Planning in PH Department
description
Transcript of Planning in PH Department
Planning in PH DepartmentPlanning in PH Department
Planning CycleWorkunits
…
Planning Cycle – CERN OverallPlanning Cycle – CERN Overall September n-1
European Strategy Session of Council general discussion of strategic directions
December n-1 Restricted Council
strategic directions to be implemented within MTP oral presentation of Management to Council
May n Scientific Policy Committee
discussion of Draft MTP n+1 – n+5 June n
Finance Committee and Council approval of MTP n+1 – n+5 approval of Budget n+1 in n prices
December n Finance Committee and Council
approval of CVI Budget n+1 in n+1 prices for information
Planning Cycle – CERN OverallPlanning Cycle – CERN Overall September 2008
European Strategy Session of Council general discussion of strategic directions
December 2008 Restricted Council
strategic directions to be implemented within MTP oral presentation of Management to Council
May 2009 Scientific Policy Committee
discussion of Draft MTP 2010 – 2014 June 2009
Finance Committee and Council approval of MTP 2010 – 2014 approval of Budget 2010 in 2009 prices
December 2009 Finance Committee and Council
approval of CVI Budget 2010 in 2010 prices for information
Planning Cycle – Derivatives for PHPlanning Cycle – Derivatives for PHOctober/November October/November n-1n-1 Budget Discussions
based on DB n, resp. MTP n – n+4
APT “Planned” in Resource Sub-Category for year n year n-1 prices
APT “Draft 1” in Resource Sub-Category for year n+1
December December n-1 n-1 / January / January nnconsolidation on departmental level
APT “Planned” for year n year n-1 prices
last budget adjustments by department
APT “Planned” → “Active” year n in n prices
February/March February/March nn discussions of following years
APT “Draft 1” year n prices for years n+1, n+2
Resource Sub-Categories for years n+3 – n+5
only Resource Categories
mid April mid April nn APT input ready in “Planned”
year n prices for years n+1, n+2
Resource Sub-Categories for years n+3 – n+5
only Resource Categories
Planning Cycle – Derivatives for PHPlanning Cycle – Derivatives for PHOctober/November October/November 20082008 Budget Discussions
based on DB 2009, resp. MTP 2009 – 2013
APT “Planned” in Resource Sub-Category for year 2009 year 2008 prices
APT “Draft 1” in Resource Sub-Category for year 2010
December December 20082008 / January / January 20092009 consolidation on departmental level
APT “Planned” for year 2009 year 2008 prices
last budget adjustments by department APT “Planned” → “Active”
year 2009 in 2009 prices
February/March February/March 20092009 discussions of following years
APT “Draft 1” year 2009 prices for years 2010, 2011
Resource Sub-Categories for years 2012 - 2014
only Resource Categories
mid April mid April 20092009 APT input ready in “Planned”
year 2009 prices for years 2010, 2011
Resource Sub-Categories for years 2012 - 2014
only Resource Categories
Workunit Status – Classification of DataWorkunit Status – Classification of DataAPT WU Status Usage Who?
Active(AC)
confirmed WU for the current year DPO/DDPO move from Planned
Planned(PL)
checked by the department DPO/DDPO copy from Draft 1 after checks and discussions
Draft 1(D1)
Planning Space WU Holders (GL, SL, PL, …)
Draft(DR)
Internal Targets DPO/DDPO
Draft 2(D2)
Old Bottom-Up Data already copied
Completed(CO)
Ex-Active DPO/DDPO move from Active
Workunits – Types in PHWorkunits – Types in PH
several types of workunits have been defined GGroup
resources on the group level, not assigned to others AActivity
activities with or without physical deliverable PProject
project in the CERN sense RResources
workunit to group central resources WWorkPPackage
a formal workpackage exists for this activity EU-PEU-Project
Workunit ResponsiblesWorkunit Responsibles
The responsible of a workunit should be closely linked to this activity and have also responsibility regarding expenditure.
G, P, A: leader, in case of experiments RC WP: workpackage supervisor R: DPO EU-P: DDPO
Distribution according to handout Ø 2 WU / holder (1: 40, 2: 16, 3/4: 10, 5+: 4) not cast in stone, please consider/check before next meeting
PH Standard WU – A Deja-VuPH Standard WU – A Deja-Vuwu v1.0 Generated: 22-Jul-2008 21:50
cmd wu WU IDStatus Description WBS Holders EMail Start Date Finish Date Comments
cmd Pxx # Skill [Missing] Email or Profile Org Code [Recharging]Duration Unit (M.WK, %)Start Date Finish Date Comments
cmd PSx # JobType Skill [Missing] Email or Profile Org Code [Recharging]Duration Unit (M.WK, %)Start Date Finish Date Comments
cmd Mxx # Expenditure Description Org Code [Recharging]Amount CurrencyStart Date Finish Date Comments
cmd de #Weight Deliverable description Actual Qty Total Qty Unit Start Date Finish Date Comments
Specify command N, M, D; Commands: N (New), M (Modify), D (Delete)
n wu D1 Your Unit Your sub-PPA Your eMail 1-Jan-08 31-Dec-08n MIS.S Industrial Support - FSU Budget Code Amount CHFn MIS.L Industrial Support - Temporary Labor Budget Code Amount CHF
n MIS.C Small Works Budget Code Amount CHFn MIS.X Small Works Budget Code Amount CHF
n MIS.E Maintenance Budget Code Amount CHFn MTP Experts and Consultants Budget Code Amount CHFn MTP Unpaid Associates (incl. Subsistence) Budget Code Amount CHFn MSP Insurance and Communications Budget Code Amount CHFn MOM Administrative Costs Budget Code Amount CHFn MOM Training and Education Budget Code Amount CHFn MOM Travel Budget Code Amount CHFn MSP Miscellaneous Budget Code Amount CHFn MOM Miscellaneous Budget Code Amount CHF
n MSP Investments - Computing Equipment Budget Code Amount CHFn MSP Investments - Others Budget Code Amount CHFn MSP Consumables (lifetime < 1 year) Budget Code Amount CHFn MTP Contribution to Common Fund Budget Code Amount CHF
Workunits in “Draft” – Internal TargetsWorkunits in “Draft” – Internal Targets
materials budget baseline planning will step-by-step be incorporated into MTP
personnel budget (Allain Gonidec) repository of all personnel on the payroll
from contractual data preview on LD-IC (slots) budget situation for future
PSI/PFE
maintained by DPO/DDPO
Timing of the ExerciseTiming of the Exercise
July 30th, 2008 next general meeting
discussion of procedure, ...
end August 2008 individual discussions GL/TL and DDPO
October/November first round of budget discussions
Your Questions …Your Questions …