Plant Layout

download Plant Layout

of 53

description

General plant layout design

Transcript of Plant Layout

  • 2015 Herv Baron

    HERVE BARON

    Engineering Training

    Welcome to this presentation.

    It is part of a suite of Engineering training modules.

    It shows the activities and deliverables of the Plant Layout discipline.

    Comments are most welcome ([email protected]), which I will incorporate for the benefit of all.

    Please download this file so that you can see my trainers notes in the top left corner latest Acrobat Pro feature.

    Herv

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    PROCESS

    PLANT LAYOUT

    EQUIPMENT

    SAFETY & ENVIRONMENT

    CIVIL

    PIPING

    PIPELINE

    INSTRUMENTATION

    ELECTRICAL

  • 2015 Herv Baron

    HERVE BARON

    Piping discipline

    Plant Layout & Piping discipline

    Plant Layout Piping installation Piping

    materials Piping stress

    analysis

  • 2015 Herv Baron

    HERVE BARON

    Plant layout

    What has to be considered in the layout of a plant?

    PresenterPresentation NotesExternal interfaces: pipelines, utilitiesTraffic of plant personnel: parking etc.Prevailing windAccess / Exit

  • 2015 Herv Baron

    HERVE BARON

    Layout/principles

    From which direction comes the prevailing wind?

    PresenterPresentation NotesFrom North West

  • 2015 Herv Baron

    HERVE BARON

    Layout/principles

    The wind rose shows the frequency of winds blowing from particular directions. The length of each "spoke" around the circle is related to the frequency that the wind blows from a particular direction per unit time, emanating from zero at the center to increasing frequencies at the outer circles.

  • 2015 Herv Baron

    HERVE BARON

    Plant layout

    The first step of Plant layout is to divide the Plant area into separate blocks and units. Why is this done? How?

    PresenterPresentation Notesto reduce escalation of fire and explosion hazardsit is done by respecting minimum space between units

  • 2015 Herv Baron

    HERVE BARON

    The Block Flow Diagram (BFD)

  • 2015 Herv Baron

    HERVE BARON

    Plant layout

    Minimum distances between Process Units are determined according to GE GAP 2.5.2/2A Classify Units in terms of Fire and

    Explosion Hazard into 3 categories:

    Moderate Hazard (MH) Intermediate Hazard (IH) High Hazard (HH)

    Apply the following minimum distances

    between units of various hazard category:

  • 2015 Herv Baron

    HERVE BARON

    Plant layout

    The first step of Plant layout is to divide the Plant area into separate blocks and units. The second step of Plant layout is to locate Equipment within each unit. Which document are used as starting points by Plant Layout?

    PresenterPresentation NotesThe PFD and the Equipment list

  • 2015 Herv Baron

    HERVE BARON

    Plot Plan

    PresenterPresentation NotesFunctional sub-systems are identified on the PFD

  • 2015 Herv Baron

    HERVE BARON

    Plant layout

    What else shall be taken into account to locate equipment?

    PresenterPresentation NotesAlloy and heavy wall piping whose runs length shall be minimized and minimum safety distances between equipment

  • 2015 Herv Baron

    HERVE BARON

    Layout Requirements from Process

    REFLUX CONDENSER

    REFLUX ACCUMULATOR

    REFLUX PUMP

    COLUMN

    What shall be the respective elevation of these equipment?

    PresenterPresentation NotesReflux condenser above reflux accumulator above reflux pump. No other constraint (except no pocket in overhead line).

  • 2015 Herv Baron

    HERVE BARON

    Layout Requirements from Process

    REFLUX CONDENSER

    REFLUX ACCUMULATOR

    REFLUX PUMP

    COLUMN

    What shall be the respective elevation of these equipment?

    PresenterPresentation NotesReflux condenser above reflux accumulator above reflux pump. No other constraint (except no pocket in overhead line).

  • 2015 Herv Baron

    HERVE BARON

    On-shore plant: Equipment spacing recommendations as per GE GAP Guidelines .2.5.2

    Clear horizontal distance, in meters, between adjacent edges of equipment

    PresenterPresentation NotesGE GAP: GE Asset Protection GuidelinesTable does not apply to equipment in similar service, e.g. pump and spare./ means provide spacing based on access for operation and maintenance

  • 2015 Herv Baron

    HERVE BARON

    Layout Requirements from Process

    What shall be the respective elevation of the column and reboiler?

    REBOILER

    COLUMN

    PresenterPresentation NotesIt depends on process requirements: refer to PDS

  • 2015 Herv Baron

    HERVE BARON

    Layout Requirements from Process

    REBOILER

    COLUMN

    PresenterPresentation NotesIt depends on process requirements: refer to PDS

  • 2015 Herv Baron

    HERVE BARON

    Layout/principles Accesses

  • 2015 Herv Baron

    HERVE BARON

    Layout principles: provision for piping flexibility

  • 2015 Herv Baron

    HERVE BARON

    Layout principles: typical Unit Layout

    PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.This grade-mounted horizontal equipment arrangement is suitable when there enough real estate for the Plant. The advantage is ease of access for operation and maintenance as well as safety. The disadvantage is high real estate use and long runs of pipes, cables etc.

  • 2015 Herv Baron

    HERVE BARON

    Structured-mounted vertical vs grade-mounted horizontal Equipment arrangement

    PresenterPresentation NotesAn alternative if the structured-mounted vertical equipment arrangement where equipment are stacked on each other, on a multilevel steel or concrete structure. The advantage is less use of plant area, suitable for housing as required by environmental or process conditions. The disadvantage is less convenient access/egress for operating personnel as well as for maintenance (monorails, drop zones to grade lay down area have to be provided) and less easy, i.e., longer construction.

  • 2015 Herv Baron

    HERVE BARON

    Layout principles: typical Unit Layout

    PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.

  • 2015 Herv Baron

    HERVE BARON

    Unit Layout

    What type of equipment has a large impact on the layout?

    PresenterPresentation NotesAir coolers their size must be estimated with the greatest possible accuracy

  • 2015 Herv Baron

    HERVE BARON

    Layout / Equipment size by vendors

    14 meters

    8 meters

    Duty spec

    Waste Heat

    Boiler

    PresenterPresentation Notesfor the same duty one vendor comes up with a 8 meter long equipment, another with a 14 meters long!

  • 2015 Herv Baron

    HERVE BARON

    Layout / package arrangement

    PresenterPresentation NotesDimensions from Vendors are specially important for packages, that involve auxiliaries etc.

  • 2015 Herv Baron

    HERVE BARON

    Layout principles: pipe routing

    There are 2 ways to run pipes. Name them.

  • 2015 Herv Baron

    HERVE BARON

    Layout principles: typical Unit Layout

    B/L(Battery limit)

    C/L of Road

    R

    Min. 7.5 m

    PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.

  • 2015 Herv Baron

    HERVE BARON

    Layout principles: typical Unit Layout

    What is the purpose of leaving 3 meters distance between the 2 vessels??

    PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.

  • 2015 Herv Baron

    HERVE BARON

    Layout principles: typical Unit Layout

    PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.

  • 2015 Herv Baron

    HERVE BARON

    Layout principles: typical Arrangement of Air-coolers

    PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.Access are provided to:motor, fan and bearing for maintenance: motors are dismantled and dropped on a four-wheel trolley at service platform level then brought up to a dvait from service platform to grade.Both headers for cleaning and instrument access

  • 2015 Herv Baron

    HERVE BARON

    Plant Layout Job specification for design / Plant layout guidelines

    Site elevation (s)

    Minimum distances between units, equipment, buildings: applicable code + supplementary information

    Clearance around equipment

    Road width, clearance

    Headroom clearance

    B/L(Battery limit)

    C/L of Road

    R

    Min. 7.5 m

    A

    Line Up C/L of Equipment

    Pipe Rack of Structure

    Min. 3 m

  • 2015 Herv Baron

    HERVE BARON

    Interfaces between Engineering disciplines Plot Plan

    Plot Plan

    Process design & simulations

    Process eqt specs

    Process Flow diagrams

    Process eqt sizing

    Eqt sizing by vendors

    Equipment dimensions

    Piping routing

    Fire water network routing

    Electrical distribution & cable routing

    Instrument JB & cable routing

    Sewage sizing & layout

  • 2015 Herv Baron

    HERVE BARON

    Overall Site plan

    PresenterPresentation NotesDefines the location of a complex and of its environment 1:5000 scale

  • 2015 Herv Baron

    HERVE BARON

    General plot plan

    PresenterPresentation NotesShows the entire Plant and the arrangement of the various units (process, utility), storage facilities, buildings and other facilities 1:1000 scale

  • 2015 Herv Baron

    HERVE BARON

    Unit plot plan

    PresenterPresentation NotesShows location of equipment, pipe-racks, structures, with co-ordinates and elevation 1:200 scale

  • 2015 Herv Baron

    HERVE BARON

    Unit plot plan Elevation view

  • 2015 Herv Baron

    HERVE BARON

    Unit plot plan Plan view

    PresenterPresentation NotesShows location of equipment, pipe-racks, structures, with co-ordinates and elevation

  • 2015 Herv Baron

    HERVE BARON

    3D modelling

  • 2015 Herv Baron

    HERVE BARON

    3D model clash check

  • 2015 Herv Baron

    HERVE BARON

    3D model review

    3 model reviews are usually done

  • 2015 Herv Baron

    HERVE BARON

    3D model review

    3 model reviews are usually done:

    What is the scope of the first model review?

  • 2015 Herv Baron

    HERVE BARON

    First model review: Scope: finalize the Plot Plan Content: Equipment + 30% of piping is modelled, i.e. all ines on PFDs Outcome: after incorporation of COMPANYs comments, the Plot plan is released as the base for the design (IFD). Aspects reviewed: Unit location, equipment location, main access and escape routes to facilities, major piping routes indicated on PFDs, arrangement around LLI, location of main manifolds, space around equipment for maintenance, platforms for main operation access

    3D model review

  • 2015 Herv Baron

    HERVE BARON

    30% model review

  • 2015 Herv Baron

    HERVE BARON

    Air-Cooled Heat Exchangers In which case would you install the ACHE at grade vs on pipe-rack?

    PresenterPresentation NotesInstall on pipe-rack when you lack real estate

  • 2015 Herv Baron

    HERVE BARON

    Air-Cooled Heat Exchangers In the case of installation on top of pipe-rack, what extra access shall be provided?

    PresenterPresentation NotesService platform for maintenance of motor, fan and bearing motors are dismantled and dropped on a four-wheel trolley at service platform level then brought up to a dvait from service platform to grade.

  • 2015 Herv Baron

    HERVE BARON

    Plot Plan review Hands-on exercise

    Please review and comment the Plot Plan

    PresenterPresentation NotesComment: off-spec tanks located upwind of furnaces: to be relocated

  • 2015 Herv Baron

    HERVE BARON

    Piping Layout Modular plants

    In which cases is a modular plant preferable vs a stick built?

    PresenterPresentation NotesConstruction not easy of costly (extreme wetaher: Siberia, Canada, remote area, high labour cost)Revamping: to minimize SIMPOS

  • 2015 Herv Baron

    HERVE BARON

    Design development

    This is the Plot at FEED stage. Which parts of it do you expect will change at EPC stage?

  • 2015 Herv Baron

    HERVE BARON

    Incinerator Package

    Design development

    FEED stage EPC Stage

  • 2015 Herv Baron

    HERVE BARON

    Combustion Air blowers + heater

    Plant layout evolution

    FEED EPC - IFD EPC - IFC

  • 2015 Herv Baron

    HERVE BARON

    The Oil & Gas Engineering Guide 2nd edition

    Do you want to know more... Much more?

  • 2015 Herv Baron

    HERVE BARON

    The Oil & Gas Engineering Guide - 2nd edition

    Table of Contents

  • 2015 Herv Baron

    HERVE BARON

    The Oil & Gas Engineering Guide 2nd edition

    Order direct from the publisher:

    http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html

    Engineering TrainingEngineering disciplines: activities and deliverables Piping disciplineSlide Number 4Layout/principlesLayout/principlesSlide Number 7The Block Flow Diagram (BFD)Slide Number 9Slide Number 10Plot PlanPlant layoutLayoutRequirements from ProcessLayoutRequirements from ProcessOn-shore plant: Equipment spacing recommendations as per GE GAP Guidelines .2.5.2LayoutRequirements from ProcessLayoutRequirements from ProcessLayout/principlesAccessesLayout principles: provision for piping flexibilityLayout principles: typical Unit LayoutStructured-mounted vertical vs grade-mounted horizontalEquipment arrangementLayout principles: typical Unit LayoutUnit LayoutLayout / Equipment size by vendorsLayout / package arrangementLayout principles: pipe routingLayout principles: typical Unit LayoutLayout principles: typical Unit LayoutLayout principles: typical Unit LayoutLayout principles: typical Arrangement of Air-coolersPlant LayoutJob specification for design / Plant layout guidelinesInterfaces between Engineering disciplinesPlot PlanOverall Site planGeneral plot planUnit plot planUnit plot planElevation viewUnit plot planPlan viewSlide Number 383D model clash check3D model review3D model review3D model review30% model reviewAir-Cooled Heat ExchangersAir-Cooled Heat ExchangersPlot Plan reviewHands-on exercisePiping LayoutModular plantsDesign developmentDesign developmentPlant layout evolutionThe Oil & Gas Engineering Guide2nd editionThe Oil & Gas Engineering Guide - 2nd editionThe Oil & Gas Engineering Guide2nd edition