Pipe system life time cost Energy will be increasingly precious Environment focus will grow The...
-
Upload
wilfrid-jackson -
Category
Documents
-
view
214 -
download
0
Transcript of Pipe system life time cost Energy will be increasingly precious Environment focus will grow The...
Pipe system life time cost
Energy will be increasingly precious
Environment focus will grow
The pipe system is expensive
Life time expectancy is over 30 Years
What is life time cost ?
Investment cost
– Pipe material
– Pipe installation
– Excavation and restoration
– Inspection
Operation cost
– Pumping
– Heat loss
Maintenance cost
– Repairs
– Management
The Calculation Example
The model system supplies 10 MW
Flow 90OC and return 50OC
The pipe system is:
2 x 1000 m. DN 250
2 x 1500 m. DN 80
100 consumer connections a´100 kW 2 x 2500 m. DN 32
100 consumer connections a´10kW 2 x 2000 m. 18 mm. Cu-flex
Investment cost Thump rules
Pipes 380 000 EUR
Insulation series 2 + 12%
Double Pipes + 25%
X-linked shrink joints +5%
Pipe installation 50% of pipes
Inspection 0- 50 000 EUR
Excavation 100% of pipes
Series 2 + 15%
Double – 20%
Asphalting 50% of pipes
Heat conductivity
PUR = SOLID +RADIATION +GAS
SOLID is not changing over time
RADIATION is not changing over time
GAS varies with the diffusion
SOLID +RADIATION app. 6 – 12 mW/mK depending upon the cell structure
The gas composition
The gas is Cyklopentane, CO2 and air
Cyklopentane, CP 40%
Carbon dioxide, CO2 55%
Air ( N2 + O2 ) 5%
Lambda gas
Cyklopentane: 0,012 W/mK
Carbon dioxide: 0,017 W/mK
Air: 0,027 W/mK
Lambda values new Logstor pipes
Conti pipes: 0.024 W/mK
Traditional pipes: 0,0275 W/mK
Flex pipes: 0,025 W/mK
Lambda ageingTraditional vs. Conti w. Barrier
22
23
24
25
26
27
28
29
30
31
32
33
New 5 Years 10 Years 15 Years 20 Years 25 Years 30 Years
22 Cu-flex
DN 32
DN80
DN250
LR-Conti
LR Cu-flex
mW/mK
German German failurefailure statisticstatistic
5
2000 25%
50%
4%
16%
5%
Weld seams
Joints
Casing+insulationDetectionsystemSundries
Swedish failure statisticsSwedish failure statistics
5
1998-200141%
45%
1%
12%
1%
Steel shells
Slide over
Weld joints
HDPE shrink
PEX shrink
Failure rates
With simple and cheap joints Joint failures may be > 0,5 failure/km./year
With PEX shrink joints or weld joints joint failures are < 0,05 failure/km./year
With low inspection rates Weld seam failures may be > 0,2 failure/km./year
With proper inspection Weld seam failures may be < 0,02 failure/km./year
Failure costs
The repair cost for a simple failure is estimated 3 000 EUR
The example: With cheap joints, repair cost is 20 000 EUR / year
With PEX- and weld joints, it is < 2 000 EUR / year
With low inspection, weld repair cost is 10 000 EUR / year
With proper inspection, it is 1 000 EUR / year
Do it cheap and easy and you have high repair costs
Do it right and you have low repair costs
Life time costs
The following picture compares:
“Series 1 cheap”:
DN 25, DN 32, DN 80, DN 250 all traditional without barrier, cheap joints and low inspection level.
“Series 1 barrier”:
18 Cu-flex, DN 32, DN 80, DN 250 Conti pipes with barrier, PEX joints and proper inspection
Series 2 barrier:
18 Cu-flex, DN 32, DN 80, DN 250 Conti pipes with barrier, PEX joints and proper inspection
Double pipes:
18 Cu-flex, DN 32, DN 80, all double and DN 250 Conti pipes with barrier, PEX joints and proper inspection
Const. Flow:
is Series 1 cheap with constant flow pumps
Life time costs
0
1000
2000
3000
4000
5000
6000
7000
Serie 1cheap
Serie 1Barrier
serie 2Barrier
Double constflow
Failures
Heatloss
Pumping
Inspection
Asphalt
Escavation
Installation
Pipes
kEUR Present values
Life time cost
Calculation settings:
Pumping energy 1% of total heat supply
Constant flow pumps 3% of total heat supply
Heat price 0,025 EUR/kWh
Power price 0,06 EUR/kWh
All amounts as present value over 20 years
Inflation 2%
Energy price rise 2%
Bank interest 6%
The lessons are:
Do not save on inspection
Do not accept “cheap” joints
Keep your heat loss down
Use flow controlled pumps