Plant Layout
-
Upload
ssureshkar7699 -
Category
Documents
-
view
39 -
download
0
description
Transcript of Plant Layout
-
2015 Herv Baron
HERVE BARON
Engineering Training
Welcome to this presentation.
It is part of a suite of Engineering training modules.
It shows the activities and deliverables of the Plant Layout discipline.
Comments are most welcome ([email protected]), which I will incorporate for the benefit of all.
Please download this file so that you can see my trainers notes in the top left corner latest Acrobat Pro feature.
Herv
-
2015 Herv Baron
HERVE BARON
Engineering disciplines: activities and deliverables
PROCESS
PLANT LAYOUT
EQUIPMENT
SAFETY & ENVIRONMENT
CIVIL
PIPING
PIPELINE
INSTRUMENTATION
ELECTRICAL
-
2015 Herv Baron
HERVE BARON
Piping discipline
Plant Layout & Piping discipline
Plant Layout Piping installation Piping
materials Piping stress
analysis
-
2015 Herv Baron
HERVE BARON
Plant layout
What has to be considered in the layout of a plant?
PresenterPresentation NotesExternal interfaces: pipelines, utilitiesTraffic of plant personnel: parking etc.Prevailing windAccess / Exit
-
2015 Herv Baron
HERVE BARON
Layout/principles
From which direction comes the prevailing wind?
PresenterPresentation NotesFrom North West
-
2015 Herv Baron
HERVE BARON
Layout/principles
The wind rose shows the frequency of winds blowing from particular directions. The length of each "spoke" around the circle is related to the frequency that the wind blows from a particular direction per unit time, emanating from zero at the center to increasing frequencies at the outer circles.
-
2015 Herv Baron
HERVE BARON
Plant layout
The first step of Plant layout is to divide the Plant area into separate blocks and units. Why is this done? How?
PresenterPresentation Notesto reduce escalation of fire and explosion hazardsit is done by respecting minimum space between units
-
2015 Herv Baron
HERVE BARON
The Block Flow Diagram (BFD)
-
2015 Herv Baron
HERVE BARON
Plant layout
Minimum distances between Process Units are determined according to GE GAP 2.5.2/2A Classify Units in terms of Fire and
Explosion Hazard into 3 categories:
Moderate Hazard (MH) Intermediate Hazard (IH) High Hazard (HH)
Apply the following minimum distances
between units of various hazard category:
-
2015 Herv Baron
HERVE BARON
Plant layout
The first step of Plant layout is to divide the Plant area into separate blocks and units. The second step of Plant layout is to locate Equipment within each unit. Which document are used as starting points by Plant Layout?
PresenterPresentation NotesThe PFD and the Equipment list
-
2015 Herv Baron
HERVE BARON
Plot Plan
PresenterPresentation NotesFunctional sub-systems are identified on the PFD
-
2015 Herv Baron
HERVE BARON
Plant layout
What else shall be taken into account to locate equipment?
PresenterPresentation NotesAlloy and heavy wall piping whose runs length shall be minimized and minimum safety distances between equipment
-
2015 Herv Baron
HERVE BARON
Layout Requirements from Process
REFLUX CONDENSER
REFLUX ACCUMULATOR
REFLUX PUMP
COLUMN
What shall be the respective elevation of these equipment?
PresenterPresentation NotesReflux condenser above reflux accumulator above reflux pump. No other constraint (except no pocket in overhead line).
-
2015 Herv Baron
HERVE BARON
Layout Requirements from Process
REFLUX CONDENSER
REFLUX ACCUMULATOR
REFLUX PUMP
COLUMN
What shall be the respective elevation of these equipment?
PresenterPresentation NotesReflux condenser above reflux accumulator above reflux pump. No other constraint (except no pocket in overhead line).
-
2015 Herv Baron
HERVE BARON
On-shore plant: Equipment spacing recommendations as per GE GAP Guidelines .2.5.2
Clear horizontal distance, in meters, between adjacent edges of equipment
PresenterPresentation NotesGE GAP: GE Asset Protection GuidelinesTable does not apply to equipment in similar service, e.g. pump and spare./ means provide spacing based on access for operation and maintenance
-
2015 Herv Baron
HERVE BARON
Layout Requirements from Process
What shall be the respective elevation of the column and reboiler?
REBOILER
COLUMN
PresenterPresentation NotesIt depends on process requirements: refer to PDS
-
2015 Herv Baron
HERVE BARON
Layout Requirements from Process
REBOILER
COLUMN
PresenterPresentation NotesIt depends on process requirements: refer to PDS
-
2015 Herv Baron
HERVE BARON
Layout/principles Accesses
-
2015 Herv Baron
HERVE BARON
Layout principles: provision for piping flexibility
-
2015 Herv Baron
HERVE BARON
Layout principles: typical Unit Layout
PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.This grade-mounted horizontal equipment arrangement is suitable when there enough real estate for the Plant. The advantage is ease of access for operation and maintenance as well as safety. The disadvantage is high real estate use and long runs of pipes, cables etc.
-
2015 Herv Baron
HERVE BARON
Structured-mounted vertical vs grade-mounted horizontal Equipment arrangement
PresenterPresentation NotesAn alternative if the structured-mounted vertical equipment arrangement where equipment are stacked on each other, on a multilevel steel or concrete structure. The advantage is less use of plant area, suitable for housing as required by environmental or process conditions. The disadvantage is less convenient access/egress for operating personnel as well as for maintenance (monorails, drop zones to grade lay down area have to be provided) and less easy, i.e., longer construction.
-
2015 Herv Baron
HERVE BARON
Layout principles: typical Unit Layout
PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.
-
2015 Herv Baron
HERVE BARON
Unit Layout
What type of equipment has a large impact on the layout?
PresenterPresentation NotesAir coolers their size must be estimated with the greatest possible accuracy
-
2015 Herv Baron
HERVE BARON
Layout / Equipment size by vendors
14 meters
8 meters
Duty spec
Waste Heat
Boiler
PresenterPresentation Notesfor the same duty one vendor comes up with a 8 meter long equipment, another with a 14 meters long!
-
2015 Herv Baron
HERVE BARON
Layout / package arrangement
PresenterPresentation NotesDimensions from Vendors are specially important for packages, that involve auxiliaries etc.
-
2015 Herv Baron
HERVE BARON
Layout principles: pipe routing
There are 2 ways to run pipes. Name them.
-
2015 Herv Baron
HERVE BARON
Layout principles: typical Unit Layout
B/L(Battery limit)
C/L of Road
R
Min. 7.5 m
PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.
-
2015 Herv Baron
HERVE BARON
Layout principles: typical Unit Layout
What is the purpose of leaving 3 meters distance between the 2 vessels??
PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.
-
2015 Herv Baron
HERVE BARON
Layout principles: typical Unit Layout
PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.
-
2015 Herv Baron
HERVE BARON
Layout principles: typical Arrangement of Air-coolers
PresenterPresentation NotesThe Equipment are arranged along a backbone = piperack. Connecting pipes run on the pipe-rack.Access are provided to:motor, fan and bearing for maintenance: motors are dismantled and dropped on a four-wheel trolley at service platform level then brought up to a dvait from service platform to grade.Both headers for cleaning and instrument access
-
2015 Herv Baron
HERVE BARON
Plant Layout Job specification for design / Plant layout guidelines
Site elevation (s)
Minimum distances between units, equipment, buildings: applicable code + supplementary information
Clearance around equipment
Road width, clearance
Headroom clearance
B/L(Battery limit)
C/L of Road
R
Min. 7.5 m
A
Line Up C/L of Equipment
Pipe Rack of Structure
Min. 3 m
-
2015 Herv Baron
HERVE BARON
Interfaces between Engineering disciplines Plot Plan
Plot Plan
Process design & simulations
Process eqt specs
Process Flow diagrams
Process eqt sizing
Eqt sizing by vendors
Equipment dimensions
Piping routing
Fire water network routing
Electrical distribution & cable routing
Instrument JB & cable routing
Sewage sizing & layout
-
2015 Herv Baron
HERVE BARON
Overall Site plan
PresenterPresentation NotesDefines the location of a complex and of its environment 1:5000 scale
-
2015 Herv Baron
HERVE BARON
General plot plan
PresenterPresentation NotesShows the entire Plant and the arrangement of the various units (process, utility), storage facilities, buildings and other facilities 1:1000 scale
-
2015 Herv Baron
HERVE BARON
Unit plot plan
PresenterPresentation NotesShows location of equipment, pipe-racks, structures, with co-ordinates and elevation 1:200 scale
-
2015 Herv Baron
HERVE BARON
Unit plot plan Elevation view
-
2015 Herv Baron
HERVE BARON
Unit plot plan Plan view
PresenterPresentation NotesShows location of equipment, pipe-racks, structures, with co-ordinates and elevation
-
2015 Herv Baron
HERVE BARON
3D modelling
-
2015 Herv Baron
HERVE BARON
3D model clash check
-
2015 Herv Baron
HERVE BARON
3D model review
3 model reviews are usually done
-
2015 Herv Baron
HERVE BARON
3D model review
3 model reviews are usually done:
What is the scope of the first model review?
-
2015 Herv Baron
HERVE BARON
First model review: Scope: finalize the Plot Plan Content: Equipment + 30% of piping is modelled, i.e. all ines on PFDs Outcome: after incorporation of COMPANYs comments, the Plot plan is released as the base for the design (IFD). Aspects reviewed: Unit location, equipment location, main access and escape routes to facilities, major piping routes indicated on PFDs, arrangement around LLI, location of main manifolds, space around equipment for maintenance, platforms for main operation access
3D model review
-
2015 Herv Baron
HERVE BARON
30% model review
-
2015 Herv Baron
HERVE BARON
Air-Cooled Heat Exchangers In which case would you install the ACHE at grade vs on pipe-rack?
PresenterPresentation NotesInstall on pipe-rack when you lack real estate
-
2015 Herv Baron
HERVE BARON
Air-Cooled Heat Exchangers In the case of installation on top of pipe-rack, what extra access shall be provided?
PresenterPresentation NotesService platform for maintenance of motor, fan and bearing motors are dismantled and dropped on a four-wheel trolley at service platform level then brought up to a dvait from service platform to grade.
-
2015 Herv Baron
HERVE BARON
Plot Plan review Hands-on exercise
Please review and comment the Plot Plan
PresenterPresentation NotesComment: off-spec tanks located upwind of furnaces: to be relocated
-
2015 Herv Baron
HERVE BARON
Piping Layout Modular plants
In which cases is a modular plant preferable vs a stick built?
PresenterPresentation NotesConstruction not easy of costly (extreme wetaher: Siberia, Canada, remote area, high labour cost)Revamping: to minimize SIMPOS
-
2015 Herv Baron
HERVE BARON
Design development
This is the Plot at FEED stage. Which parts of it do you expect will change at EPC stage?
-
2015 Herv Baron
HERVE BARON
Incinerator Package
Design development
FEED stage EPC Stage
-
2015 Herv Baron
HERVE BARON
Combustion Air blowers + heater
Plant layout evolution
FEED EPC - IFD EPC - IFC
-
2015 Herv Baron
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
Do you want to know more... Much more?
-
2015 Herv Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
-
2015 Herv Baron
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
Order direct from the publisher:
http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html
Engineering TrainingEngineering disciplines: activities and deliverables Piping disciplineSlide Number 4Layout/principlesLayout/principlesSlide Number 7The Block Flow Diagram (BFD)Slide Number 9Slide Number 10Plot PlanPlant layoutLayoutRequirements from ProcessLayoutRequirements from ProcessOn-shore plant: Equipment spacing recommendations as per GE GAP Guidelines .2.5.2LayoutRequirements from ProcessLayoutRequirements from ProcessLayout/principlesAccessesLayout principles: provision for piping flexibilityLayout principles: typical Unit LayoutStructured-mounted vertical vs grade-mounted horizontalEquipment arrangementLayout principles: typical Unit LayoutUnit LayoutLayout / Equipment size by vendorsLayout / package arrangementLayout principles: pipe routingLayout principles: typical Unit LayoutLayout principles: typical Unit LayoutLayout principles: typical Unit LayoutLayout principles: typical Arrangement of Air-coolersPlant LayoutJob specification for design / Plant layout guidelinesInterfaces between Engineering disciplinesPlot PlanOverall Site planGeneral plot planUnit plot planUnit plot planElevation viewUnit plot planPlan viewSlide Number 383D model clash check3D model review3D model review3D model review30% model reviewAir-Cooled Heat ExchangersAir-Cooled Heat ExchangersPlot Plan reviewHands-on exercisePiping LayoutModular plantsDesign developmentDesign developmentPlant layout evolutionThe Oil & Gas Engineering Guide2nd editionThe Oil & Gas Engineering Guide - 2nd editionThe Oil & Gas Engineering Guide2nd edition