch functionality of objects based on the value of a tagname or

expression.

Page 52: PLC SCADA report Paras Singhal

52

6.2.7 VALUE DISPLAY LINKS:

Value Display Links provide the ability to use a text object to display the value of a discrete,

analog, or string tagname. There are three types:

Discrete :

Uses the value of a discrete expression to display an On or Off user defined message in a text

object.

Analog:

Displays the value of an analog expression in a text object.

String:

Displays the value of a string expression in a text object.

6.3 APPLICATIONS OF SCADA:

SCADA systems can be relatively simple, such as one that monitors environmental

conditions of a small office building, or incredibly complex, such as a system that monitors

all the activity in a nuclear power plant or the activity of a municipal water system.

SCADA monitors and controls industrial, infrastructure, or facility-based processes, as

described below:

Industrial processes include those of manufacturing, production, power generation,

fabrication, and refining, and may run in continuous, batch, repetitive, or discrete modes.

Infrastructure processes may be public or private, and include water treatment and

distribution, wastewater collection and treatment, oil and gas pipelines, electrical power

transmission and distribution, wind farms, civil defense siren systems, and large

communication systems.

Facility processes occur both in public facilities and private ones, including buildings,

airports, ships, and space stations. They monitor and control HVAC, access, and energy

consumption.

Industries that are catered to are:

Automotive

Building Automation

Cement & Glass

Chemical

Page 53: PLC SCADA report Paras Singhal

53

Electronics

Food and Beverage

Machinery & Manufacturing

Aerospace & Defense

Metals & Mining

Oil & Gas

Pharmaceutical

Power, Utilities & Generation

Transportation

Water & Wastewater

6.4 ADVANTAGES:

The SCADA system provides onboard mechanical and graphical information

The SCADA system is easily expandable. We can add set of control units and sensors

according to the requirement.

The SCADA system ability to operate critical situations

Page 54: PLC SCADA report Paras Singhal

54

FUTURE SCOPE

The PLC offers a compromise between advance control techniques and present day

technology. It is extremely difficult to forecast the rate and form of progress of PLCs, but

there is strong evidence that development is both rapid and cumulative. Though a PLC is not

designed to replace a computer, it is useful and cost effective for medium sized control

systems. With the capability of functioning as local controllers in distributed control

systems, PLCs will retain their application in large process plants.

A further development of PLCs leads to the development of programmable function

controller (PFC) is compatible to PCs and directly controls the desired functions.

In India every process industry is replacing relay control systems by PLCs and will go for

PFCs in near future. In the near future every flats and offices may possess PFCs to control

room temperature, as elevator controller, maintain water tank levels, as small telephone

exchange etc.

Page 55: PLC SCADA report Paras Singhal

55

CONCLUSION

Thus it can be concluded using cost benefit analysis and some technical aspects being

included in the report that through total automation solution, synthetic chemical plant

following gain points can be achieved:

Enhanced control over plant operation

Better usage of utilities like boiler etc.

Higher productivity

Improved skill of workmen

Better monitoring leading to reduced maintenance

Greater safety of plant and personal

Page 56: PLC SCADA report Paras Singhal

56

REFERENCES

1. International Conference paper on “WHAT IS SCADA?”A. Daneels,W.Salter.

2. Rockwell automation software manual.

3. Inouch wonderware software manual.

4. Wikipedia “PLC and SCADA”.