Planning for Alresford’s Future
Steve Opacic - Head of Strategic Planning Winchester City Council
![Page 2: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/2.jpg)
Local Plan Part 1: Alresford
Policy MTRA2:
• 500 dwellings (2011-2031)
• Maintain & improve shopping, tourism, etc
• Maintain & improve housing/employment balance
• Assess capacity within settlement before extending boundary
• Be appropriate in scale, design, etc
![Page 3: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/3.jpg)
Local Plan Part 2 - process
• Define Alresford’s needs – housing, employment, open space, infrastructure
• Assess potential sites objectively – fully meet needs, SHLAA and other sites, initial sieve followed by detailed assessment
• Develop and consult on conclusions – leading to proposed allocations
• Alresford-specific development management policies? – if not covered in LPP1/LPP2
![Page 4: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/4.jpg)
Alresford Needs Groups
• WCC drafted ‘templates’ on housing, employment and infrastructure needs
• Alresford public meeting 23 Jan 2013 invited volunteers for ‘Needs Groups’
• 4 ‘Needs Groups’ met from January – April 2013 – Housing, Employment & Economy, Infrastructure, Open Space & Recreation
• Each Group’s conclusions on needs presented at public exhibition & meeting 25 April 2013
![Page 5: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/5.jpg)
Summary - Housing
• 500 required, with 80 permitted/committed
• 40% to be affordable housing
• 75+ age group may double in size by 2031
• Half of dwellings 1-2 bed (2 preferred)
• Need for sheltered/nursing facility
• Use sites close to centre for higher density
• Explore possibility of using industrial or school sites
![Page 6: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/6.jpg)
Summary – Employment / Econ
• Retain Alresford as a ‘working’ town
• Provide 200 new jobs (maintain proportion of residents working locally - 38%)
• Need 1.5 – 3 hectares for new / relocated businesses, with good access & parking
• Need high-speed telecommunications
• No significant new retail needs
• Tourism is important to local economy
![Page 7: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/7.jpg)
Summary – Infrastructure
• Any expansion of Perins School likely to be on existing site. Need for pre-school places
• Need to safeguard future of town centre car parks (sites leased)
• Future need for extra care / nursing / dementia accommodation
• Need for further burial ground / space• Developments to provide safe routes connecting
to the town• Various detailed highway/pedestrian/cycling
improvements suggested
![Page 8: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/8.jpg)
Summary – Open Space & Rec.
• Shortfall of open space (using Local Plan standards) of 15+ ha, rising to 20+ ha
• Need for various types of open space:– allotments (0.5ha)– cricket ground (1.5ha)– rugby (2ha)– tennis (0.5ha)– children’s play– BMX park
![Page 9: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/9.jpg)
Summary – Land ‘Budget’• Housing * 14 ha
• Commercial 3 ha
• Open Space – new development 5 ha
• Open Space – existing population 15 ha
• Burial ground 0.5 ha **
• Total 37.5 hectares (93 acres)* Assuming 420 houses at 30 houses per hectare beyond the town
centre and at higher densities in the centre
** Reduced from original 5ha recommendation
![Page 10: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/10.jpg)
Available Sites
![Page 11: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/11.jpg)
Initial Site ‘Sieve’
Site Ref Address
Area (Ha)
Gross
Natural Designat
ions
Historic Designat
ionsMineral
resources
Trees and
planting Overhead
cables
Water and
flooding
Settlement
GapHighway
access
276 Rear of 58 -72 The Dean 0.67 g g a g g a g a
277 Langtons Farm, Sun Lane 31.62 g g g g g g g g
278 Arlebury Park (1) 6.95 g a a g g g g a
1927 West of New Farm Road (1) 8.65 a g a g g a g g
1966 Cricketers Arms, Jacklyns Lane 0.36 g g g g g g g g
2408 Land off Drove Lane 2.30 g g a g g g g g
2532 Land at Arlebury Park (2) 1.21 g a g g g g g g
2533 Long Barn, Bishops Sutton Rd 1.18 a g g g g g g g
2534 Ceejay Systems (SV) Ltd 0.76 g g g g g g g g
2535 Huxley (UK) Ltd 0.64 g g g g g g g g
2552 Land at Arlebury Park (3) 2.63 g a g g g g g g
2553 Land off New Farm Road (2) 2.04 g g g a g g g r
Green = no constraintsAmber = some constraints (consider mitigation)Red = absolute constraint (no mitigation possible)
![Page 12: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/12.jpg)
Further Studies / Evidence
• Constraints mapping
• Landscape Sensitivity Assessment
• Windfall Trends & Potential
• Open Space Assessment
• Historic Environment Assessment
• Transport / Accessibility Assessment
• Initial Sustainability Appraisal
• Traveller needs assessment
![Page 13: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/13.jpg)
Allocations Workshop/Conclusions
• Site allocations workshop with NATC in Sept considered evidence / studies
• Not just assessing sites 1 by 1, but developing a strategy to meet needs
• Includes mix of housing, employment, open space, recreation, burial ground, etc totalling 37.5ha
• Housing is ‘easy’ other uses more difficult
![Page 14: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/14.jpg)
? Employment Locations ?
![Page 15: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/15.jpg)
Developing a Strategy 1
• About meeting a range of needs, not just housing
• Housing could potentially go on several sites
• Open space and employment more difficult
• Risk of diluting ability of development to achieve needs
![Page 16: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/16.jpg)
Developing a Strategy 2
• The strategic options are: – large mixed-use site– spread development around smaller sites
• No easy option - will be opposition to any
• Only east of Sun Lane capable of delivering all needs
• Other options not suitable for employment, etc and more limited open space provision
![Page 17: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/17.jpg)
Proposed Site Allocations
![Page 18: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/18.jpg)
Sun Lane – Land Uses
![Page 19: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/19.jpg)
Deliverability
• Sun Lane is best to deliver range of needs
• But… delivery of all the elements is critical
• Including new access to A31, employment, open space, traveller site, sequence of development, etc
• Discussions with promoter suggest it is do-able, if not reconsider alternatives
• The Dean dependent on employment relocation
![Page 20: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/20.jpg)
These Are Early Stages
• ‘Needs Groups’ have been consulted and came up with various ideas
• Don’t have all the details/answers at this stage
• Traffic will be an issue for any site, will look at options/opportunities
• Further work and testing needed to address problems and find solutions
![Page 21: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/21.jpg)
Conclusions
• A bold solution but capable of meeting a range of needs and benefits
• Promoters keen to work with community to make it work
• Proposal put forward jointly by NATC and WCC for consultation - is this the best way to meet Alresford’s future needs?
• If not, is there a deliverable alternative?
![Page 22: Planning for Alresford’s Future Steve Opacic - Head of Strategic Planning Winchester City Council](https://reader033.fdocuments.in/reader033/viewer/2022051417/56814957550346895db6aadf/html5/thumbnails/22.jpg)
Next Stages
• Public exhibition/event 7 Jan 2014
• 6-week consultation – to 21 Feb 2014
• Consider responses Feb – May 2014
• Draft Local Plan Part 2 – July 2014
• ‘Pre-Submission’ – Jan 2015
• Submission / examination – Apr-Jul 2015
• Inspector’s Report – Nov 2015
• Adoption – Dec 2015