Pickavance - Appendix 1 Glossary of Terms and Definitions

download Pickavance - Appendix 1 Glossary of Terms and Definitions

of 27

Transcript of Pickavance - Appendix 1 Glossary of Terms and Definitions

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    1/27

    APPENDIX 1GLOSSARY OF TERMS AND DEFINITIONS

    A201.Standard form of building contract published by the American Institute of

    Architects, 1997.

    ACA.SeeAssociation of Consultant Architects.

    ACA82.ACA Building Contract 1982. Includes 1984 and 1992 revisions.

    ACA98.ACA Building Contract 1998. Includes 1999 revision.

    acceleration.The execution of work in a shorter time than previously intended. This

    may be achieved by re-sequencing, by the adoption of increased working hours,

    overtime and double/triple day shifts or by parallel working and trade stacking.1

    activity.An operation or process consuming time and resources.2The work content that

    can be managed by an individual or work team. It contains effort, which can be formally

    defined and programmed, and consumes resources. It is a measurable element of the

    total project programme.

    activity float.Unallocated time within a planned duration of a single activity. The float

    is established simply by dictating an activity duration that is greater than the actual time

    needed to complete that activity with the planned resources and productivity.

    Alternatively, it may be created automatically by some project programming software

    products. An activity with float so created can be referred to as a discontinuous, an

    interruptible, or stretched activity. Where C intends to use this unallocated time as a

    contingency (q.v.) it should be separately identified as such. In Figure A1, below, the

    activity float relates only to activity 6 and is equal to A(6)1 + A(6)2 + A(6)3.

    Figure A1 - Activity float, free float and external float

    activity-on-arrow network.The activity-on-arrow method of planning was developed

    by EI du Pont de Nemours Company in the late 1950s and was the first planning method

    to be called a CPM (q.v.). It is a network in which the activity durations are indicated by

    arrows linked in sequence and relationships by identifiable nodes. The arrows are

    connected together to indicate precedence. The first activity is situated on the left-handside of the diagram with the last activity on the right. Activities are usually placed at

    different levels (not in a single row)to accommodate activities that are performed

    simultaneously. The arrows represent events and the event has not occurred until all the

    activities that terminate it have been completed. The tail of the arrow represents the

    beginning of an activity and the arrowhead the end of it. The number of the node that

    starts and ends the arrow activity usually identifies activities.

    activity-on-node network.A network in which the nodes symbolise the activities.3A

    precedence diagram. This is the form in which almost all modern computerised project

    planning programmes illustrate their output. (See also activity-on-arrow network for

    converse.) In this form of network the nodes are the activity and the arrows represent thelogic between them.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    2/27

    adjudication.A dispute resolution process involving a determination by a third party. In

    the context of construction contracts, a binding but non-final process to which parties

    have statutory recourse pursuant to, in the UK, the HGCRA (q.v.).

    adjusted as-planned programme.An as-planned programme which, for analytical

    purposes, has been amended to include all those activities on the as-built programme

    which were not anticipated at the time of tender but which, in order to maintain the

    construction logic of the original plan, are incorporated in the programme with zero

    durations.

    adjusted master programme.A master programme that has been corrected by

    removing programming errors so as to render it suitable for analytical purposes.

    AIA.SeeAmerican Institute of Architects.

    American Institute of Architects (AIA).The main professional association for

    architects in the US, which also produces a set of standard form contracts for building

    works.

    arbitration.A traditional form of dispute resolution whereby disputants agree that a

    third party arbitrator hear their submissions in private but provide a resolution that isenforceable by the courts. A very common means of dispute resolution in the

    construction industry.

    AS2124.Australian Standard Conditions of Contract 1992.

    AS4000.Australian Standard Conditions of Contract 1997 (supersedes AS2124).

    as-built but-for analysis.Sometimes referred to as the collapsed as-built method. A

    method of analysis which uses the as-built programme as a base-line from which the

    effect of delaying events are removed in order to calculate what would have been the

    completion date but for those events.4

    as-built critical path.The sequence of immediately critical activities, as traced through

    the history of a project.as-built programme.The record of the history of the construction project in the form of

    a programme. The as-built programme does not necessarily have any logical links. It can

    be merely a bar chart record of the start and end dates of every activity which actually

    took place.

    as-planned impacted programme.A method of analysis based on the as-planned

    programme as baseline. In this method of analysis an objective assessment of the effects

    of delaying events is added to the as-planned programme to demonstrate the impact of

    those events on the planned programme.5

    as-planned programme.The updated and amended programme illustrating Cs intent

    for the future conduct of the works at the time of its publication (q.v.). Depending upon

    the circumstances of its publication, it may also be referred to as the master programme

    (q.v.).

    Association of Consultant Architects (ACA).An organisation whose membership

    consists of architectural practices and which produces the ACA and PPC contract forms.

    average progress.The rate of progress at any time that C expected to make with the

    degree of productivity allowed for and upon which Cs tender was based.

    bar chart.A graphic display of activity durations in which the size of the bar is

    proportionate to the duration of the activity it represents. Activities are listed with other

    tabular information on the left-hand side with time intervals over the bars. Activity

    durations are shown in the form of horizontal bars. Sometimes called a Gantt chart, (q.v.

    ).BCA.SeeBoard of Contract Appeals.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    3/27

    BCIS.SeeBuilding Cost Information Service.

    baseline.A fixed criterion by reference to which a variable can be measured. In the

    context of construction programmes, the baseline is frequently an earlier version of the

    programme, thus enabling changes between the two programmes to be identified.

    Board of Contract Appeals (BCA).One of a set of specialist tribunals in the US

    founded to decide contractual claims against Federal Government departments. The

    tribunals include Boards of Contract Appeals for the Department of Agriculture

    (AGBCA), the Armed Services (ASBCA), the Department of Energy (DOEBCA), the

    Department of Interior (DOIBCA), the Department of Labor (DOLBCA), the

    Department of Transportation (DOTBCA), the General Services (GSBCA), the US

    Postal Service (USPBCA) and the Department of Veterans Affairs (VABCA).

    British Standards (BS).The main organisation in the UK for administering standards.

    BS.SeeBritish Standards.

    Building Cost Information Service (BCIS).An organisation established by RICS (q.v.

    ) in 1962 to collate and analyse data submitted by members of the BCIS and other

    relevant sources. Information is made available to the construction industry throughseveral publications and an on-line service.

    building forms of contract.Those standard forms of contract specifically intended for,

    but not necessarily used for the construction of building works. They include those

    published by the JCT (q.v.), ACA (q.v.) and include FIDIC/Build98 (q.v.) and

    FIDIC/SF98 (q.v.).

    burden of proof.The rule that it is for the party who makes the assertion to satisfy the

    deciding tribunal as to the truth of its allegation. When that party has put forward

    sufficient evidence to raise a presumption that what it asserts is true, the burden of proof

    shifts in that the allegation is then assumed to be true unless the other side can produce

    evidence to rebut the presumption.C.Seecontractor.

    C21.New South Wales Government (Department of Commerce) Standard Form. The

    standard form government construction contract in the Australian state of New South

    Wales. Remarkable primarily for its unconventional extension of time clause.

    CA.Seecontract administrator.

    calendar.Calendars are diaries that are a vital component of all project management

    systems and without them it is impossible to programme activities or resources. They are

    used to specify the number of hours to a day, days in a week, and weeks in a year for

    working or not working. This arrangement defines the amount of time available for

    programming activities to be carried out and people related resources to be organised.

    Each calendar can be customised with its own holidays and extra work days or

    suspensions and they can be used to identify the effect on activity of a suspension of

    work. Some software packages support multiple calendars for individual projects, the

    whole organisation, and individual resources if necessary and in some software packages

    calendars can also be applied to the relationship between activities to enable periods of

    lag to be more closely defined.

    cascade diagram.A graphic display, sometimes referred to as a linked bar-chart (q.v.

    ), in which the critical path network is illustrated by arrows linking nodes representing

    the activities. On this type of diagram the nodes are proportionate in size to the duration

    of the activities and are positioned on the diagram according to their calendar dates. The

    logical links between activities indicate the order in which the activities are intended to

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    4/27

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    5/27

    beneficial use. The completion date may not be the same as the date for completion

    (q.v.).

    concurrency.A term used to describe two or more causative events occurring over a

    calendar period (at least one of which is at Ds risk and at least one at Cs risk) and

    where the effects of each may also be experienced over another single calendar period.

    Concurrency is sometimes used to describe the circumstances of the effects being

    experienced over a single calendar period but where the causative events giving rise to

    the effects occur over different calendar periods. This is more correctly termed the

    concurrent effect of sequential events.

    concurrent delay.A delay to progress, to completion, or to the date for completion

    where at least one of the causes of the causative events is at Cs risk and at least one is at

    Ds risk. con-

    confirmation of verbal instruction (CVI).A document issued by C, to confirm oral

    instructions issued by the CA or D. In some contracts such confirmation must be issued

    within a limited time and not dissented from with a limited time before it becomes of

    contractual effect.constructive acceleration.Acceleration which C is impliedly required to implement as

    a result of the actions or omissions of D, or the CA acting on Ds behalf.

    constructive change.A change which C is impliedly constrained to implement as a

    result of the actions or omissions of D, or the CA acting on Ds behalf.

    contemporaneous documents.The documents which come into being as a result of the

    performance of the works.12

    contingency period.A fixed time duration allocated for an unspecified purpose in

    relation to a particular activity, sequence of activities or the works as a whole to be taken

    up or deducted as required. It may be for C or Ds use depending upon whether C has set

    it aside in its programme for its use or D has required it to be set aside in Cs programmefor Ds use. It is to be distinguished from float (q.v.), which is unallocated time.13

    contingency sum.A fixed sum of money, which C is required to include in its tendered

    price for unallocated purposes, usually to be expended, or deducted from the contract

    sum as required by D. It is to be distinguished from prime cost and provisional sums

    which are sums allocated for a purpose yet to be particularised.

    contract administrator (CA).The term given to the person responsible under the

    contract for administering the provisions of the contract including determining and

    certifying what delay may be excused by the grant of an extension of time, or what

    losses or expenses are to be reimbursed. In standard form contracts, this person is

    alternatively referred to as the engineer, architect, project manager or superintendent.

    contract documents.The documents, usually signed by both parties, defining what is to

    be done in consideration for the contract sum. These are the most important of all and

    form the starting-point for any analysis of change.

    contractor (C).The party responsible for carrying out the works.

    contractor improvements.C may offer to introduce changes when superior methods or

    materials become apparent. When C initiates such changes purely for its own advantage,

    D may avoid increased costs and time allowances provided it chooses its words of

    acceptance carefully, otherwise they may constitute a constructive change.14

    contractors delay to completion.A culpable delay to completion (q.v.).

    contractors delay to progress.A culpable delay to progress (q.v.).

    contractors risk event.An occurrence, the effects of which are at Cs risk under thecontract.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    6/27

    cost data. The documents referable to the calculation of loss and expense in relation to

    any event.

    counterclaim.The claim asserted by a defendant or respondent against the claimant.

    Under the CPR it is referred to as a Part 20 claim. In principle a counterclaim stands in

    its own right. But for the fact that the claim originated earlier, it would have been the

    claim.

    critical activity.An activity that has a connection to the critical path in a network.

    Critical activities may have float and may not necessarily be critical to completion

    throughout their duration. For example, an activity that has a start-start relationship with

    an activity that is on the critical path (q.v.) will, by virtue of that connection, have a

    critical start. Because of that critical start, it will remain a critical activity even if there is

    no constraint at all on its completion. Most computer software programmes indicate

    critical activities by either a red outline or as red bars.

    Court of Federal Claims (COFC).A US Federal court which frequently hears

    construction-related disputes, including appeals from the Boards of Contract Appeals.

    CPM.Seecritical path method.CPR.SeeCivil Procedure Rules.

    critical delay.A delay to progress that aversely affects a critical activity and causes the

    critical path to be extended.

    critical path.The sequence of activities through a project network from start to finish,

    the sum of whose durations determines the overall project duration.15In any network

    there will be one or more critical paths to each key date (q.v.).

    critical path analysis.The adoption of the critical path method (q.v.) in the analysis

    and/or management of the cause and effect of a type of delay.

    critical path method (CPM).A schematic and written description of the sequence of

    work that C plans to use to manage the progress and completion of the works, basedupon a network illustrating the activities that must be accomplished with their mutual

    logical dependencies and durations.

    culpable delay.A delay to progress or a delay to completion caused by an event, which

    is at Cs risk and for which it is not entitled to relief nor compensation for the effects

    thereof. The SCL Protocol describes this as contractor delay.16

    culpable delay to completion.A delay to the completion date caused by a contractor

    risk event (q.v.).

    culpable delay to progress.A delay to progress caused by a contractor risk event (q.v.).

    cumulative impact.The impact identified as caused by the consequential effects of an

    event as opposed to the direct effect of an event.

    cumulative impact costs.Costs associated with the impact on work not directly

    associated with the event itself.

    CVI.Seeconfirmation of verbal instruction.

    D.Seedeveloper.

    dangle.An activity in a network that has no dependent successor. Also referred to as an

    open end (q.v.).

    data date.The date upon which the status of an as-planned programme (q.v.) is

    established in relation to progress actually achieved prior to that date. The start of the

    planned sequence from which the critical path (q.v.) will be calculated.

    database.An organised collection of information. The essence of a database is that

    information is categorised by information type or subject, referred to as a field inwhich the data is entered and which can be retrieved on many different occasions in a

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    7/27

    variety of combinations depending upon which fields are selected and in which order

    they are selected for retrieval. At its simplest level, it may comprise a list of names,

    addresses, phone numbers and other details which can be sorted, filtered and retrieved in

    differing combinations. The sort of project planning software commonly used for the

    preparation of a CPM network is often constructed as a database with a graphic front

    end17although not all software used for project planning is constructed around a

    database.

    date for completion.The date indicated from time to time on Cs programme as the

    date by which C plans to complete the works. Referred to in the SCL Protocol as the

    contractors planned completion date.18

    DB2005.JCT Standard Form of Design and Build Contract, 2005 Edition.

    defence.A defendants (q.v.) formal response to a claimants (q.v.) claim. One

    principle of stating ones case formally is that any allegation not specifically disputed by

    the defendant is deemed to be admitted. The defence must indicate which parts of the

    claim the defendant admits, which it denies, which it doubts to be true (and why), which

    it neither admits nor denies because it does not know whether they are true but which itwishes the claimant to prove. The defendant must give its version of the facts in so far as

    they differ from those stated in the claim; say why it disputes the entitlement to any

    particular remedy, or the value of the claim, or assessment of damages; and specify any

    document vital to the defence.

    defendant.The title given in litigation to the party denying a right claimed and upon

    whom, in respect of any counterclaim, the burden of proof rests.

    delay.An adverse effect on timing in relation to what was intended. There are many

    different types of delay, each having different consequences under different contracts

    depending upon which party is responsible for it.

    delay to completion.An instance of an entire project (or section of a project) beingcompleted later than intended.

    delay to progress.An instance of an element of works being performed or completed

    later than intended.

    developer (D).The party who agrees to pay for the construction works.

    developers change.Commonly referred to as a variation (q.v.).

    developers cost risk event.Also referred to as a compensable or reimbursable event. A

    developers risk event (q.v.) for which D is liable to compensate C for loss or expense

    suffered but which is not necessarily eligible for an extension of time (q.v.).

    developers delay to progress.A delay to progress (q.v.) caused by a developers risk

    event (q.v.).

    developers risk event.An event specified under the contract to be at Ds risk as to time

    and/or cost.

    developers time risk event.Also referred to as an excusable event. A developers

    risk event (q.v.) for which D is liable as to time by way of an extension of time to

    complete (q.v.), but not financial compensation.

    direct impact.The foreseeable consequences of an event.

    direct impact costs.The costs foreseeable as a direct consequence of an event.

    direct loss or expense.The term used to describe direct impact costs under the JCT

    family of contracts.

    disclosure.Previously known as Discovery under Rules of the Supreme Court Order

    24. Disclosure is a process whereby the parties to a dispute disclose to each other thedocuments in their power, custody, or control relating to the matters in dispute.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    8/27

    Disclosure is compulsory in litigation under CPR Part 31, but it is usually discretionary

    in arbitration. Rule 31.2 of CPR defines disclosure as the admission by a party to

    litigation that a document exists or has existed. Rule 31.6 requires a party to litigation to

    disclose to the other side the documents on which it relies, and those which adversely

    affect its own case; adversely affect another partys case; or support another partys case;

    and the documents which it is required to disclose by a relevant practice direction.

    discovery.Another term for disclosure (q.v.) This was the term used in England and

    Wales prior to the CPR (q.v.) reforms.

    discrepancies.Differences between two or more of the plans, specifications, details,

    dimensions or drawings to which C is contractually obliged to conform and later editions

    or instructions given during the course of the works.

    disruption.Disturbance, hindrance or interruption of a contractors normal work

    progress, resulting in lower efficiency or lower productivity than would otherwise be

    achieved.

    disruption damages.Commonly referred to as loss and expense.19The increased cost

    arising out of the lost productivity caused by disruption (q.v.).DMS.Seedocument management system.

    document.According to Rule 31.4 of CPR anything in which information of any

    description is recorded.

    document management system (DMS).A database (q.v.) which compiles information

    about a document generally including such objective information as its author, recipient,

    date of creation, date last edited, subject matter, and so on and can also be attributed with

    fields to record subjective information such as to what it is considered to be referable

    under a variety of fields. It can be compiled with a scanning system to provide an image

    recovery system. By the definition of document within CPR the DMS is itself a

    document.DOM/1.Standard form of domestic subcontract for use with JCT80.

    domestic subcontractor.A subcontractor selected by C and with which C enters into a

    subcontract for work. C generally remains responsible for the subcontractors

    performance. Many standard forms contain provisions requiring the express approval of

    the CA to the employment of a subcontractor.

    draft programme.Any programme that has not been accepted as a master programme

    (q.v.).

    dummy.A logical link which absorbs neither time nor any other resource. In activity-

    on-arrow networks (q.v.) relationships that are not in themselves activities are indicated

    by dummy activities.

    duplication.Where the same item is specified in different specification sections or the

    same item is specified in different areas of the same specification it is referred to as

    duplication. Duplication often results in disputes about which nominated subcontractor

    or works contractor is intended to perform the work or which method or material the CA

    actually had in mind.

    duration.The amount of time needed to complete an activity. The time period can be

    determined inductively, by determining the start and finish date of an activity or

    deductively by calculation from the planned productivity of applied resources.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    9/27

    early finish.The earliest programmed calendar date on which the activity can be

    finished before any of its succeeding float is consumed. See Figure A2.

    Figure A2 - Early and late finish

    Figure A3 - Early and late start

    early start.The early start is the earliest programmed calendar date on which the

    activity can be started before any of its preceding float has been consumed. See Figure

    A3.

    earned value.The measurement of how much work has been accomplished on a project

    in relation to its value. Earned value is synonymous with performance measurement,

    calculated by multiplying a tasks planned cost by the percentage of work complete.

    employer.The term used under UK, Hong Kong and Singapore standard forms of

    building contract for the developer (q.v.).

    ECC2.Engineering and Construction Contract 2nd Edition (2002). The primary

    standard form in the NEC2 suite.

    ECC3.Engineering and Construction Contract 2nd Edition (2005). The primary

    standard form in the NEC3 suite.

    EDI.SeeElectronic Data Interchange.Electronic Data Interchange (EDI).A system that enables parties to it are able to share

    electronic information from a common platform.

    engineering contracts. Those standard forms of contract specifically intended for, but not

    necessarily always used for, civil engineering work, including the ICE and FIDIC

    contracts.

    EPC.Engineer, procure and construct. A form of procurement in which C is required to

    design the works together with the equipment and plant and commission the project

    ready for use. Sometimes called a turnkey contract (q.v.).

    event.The direct cause of a change (q.v.).

    excusable delay.A delay to progress (q.v.) caused by a developers time risk event (q.v.).

    extension of time.Additional time granted by D to C to relieve it from liability for

    liquidated damages (q.v.) and to provide an extended contractual time period or date20

    by which the works, or a defined part of it are to be, or should have been completed.

    extras.A term commonly used to describe the performance of additional work.

    Fdration Internationale des Ingnieurs-Conseils (FIDIC).A Geneva-based

    international engineering organisation responsible for producing a set of standard form

    contracts designed for international construction projects under this name.

    FIDIC.SeeFdration Internationale des Ingnieurs-Conseils

    FIDIC4.FIDIC Conditions of Contract for Works of Civil Engineering Construction,

    Fourth Edition 1987 (revised 1992, termed the Red Book).

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    10/27

    FIDIC/Build99.FIDIC Conditions of Contract for Building and Engineering Works

    Designed by the Employer, 1st Edition 1999 (the Red Book).

    FIDIC/DB99.FIDIC Conditions of Contract for Design Build and Turnkey, First

    Edition, 1999 (the Silver Book).

    FIDIC/M&E87.FIDIC Conditions of Contract for Electrical and Mechanical Works,

    Third Edition, 1987 (the Yellow Book).

    FIDIC/PD+B99.FIDIC Conditions of Contract for Plant and Design-Build, First

    Edition, 1999 (the Yellow Book)

    FIDIC/SF98.FIDIC Short Form of Contract, Test Edition, 1998 (termed the Green

    Book).

    field costs.An American expression for site related preliminaries (q.v.).

    Figure A4 - Finish-to-finish

    Figure A5 - Finish-to-start

    finish-to-finish.In the example at Figure A4, of a finish-to-finish relationship, activity B

    cannot finish until activity A has finished. It implies that B can finish at the same time as

    A, but not before it.

    finish-to-start.The convention in Figure A5 shows the normal sequential relationship of

    one activity following another. For example, activity B cannot start until activity A has

    finished.

    fitness for purpose.The standard of performance statutorily required under the Sale of

    Goods Act 1979 and a term that may be implied in design and build contracts in the

    absence of express words to the contrary. Under this standard, in any contract for the

    design and supply of a finished product, if that product is proved unfit for the intended

    and mutually understood purpose for which it was supplied, then, irrespective of whether

    the provider of the product has been negligent, there will be a liability for failure of that

    product.21float.Unallocated time in a critical path network. It may be more precisely described as

    free float (q.v.),22interfering float (q.v.), total float (q.v.),23or activity float

    (q.v.) depending upon its position in the network.24

    force majeure.A compendious expression used in some contracts to denote defined

    types of unforeseen occurrences that are caused by neither D or C, but which may give

    rise to an extension of time entitlement on Cs part. Typical examples include

    exceptional weather events, terrorist acts, earthquakes, war and civil disorder.

    fragnet.This is a term used in proactive project planning for a pre-defined segment of a

    network devised for particular sequences of work. In delay analysis the term is used to

    describe a section of a programme in which an activity is broken down into a number of

    sub-activities for the purpose of detailed analysis. In effect a fragnet is the obverse of a

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    11/27

    hammock (q.v.). In Figure A6, a fragnet has been developed for an activity initially

    comprising only foundations to produce a fragnet containing activities for

    excavation, formwork, reinforcing steel, concrete pouring and concrete

    curing. The start date of excavation is the same as the start of foundations and the

    finish date of concrete curing is the same as the finish date of foundations.

    Figure A6 - Fragnet

    free float.The amount of time that an activity can be delayed beyond its early start/early

    finish dates without delaying the early start or early finish of any successor activity.25

    Gantt chart.A chart was developed by Henry L. Gantt and Fredrick W. Taylor in the

    early part of the twentieth century. The Gantt chart was the first formal programming

    system to be used in conjunction with scientific management techniques. It is normally

    constructed with the time periods along the horizontal axis with personnel, organisations,

    plant, materials and so on along the vertical axis. The bar of a Gantt chart is usually

    open, as opposed to the closed box of the bar on a bar chart (q.v.) and contains details of

    the activity time of units of work for each piece of plant, person or organisation.

    GC/Works.A suite of contracts is designed for projects developed by the UK

    government. Prior to 1998 the Department of the Environment was responsible for

    developing this suite of contracts; since then it has been the Property Advisers to the

    Civil Estate, Central Advice Unit.

    GC/Works/1.General Conditions of Contract for Building & Civil EngineeringLump

    Sum with Quantities, Third Edition, 1989 (revised 1990).

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    12/27

    GC/Works/1/98.General Conditions of Contract for Building & Civil Engineering

    Major Works with Quantities, 1998.

    Figure A7 - Hammock

    GC/Works/1/98.General Conditions of Contract for Building & Civil EngineeringMajor Works with Quantities, 1998.

    GC/Works/1DB.General Conditions of Contract for Building & Civil Engineering

    Design & Build Version, 1993.

    GC/Works/1DB/98.Contract for Building & Civil EngineeringDesign & Build

    Version, 1998.

    GC/Works/2.General Conditions of Contract for Building & Civil EngineeringMinor

    Works, Second Edition, 1980 (revised 1989).

    GC/Works/2/98.General Conditions of Contract for Building and Civil Engineering

    Minor Works, 1998.

    global claim.A claim in which the amount claimed to be lost is not causally linked to

    the breaches alleged. A claim in which the contractor seeks compensation for a group of

    developer risk events but does not or cannot demonstrate a direct link between the loss

    incurred and the individual developers risk events.26

    hammock.A project planning device used to summarise the early-start and early-finish

    dates of a set of activities. It is generally used for reporting durations of work packages

    as opposed to activities. When a series of activities is designated as a hammock the

    computer software generally calculates the duration by measuring the time period

    between the earliest start date of the hammocks predecessor activities and the latest

    early-finish date of its successor activities.In Figure A7, a hammock called

    foundations has been developed for a group of activities containing activities for

    excavation, formwork, reinforcing steel, concrete pouring and concrete

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    13/27

    curing. The start date of excavation is the same as the start date of foundations and

    the finish date of concrete curing is the same as the finish date of foundations.

    hanging activity.Also referred to as an open end (q.v.).

    head office overheads.The incidental costs of running Cs business as a whole. They

    are indirect costs which cannot be directly allocated to production as opposed to

    direct costs which are the costs of production. Amongst other things, overheads may

    include such things as rent, rates, directors salaries, pension fund contributions, and

    auditors fees. In the US head office is referred to as home office. In accountancy,

    head office overheads are generally referred to as administrative expenses whereas the

    direct costs of production are referred to as costs of sales.

    HGCRA.SeeHousing Grants, Construction and Regeneration Act 1996.

    High Court.In England and Wales, the highest court of first instance for civil disputes.

    It is divided into the Queens Bench Division, Equity Division and Family Division. The

    Queens Bench Division further incorporates some specialist courts, including,

    relevantly, the Commercial Court and the Technology and Construction Court. In

    Australia, conversely, the High Court is the ultimate court of appeal.histogram.A chart that illustrates quantitative values along one axis. It is often used for

    illustrating the effect of changes in resources over time.

    HKBC05.Hong Kong Special Administrative Region of the Peoples Republic of

    China, General Conditions of Contract for Building Works (2005).

    HKGC99.Hong Kong Special Administrative Region of the Peoples Republic of

    China, General Conditions of Contract for Civil Engineering Works (1999).

    HKRICS86.Hong Kong (Royal Institute of Chartered Surveyors) Contract. Standard

    Form of Building Contract (1986) Private Edition, With Quantities published by RICS

    Hong Kong, 1999 Amendment.

    House of Lords.In the UK, the ultimate court of appeal.Housing Grants, Construction and Regeneration Act 1996 (HGCRA).An Act of

    Parliament affecting construction contracts (as defined in the Act) entered into on or

    after 1 May 1998 which implies into such contracts (i) a statutory right to refer disputes

    to adjudication and (ii) certain rights of payment for contractors.

    ICE.SeeInstitution of Civil Engineers.

    ICE/MW/98.ICE Conditions of ContractMinor Works, Second Edition 1995 (revised

    March 1998).

    ICE6.ICE Conditions of Contract, Sixth Edition, 1991 (revised March 1998).

    ICE7.ICE Conditions of Contract, Measurement Version, Seventh Edition, September

    1999.

    ICE6DC.ICE Design and Construct Conditions of Contract, Sixth Edition, 1992

    (revised March 1998).

    IChemE.SeeInstitution of Chemical Engineers.

    IChemE.Institute of Chemical Engineers lump sum contract, 4th edition, 2001 (the Red

    Book). D is referred to as the Purchaser and the CA is referred to as the Engineer.

    IEE.SeeInstitution of Electrical Engineers.

    IFC84.JCT Intermediate Form of Building Contract, 1984 Edition (revised 1995).

    IFC98.JCT Intermediate Form of Building Contract, 1998 Edition.

    IFC2005.JCT Intermediate Form of Building Contract, 2005 Edition.

    IMechE.SeeInstitution of Mechnical Engineers.

    impact.The effect of a change.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    14/27

    impossibility.The inability of a party to a contract to fulfil its contractual obligations as

    a result of external circumstances. A cause of frustration of a contract at common law.

    inconsistencies.The differences between information given on one document in relation

    to another in respect of the same element of work.

    independent standards.Reference documents relevant to specific issues that are not

    necessarily referred to in the contract data.

    information release schedule (IRS).The name given under JCT contracts to the

    document issued to C at the time of tender as the CAs programme for the issue of

    posttender information, drawings, details and levels. Under ACA82 and ACA9827it is

    referred to as a Time Schedule. Failure to provide such information in accordance with

    the IRS is an excusable and compensable event under those forms. The essential

    character of an IRS is that it is prepared by, or on behalf of D as a contract document

    upon which C intends to rely.

    Institution of Electrical Engineers (IEE).A professional body that controls the

    education and conduct of electrical engineers in the UK. Together with the Institution of

    Mechanical Engineers (IMechE), in produces the MF/1 contract form (q.v.).Institution of Chemical Engineers (IChemE).The professional body that controls the

    education and conduct of chemical engineers in the UK and also produces a series of

    standard form contracts intended for use with projects in the process and petrochemical

    industries.

    Institution of Civil Engineers (ICE).The professional body that controls the education

    and conduct of civil engineers in the UK and also produces a series of standard form

    contracts intended for use with civil engineering projects.

    Institution of Mechanical Engineers (IMechE).A professional body that controls the

    education and conduct of mechanical engineers in the UK. Together with the Institution

    of Electrical Engineers (IEE), it produces the MF/1 contract form (q.v.).interfering float.That proportion of total float which, if used, will not delay the

    completion date, but will nevertheless interfere with the timing of successor activities.

    The difference between total float and free float.

    IRS.Seeinformation release schedule.

    JCT.SeeJoint Contracts Tribunal.

    JCT63.JCT Standard Form of Building Contract with Quantities, 1963 Edition (revised

    1976).

    JCT80.JCT Standard Form of Building ContractPrivate with Quantities, 1980

    Edition (revised 1995).

    JCT98.JCT Standard Form of Building ContractPrivate with Quantities, 1998

    Edition.

    JCT2005.JCT Standard Form of Building ContractPrivate with Quantities, 2005

    Edition.

    Joint Contracts Tribunal (JCT).The organisation responsible for the most widely

    used suite of standard forms in the UK for building works. The organisations

    membership includes representatives of the Royal Institute of British Architects (RIBA)

    and other representative industry bodies. The forms have evolved since the early 20th

    century from what were previously known as the RIBA forms.

    key date.Sometimes referred to as a milestone date or critical date. A key date is a date

    by which an identifiable accomplishment must be started or finished. For example

    power on, weathertight or the start or completion of phases of construction or ofphases or sections of the contract or work of particular subcontractors.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    15/27

    ladder.An arrangement consisting of a chain of lagged start-to-start and lagged finish-

    to-finish (q.v.) activities. It can produce some anomalous results in delay analysis and

    should be avoided.

    lag.The minimum necessary lapse of time between the start or finish of one activity and

    the start or finish of another activity.28It may also be described as the amount of timerequired between the start or finish of a predecessor task and the start or finish of a

    successor task.

    Figure A8 - Lagged finish-to-finish

    Figure A9 - Lagged finish-to-start

    lagged finish-to-finish.In Figure A8, d indicates a finish-to-finish relationship but

    with a delay, i.e., activity B cannot finish until d days (or whatever time period has

    been used) after activity A has finished. This convention provides a second means of

    overlapping the timing of activities.

    lagged finish-to-start.In Figure A9, d implies a normal lag relationship between

    activities A and B; that is, B cannot start until d days after activity A is finished. An

    example of this might be the curing time of concrete between completion of the pour and

    the commencement of work on it.

    lagged start-to-start.In Figure A10, however, d indicates a start-to-start relationship

    with the delay imposed showing that activity B cannot start until the period d has

    elapsed after activity A has started. This convention provides one of the facilities to

    overlap the execution of activities.

    Figure A10 - Lagged start-to-start and finish-to-finish

    lagged start-to-start and lagged finish-to-finish.There may be occasions where a lag

    is required both on the start and finish of related activities. This is achieved by the

    convention shown in Figure A10, sometimes referred to as a ladder (q.v.). In this

    arrangement, activity Bcannot start until d days after activity A has started and activity

    B cannot finish until d days after activity A has finished. For example, in the case of a

    pipeline, the activity to lay pipes cannot start until x days after the start or until y

    days after the finish of activity excavate. Thus, lay pipes has a lag start of x days

    and a lag finish of y days after the start and finish date of the activity excavate.

    late finish.The latest programmed calendar date on which an activity can be finished

    when all its succeeding float (if any) has been consumed but the activity can still be

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    16/27

    completed without delaying the commencement of a successor activity (See Figure A2

    above).

    late start.The late start is the latest programmed calendar date on which an activity can

    be started when all float preceding it has been consumed (See Figure A3 above).

    latent conditions.The underlying conditions of the site upon which construction work is

    to

    take place.If latent conditions diverge significantly from what C could have reasonably

    foreseen at the time of tender, C will, under many contracts, be entitled to a variation.

    lead.The opposite of lag (q.v.), but in practice having the same meaning. A preceding

    activity may have a lag to a successor activity - from the perspective of the successor

    activity, that is a lead.

    link line.The connecting flow lines between activities on a flow chart or in a network

    using precedence network notation. The direction of flow is indicated by an arrow head.

    linked bar chart.Sometimes referred to as a cascade diagram (q.v.).

    liquidated and ascertained damages.A fixed sum, usually per week or per day,

    payable by C to D in the event that the specified work is not completed by the specifieddate. In some forms of contract, liquidated damages are referred to as delay damages.

    liquidated damages.Also referred to as liquidated and ascertained damages (q.v.).

    logic.The sequence in which activities are planned to be performed, with the start and/or

    finish of some activities independent, dependent, or restrained, by the start and/or

    completion of other activities.

    M&E.Seemechanical and electrical.

    management contractor.The party contracting with the works contractors (q.v.) and

    responsible to D for programming their work but not, generally, the sufficiency of their

    work.

    master programme.The accepted programme from time to time, which represents Csintentions for the future conduct of the works at the time it is published (q.v.). It

    illustrates the major sequencing and phasing requirements of the work. At inception it

    may be the same as the tender programme and as it is reviewed and updated it becomes

    the as-planned programme.

    mechanical and electrical (M&E).Design and/or work comprising mechanical and

    electrical engineering.

    method statement.A written description of the programme setting out the assumptions

    underlying the programme, the reasoning behind the approach to the various phases of

    construction and a listing of all the work encapsulated in the programme activities. It

    should contain the activity resource and productivity assumptions and hence justify the

    duration calculations.

    MC87.JCT Standard Form of Management Contract, 1987 Edition.

    MC98.JCT Standard Form of Management Contract, 1998 Edition.

    MF/1.Model Form 1, lump sum contract, 4th edition, 2000.

    Microsoft Project

    .A proprietary software package for creating and managing

    construction programmes, produced by Microsoft Corporation.

    milestone.A project event of zero duration that represents a checkpoint, a major

    accomplishment or a measurable goal. Sometimes referred to as representing a key date

    (q.v.). A key event selected for its importance in the project.29

    mitigation.Mitigation means making less severe or less serious. In connection with

    delay and disruption, it means minimising the period of, or cost of delay and disruption.Generally, it is the duty of the party whose legal rights have been infringed to act

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    17/27

    reasonably in the mitigation of damages when that party seeks to assert a legal right.

    Failure to mitigate can be a defence, or a partial defence to a claim.

    Monte Carlo simulation.An estimating and simulation technique based on the use of

    random numbers and probability statistics to investigate the likely effect of potential

    outcomes from an event being simulated. Monte Carlo simulation tends to be used

    widely from economics to nuclear physics and can be used to predict the likely pattern of

    activity durations having an overall effect on completion of a construction project.

    MPF.JCT Major Project Form 2003 Edition.

    MTC89.JCT Standard Form of Measured Term Contract, 1989 Edition (revised 1994).

    must finish constraint. A manually applied calendar date specifying when the activity

    must finish. It functions in the same way as a must start constraint (q.v.). Using the

    software in this way can restrict the flexibility of the network to react dynamically to

    change and can produce false criticality.

    must start constraint. A manually applied calendar date specifying when the activity

    must start. Most project management software products permit the user to specify that an

    activity must start on a specific date in spite of the construction logic, if any, that maydictate otherwise.

    MWA80.JCT Agreement for Minor Building Works, 1980 Edition (revised 1994).

    MWA98.JCT Agreement for Minor Building Works, 1998 Edition.

    MW2005.JCT Agreement for Minor Building Works, 2005 Edition.

    NEC.SeeNew Engineering Contract.

    NEC/SF99.NEC Short Form 1999. A contract intended for relatively small construction

    projects.

    negative total float.An expression sometimes used to describe the time by which the

    duration of an activity or path has to be reduced in order to permit a limiting imposed

    date to be achieved.30

    Negative total float only occurs when an activity on the criticalpath is behind programme. It is a programming concept, the manifestation of which is, of

    course, delay. neutral event. An event caused by acts for which the risk as to cost is with

    C, but where the risk as to time remains with D.

    New Engineering Contract (NEC).This suite of contracts was developed in the 1990s

    in the UK and is designed to be simpler and more versatile than the JCT and ICE forms.

    It includes the ECC and NEC/SF99 forms (q.v.).

    node.In an activity-on-arrow network (q.v.) the node is the point at which the activity

    arrows meet. In a activity-on-node network (q.v.) it is the activity itself which is

    represented by the node.

    nominated subcontractor.A contractor who is selected by the CA, often for specialist

    work within a main contract, and sometimes with design responsibilities. Where there

    are provisions for nomination, the CA may instruct C to enter into a subcontract with the

    nominated subcontractor. Although C generally remains responsible for the nominated

    subcontractors work and materials, it may not be responsible for the sufficiency of the

    nominate subcontractors design (which may be covered by a collateral warranty with

    D). Dependingupon the terms of the contract, C may also be relieved of liability for

    liquidated damages arising out of delay to completion caused by an nominated

    subcontractor.31

    non-compensable event.An American expression used to describe a non-reimbursable

    event, the financial consequences of which remain with C under the contract.

    non-excusable delay.An American expression used to describe a delay to a completiondate for which no extension of time (q.v.) may be granted.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    18/27

    NSC/4.JCT Standard Form of Subcontract for nominated subcontractors for use with

    JCT80 and JCT98.

    OCR.Seeoptical character recognition.

    Official Referee.Prior to the establishment of the Technology and Construction Court

    (q.v.) a specialist judge appointed by the High Court of England and Wales to hear

    construction-related matters.

    omissions.Work can be instructed to be omitted from a given work content or an

    accidental omission from the contract documents can be supplemented by an instruction

    to change by addition. Where a necessary specification design or work content is not

    included in Cs contract documents it is also said to be an omission from the contract

    works.

    open end.An open-ended activity is one that is not constrained by any logic controlling

    its completion. It is sometimes called a dangle or hanging activity. This type of

    activity has a start-only constraint and no successor that depends upon its completion. It

    is to be avoided as it can create false criticality.

    optical character recognition (OCR).A computerised method of connecting thepattern of dots in a scanned bitmap image into readable characters which can be searched

    and edited with word-processing software. The system by which a computer programme

    is able to convert, via a scanner printed text to a file that other software can read and

    understand as a text file.

    parallel delay to progress.A delay to progress involving at least two events both of

    which are at the risk of the same party. Contrast with concurrency (q.v.).32

    path.An activity or an unbroken sequence of activities in a project network.33

    PCC92.JCT Standard Form of Prime Cost Contract, 1992 Edition (revised April 1998).

    PCC98.JCT Standard Form of Prime Cost Contract, 1998 Edition.

    PDA.Seepersonal digital assistant.PDMSeeprecedence diagram (method).

    personal digital assistant (PDA).A small hand-held computer that can synchronise

    with an office-based computer by wire or wireless technology.

    PERT.Program Evaluation and Review Technique. A programming technique

    developed in the US between 1956 and 1958 in relation to the programming of the

    development of the Polaris missile. In this method of planning, time was estimated on

    three assumptions: pessimistic, optimistic and most likely and then

    mathematically assessed to determine the probable completion date. Originally, cost data

    was assumed to be constant and not reviewed although later developments of the PERT

    chart permitted costs to be reviewed on a similar basis. A PERT chart is a form of

    network diagram. It is a graphical depiction of task dependencies shown by connecting

    lines or arrows indicating the workflow between nodes. It is similar to a PDM diagram

    (q.v.) and there is often confusion between the two. Indeed, some software programs

    refer to their PDM diagram as a PERT diagram.34

    Pertmaster Project Risk. A project planning software package which allows project

    simulations to be conducted using the Monte Carlo method (q.v.).

    PFI.SeePrivate Finance Initiative.

    PIX Protocol.A standard, developed in the UK, that sets out a process for parties to a

    construction project to follow in an effort to ensure that electronic information is shared

    among them with optimal efficiency. The acronym derives from the phrase project

    information exchange.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    19/27

    plaintiff.Prior to CPR, the title given in litigation proceedings to the party asserting a

    right and upon whom the burden of proof rested in respect of any claim.

    planned completion date.The date for completion (q.v.).

    positive total float.A positive total float at any one time represents the period that any

    activity on the critical path may slip before it will affect the completion date. In Figure

    A1 above, the positive total float for all activities on the programme is x, activities 2, 3

    and 4 also have additional total float of T(2,3,4).

    PowerProject

    . A proprietary software package for creating and managing

    construction programmes, produced by ASTA Developments Ltd. Popular in the UK.

    PPC2000.ACA Project Partnering Contract 2000 Edition. This is the UKs first

    standard form contract based around a partnering philosophy. C is referred to as the

    Constructor, D as the Client and the CA as the Consultants.

    PPP.SeePublic-Private Partnership.

    PQS.Seeproject quantity surveyor.

    practical completion.The term used to describe the state of the works at the date the

    works are fit to be taken into beneficial use. It is generally the date when the obligationto insure passes from C to D and the date from which the latent defects liability period

    runs. This is the term used under the JCT family of contracts. Under the ICE forms and

    in FIDIC forms it is referred to as substantial completion (q.v.).

    precedence diagram.A form of notation for illustrating project workflow in which the

    activities are on the node and workflow is indicated by arrows connecting the nodes. It is

    sometimes called activity-on-node (q.v.) notation. Each activity is assigned a unique

    identifier and workflow direction is indicated by showing each of the activitys

    predecessors and their lag relationships. A number of project planning software products

    refer to this as a PERT diagram.35

    pre-contract documents.The documents that come into being before the parties agreeto proceed with the works.36

    predecessor.In a dependency relationship between two tasks, the predecessor is the task

    that must start or finish before the start or completion of the following task.

    preliminaries.The costs of running a site as a whole (rather than any particular zone of

    the site or any particular activities) together with the head office overheads (q.v.) and

    profit which the project as a whole has to finance. Amongst other things, these costs may

    include such things as site management, huts, safety precautions, job-related insurances,

    bonding costs, telephone, water and electricity costs, directors salaries, rent and capital

    finance. The essential characteristic of preliminaries is that they serve more than one

    activity, e.g. tower crane, skips, general site labour etc. However, in practice some

    resources that could be allocated to an activity, e.g. scaffolding for falsework, are

    included in the preliminaries section of Cs contract price because of its preferred

    method of pricing.37Thus it is essential that each case isinspected on its facts to

    determine which resources are affected by a delay or disruption irrespective of how C

    has priced that resource.

    Primavera Project Planner(P3).A proprietary software package for creating and

    managing construction programmes, produced by Primavera Corporation.

    Primavera Project Planner (Enterprise Edition)

    (P3E).A variant on Primavera

    Project Planner (q.v.) with enhanced capabilities.

    Private Finance Initiative (PFI).A form of project procurement in which C (usually a

    joint venture) is responsible for financing the project, design and construction ofbuilding works, and may also be responsible for design, selection and installation of

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    20/27

    plant and equipment, commissioning and also management of the end product for a fixed

    term. In this form of contract, D is usually a special purpose vehicle devised for the

    purpose of the project with whom the end beneficiary is in contract for the purpose of

    the project.

    Privy Council.Previously, the final court of appeal for many Commonwealth

    jurisdictions, including Australia, Canada and New Zealand. Nowadays, the final court

    of appeal for a few small Commonwealth jurisdictions.

    product data management.Process management systems normally have three broad

    functions: they manage what happens to the data when someone works on it; they

    manage the flow of data between people; and they keep track of all the events and

    movements of data during the history of a project. A PDM system is a database which

    captures all new and changed data as it is generated, maintaining a record of which

    version is in use, recalling it on demand and effectively keeping track of change.

    productivity.The efficiency of a process, measured by the ratio of input to output.

    programme.Commonly referred to in the US as a schedule. A chart of activities

    identifying their descriptions and start and finish dates. Depending upon the level ofsophistication it could be a bar chart (q.v.) at its lowest or at its highest a fully resourced

    CPM network (q.v.).

    project manager.The person responsible to D for managing communications between

    D and the design team. It is sometimes the case that the project manager is also

    responsible for communications between the design team and C although this is less

    common. In government contracts the CA is referred to as the project manager. This can

    cause significant problems in the drafting of appointment service contracts when there is

    also an architect responsible for the leading of the design team and administration of the

    construction contract.

    project quantity surveyor (PQS).A quantity surveyor (q.v.) appointed by D to adviseit on appropriate methods of procurement, techniques to be used to obtain and monitor

    appropriate cost information, the credibility of contractor bids and to advise during the

    course of the works on the valuation of the work in progress.

    prolongation.The period between the date C planned to cease funding the site related

    and head office overheads attributable to the project and the date it actually ceased to

    fund them.

    prolongation damages.The loss and expense that is directly related to and incurred

    during the period of time between the contract completion date or such earlier date for

    completion as may have been agreed between the parties, expressly or implicitly, and the

    prolonged completion date. They are costs which would not have been incurred but for

    the later completion date.

    Public-Private Partnership (PPP).An alternative term for Private Finance Initiative

    (PFI).

    publish.The term used by the Change Management Supplements to describe the process

    of electronic distribution to the designated parties of submittals in editable form in the

    software in which the submittals were created.

    QS.Seequantity surveyor.

    quantity surveyor (QS).The person generally responsible for advice on construction

    economics during the design phase, for preparation of bills of quantity and tendering

    documentation,valuation of work (but not certification) and agreeing (but not certifying)

    the final account

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    21/27

    quantum meruit.As much as has been earned. At law a claim for quantum meruit

    would be a claim for reasonable recompense calculated pro rata for work actually done.38

    reasonable skill and care.The standard of performance imposed on a professional who

    provides advice or a service. It is a matter for professional judgement whether in

    producing that advice or service the consultant has exercised all the skill and care that

    can reasonably be expected. Only if professional negligence can be proved is the

    consultant liable for the failure of the end product.

    reimbursable delay.Also known as a compensable delay. A delay to progress or the

    date for completion, for which the contract provides for C to be compensated in respect

    of any adverse financial effect flowing from the event. In so far as C is entitled not only

    to be paid for the cost of the work element in question, but also for any direct loss or

    expense which flows from the event, the event is said to be reimbursable or

    compensable.

    reimbursable event.An event for which D bears the risk as to cost and for which C is

    entitled to compensation for loss or expense suffered. It is usually described in the

    contract between the parties. It is an event that causes a reimbursable delay (q.v.).relevant event.The term used to describe an event that is specified to be at Ds risk

    under the JCT suite of contracts. Under the NEC forms of contract it is referred to as a

    compensation event and in the engineering forms it is referred to as a notified event.

    reply.In litigation, a form necessary in order to set out a claimants challenges to a

    defence (q.v.). Replies should not produce any new head of claim and should deal solely

    with the other sides statement of case in so far as it has not already been addressed.

    resource.A person, item of equipment, service or material used in accomplishing a

    project task.

    resource levelling.Expression used to describe the process of amending a schedule to

    reduce the variation between maximum and minimum values of resource requirements.39

    The process removes peaks, troughs and conflicts in resource demands by moving

    activities within their early and late dates and taking up float. Most project planning

    software offers an automated resource-levelling routine that will defer the performance

    of a task within the imposed logical constraints until the resources assigned to the tasks

    are available.

    resource monitoring.The process of determining activity duration, remaining duration,

    and percentage complete as a result of computing the actual resource usage against the

    planned resource usage. The resource requiring the greatest time to complete the

    specified amount of work on the activity will determine its duration.

    respondent.The title given in arbitration proceedings to the party disputing a right

    claimed.

    request for information (RFI).A formal request issued by C to the CA, usually for

    further particulars or for an explanation of information already provided. Some contracts

    specify a limited period of time within which the CA may respond before the delay in

    response becomes an event at Ds risk as to both time and cost.

    RFI.Seerequest for information.

    RIBA.SeeRoyal Institute of British Architects.

    RICS.SeeRoyal Institution of Chartered Surveyors.

    risk.Any potential future consequence; measured by reference to both the probability

    that it will materialise and the magnitude of those consequences if it does materialise.

    risk manager.The title given by the Change Management Supplements to Ds adviserin regard to the techniques to be used to prepare the programme and other time

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    22/27

    management information and to advise on its use in practice in the management of the

    time and cost effects of change (q.v.) contemporaneously throughout the construction

    phase. The role of the risk manager is not one normally played by any member of the

    design or construction teams under the standard forms of building contract but it is

    analogous to the role as to time that a PQS (q.v.) has to money.

    Royal Institute of British Architects (RIBA).The professional body that controls the

    education and conduct of architects in the UK.

    Royal Institution of Chartered Surveyors (RICS).The professional body that controls

    the education and conduct of both general practice and quantity surveyors in the UK.

    scanning.The process of converting a printed image into a digitised bit-map planned

    programmed image or computer file. A bit-map planned programmed image is defined

    by computer software as a pattern of dots.

    schedule.An American term used to describe the CPM (q.v.) network or other

    programme (q.v.).

    SCL Protocol.SCL Delay and Disruption Protocol (October 2002) published by the

    Society of Construction Law (UK).40Scott schedule.A form of pleading (q.v.) named after its inventor, His Honour Judge

    George Scott, QC, Official Referee 1920-1933. The Scott schedule is a peculiar device

    used in construction disputes in the UK to clarify claims and defences that involve

    complex factual allegations. The shape and content of a Scott schedule will depend upon

    the nature of the matters in dispute and the process of reasoning adopted by the analyst.

    However, a Scott schedule differs from other methods in that, if it is to be an effective

    clarification of the issues in dispute, it requires the active participation of both sides to

    the dispute in its drafting.

    sectional completion.Where a contract is split into separable parts, each of which has a

    defined scope of works and a commencement and completion date it is said to be asectional completion contract. In such an arrangement, liquidated damages (q.v.) and

    extensions of time (q.v.) apply to each individual section as well as the contract as a

    whole. Reference to completion may then apply to the completion of a section, key

    date (q.v.) or phase as well as the contract as a whole.

    sequence.The order in which activities will occur in relation to one another. This

    establishes the priority and dependencies between activities. Successor and predecessor

    relationships are developed in a network format which enables those involved in the

    project to visualise the workflow.

    set-off.A claim in a liquidated amount made by a defendant or respondent as a defence

    to a claim formulated on the basis of a right to reduce the amount of debt by the amount

    the creditor owes the debtor.41

    SI.Seesite instruction.

    SIA.SeeSingapore Institute of Architects.

    SIA80.Singapore Institute of Architects Lump Sum Contract, (1980) 1999 Revision.

    Notable primarily because it was drafted by prominent UK construction law

    commentator, Professor Ian Duncan Wallace QC.

    simulated as-built programme.The as-built programme that has been converted to a

    CPM programme for the purposes of statistical analysis by removing the actual start and

    completion dates of activities and replacing them with start and completion dates with

    logical links and lags to maintain the activities at the same dates as the as-built

    programme.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    23/27

    simulation.The processing of a project model programme to reproduce what would be

    expected to happen in the project, with different conditions and different starting points.

    Singapore Institute of Architects (SIA).The main professional association for

    architects in Singapore, which also produces standard form contracts for construction

    works.

    site instruction (SI).An instruction in writing issued by the CA to C on site, which

    constitutes an instruction under the contract.

    slack.Float (q.v.).

    slow progress.Progress falling behind programme due to failures which are at Cs risk.

    SMM.SeeStandard Method of Measurement.

    standard of proof.The degree to which something must be proved. In civil litigation

    and arbitration, the standard of proof required for most claims or counterclaims is proof

    on a balance of probabilities.

    Figure A11 - Start-to-start

    Standard Method of Measurement (SMM).A set of rules governing how quantities of

    materials in building projects are to be measured and intended for incorporation into

    building contracts which use bills of quantities. It is now in its 7th edition (1988), and is

    incorporated by reference into the JCT family of contracts.

    Standards Australia.The central standards authority in Australia, responsible for

    producing that countrys most widely used standard form construction contracts. See

    AS2124 and AS400.start-to-start.In the relationship shown in Figure A11, activity B cannot start until

    activity A has started or perhaps, more accurately, activity B can start at the same time as

    activity A but not before it.

    statement of case.The expression used in both litigation and in arbitration to describe a

    partys pleading, which comprises not just the arguments but also documentary evidence

    upon which the arguments rely. The content of a statement of case in litigation is

    governed by CPR.42In essence the statement of case must contain a concise statement of

    the nature of the claim, specify the remedy sought, give a statement of the value of the

    claim (where it is a claim for money) and set out any other matters required by a relevant

    practice direction. Contrary to the position in regard to statements of case under CPR,

    statement of case procedures under the JCT Arbitration Rules do not imply that

    anything not disputed is admitted, nor is there any firm rule that complaints that come to

    light during the proceedings may not be raised.

    statutory requirements.It is generally the CAs responsibility to make sure that the

    project design meets all applicable building legislation and regulatory requirements. In

    build-only forms of contract (as opposed to design and build) additional work or changes

    required to meet statutory or other regulatory requirements constitutes a variation.

    subcontract works.The subject matter of the construction contract between a

    subcontractor and C, the completion of which is the responsibility of the subcontractor,

    and which result in the execution of that part of the construction project. The contract

    agreement may be for the construction only, or for the assembly of a building or part of a

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    24/27

    building, or it may involvecivil engineering work in, over, or under ground, which is

    designed by others, or it could also include design by the subcontractor.

    sub-network.A fragnet (q.v.).

    sub-project.A group of activities usually comprising the work in connection with a

    definable section or zone of the works that is treated as a single task in a master

    programme. Computer programs use the concept of sub-projects to keep all the data

    relevant to a group of activities in a single project file that can be linked with other sub-

    projects for ease of management in complex projects/programmes.

    substantial completion.Practical completion (q.v.).

    successor.In a dependency relationship between two tasks, the successor is the task that

    cannot start or finish before the start or completion of the former task.

    Supreme Court.In the UK, a collective term for the English High Court, Court of

    Appeal and House of Lords. In Canadian provinces and Australian and US states,

    typically the highest court of first instance and/or a high appellate court. In the US

    Federal jurisdiction, the ultimate court of appeal.

    SureTrak

    .A simplified version of Primavera Project Planner (q.v.), designed forsmaller projects. Produced by Primavera Corporation.

    TCC.SeeTechnology and Construction Court.

    Technology and Construction Court (TCC).The UK court previously known as the

    Official Referees (q.v.) Court. It is the specialist court concerned with disputes arising

    out of construction or technology matters. It is part of the Queens Bench Division of the

    High Court.

    tender programme.The programme prepared by C in support of its tender. This may

    form part of the tender and become a representation of Cs intentions before the contract

    is agreed. Sometimes referred to as a bid programme. It is often produced from very

    little data.time impact analysis.Sometimes referred to as time slice analysis. It is a method of

    analysis of causation in which the impacts of events are calculated from the date upon

    which they occur in relation to the programme identified as representing Cs intent at

    that time.43

    total float.The overall time by which an activity may be delayed or extended without

    affecting the total project duration.44

    turnkey.A form of project procurement in which the contractor (usually a joint venture)

    is responsible for design and construction of building works, design, selection and

    installation of plant and equipment and commissioning ready for use.

    trade stacking.The undertaking of work of disparate trades in the same calendar period.

    Often attempted by logic changes to compress the work sequences.

    unabsorbed overheads.The accrual of unrecovered head office overheads (q.v.).

    updated programme.The as-planned programme (q.v.) with actual start dates, actual

    completion dates and percentage complete added against the activities progressed up

    until the data date (q.v.). The last updated programme should be the as-built programme

    (q.v.).

    variation.An express or implied instruction for change (q.v.) Under the standard forms

    of contract, D is deemed to have instructed variations in relation to some occurrences

    and has the express power to order changes specifically described. In this kind of

    change, D tells C to perform an activity in a way that differs from the original

    specifications of the contract in terms of quantity, quality, timing or method. Althoughvariations usually affect the content or quality of the work, they can affect a projects

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    25/27

    layout or space configuration and can also affect Csprogramme and/or sequence of

    work through changes in programmed deliveries of developer-supplied equipment or

    work. The Change Management Supplements also provide for variations to the resources

    to be used, the sequence and timing of work and also the requirements for programmes,

    method statements and progress records.

    variation order (VO).A formal instruction in writing issued by the CA to C to carry out

    a variation (q.v.).

    VO.Seevariation order.

    WBS.Seework breakdown structure.

    WC/87.JCT Works Contract Conditions (Works Contract/2), 1987 Edition.

    WC/98.JCT Works Contract Conditions (Works Contract/2) 1998 Edition.

    WCD81.JCT Standard Form of Building Contract With Contractors Design, 1981

    Edition (revised 1995).

    WCD98.JCT Standard Form of Building Contract With Contractors Design, 1998

    Edition.

    window.A period of time selected for the purposes of delay analysis in which all delayswhich affect the project within that period are taken together.

    work breakdown structure (WBS).A project-oriented family tree in which the

    elements or work are related to each other and to the project as a whole. It is a system for

    organising activities wherein each level consists of the subordinate divisions of the level

    beneath it. In other words, each level is a more detailed breakdown of the previous level.

    work package.A distinguishable unit of work at the level of performance, assignable to

    a single organisational element; it has programmed start and completion date (with

    interim milestones, where applicable) and may have budget cost or assigned value

    usually expressed in pounds, man-hours, or other measurable units. The duration of a

    work package is relatively short unless it is subdivided by discrete value milestones toassist in the monitoring of work performed and other work packages.

    works.The term used to describe the subject matter of the contract between D and C in

    all standard forms of contract.

    works contractor.The party required to carry out a limited portion of a construction

    contract, often limited to a single trade, such as brickwork, or a single element of the

    works, e.g. substructure. The label works contractor is used here to identify the party

    actually carrying out the works in both management contracting and construction

    management. In the US, under the arrangement for construction management the works

    contractor is known as a multiple prime contractor.

    zero activity.Sometimes referred to as a zero duration activity. An activity that has no

    allocated duration and is not designated as a milestone or as a flag. When an activity

    with zeroduration is added to a project, it displays both the start and finishing date, but

    they are both represented at the same point in time.45The purpose of zero-duration

    activities is generally to indicate a position in the construction logic for an activity to

    take place, the duration of which is not known at the time that the project is developed or

    which, whilst originally allowed for, has since been omitted. The process of

    demonstrating the effect of the omission of an activity by replacing its planned or actual

    duration with zero days duration is referred to as zeroing.

    zero free float constraint.A manually applied limitation on the free float (q.v.) that

    would otherwise be available between one activity and another. It can function in the

    same way as a must start constraint (q.v.) to interfere with the flexibility of the networkand may produce false criticality. However, it can also usefully be used in connection

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    26/27

    with lag to indicate dynamicallythe period which must lapse between the supply of

    information and the activity for which the information is required.

    zero total float constraint.A manually applied limitation on the total float (q.v.) that

    would otherwise be available between the last activity and the date for completion. It can

    function in the same way as a must start constraint (q.v.) to interfere with the flexibility

    of the network and may produce false criticality.

    1See Chapter 11, Mitigation and Acceleration.

    2BS 6079-2:2000 Part 2, 2.7.

    3BS 6079-2:2000 Part 2, 2.5.

    4See Chapter 14, The Analysis of Cause and Effect.

    5See Chapter 14, The Analysis of Cause and Effect.

    6See Appendix 4.

    7The Rt Hon the Lord Woolf MR, Access to Justice (1996, HMSO). The Final Report to the Lord Chancellor on

    the Civil Justice System in England and Wales.

    8SCL Protocol (Oct 2002), Appendix 1.

    9SCL Protocol (Oct 2002), Appendix 1.

    10The term generally used by the building contracts (q.v.).

    11The term generally used by the engineering contracts (q.v.).

    12See Appendix 2.

    13See Chapter 15, Float and Contingency.

    14See GC/Works/1 and GC/Works/1/98, clause 52.

    15BS 6079-2:2000 Part 2, 2.41 and SCL Protocol, Appendix 1.

    16SCL Protocol (Oct 2002), Appendix 1.

    17The Primavera suite of project management software.

    18SCL Protocol, Appendix 1.

    19Under the JCT suite of contracts.20Depending on the form of contract.

    21See clause 10 (alternative B) of GC/Works/1DB/98.

    22At Figure A1 above, that identified as F(6) is free float.

    23At Figure A1 above, that identified as T(2,3,4) is internal float and that identified as x is external float.

    24See Chapter 15, Float and Contingency.

    25At Figure A1 above, that identified as F(6) is free float.

    26See Chapter 19, Global Claims and Total Loss Claims.

    27Time Schedule TS3.

    28BS 6079-2:2000 Part 2, 2.83.

    29BS 6079-2:2000 Part 2, 2.92.

    30BS 6079-2:2000 Part 2, 2.94.

    31JCT80, JCT98 (Part 2) and NSC/4 contain some extremely complicated provisions for the administration of the

    selection and appointment of nominated subcontractors and any delay caused to and/or by them.

    32See also Chapter 16, Concurrency, Parallelism and Apportionment.

    33BS 6079-2:2000 Part 2, 2.105 and SCL Protocol (October 2002), Appendix 1.

    34For example, Microsoft Project

    .

    35See, for example, Primavera Project Planner (P3)

    , Primavera SureTrak

    and Microsoft Project

    .

    36See Appendix 2.

    37In practice it is generally the case that contractors include the costs of trade foremen, supervisors and

    coordinators in preliminaries with other administrative staff whereas they are actually trade specific.

    38Levine, MF, and Williams, JH, Restitutionary Quantum MeruitThe Crossroads (1992) 8 Const. LJ 244.

    39BS 6079-2:2000 Part 2, 2.144.

  • 7/26/2019 Pickavance - Appendix 1 Glossary of Terms and Definitions

    27/27

    40See Appendix 3.

    41See CPR Rule 16.6.

    42See CPR Part 16. Specific requirements of the particulars of claim are set out in CPR Rule 16.4.

    43See Chapter 14, The Analysis of Cause and Effect.

    44BS 6079-2:2000 Part 2, 2.175. At Figure A1 above, by the definitions adopted in Chapter 15, that identified as

    T(2,3,4) is internal total float and that identified as x is external float.

    45See Some software illustrates the finish date as occurring before the start date when a duration of zero is applied, e.g. Primavera SureTrak

    .