March 2000 Process Industry Practices Civil CVC01017 Plant Site Data Sheet

Transcript of Plant Site Data Sheets (Goes With CVC01016) CVC01017_EEDS

Page 1: Plant Site Data Sheets (Goes With CVC01016) CVC01017_EEDS

March 2000

Process Industry PracticesCivil

CVC01017Plant Site Data Sheet

Page 2: Plant Site Data Sheets (Goes With CVC01016) CVC01017_EEDS

PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES

In an effort to minimize the cost of process industry facilities, this Practice has been prepared from the technical requirements in the existing standards of major industrial users, contractors, or standards organizations. By harmonizing these technical requirements into a single set of Practices, administrative, application, and engineering costs to both the purchaser and the manufacturer should be reduced. While this Practice is expected to incorporate the majority of requirements of most users, individual applications may involve requirements that will be appended to and take precedence over this Practice. Determinations concerning fitness for purpose and particular matters or application of the Practice to particular project or engineering situations should not be made solely on information contained in these materials. The use of trade names from time to time should not be viewed as an expression of preference but rather recognized as normal usage in the trade. Other brands having the same specifications are equally correct and may be substituted for those named. All Practices or guidelines are intended to be consistent with applicable laws and regulations including OSHA requirements. To the extent these Practices or guidelines should conflict with OSHA or other applicable laws or regulations, such laws or regulations must be followed. Consult an appropriate professional before applying or acting on any material contained in or suggested by the Practice.

© Process Industry Practices (PIP), Construction Industry Institute, The University of Texas at Austin, 3208 Red River Street, Suite 300, Austin, Texas 78705. PIP member companies and subscribers may copy this Practice for their internal use.

Not printed with State funds

Page 3: Plant Site Data Sheets (Goes With CVC01016) CVC01017_EEDS

Plant Site Data Sheet(Refer to PIP CVC01016)

CVC01017

Page 1 of 4

March 2000

Owner’s Name:

     

Plant Site Name and Location (City, State, Country):               

Units: U.S. Customary SI (This will apply to all units throughout this document.)Building Code

Design at this plant site shall be in accordance with the following building code(s):

(check) Year of Locally Adopted Edition

National Building Code (BOCA)      

Standard Building Code (SBC)      

Uniform Building Code (UBC)      

NFPA 101, Life Safety Code (LSC)      

Other            

None

Owner’s Liaison with Building AuthorityName:       Phone:      

Local Building Authority, Building Official Name, Address, and Phone:     

     

     

     

State or Other Fire Authority, Name, Address, and Phone:     

     

     

     

NPDES (Storm Water Pollution Prevention Plan) Governing Authority, Name, Address, and Phone:     

     

     

     

Permit required for greater than       acres (hectares) disturbed

Erosion control plan required (even without permit) Yes No

Page 4: Plant Site Data Sheets (Goes With CVC01016) CVC01017_EEDS

Plant Site Data Sheet(Refer to PIP CVC01016)

CVC01017

Page 2 of 4

March 2000

Topographical and Survey Data

North American Datum: NAD 27 or NAD 83

Plant datum elevation:       ft (m) =       ft (m) above mean sea level (MSL)

Angular relation between true north and plant descriptive north:       deg.

Plant coordinate 0,0 =       (latitude),       (longitude) based on

the       coordinate system

Wind Direction

Prevailing wind direction N NE E SE S SW W NW

Percent annually in each direction    %    %    %    %    %    %    %    %

in terms of true north or plant north

Temperature

Highest max. temperature:       °F (°C) Lowest min. temperature:       °F (°C)

HVAC design dry bulb: Summer:       °F (°C) Winter:       °F (°C)

HVAC design wet bulb: Summer:       °F (°C)

Relative humidity: Summer: % Winter:       %

Source: ASHRAE Owner Other      

RainfallDesign rainfall intensity:       inch/hr (mm/hr), based on a       min. rainfall

duration period associated with the       - year storm

Design accumulated 24-hour rainfall:       inch (mm), based on the       - year storm

Rainfall intensity for evaluation of potential flooding:       in/hr (mm/hr), based on

a       min. rainfall duration associated with the       - year storm

Peak rainy season for this plant site is from       to      

Floods

100-year flood elevation:       ft (m) above Plant datum or MSL

Max. probable flood elev.:       ft (m) above Plant datum or MSL

Railroads

Railroad design at this site shall be in accordance with the following railroad code:

(check)

American Railway Engineers Association (AREA)

Other      

Local operating railroad:      

Railcar clearances: Vertical       ft (m) Horizontal

      ft (m)

Minimum weight and type rail:      

Page 5: Plant Site Data Sheets (Goes With CVC01016) CVC01017_EEDS

Plant Site Data Sheet(Refer to PIP CVC01016)

CVC01017

Page 3 of 4

March 2000

Plant Roads and Streets

Road and street design at this site shall be in accordance with the following code:

American Association of State Highway and Transportation Officials (AASHTO)

State D.O.T. specification      

Other      

Crane loading:      

Primary roads – main traffic routes, tanker and semi-trailer truck traffic occurs

Road width       ft (m)

Shoulder width

      ft (m)

Horizontal clearance       ft (m) from centerline, edge of road

Vertical clearance       ft (m)

Roadway surface material      

Secondary roads – regular operational & maintenance traffic, not subject to high traffic

Road width       ft (m)

Shoulder width

      ft (m)

Horizontal clearance       ft (m) from centerline, edge of road

Vertical clearance       ft (m)

Roadway surface material      

Accessways - travel ways that provide access to equipment or congested areas

Min. single lane width       ft (m)

Shoulder width

      ft (m)

Horizontal clearance       ft (m) from centerline, edge of road

Vertical clearance       ft (m)

Roadway surface material      

Wetlands

Location / limits      

     

     

Water Distribution

Cooling water       psi (kPa) Fire water       psi (kPa)

Potable water       psi (kPa) Fire water       psi (kPa)

Wind Loads

All wind loads at this site shall be computed in accordance with the following code,using the site specific parameters indicated below:

ASCE 7-       “Minimum Design Loads for Buildings and Other Structures”

Building code indicated above

Other      

Basic wind speed:       mph (km/hr) 3-second gust or fastest mile

Recurrence interval: 50 year 100 year Other:       year

Exposure category: A B C D

Topographic factor: Kzt       See Project Data Sheet N/A

Page 6: Plant Site Data Sheets (Goes With CVC01016) CVC01017_EEDS

Plant Site Data Sheet(Refer to PIP CVC01016)

CVC01017

Page 4 of 4

March 2000

Earthquake Loads

All seismic loads at this site shall be computed in accordance with the following code,using the site specific parameters indicated below:

ASCE 7-       “Minimum Design Loads for Buildings and Other Structures”

Uniform Building Code (UBC, year       )

Building code indicated above

Other      

For ASCE 7 and other codes based on NEHRP provisions:

Effective peak acceleration, Aa =      

Effective peak velocity – related acceleration, Av =      

Soil profile type: A B C D E F or S =

     

Ca =       Cv =      

For UBC:

Earthquake zone, Z =      

Soil profile type and site coefficient, S =      

Snow Loads

All snow loads at this site shall be computed in accordance with the following:

ASCE 7-       “Minimum Design Loads for Buildings and Other Structures”

Building code indicated above

Other      

Ground snow load:       psf (kPa), 50-year recurrence interval

Frost Depth

Site frost depth:       ft (m) below grade