Pl Rylandsholm 16 June 2009 DRAFT DDR Phase 2 Status EPIM RUF meeting June 16th 2009.

7
Pål Rylandsholm 16 June 2009 DRAFT DDR Phase 2 Status EPIM RUF meeting June 16th 2009

description

© Det Norske Veritas AS. All rights reserved. DDR Phase 2 Status 16 June 2009 DRAFT 3 Status  As of March 24th EPIM officially owns the DDR XML schema  Partner reporting in License web - Same information content as submitted to PSA Status: - Specification document completed - Build - in progress  Updates to XML schema – documented in separate document - WITSML compliance - Correction of misspelling of enumerated values - Correct use of wrong data types (For example on comments which are limited to 256 characters) - Some elements may be changed from ‘optional’ to ‘mandatory’ in the report. - SAWSDL annotation - Coordination with Energistics Status: - Tested and completed – ready for approval by project group

Transcript of Pl Rylandsholm 16 June 2009 DRAFT DDR Phase 2 Status EPIM RUF meeting June 16th 2009.

Page 1: Pl Rylandsholm 16 June 2009 DRAFT DDR Phase 2 Status EPIM RUF meeting June 16th 2009.

Pål Rylandsholm 16 June 2009

DRAFT

DDR Phase 2 Status

EPIM RUF meeting June 16th 2009

Page 2: Pl Rylandsholm 16 June 2009 DRAFT DDR Phase 2 Status EPIM RUF meeting June 16th 2009.

© Det Norske Veritas AS. All rights reserved.

DDR Phase 2 Status

16 June 2009

2

DRAFT

DDR to regulators and license partners- Scope and deliverables of DDR phase 2

Drilling App/DB

Drilling data

PSA/NPD app

Schema/Business validation

DDR XSD

Daily Drilling reportsXML

NPD/PSAFact database

Operators Regulators

License Partners

LicenseWeb

Drilling App/DB

Daily Drilling reportsXML

Daily Drilling reportsXML

pdfpdfpdf

PCA RDS

Page 3: Pl Rylandsholm 16 June 2009 DRAFT DDR Phase 2 Status EPIM RUF meeting June 16th 2009.

© Det Norske Veritas AS. All rights reserved.

DDR Phase 2 Status

16 June 2009

3

DRAFT

Status As of March 24th EPIM officially owns the DDR XML schema

Partner reporting in License web - Same information content as submitted to PSAStatus:- Specification document completed- Build - in progress

Updates to XML schema – documented in separate document- WITSML 1.4.0 compliance- Correction of misspelling of enumerated values- Correct use of wrong data types (For example on comments which are limited to 256 characters)- Some elements may be changed from ‘optional’ to ‘mandatory’ in the report.- SAWSDL annotation- Coordination with EnergisticsStatus:- Tested and completed – ready for approval by project group

Page 4: Pl Rylandsholm 16 June 2009 DRAFT DDR Phase 2 Status EPIM RUF meeting June 16th 2009.

© Det Norske Veritas AS. All rights reserved.

DDR Phase 2 Status

16 June 2009

4

DRAFT

Status Standard report layout for PDF reports

Status:- Completed – approved by project group in meeting February 9th 2009

User guide updates - PSAStatus:- Draft version available at (http://www.ptil.no/getfile.php/PDF/DDRS%20-

%20borerapportering/WITSML_drillReport_profiled_schema_for_usermanual.xml)

Schema validation error messages - PSAStatus:- Business rule validation error messages will be updated by cut of to new formats

Page 5: Pl Rylandsholm 16 June 2009 DRAFT DDR Phase 2 Status EPIM RUF meeting June 16th 2009.

© Det Norske Veritas AS. All rights reserved.

DDR Phase 2 Status

16 June 2009

5

DRAFT

Way forward1. Completion of DDR partner reporting in LW – Responsible Tieto, follow up by LW User forum

2. Communication to EPIM members regarding new DDR formats and date for go live of DDR reporting in Licenseweb – responsible EPIM Report User Forum – Drilling

3. Communicate to operators regarding cut of date for new formats to PSA – Responsible PSA

4. Project documentation will be added to EPIM’s document repository

5. October 1st is the date when PSA will require DDR according to the new formats, and the new DDR partner reporting solution in Licenseweb will be ready for use!

6. Further improvements and extensions of the DDR XML schema will be handled by EPIM RUF – Drilling A possible first case can be increased information scope in DDR. See Next slide

Page 6: Pl Rylandsholm 16 June 2009 DRAFT DDR Phase 2 Status EPIM RUF meeting June 16th 2009.

© Det Norske Veritas AS. All rights reserved.

DDR Phase 2 Status

16 June 2009

6

DRAFT

Additional information requirements – NB not included project scope

Identified during DDR Phase 2 Cost Report nr -> A sequence number.

Each day of operation is a new number increment

Start date -> Start of reporting/operation

Water depth Bit record (additional info): grading,

depth in, depth out, drill lenght (m), duration (hr), rop (m/hr)

Casing (new section): OD (in),top, bottom, weight, grade, estimated top of cement

"Duration" should be included for all time intervals.

Identified during DDR Phase 1 Operation codes Cement Period of operation “Drilling like units of measure” Formation name – selection list Datum (reference points) Casing type Pressurized coring Well stimulation (At well testing) indicator Perforation - Shot density RIGTYPE Bit data Side track Tight wells

Page 7: Pl Rylandsholm 16 June 2009 DRAFT DDR Phase 2 Status EPIM RUF meeting June 16th 2009.

© Det Norske Veritas AS. All rights reserved.

DDR Phase 2 Status

16 June 2009

7

DRAFT

Safeguarding life, property and the environment

www.dnv.com