PJM Reliability Pricing Model Bhavaraju 200706271 -...
Transcript of PJM Reliability Pricing Model Bhavaraju 200706271 -...
PJM ©2007
PJM Reliability Pricing Model
Murty P. BhavarajuPJM InterconnectionIEEE/PES General Meeting Tampa, FLJune 27, 2007
Note: Presentation by B. Hobbs et al. on the dynamic analysis of the RPM is attached
©2007 PJMwww.pjm.com 2
Forward Procurement of Capacity Resources
• Reliability Pricing Model (RPM) is PJM’s new resource adequacy construct that will replace the existing capacity construct effective June 1, 2007.
• RPM’s FORWARD procurement of resources through a base residual auction three years prior to the delivery year:Provides long-term price signal for capacity resources.Encourages Load Serving Entities (LSEs) to make long-term bilateral contracts to hedge their locational reliability charges.Supports the Regional Transmission Expansion Planning Process (RTEPP).
©2007 PJMwww.pjm.com 3
Locational Value of Capacity Resources
• RPM recognizes import capability limitations in certain areas as identified in the PJM Regional Transmission Expansion Planning Process (RTEPP).
• RTEPP has currently identified 23 sub-regions as Locational Deliverability Areas (LDAs) for evaluating the locational constraints.
• LDA with import capability limit less than 105% of import capability requirement will be modeled as constrained LDA in RPM.
• RPM auction could result in higher capacity prices in the constrained areas that would encourage new generation additions or keep generating units from retiring.
©2007 PJMwww.pjm.com 4
Variable Resource Requirement Stabilizes Prices
• Variable Resource Requirement (VRR) is also referred to as Demand Curve.
• Defines a relationship between level of reserve and capacity price based on the net annual cost of a new combustion turbine.
• Recognizes the value of additional capacity above the reserve required to meet the reliability criterion.
• Higher price accepted when there is shortage in meeting the required capacity.
• VRR curves established for PJM Region and each constrained Locational Deliverability Area (LDA).
©2007 PJMwww.pjm.com 5
RTO Variable Resource Requirement Curve
0.0050.00
100.00150.00200.00250.00300.00
139723
.7141
013.0
14230
2.414
3591.8
14488
1.1146
170.5
147459
.914
8749.2
15003
8.615
1328.0
15261
7.3
Quanitity, UCAP MW
UCAP
Pric
e, $
/MW
-Day
RTO VRR Curve
RTO Variable Resource Requirement Curve
©2007 PJMwww.pjm.com 6
Participation in RPM
• Participation by LSEs for load served in PJM region is mandatory, except for those LSEs that have elected Fixed Resource Requirement (FRR) Alternative.– Each LSE shall be responsible for paying a Locational
Reliability Charge.– May choose to hedge Locational Reliability Charges
by offering capacity into the auction.• Participation by resource providers is subject to
the market power mitigation rules described in the tariff.
©2007 PJMwww.pjm.com 7
Supply in RPM Auctions
• Eligible Capacity Resources:– Existing & planned generation in PJM– Existing external generation– Bilateral contracts for unit-specific capacity resources– Existing & planned demand resources– Qualifying Transmission Upgrades
• Resources must meet the requirements specified in PJM Agreements and Business Rules.
©2007 PJMwww.pjm.com 8
2007/2008 RPM Auction Resource Clearing Prices, $/MW-Day
$40.80
$188.54
$197.67
$188.54
$197.67
$40.80
Resource Clearing
Price [$/MW-day]
$140.16 $147.74 $40.80 SWMAAC
$177.51 $156.87 $40.80 EMAAC
$40.80 $0.00 $40.80 RTO
Final Zonal ILR Price/
Prelim. Load Obligation
Rate [$/MW-day]
LocationalPrice Adder [$/MW-day]
System Marginal
Price [$/MW-day]LDA
©2007 PJMwww.pjm.com 9
EMAAC 07/08
$0.00
$50.00
$100.00
$150.00
$200.00
$250.00
36000.0 36500.0 37000.0 37500.0 38000.0 38500.0 39000.0
07/08 EMAAC VRR Curve intersect
Eastern MAAC Results
©2007 PJMwww.pjm.com 10
SWMMAC 07/08
$0.00
$50.00
$100.00
$150.00
$200.00
$250.00
15400.0 15600.0 15800.0 16000.0 16200.0 16400.0 16600.0 16800.0
07/08 SWMAAC VRR Curve intersect
Southwestern MAAC Results
©2007 PJMwww.pjm.com 11
RTO 07/08
$0.00
$50.00
$100.00
$150.00
$200.00
$250.00
$300.00
120000 121000 122000 123000 124000 125000 126000 127000 128000 129000 130000 131000
07/08 RTO VRR Curve intersect
RTO Results (Excluding FRR Obligations)
©2007 PJMwww.pjm.com 12
Discussion of Results
• 127.6 MW of demand response cleared • Approx. 350 MW of new capacity offered of
which 311 MW cleared• Total value of CTRs = $1.48 million/day• Resource clearing prices in Eastern MAAC and
Southwestern MAAC above net Cost of New Entry
• Uncleared MW in RTO: 1,443.5 (UCAP)
©2007 PJMwww.pjm.com 13
Timing of RPM Auctions
Base Residual Auction
Delivery Year
3 Years
Second Incremental Auction
Third Incremental Auction
June May4 months
13 months
First Incremental Auction
23 months
EFORd Fixed
Ongoing Bilateral Market – (shorter-term reconfiguration)
Interruptible Load for
Reliability (ILR)
©2007 PJMwww.pjm.com 14
RPM Auction Process
Optimization Algorithm
Supply Resource-
specific Sell Offers
Demand•Variable Resource Requirement (VRR)
Curves for Base Residual Auction•Locational Buy Bids for Incremental
Auctions
Locational Constraints
Auction Results•Resource Commitments•Resource Clearing Prices•UCAP Obligation values•Capacity Transfer Rights
Zonal CapacityPrices
ILR PricesCTR Rates
©2007 PJMwww.pjm.com 15
Bilateral Market
• Provides LSEs the opportunity to self-supply and hedge against the Locational Reliability Charge determined through the Base Residual and Second Incremental Auction.
• Provides resource providers an opportunity to cover any commitment shortages due to resource cancellations, delays, deratings, or EFORd increases, or decrease in nominated value of a planned demand resource.
©2007 PJMwww.pjm.com 16
Base Residual Auction
• Allows for procurement of unit-specific resource commitments required, after accounting for self-supply, to satisfy the region’s unforced capacity obligation for a future Delivery Year (less an amount reserved for Interruptible Load for Reliability (ILR)).
• Cost of procurement is allocated to LSEs serving load in the actual Delivery Year through the Locational Reliability Charge.
©2007 PJMwww.pjm.com 17
Incremental Auctions: First and Third
• Allow for an incremental procurement of resource commitments for future Delivery Year to accommodate adjustments to participants’ resource positions due to resource cancellations, delays, deratings, or EFORd increases, etc.
• Buyers pay suppliers with no change in the Locational Reliability Charge assessed to LSEs during the Delivery Year.
©2007 PJMwww.pjm.com 18
Incremental Auctions: Second Incremental Auction
• Second Incremental Auction is held ONLY to mitigate reliability concern. – If increased obligation (due to increase in
peak load forecast) compared with capacity cleared in the Base Residual Auction > 100 MW UCAP, the auction is conducted.
• Cost of procurement is allocated to LSEs serving load during the actual Delivery Year through the Locational Reliability Charge.
©2007 PJMwww.pjm.com 19
Locational Deliverability Areas (LDA)
1. AE2. AEP3. APS4. BGE5. ComEd6. Dayton7. DLCO8. Dominion9. DPL10.JCPL11.MetEd12.PECO 13.Penelec14.PEPCO15.PPL16.PSEG
17.Mid-Atlantic Area Council (MAAC) Region 18.ComEd, AEP, Dayton, APS, and
Duquesne19.Eastern MAAC (PSE&G, JCP&L, PECO,
AE, DPL & RECO)20.Southwestern MAAC (PEPCO & BG&E)21.Western MAAC (Penelec, MetEd, PPL)22.PSEG northern region (north of Linden
substation); and23.DPL southern region (south of
Chesapeake and Delaware Canal)
PJM required to make a filing with FERC before adding a new LDA.
©2007 PJMwww.pjm.com 20
LDAs for Transition Period
All 23 LDAs2010/2011
•PJM Mid-Atlantic Region and APS•Eastern MAAC (PSE&G, JCP&L, PECO, AE, DPL, and RECO)•Southwestern MAAC (PEPCO & BG&E)•Rest of Market - ComEd, AEP, Dayton, Dominion and Duquesne
2007/2008, 2008/2009, & 2009/2010
Locational Deliverability Areas
Transition Delivery Year
©2007 PJMwww.pjm.com 21
Zonal Capacity Prices
Base Residual Auction Results
Second Incremental
Auction Results
ILR Certification
•Preliminary Zonal Capacity Prices•Preliminary Zonal ILR Prices•Base Zonal Capacity Transfer Right (CTR) Credit Rate
•Adjusted Zonal Capacity Prices•Final Zonal ILR Prices•Final Zonal CTR Credit Rate
Final Zonal Capacity Prices
Locational Reliability Charge = Daily Zonal UCAP Obligation * Final Zonal Capacity Price
©2007 PJMwww.pjm.com 22
Unforced Capacity Obligations•Zonal W/N Summer Peak – 4 yr•Preliminary RTO Peak Load Forecast•Forecast Pool Requirement
Base RTO UCAP
Obligation
Base Zonal RPM Scaling
Factors
Base Zonal UCAP
Obligation
•Zonal W/N Summer Peak – 4 yr•Forecast Pool Requirement•Forecast Zonal ILR Obligation
•Zonal W/N Summer Peak – 1 yr•Forecast Pool Requirement
•Preliminary Zonal Peak Load Forecast•Final Zonal Peak Load Forecast
Zonal Allocation of Incremental Obligation
Satisfied in 2nd IA
Final Zonal UCAP
Obligation
Final Zonal RPM Scaling
Factors
•LSE Allocation of Zonal W/N Summer Peak – 1 yr
LSE Obligation Peak Load
LSE Daily UCAP
Obligation
Base Residual Auction
Second Incremental
Auction
Delivery Year
©2007 PJMwww.pjm.com 23
Summary of RPM Activities
Pre-Delivery Year Activity• RPM Auctions
– Base Residual Auction– 1st Incremental Auction– 2nd Incremental Auction– 3rd Incremental Auction
• Interruptible Load for Reliability Nomination
Delivery Year Activity• Auction Credits/Charges• ILR Credits• Daily Unforced Capacity
Obligations & Locational Reliability Charges
• CTR Credits• Resource Performance
Assessments• Deficiency & Penalty
Charges/Credits• Non-Unit Specific Capacity
Transactions Charges/Credits
On-going Bilateral Market
Model-based Assessment of the PJM Reliability Pricing Model
Benjamin F. Hobbs, Ming-Che Hu, and Javier Inon
Whiting School of EngineeringThe Johns Hopkins University
Murthy Bhavaraju
PJM Interconnection, LLC
This is a summary of work conducted at JHU sponsored by PJM Interconnection; however, the authors are solely responsible for all opinions expressed, which do not necessarily represent the
position of the sponsor.
Outline
Dynamic Model Analysis of PJM RPMQuestions askedModel assumptions & structure• Simple model of representative agent• Transient simulation with random shocksResultsConclusions
Dynamic Analysis: Questions
1. How do different curves affect….• Stability of capacity market?• Costs to consumers? • Ability to meet reserve requirement, reliability
criterion?
2. How robust are these conclusions to different assumptions about:• Generator behavior? • Demand curve parameters?
Dynamic Analysis: Basic Assumptions
Capacity additions are a dynamic process. Investment depends on:1. Forecast revenue streams
– Based on capacity and energy prices from recent auctionsMore forecast net revenue investment ↑
2. Revenue stream variability– Variations due to forecast changes and weather
Highly variable energy and capacity prices investment ↓(due to risk aversion)
3. Risk attitudes: – No hedges (incomplete market) – Risk aversion– Short-sightedness
Random shocks (weather, economic fluctuations) cause variation in returns
• Result: boom/bust cycles in investment
Use of demand curve changes the market dynamics
Dynamic Model Overview
1. Simple & transparent model simulates: • annual construction of turbine capacity,
• revenues from energy, ancillary services, & capacity markets,
• market stability in face of random demand shocks,
• consumer costs
2. Allows exploration of assumptions3. The model assesses profitability of CTs needed to
meet the reliability requirement • Other generation types and profitability not modeled• “Representative Agent” approach• Annual time step
Simulation Overview: Auction in Year y-4for Capacity Installed by Year y: Repeated for 100 years
Risk-Adjusted Forecast Profit (RAFPy)(↑ if profits higher, ↓ if profits more variable)
Maximum New Capacity Additions NCAy
Capacity Price from Demand Curve(Assume existing capacity bids 0, and NCAy bids B)
Year y-7:Profit =
PRPM + E/ASGross Margin– Fixed Cost
Year y-6:PRPM
+E/AS GM
– FC
Year y-5:PRPM
+E/AS GM
– FC
Year y-4:PRPM
+E/AS GM
– FC
Year y-3:PRPM
+E/AS GM
– FC
Year y-2:PRPM
+E/AS GM
– FC
Year y-1:PRPM
+E/AS GM
– FC
Year y:PRPM
+E/AS GM
– FC
Actual and Estimated Profits: Blue = Known at Auction in Year y-4; Brown = Estimated
Forecast Weights for Profits in y-7, …, y
Risk averse utility functionpenalizes variable profits
NCAy
1.7%
0% RAFPy
PRPM,y
0Total CAP
Risk Adjusted Forecast Profit (RAFP) Calculation
Actual and anticipated combustion turbine profits π• π = Gross Margin (Energy, A/S) + PRPM
• Gross margin based on reserve margins, 1999-2004 experience
• RAFP = single profit with same utility as 7 years of experienced/estimated profit
0
10000
20000
30000
40000
50000
60000
70000
80000
0.95 1 1.05 1.1 1.15
Ratio of (Unforced Reserve Margin) / (Target IRM)
E/AS
Net
Rev
enue
$/In
stal
led
MW
/yr
$10,000 + Simulated Scarcity Rent
Historical E/AS Net Revenues
```
Determination of Capacity Price
PCAP,y
B
Total Cap
Capacity Demand CurveCapacity Bid Curve
Existing Capacity
Max New Capacity
New CapacityChosen
PJM Analysis: Five Curves Considered
Vertical Demand
Results: Summary
1. Sloped curve stabilizes capacity payments
2. More stable payments even out investment, forecast reserves
3. More stable revenues lowers capital costs. Consumer costs (capacity, scarcity) fall:• $129/peak kW/yr for
vertical• $71/peak kW/yr for
sloped
4. Results robust 0.96
0.98
1.00
1.02
1.04
1.06
1.08
0 20 40 60 80 100
Time
Rese
rve/IR
M R
atio
.
VRR (IRM+1%)Vertical at Target IRM
0
40,000
80,000
120,000
160,000
0 20 40 60 80 100
Time
Capa
city P
rice (
$/MW
/yr)
.
VRR (IRM+1%)
Vertical at Target IRM
(values depend on assumptions)
Sample Results: Average (Risk aversion parameter = 0.7; Results depend on specific assumptions)
14
21
26
37
47
ScarcityRev.
$/kW-yr
10
10
10
10
10
E&A/SRevenue$/kW-yr
745013{17%}
3.40985. Alternate Curve with New Entry Net Cost at IRM + 4%
714212{17%}
1.79984. Alternate Curve with New Entry Net Cost at IRM + 1%
744015{17%}
1.23923. Alternate Curve with New Entry Net Cost at IRM
843925{21%}
-0.06542. Original PJM Curve, Based on VOLL
1297066 {35%}
-0.44391. Vertical Demand
Scarcity + RPM
Payment by Consumers (Peak Load
Basis)
RPM Payment $/kW-yr
Generation Profit
$/kW-yr {Return on
Equity}
Average%
Reserve over IRM
% Yearsmeet or Exceed
IRMCurve
⇒ Alternate (sloped) curves have lower consumer cost and better adequacy
Sensitivity AnalysesDemand Curve Shapes:• Where right-hand tail drops to zero• Max. P: dropped by 25%, 40%
Investment Assumptions:• Percent CT added when profit is equal to cost (base: 7%)
+ 2%• Degree of risk aversion:
– risk neutral– very risk averse
• Relative weight placed on earlier year profits in forecast:– low– high
Bidding Assumptions:• Existing capacity bids positive • Potential capacity bids various amounts B
Result: Sloped demand always preferred to vertical
5. Conclusions:Advantages of Sloped Demand
Logically reflects reality of capacity value:– If there are extra reserves, the marginal value of
capacity can be close to but not equal to zero– If reserves are short, payments should be higher
Compared to vertical demand, it lowers risk to generators. Result:– Lower required return to capital– More investment in generation – Dampened capacity cycles– Lower consumer cost
Elasticity mitigates market power in capacity market