Plant Optimizing Present

36
Content : • Plant Operating Overview 1. Chlorination Plant 2. Desalination Plant a. Clarification b. Filtration c. RO Desalination 3. Demineralization Plant 4. Waste Water Treatment Plant Plant Optimizing Tanjung Jati B Unit 1&2

Transcript of Plant Optimizing Present

Page 1: Plant Optimizing Present

Content :• Plant Operating Overview

1. Chlorination Plant2. Desalination Plant

a. Clarificationb. Filtrationc. RO Desalination

3. Demineralization Plant4. Waste Water Treatment Plant

• Plant OptimizingTanjung Jati B Unit 1&2

Page 2: Plant Optimizing Present

1. Chlorination Schematic Flow Diagram

SEAWATER INLET

PUMP

PUMP

SELF CLEANING STRAINER

MANUAL STRAINER

GENERATORTRAIN A

TR/RE

+ -

GENERATORTRAIN B

TR/REGAS RELEASE CYLINDER

+ -

GAS RELEASE CYLINDER

Page 3: Plant Optimizing Present

Desalination Plant Overview

Page 4: Plant Optimizing Present

a. Clarification

Page 5: Plant Optimizing Present

b. Filtration Section

Page 6: Plant Optimizing Present

c. Reverse Osmosis

Page 7: Plant Optimizing Present

RO Desalination Product as Feed Demineralization Plant

Page 8: Plant Optimizing Present

Cation Exchanger Anion Exchanger Mixed Bed

3. Demineralization Overview

Page 9: Plant Optimizing Present
Page 10: Plant Optimizing Present

4. Waste Water Treatment Overview

Page 11: Plant Optimizing Present

Waste Water Treatment

Page 12: Plant Optimizing Present

Chlorination Plant

Desalination Plant

Demineralization Plant

Waste Water Plant

Page 13: Plant Optimizing Present

PLANT OPTIMIZING1. Piping Connection From

Demineralization Plant To Waste Water Treatment (Implemented)

2. Sediment Pond For FGD Blow Down (Planned)

3. RO Membrane Replacement Plan (Planned)

Page 14: Plant Optimizing Present

PIPING CONNECTION FROM DEMINERALIZATION PLANT TO WASTE WATER TREATMENT

Regeneration Waste in Neutralizing Tank (DM Area)

- High pH ( 11-12 )- Direct Neutralizing by HCl until

pH 6-9- Discharge to The Sea Directly- Neutralize By Decrease pH- Environment Concern Only pH,

Because Chemical Used Only NaOH and HCl

Retention Basin Water (WWTP Area)

- Relatively Low pH at WWTP (pH 5-7)

- There is pH Neutralizing Equipment

- Accepted pH Range before discharging to The Sea 6-9

- Neutralize By Increase pH

Page 15: Plant Optimizing Present

SEA

Original Design Installing Pipeline Connection to WWTP Retention Basin

Page 16: Plant Optimizing Present

Action :

- About 1000 m Piping Connection was Implemented From Neutralizing Tank (DM Plant Area) to Retention Basin (WWTP Area)

- Pumps and Control Instrument are used existing at DM Plant

Page 17: Plant Optimizing Present

Pipeline Connection to WWTP Retention Basin Overview

Page 18: Plant Optimizing Present

Additional PipelineStarting Point

End PointPipeline Overview

BOLER TURBINE AREA

Page 19: Plant Optimizing Present

Progress

• IMPLEMENTED Agustus 2008

• Done Well !!!!

Page 20: Plant Optimizing Present

After Connection

Neutralizing Tank

(DM area)

HCl

The Sea

RETENTION BASIN (WWTP AREA)

NaOH

Page 21: Plant Optimizing Present

Current Condition

Regeneration Waste in Neutralizing Tank (DM Area)

- No pH Neutralizing Required Before discharging to WWTP

- Neutralized by Retention Basin Water

Waste Wa ter Treatment Plant Condition Retention Basin (WWTP Area)

- pH Increasing Assisted by New Waste Supply from DM Plant

- There is pH Neutralizing Equipment, but Decreasing of Operating Time

Page 22: Plant Optimizing Present

2. Sediment Pond for FGD Blow downat WWTP Area

Background• High TSS ( +10 % solid) Flue Gas Desulphurization

Blowdown to Retention Basin• Performance of WWTP is not for High Solid

Treatment• No Dredging Access for Retention Basin so, Heavy

Equipment Needed for Retention Basin Dredging Activity

• Operational of WWTP Cannot be Stopped for Long Time

Page 23: Plant Optimizing Present

DM Plant

Boiler Blow down

FGD Blow down

WWTP SYSTEM

RETENTION BASIN

Sludge FGD FGD SLUDGE

Current Condition

Page 24: Plant Optimizing Present

Planned Action

FGD Sediment Pond Required> Required Condition

– Sediment Pond consist of two Side ( A and B ) to Accommodate continuity of FGD Blowdown

– Must Be Easy Accessed By Wheel Loader, Wheel Loader In charged By Material Handling Operation

– Completed by Control System and Integrated with WWTP Operating Panel, and Operational In charged by WWTP Operator

– Will Reduce Issue for Environment, Because FGD Blow down Sludge is not Part Of Hazardous Waste

Page 25: Plant Optimizing Present

RETENTION BASIN WWTP SYSTEM

DM Plant

Boiler Blow down

FGD SEDIMENT POND

FGD Blow downPlanned Illustration

Page 26: Plant Optimizing Present

FGD Sediment Pond Technical Overview

Page 27: Plant Optimizing Present

PROGRESS

Will be Implemented ASAP!!!!

Page 28: Plant Optimizing Present

3. RO Membrane Replacement Plan

HISTORY• The existing RO Membrane is TOYOBO Product with series HB10255SI• Current condition has been in operation in average of more than 2 years without

Spare membrane replacement. (for RO B is almost 3 years / tactical time)• Manual book by Toyobo, it is advisable to replace 10-15% per year• Current RO membrane conditions, it is found defective product in the form of an

imperfect molding off "cap“ RO membrane cover.• The trend of increasing product conductivity, current average conditions is

above 300 us / cm. Estimated normal membrane operation life time that still "cover" reasonable make-Up Plant Feed is less than one year (estimation) if no RO membrane replacement.

Page 29: Plant Optimizing Present

Background of the RO membrane replacement

• Special order for existing RO Membrane [to have more competitive price]

• The warranty existing product is not valid

Page 30: Plant Optimizing Present

Technical ReviewComparison between Spiral Wound and Hollow Fiber

Spiral Wound Hollow Fiber

Page 31: Plant Optimizing Present

Technical Review

Page 32: Plant Optimizing Present

Some Problem Found : Demineralization Plant units 1 and feeds to make up: “conductivity <300us/cm” (TDS + 205 ppm)”

• RO Product as Feed Of Demineralization Plant Requirements

Page 33: Plant Optimizing Present

ITEM

TOYOBO TORAY METITO

Replacement of existing elements New trains New trains

PROCESS DESCRIPTION One Stage with Hollow FibreOne Stage with Spiral Wound

Two Stages with Spiral Wound

(existing membrane type) type type

Product Quality (Condutivity)

inlet 51 500 … 54600 uS/cm 51 500 … 54600 uS/cm 51 500 … 54600 uS/cm

outlet 1st stage < 250 uS/cm 350 max value at one stage 1st stage <750 uS/cm

outlet 2nd stage second Stage <30 uS/cm

Membrane manufacturer Toyobo Toray several manufacturers

AVAILABLE OPTION

Page 34: Plant Optimizing Present

Spiral Wound

Turbidity, NTU < 1.0 < 1.0

Silt Density Index, SDI < 3.0 < 3.0

Iron, Fe+3, ppm < 0.3 < 0.05

Strontium, ppm NS < 0.1

Barium, ppm NS < 0.1

Silica, reject, ppm 50-160 50-160

Organics, ppm NS NS

Chlorine, residual, ppm 0.1-0.5 max 0

pH Range 4-6 4-11

Feed Temperature Max, o C 35 ° 45°

Parameter Control - manufactureHollow Fibre

Page 35: Plant Optimizing Present

Base on Parameter Control

• Spiral Wound Type of Membrane can be applied by existing Condition pre-treatment before entering Membrane

• More concern only about chlorine residual because currently Residual Chlorine still 0.2 ppm feed the Membrane

• Can be solve by Anti-Chlorine Chemical Injection

Page 36: Plant Optimizing Present

PROGRESS

Will be Implemented ASAP Paper Work is Done