Phone Fax: rirr,environmentclearance.nic.in/writereaddata/EIA/0808201640...and Dist: Devbhumi...
Transcript of Phone Fax: rirr,environmentclearance.nic.in/writereaddata/EIA/0808201640...and Dist: Devbhumi...
Phone :0286 -2244288Tele Fax: 0286 -2244288
+BauxiteSuppliers& Mines Owners
Mayur Pankh Society, Opp. Circuit Villa, Chopati Road, Porbandar - 360 575 (Gujarat)
rirr,No. : PPIVI/MoEFC CIEIA/2 016-17 I
To,
The Director, (IA-II)Expert Appraisal Committee (Non Coal Mining)Ministry of Environment, Forest and Climate Change
Indira P ary av ar an Bhavan, Vayu Wing,Jor Bagh Road,
New Delhi - 110 003
Date:06.08.2016
Project No.: J-l101 51 120/2013-IA.tr (M)
Sub: Regarding Environmental Clearance for Virpur (Gunawali) Bauxite Mine (55.2520 ha)
of iVIs. Smt. Pushpaben Prabhudas Makhecha, Village: Virpur (Gunawali), Tehsil:
Kalyanpur, District: Devbhumi Dwarka, State: Gujarat.
Ref.: 1. ToR approved vide letter no. J-11015/26412013-LA.II (I\'f) dtd04.02.2015
2. Amended ToR approved vide letter no. J-110151120t2013-IA.tr (I\[) dtd 04.12.2015
Dear Sir,
IWs. Smt. Pushpaben Prabhudas Makhecha, has applied for EC for Virpur (Gunawali), Bauxite Mine(55.2520 ha), Village: Virpur (Gunawali), Tehsil: Kalyanpur, District: Devbhumi Dwarka, State: Gujarat
for Production of Bauxite 1,51,875 TPA. IWs. Smt. Pushpaben Prabhudas Makhecha hereby submitting
EIA/EMP Report incorporating general and specific points of Terms of Reference, along with the
necessary Annexures and documents & Pubic hearing Minutes, (Hard & Soft Copies)
We request MoEF&CC to kindly process the application to grant environmental clearance to the Project
based on the above documents.
Thanking you,Yours faithfully,For NOs. Smt. Pushpaben Prabhudas Makhecha(Virpur (Gunawali) Bauxite Mine)
Encl: Final EIA report with CD
Environment Consultant
PROJECT PROPONENT
EXECUTIVE SUMMARYOF
ENVIRONMENTAL IMPACT ASSESSMENT
FOR PROPOSEDVIRPUR (GUNAWALI) BAUXITE MINE
ATVIRPUR VILLAGE, TALUKA KALYANPUR,
DISTRICT, DEVBHUMI DWARKA (JAMNAGAR)Area: 55.2520 Ha (Mine working area 37.167)
Production Capacity 1,51,875 TPA
Bharatbhai Makhecha and Naresh Makhecha LegalHairs of
Smt, Late Pushpa Ben P. MakhechaAddress, Opp Circuit Villa, Chopati Road, Porbandar
(Gujarat)
GRASS ROOTS RESEARCH & CREATION INDIA (P) LTD.
(An ISO 9001:2008, 14001:2004 & OHSAS 18001:2007 Certified Co. Accredited by QCI/NABET)F-374,375, Sector-63, Noida, U.P
Ph.: 0120-4044630 Tele fax: 0120-2406519Email: [email protected], [email protected]
Website: http://www.grc-india.com
M/s. Smt PUSHPABEN PRABHUDAS MAKHECHA
Executive summary for Virpur (Gunawali) Bauxite Minefor Production Capacity 151875 TPA Bauxite ROM
in Lease Area 55.2520 Ha (Mine working area 37.1670 ha)at Survey No. 110/P, Virpur Village, Kalyanpur Taluka,
District Devbhumi Dwarka, Gujarat
EXECUTIVE SUMMARY
Virpur (Gunawali) Bauxite Mine Executive Summary
EXECUTIVE SUMMARY
1.0 INTRODUCTION
The Mining Lease was granted over an area of 55.2520 ha in Village: Virpur, Taluka: Kalyanpur,and Dist: Devbhumi Dwarka, in favor of Late Smt, Pushpaben Prabhudas Makhecha, on dated01‐02‐1992 and executed on 27.06.1994 for a period 20 years. Lessee has applied for renewalon 16.06.2012 and lease is valid as per new MMDR 2015. The lessee Smt. Pushpaben PrabhudasMakhecha expired on 5.4.2012. Modified Mine Plan has been approved by IBM vide letter682(23) (M.P. – 522/2009‐II MCCM (N) Udaipur dated 03.09.2015. As per Modified Mining Planproduction capacity is 1, 51,875 TPA with mining working area 37.1670 ha as leaving the fallingin the Eco Sensitive Zone (ESZ) as per the notification issued by MOEF&CC dated 22.08.2013.The estimated project cost is Rs. 23.98 Lakh.
The Environmental Impact Assessment (EIA) study report is prepared for obtainingEnvironmental Clearance (EC) from the Ministry of Environment and Forests (MoEF),Government of India, New Delhi for the proposed Virpur (Gunawali) Bauxite mine. It is classifiedas “CATEGORY‐A”, as per the EIA notification dtd 14th September 2006 & its amendmentsthereof.
2.0 PROJECT DESCRIPTION
Location: The mining area is located in the Village: Virpur, Taluka: Kalyanpur, Devbhumi Dwarka
District of Gujarat state.
Toposheet Details
Latitude : 22° 15' 38.7" to 22° 16' 17" N.
Longitude : 69° 17' 43.6" to 69° 18' 25.5” E
Area & production: The total Mining Lease area is 55.2520 ha with mine working area
37.1670ha.
Toposheet No. Area ( ha) Mine Working Area (ha)
Restricted (41F7) 55.2520 37.1670
Total 55.2520 37.1670
1
Virpur (Gunawali) Bauxite Mine Executive Summary
Modified Mining Plan production capacity is revised as 1,51,875 TPA with mining working area
37.1670 ha excluding block falling in the Eco Sensitive Zone (ESZ ) as per the notification issued
by MOEF&CC dated 22.08.2013. Estimated cost of the project is Rs. 23.98 Lakh.
2.1 Salient Features of Project :Name of the applicant Smt Pushpaben Prabhudas Makhecha (Late).
(Leagal hairs Shri. Bharatbhai Makhecha and
Shri Naresh bhai Makhecha)
Name & Address of Lessee M/s. Smt. Pushpaben Prabhudas Makhecha
Mayurpark Society, Opp Circuit Villa
Chopati Road, Porbandar (Gujarat)
Phone No: 0286‐22444288
Name of Mine Virpur( Gunawali) Bauxite mine
Village Virpur
Taluka Kalyanpur
District & State Devbhumi Dwarka, Gujarat
Latitude 22° 15' 38.7" to 22° 16' 17" N.
Longitude 69° 17' 43.6" to 69° 18' 25.5” E
Elevation 10.53m RL to 26m RL
Nearest town Bhatia (about 20 Km SSE)
Reserved / Protected Forest Nil
Mineral Bauxite
Area (ha) 55.2520 ha
Mine working area (ha) 37.1670 ha
No. of Working days 301
Mineable Reserve 6,29,323 tonnes
Total Geological Reserve 36,80,826 tonnes
Source of Water Near villages (Dug well)
Life of mine 5 years (as per as present level of exploration)
2
Virpur (Gunawali) Bauxite Mine Executive Summary
Method of mining Semi – mechanized Opencast
Postal Address M/s. Smt. Pushpaben Prabhudas Makhecha
Mayurpark Society, Opp Circuit Villa
Chopati Road, Porbandar (Gujarat)
Phone No: 0286‐22444288
Period of Lease (Yrs) 20 Years
Seismic Zone Zone – IV as per IS‐ 1893(part‐1)‐2002
Nearest Railway Station Bhopalka Railway Station about 17 km in SSE
direction from the site.
Near Airport Porbandar Airport about 75 km in SSE dirction.
Ecological Sensitive Areas Marine National Park is about 4.12 km in NW
(Wildlife sanctuaries & direction from project site.
National Parks) Marine Sanctuary is about 1 km in NW
direction from mine working boundary.
Gaga Bird Sanctuary is about 16.55 km in SW
direction from project site.
Nearest Road SH – 25 about 10km away in South direction
from the site. A metaled road passing near to
the sight, leads to Ran.
2.2 Basic Requirements for the Project :
S. No. Requirements Area/Quantity/No. Source
1 Land 55.2520 ha Renewal Mine
2 Water 8 KLD From Nearby villages
3 Manpower 48 nos. Nearby villages
3
Virpur (Gunawali) Bauxite Mine Executive Summary
2.3 Details of Mining:
Sr. Parameter DescriptionNo.
1 Total ML area 55.2520 ha
2 Production level Bauxite 1,51,875 TPA
3. Mineable Reserve 6,29,323 Tonnes
4. Total Geological Reserves 36,80,826 Tonnes
5 Top Soil (Cum) 16149 (Cum)
4 Mine technology Open Cast Semi Mechanized Method
5 Name of the lessee Smt. Pushpaben Prabhudas Makhecha (Late)
(Bharatbhai Makhecha and Shri Naresh bhai
Makhecha are Legal Hairs)
2.4 Drilling & Blasting:
Some bauxite horizon being of compact formation, require drilling and blasting in the 30% of
bauxite zone. For this purpose 2.00m deep hole will be drilled by jack hammer and will be
blasted by the 25mm dia and 250mm long explosive available in the region. The spacing and
burden will be kept as 1.0 m.
The broad parameters are as under:
1. Spacing 1.5 M
2. Burden 1.5M
3. Depth 2.0M
4. Diameter of hole 30MM
5. Explosive per wise hole 1.6 Kg
6. Power Factor 7 MT/Kg
7. No of holes blasted per round 10holes as per round
8. Maximum hole blasted per day 10holes in one round only
4
Virpur (Gunawali) Bauxite Mine Executive Summary
The blasted material from the bauxite horizon will be broken and sorted manually. About 25
holes will be required daily and 30 kg, Gelatin, 25 detonator and 62.5 m fuse coil will be
required daily.
The blasting will be done by qualified blaster. The explosive will be stored at magazine of M/s
Prabhudas Vithaldas situated at Block A of A Virpur Kenedy bauxite. The explosive will be
transported from the magazine to the mine working area.
Precautions to be observed during drilling & blasting:
During drilling, for the safety of the workers, ear muffs will be provided to the workers to
protect them from the effect of noise created by blasting. Prior to blasting, mine workers will
be posted at appropriate distances of all safety points around the lease area to prevent the
vehicles as well as pedestrians entering the area.
Loading Equipment:
S.No Type Nos. Bucket Make Motive HP
capacity in Power
M3
1 Excavator One 1.0M3 Tata Diesel 250
Haulage and transport equipment
1. Haulage with in the mining lease hold : ‐
S.No Type Nos. Size Make Motive HP
capacity in Power
tonns
1 Tippers Two 10 MT Tata ‐‐ ‐‐
Drilling Machine: ‐
S.No Type Nos. Diameter Make Motive HP
of hole in Power
MM
1 Jack hummar (RH One 32MM Atlas ‐ ‐
5
Virpur (Gunawali) Bauxite Mine Executive Summary
658/42) Capco
2 Compressor One 100CFT/M Atlas ‐ ‐
Capco
3 Water Pump One ‐ ‐ ‐ 5
2.6 Use of Mineral
The bauxite produced in the mining lease falls under low category. The low grade only.
The low category of bauxite is used in the manufactures of cement which is exported to MiddleEast countries. Physical and chemical specification of low grade bauxite used in cementmanufacture is as under:
AL2O3 – upto 30% .
SiO2 – 10 % (Max).
2.7 Land Use Pattern (Area in Ha) as per the IBM Approved Modified Minig Plan:
Area put on use at Area put on use up Area put on useS.No. Head to end of modified
start of the scheme up to life of minemining plan period
1 Area under mining 19.4402 23.4774 24.3954
2 Storage soil 0 0 0
3 OB dump 0 0 0
4 Mineral storage 0.0500 0.0500 0.0500
5 Infrastructure 0.0050 0.0050 0.0050
6 Green belt 0.0100 0.3100 0.2000
7 Road 0.0460 0.0460 0.5000
8 Township area 0 0 0
6
Virpur (Gunawali) Bauxite Mine Executive Summary
9 Railway 0 0 0
10 Tailing pond 0 0 0
11 Effluent treatment plant 0 0 0
12 Mineral separation 0 0 0
13 Sub grade 0 0 0
Grand Total 19.5512 23.8884 25.3354
3.0 DESCRIPTION OF THE ENVIRONMENT:
The baseline environment quality was carried out over a radial distance of 10 km around the
mine during summer season of March 2015 to May 2015.
3.1 Meteorology
The Summarized Meteorological Data for the Monitoring Period March 2015 to May 2015 is
given below:
Wind Speed (km/h) Temperature (°C)Rainfall
Relative Humidity (%)
MonthMax Avg Calm Max Min Avg (mm) Max Min Avg
(%)
March18.2 8.9 25 34.8 19.1 46.9 0.1 63.7 15.1 37
2015
April24 13.3 21 40.1 24.4 32.3 0.0 73.8 12 40.2
2015
May26.5 16.2 19 42.2 25.8 34.0 0.19 79.4 11.74 44.7
2015
7
Virpur (Gunawali) Bauxite Mine Executive Summary
3.2 Ambient Air Quality:
To assess the ambient air quality level, 7 monitoring stations were set up. Ambient air quality
monitoring was carried out twice a week with a frequency of 24 hours for 12 weeks. The results
when compared with National Ambient Air Quality Standards (NAAQS) of Central
Pollution Control Board (CPCB) for "Residential and Rural Areas" show that the average values
of ambient air quality parameters are well within the stipulated limit.
The minimum and maximum concentration of PM10 recorded within the study area was 50.5µg/m3 to 139.4 µg/m3 with the 98th percentile ranging between 63.3 µg/m3 to 130.7 µg/m3.
The minimum and maximum concentration of SO2 recorded within the study area was <5 to 6.8µg/m3 with the 98th percentile ranging between 6.2 µg/m3 to 6.8 µg/m3.
The minimum and maximum concentration of NOx recorded within the study area was 6.5µg/m3 to 15.3 µg/m3 with the 98th percentile ranging between 12.7 µg/m3 to 15.1 µg/m3.
3.3 Noise Levels:
The values of noise observed in some of the areas are primarily owing to vehicular traffic andother anthropogenic activities. Assessment of night time Leq (Ln) varies from 38.1 to 54.6 dB(A) and the daytime Leq (Ld) varies from 46.3 to 68.4 dB (A) within the study area. The status ofnoise quality within the 10 km zone of the study area is, therefore, within the MoEF standards.
3.4 Water Quality:
Selected water quality parameters for water resource of the study area have been used for
describing the water environment and assessing the impacts. Seven ground water samples
were collected in the study area to assess the water quality. Water samples were also drawn
from the hand pumps and open wells and two surface water samples were drawn from the
natural springs being used by the villagers for domestic needs. For surface water quality,
comparing the values of pH, DO, BOD and total coliforms with ‘Use based classification of
surface waters’ published by Central Pollution Control Board; it can be seen that all the
analyzed surface waters can be compared with class “C” and can be used as drinking water
sources after conventional treatment and disinfection.
8
Virpur (Gunawali) Bauxite Mine Executive Summary
3.5 Soil Characteristics:
The soil samples were collected in the month of May 2015. Soil samples were collected from 7
locations to assess the existing soil conditions representing various land use conditions and
geological features. Each of these locations was identified randomly. Soil sample was collected
from 30 cm below the surface. pH of the soil were found to be Neutral (7.46 to 7.86 ). Electrical
conductivity (EC) is a measure of the soluble salts and ionic activity in the soil, and ranged from
241‐432 µmhos/cm.
3.6 Biological Environment:There are few forest patches and reserved and protected forests in study area. Marine National
Park/Marine Sanctuary is present within 5 Km of the study area. Conservation plan of Schedule
–I species found in study and has been prepared.
3.7 Socio economic environment
The impact of mining activity in the area is positive on the socio-economic environment of the
region. Virpur (Gunawali) Bauxite Mine is providing employment to local population and
preference will be given to the local people for man power.
4.0 Post Project Monitoring Program
The frequency of post – project monitoring program is given below.
SI.Description Frequency of Monitoring
No.
1 Ambient Air Quality Quarterly/Half yearly
2 Meteorological data Daily
3 Noise Level Monitoring Half yearly
4 Water Level & Quality Quarterly/Half yearly
5 Soil Quality Yearly
6 Monitoring of Agricultural crops Yearly
9
Virpur (Gunawali) Bauxite Mine Executive Summary
5.0 Additional Studies:
The Additional Studies conducted are Risk Assessment & Disaster Management / Hazard
Management & Occupational Health & Safety.
5.1 Risk Assessment and Disaster Management Plan
The complete mining operation will be carried out under the management control and
direction of a qualified mine manager with Certificate of competency to manage a
metalliferous mine granted by the Directorate General of Mines Safety (DGMS),
Dhanbad. The DGMS have been regularly issuing standing orders, model standing orders
and circulars to be followed by the mine management in case of disaster, if any.
Moreover, mining staff will be sent to refresher courses from time to time to keep them
alert.
5.2 Disaster Management Plan
Emergency preparedness is an important aspect in the planning of Disaster
Management. Personnel would be trained suitably and prepared mentally and physically
in emergency response through carefully planned, simulated procedures. Similarly, the
key personnel and essential personnel shall be trained in the operations.
6.0 PUBLIC CONSULTATION
6.1 Public Hearing
The draft EIA is prepared and submitted to Pollution Control Board for Public Hearing. Thepublic hearing for the Virpur (Gunawali) Bauxite mine for 1, 51,875 TPA capacities by semimechanized open cast method in Virpur (Gunawali) village, Kalyanpur Taluka, DevbhumiDwarka District, Gujarat was conducted on 29.03.2016, as per the Environment ImpactAssessment Notification dated 14th September 2006. The public hearing proceedings &related papers are attached as Annexure- XIII.
7.0 Project Benefits:
The project will prove beneficial to the people as the lessee has already agreed to provide
infrastructural facilities to the villagers like Educational facilities, Medical facilities,
10
Virpur (Gunawali) Bauxite Mine Executive Summary
Transportation facilities, water supply etc. which will improve the socio-economic environment
of the area.
8.0 Environmental Management Plan
The mining activities involve, dozing, excavation, loading, haulage and transportation of mined
minerals. These activities lead to generation of air borne dust, which can cause air pollution in
and around the mining lease area, if appropriate control measures are not taken. Similarly mining
causes Land Degradation, Noise and Water Pollution etc. in the area.
In order to minimize impacts of mining on different environmental parameters and to keep air
and water quality within prescribed limits of CPCB, a rapid Environmental Management Plan
(EMP) is prepared to strictly follow it. This helps in resolving all environmental and ecological
issues due to mining in the area. The environmental management plan includes all measures and
safety precautions necessary for safe mining along with rehabilitation measures for mined out
areas
8.1 Green Belt/Plantation
0.2000 ha area will be developed under as green belt.
8.2 Budgets for Environmental Protection
SI. No. Measures Capital cost Annual recurring cost(in Rs.) (in Rs.)
Proposed Proposed1 Pollution Control
i) Dust Suppression
ii) Garland drain & ground 25,000
dump 25,000 50,000
2 Pollution Monitoring
i) Air pollution 25,000 30,000
ii) Water pollution 25,000 30,000
11
Virpur (Gunawali) Bauxite Mine Executive Summary
3 Reclamation & 25,000 30,000Rehabilitation
Green Belt
4 Others (Environmental 50,000 30,000study, Statutory compliance,etc.)
Total 1,75,000 1,80,000
8.3 Conclusion
Based on the EIA study it is observed that there will be generate minor dust emission, which will
be controlled by sprinkling of water and plantation. There will be an insignificant impact on
ambient environment and ecology due to the mining activities moreover the mining operation
will lead to direct and indirect employment generation in the area. Green belt development
around the area will also be taken up as an effective pollution mitigative technique, as well as to
control the pollutants released from the premises of the Mine.
Monitoring program will be followed till the mining operations continue. Around Rs 1.75 lakhs
as capital cost and Rs 1.8 lakhs as recurring budget for environmental protection have been
formulated to achieve the environmental quality as desired. Hence, it can be summarized that the
development of the mine will have a positive impact on the socio-economic of the area and lead
to sustainable development of the region.
The study area is still lacking in education, health, housing, water, electricity etc. It is expected
that same will improve to a great extent due to proposed mining project and associated industrial
and business activities. Proposed activities and expenses on Corporate Social Responsibility will
be as per CSR Mandate of the Government.
*****
12
Environment Consultant
PROJECT PROPONENT
ENVIRONMENTAL IMPACT ASSESSMENT&
ENVIRONMENTAL MANAGEMENT PLAN
FOR PROPOSEDVIRPUR (GUNAWALI) BAUXITE MINE
ATVIRPUR VILLAGE, TALUKA KALYANPUR,
DISTRICT, DEVBHUMI DWARKA (JAMNAGAR)Area: 55.2520 Ha (Mine working area 37.167)
Production Capacity 1,51,875 TPA
Bharatbhai Makhecha and Naresh Makhecha LegalHairs of
M/s Smt Pushpaben Prabhudas MakhechaAddress, Opp Circuit Villa, Chopati Road, Porbandar
(Gujarat)
FINAL EIA REPORT
GRASS ROOTS RESEARCH & CREATION INDIA (P) LTD.
(An ISO 9001:2008, 14001:2004 & OHSAS 18001:2007 Certified Co. Accredited by QCI/NABET)F-374,375, Sector-63, Noida, U.P
Ph.: 0120-4044630 Tele fax: 0120-2406519Email: [email protected], [email protected]
Website: http://www.grc-india.com
TABLE OF CONTENTSSECTION TITLE PAGE
NO.
CHAPTER 1- INTRODUCTION1.0 Introduction I/2
1.1 Purpose of the report I/2
1.2 Identification of project & project proponent I/2
1.3 Brief description of project I/4
1.4 Scope of the study I/12
CHAPTER 2- PROJECT DESCRIPTION2.0 Project Description II/2
2.1 Type of Project II/2
2.2 Need of the Project II/2
2.3 Status of Regulatory Clearances of the Project II/2
2.4 Size/Magnitude of Operation II/3
2.5 Land Requirement II/3
2.6 Physiography II/5
2.7 Geology II/7
2.8 Mineable reserve II/15
2.9 Anticipated life of the mine for Bauxite mining II/16
2.10 Conceptual Mining Plan: II/18
2.11 Post mining land use II/20
2.12 Generation of Waste II/20
2.13 Drilling & Blasting II/23
2.14 Water Requirement II/14
2.15 Power Supply II/25
2.16 Proposed Manpower II/25
2.17 Characteristics of Ore II/25
2.18 Use of Mineral II/26
CHAPTER 3- DESCRIPTION OF ENVIRONMENT
3.0 Description of the environmental III/2
3.1 Baseline environmental status III/2
3.2 Study area III/2
3.3 Study period III/2
3.4 Meteorology/Approach III/2
3.5 Meteorological Conditions III/3
3.6 Air environment III/5
3.7 Noise levels III/11
3.8 Water environment III/14
3.9 Soil characteristics III/35
3.10 Land use/land cover mapping III/39
3.11 Traffic analysis III/41
3.12 Biological environment III/44
CHAPTER 4- ANTICIPATED ENVIRONMENTAL IMPACTSAND MITIGATION MEASURES
4.1 Details of the Investigated Environmental Impacts IV/2
4.2 Air environmental IV/4
4.3 Water environment IV/9
4.4 Impact on Land Use IV/12
4.5 Impacts due to disposal of Overburden IV/17
4.6 Impact on Air Quality IV/18
4.7 Proposed Mitigation Measures for Dust Suppression IV/20
4.8 Noise environment IV/21
4.9 Impact due to Ground Vibrations IV/25
4.10 Greenbelt and Plantation IV/29
4.11 Biological Environment IV/30
4.12 Occupational Health (Impacts and Mitigation Measures) IV/32
CHAPTER 5- ANALYSIS OF ALTERNATIVES (TECHNOLOGY &SITE)
5.1 Analysis of alternatives technology V/2
5.2 Analysis of alternative site V/2
CHAPTER 6- ENVIRONMENTAL MONITROING PROGRAM6.1 Introduction VI/2
6.2 Implementation Schedule of Mitigation Measures VI/2
6.3 Environment Monitoring Programme VI/5
6.4 Reporting Schedules VI/5
6.5 Cost Estimates VI/8
6.6 Corporate Environmental Policy VI/9
CHAPTER 7- ADDITIONAL STUDIES7.0 Public Consultation VII/2
7.1Risk Assessment & Occupational Health & Safety and Disaster
Management
VII/12
7.2 Occupational Health – Proposal for Surveillance VII/14
7.3 Plan of evaluation of health of workers VII/10
7.4 Disaster Management PlanVII/21
7.5 Major Hazards and their Control VII/23
7.6 Disaster Preventive Measures VII/25
7.7 The responsibility of the members of the Disaster Control Team VII/31
7.8 Disaster due to Natural Calamity and External Factors VII/34
7.9 Conclusion VII/35
7.10 Contact Details VII/39
7.11Socio-Economic Impact Assessment of Virpur Gunawali Bauxite
Mining Project, Jamnagar, Gujarat
VII/39
CHAPTER 8- PROJECT BENEFITS8.0 Project Benefits VIII/2
8.1 Improvement in the Physical Infrastructure VIII/2
8.2 Improvement in the Social Infrastructure VIII/2
8.3 Employment Potential VIII/2
CHAPTER 9- PROJECT BENEFITS
9.0 Environment management plan IX/2
9.1 Air quality management IX/2
9.2 Noise pollution control IX/3
9.3 Water quality management IX/4
9.4 Waste management IX/4
9.5 Greenbelt and plantation IX/5
9.6 Biological management measures IX/6
9.7 Occupational hazards and safety IX/9
9.8 Socio economic measures IX/11
9.9 Policy and action plan on social responsibility IX/11
CHAPTER-10 SUMMARY & CONCLUSION10.0 Introduction X/2
10.1 Environmental clearance X/2
10.2 Project description X/4
10.3 Baseline environmental status X/6
10.4 Cost estimates X/9
10.5 Additional studies X/10
10.6 Public consultation X/10
10.7 Project benefits X/10
10.8 Conclusions X/11
CHAPTER-11 DISCLOSURE OF CONSULTANT
LIST OF FIGURE
TABLENO
TITLE PAGENO.
1.1Geographical Location of the Project
II/7
1.2Corner co – ordinates of the mine lease area
II/8
1.3Study Area Map of the Project
II/9
1.4Photographs of the Mine Lease Area
II/10
2.1Surface Plan of the mine lease area
II/6
2.2Geological Plan of the mine lease area
II/14
2.3Geological Section of the mine lease area
II/17
2.4Year wise development Plan
II/18
2.5Conceptual Plan & Section
II/22
3.1The wind-rose diagram (Mar – April, 2015)
III/4
3.2Ambient Air Monitoring Locations
III/9
3.3Noise monitoring stations
III/12
3.4Water Quality Monitoring Location
III/16
3.5Soil Sample Collection Points
III/36
3.6Land use delineation of 10 km radius area
III/40
3.7Transportation Route Map
III/43
4.1Drainage map
III/3
4.2Wind Rose Diagram
IV/7
4.3Isopleths for fugitive dusts (Area source + Line Source)
IV/9
4.4Environmental Management Plan
IV/16
6.1Organization Structure for Environment Management
VI/4
7.1Occupational Health – Policy and Methods
VII/14
7.2OHS System
VII /15
7.3Identification of hazards in open cast mine
VII/20
7.4On – site emergency plan
VII/37
7.5Off – site emergency plan
VII/38
LIST OF TABLE
FIGURENO
TITLE PAGENO.
1.1 Status of the Mining lease I/3
1.2Status of the Environmental Clearance
I/3
1.3 Year wise Production of Virpur (Gunawali) Bauxite mine I/4
1.4Cost details of the project
I/5
1.5 Details of environmental setting I/5
1.6TOR Compliance
I/13
2.1Details of the project
II/2
2.2Details of the mine
II/2
2.3Description of the mine
II/3
2.4Land ownership details of the mine lease
II/4
2.5Mineable reserve details
II/15
2.6Water Requirement
III/25
3.1Summarized Project site Meteorological Data for Post-Monsoon
III/5
3.2Location of Ambient Air Quality Monitoring Stations
III/6
3.3Ambient Air Quality in the Study Area PM10
III/7
3.4Ambient Air Quality in the Study Area SO2
III/7
3.5Ambient Air Quality in the Study Area NOx
III/8
3.6Noise Level Monitoring Stations in the Study Area
III/13
3.7Hourly Leq Noise Level in the Study Area (March 2015 to May 2015)
III/13
3.8 Ambient Quality Standards in respect of Noise III/14
3.9Location of Water Sampling Sites
III/15
3.10 Surface water Sample Analysis Results during March -2015 III/18
3.11Surface water Sample Analysis Results during April -2015
III/19
3.12Surface water Sample Analysis Results during May -2015
III/22
3.13Groundwater Sample Analysis Results during March -2015
III/24
3.14Groundwater Sample Analysis Results during April -2015
III/27
3.15Groundwater Sample Analysis Results during May -2015
III/30
3.16Water Quality Criteria as per Central Pollution Control Board
III/33
3.17 Soil Sample Collection Points III/35
3.18Phyisco-Chemical Properties of Soil
III/37
3.19The land use of the study area
III/39
3.20Existing Traffic Scenario & LOS
III/41
3.21Additional Traffic Scenario & LOS due to proposed project
III/41
3.22V/C Ratio & LOS
III/42
4.1Emission Factors
IV/6
4.2PM10 Contribution at the Nearby Locations
IV/8
4.3Stage – wise land use pattern
IV/13
4.4Sources of pollutants
IV/18
4.5Proposed Traffic due to the project
IV/19
4.6Noise Exposure levels & its Effects
IV/23
4.7Typical Noise Generation due to Excavation / Loading/ Transportation
Equipment IV/24
4.8Permissible peak Particle velocity (mm/s)
IV/26
4.9Species Suggested for Plantation
IV/30
4.10Proposed Periodical check up for employees
IV/333
4.11Possible pollutants from different operations
IV/33
4.12Budget for Occupational Health
IV/34
6.1Implementation Schedule
VI/2
6.2Post Project monitoring programme
VI/6
6.3Cost of Environmental Protection measures
VI/8
7.0Public Hearing Details
VII/2
7.1Medical Examination Schedule
VII/207.2 List of Fire Extinguishers Required at Different Locations
VII/267.3 Contact Details
VII/399.1 Afforestation Scheduled
IX/59.2 Species recommended for greenbelt development
IX/79.3 Key Suggestive measures under EMP
IX/89.4 Budget for Environmental Protection
IX/109.5 Fund for the various CSR Activities
IX/13
10.1Mineable reserve details
X/5
10.2Bauxite production
X/5
10.3Cost of Environmental Protection Measures
X/9
LIST OF ANNEXURES
NO. ANNEXURE
Annexure - I Lease documents
Annexure – II a Renewal Application Receipt
Annexure – II b PPM (legal heirs notarized )
Annexure - III Death Certificate
Annexure – IV a Terms of Reference
Annexure – IV b PPM Amendment of ToR
Annexure - V Environmental Policy
Annexure- VI Forest Distance certificate Letter
Annexure- VII An authenticated list of flora and fauna
Annexure- VIII
Acknowledgement Letter with Conservation
Plan
Annexure - IX Authenticated CRZ map & Report
Annexure - X Approved mine plan.
Annexure – XI (22.08.2013 MoEF & CC ESZ NOTIFICATION)Annexure - XII CGWA Guidline for Taluka, Gujarat
ANNEXURE – XIII
(PUBLIC HEARING PROCCEDING)
ANNEXURE –XIV (10 year earthquake data Gujarat Year)
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-1
CHAPTER-1
INTRODUCTION
INDEX
SI.NO CONTENT PAGE NO
1.0 INTRODUCTION I/2
1.1 PURPOSE OF THE REPORT I/2
1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT I/2
1.3 BRIEF DESCRIPTION OF PROJECT I/4
1.4 SCOPE OF THE STUDY I/12
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-2
1.0 INTRODUCTION
1.1 PURPOSE OF THE REPORT
The mining Lease was granted over an area of 55.2520 in Village Virpur, TalukaKalyanpur and Dist : Devbhumi Dwarka, in favor of M/s. Smt. Pushpaben PrabhudasMakhecha, on dated 01-02-1992 and executed on 27.06.1994 for a period 20years.(Enclosed as Annexure – I). Lessee has applied for renewal on 16.06.2012(Enclosed as Annexure – II a) and lease is valid as per new MMDR 2015 ByGovernment of India. The lessee M/s. Smt. Pushpaben Prabhudas Makhecha expiredon 5.04.2012. The legal heirs the Late Pushpaben Prabhudas Makhecha are ShriBharatbhai Makhecha and Shri Naresh bhai Makhecha (The letter is attached asAnnexure – II b). The lease period has been increased as per norms. Modified mineplan has been approved by IBM vide letter 682(23) (M.P. - 522/2009-II MCCM (N)Udaipur dated 03.09.2015 (Enclosed as Annexure - X) As per Modified mining planproduction capacity is revised as 1, 51,875 TPA with mining working area 37.1670 haas block falling in the ECO Sensitive Zone/CRZ as per the notification issued by MOEF& CC dated 22.08.2013 has been enclosed as Annexure – XI). The estimated projectcost is Rs. 23.98 Lakh. The project proponent has informed that the baselinemonitoring has been conducted for summer season March to May – 2015 based onToR conditions and the same is informed to the ministry vide letter no. PPM/MoEF&CC/15-16/300 dated 22.04.2015. Ministry has accorded ToR to the project videletter no. J-11015/120/2013-IA-II (M) dated 04.02.2015 (Enclosed as Annexure – IVa). The PP has request to amend the ToR with respect to change of proposedproduction capacity 8, 18,418 TPA (ROM) to 1, 51,875 TPA (ROM) of Bauxite, leasearea 55.2520 ha with mining working area 37.1670 as per Modified Mine Plan (Letteris attached as Annexure – IV b). The expected life of mine is 5 years (as per aspresent level of exploration). The amended ToR was received vide letter No. J-11015/120/2013-IA.II (M) dated 4th December, 2015.The Environmental Impact Assessment (EIA) study report is prepared for obtainingEnvironmental Clearance (EC) from the Ministry of Environment and Forests (MOEF),Governmental of India, New Delhi for proposed Virpur (Gunawali) Bauxite mineMarine National park & Marine Sanctuary is present within 5 km of the study area asper ESZ Notification issued on dated 22nd August, 2013. It is classified as “Category –A” as per the EIA notification dtd 14th September 2006.
1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT
1.2.1 Identification of Project
The Mining Lease was granted over an area of 55.2520 ha in Village: Virpur, Taluka:Kalyanpur, and Dist: Devbhumi Dwarka.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-3
The status of the mining lease is given in Table-1.1. The status of the Environmentalclearance is given in Table-1.2. The year wise prior production details for the projectis given in Table-1.3.
Table-1.1 Status of the Mining lease
Sr. No. Particulars Description1 Mine area 55.2520 ha2 Mining lease letter The Mining Lease was granted over an area
of 55.2520 ha in favor of Smt, PuspabenPrabhudas Makhecha, on dated 01-02-1992and executed on 27.06.1994 for a period 20years. (Enclosed as Annexure – I). Lesseehas applied for renewal on 16.06.2012(Enclosed as Annexure – II a) and lease isvalid as per new MMDR 2015, till26.06.2034. The legal heirs the latePushpaben Prabhudas Makhecha are ShriBharatbhai Makhecha and Shri Naresh bhaiMakhecha (The letter is attached asAnnexure – II b).
3 Approval of modifiedMining plan form IBM
IBM vide letter 682 (23) (M.P. - 522/2009 –II MCCM (N) Udaipur dated 03.09.2015.
Table-1.2Status of the Environmental Clearance
Sr. No. Particulars Details1 Screening category of the
proposed project as perEIA Notification dated14.09.2006, amended ason date.
Category ‘A’, Project or activity 1 (a) , dueto presence of Marine National Park at4.12 km distance.
2 ToR presentation date for8,18,418 TPA
27th June ,2013
3. ToR Amendmentpresentation date forrevised proposed capacity1,51,875 TPA
24th September, 2015
4 ToR letter issued by MoEF,New Delhi
Vide letter no. J-11015/120/2013-IA.II (M),4th February,2015
5 ToR Amendment No. J-11015/120/2013- IA.II(M),04th Dec2015
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-4
Sr. No. Particulars Details6. Baseline study period March 2015 to May 20157. Public Hearing held on Conducted on dated 29.03.2016
Table 1.3 Year wise Production of Virpur (Gunawali) Bauxite mine
1.2.2 Project Proponent
Address of the applicantName of the Mine : Virpur (Gunawali) Bauxite MineLessee : Smt. Pushpaben prabhudas MakhechaAddress : Opp Circuit Villa, Chopati Road, Porbandar (Gujarat)District : PorbandarState : GujaratPhone : 0286 – 22444288
1.3 BRIEF DESCRIPTION OF PROJECT
1.3.1 Nature of the Project
Year Production (TPA)1994-1995 -1995-1996 -1996-1997 -1997-1998 -1998-1999 -1999-2000 7382000-2001 3802001-2002 2,2452002-2003 -2003-2004 -2004-2005 9,0002005-2006 49,2442006-2007 1,82,4272007-2008 5,53,5762008-2009 1,16,1712009-2010 1,09,1322010-2011 5672011-2012 8252012-2013 36,807
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-5
The proposed Virpur (Gunawali) Bauxite mine lease extends over an area of 55.2520ha with mine working 37.167 due to CRZ area in mine lease. As the proposed minelease area is within 5 km from Marine National Park/Marine Sanctuary, it is classifiedas “CATEGORY-A”, as per the EIA notification dtd 14th September 2006 & itsamendment.
1.3.2 Size of the Project
The Mining Lease was granted over an area of 55.2520 ha in Village: Virpur, Taluka:Kalyanpur, and Dist: Devbhumi Dwarka.
1.3.3 Anticipated Life of Project and Cost of the Project
The projected life of the mine is 5 years. The cost of mining land and miningmachinery for the present mining lease area is about Rs. 23.98 Lakh and the breakupof the EMP cost are given in Table 1.4.
Table 1.4 Cost details of the project
Sr. No. Particulars Details1 Total project cost Rs. 23.98 Lakh2 Cost for EMP Capital Cost – Rs. 1.15 Lakh
Recurring Cost for EMP– Rs. 2 Lakh
1.3.4 Location of the Project
The proposed Virpur (Gunawali) Bauxite lease comes under Village: Virpur, Taluka:Kalyanpur, and Dist: Jamnagar. Geo-graphically the ML area extends from EastLongitude 69° 17' 43.6" to 69° 18' 25.5” E and North Latitude 22° 15' 38.7" to 22°16'17" N. The location map is shown in Figure-1.1. The study area of the proposedproject comprises of 10 km radius around the mining lease boundary, the mapshowing the core zone (ML area) and buffer zone (10 km radius from the leaseboundary) is shown in Figure-1.2. The photographs of the mine lease area areshown in Figure-1.3. The details of environmental setting are given in Table-1.5.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-6
TABLE-1.5DETAILS OF ENVIRONMENTAL SETTING
Sr. No. Particulars in 10 km Details
1. State Highway SH- 25 about 10 km away in South directionfrom the site. A mettaled road passing nearto the sight, leads to Ran.
2. LatitudeLongitude
22° 15' 38.7" to 22° 16' 17" N.69° 17' 43.6" to 69° 18' 25.5” E
3. National Highway NH 8E about 29 km away in South Westdirection from the site.
4. State, National Boundaries Nil in 10 km
5. Railway station Bhopalka railway station about 17 km in SSE
direction from the site.
Bhatiya railway Station about 20 kms in SSWdirection from the site.
6. Airport Porbandar Airport about 75 km away in SSEdirection from the site.
7. Ecological Sensitive Areas(Wildlife Sanctuaries)
Marine National Park is about 4.12 Km. in
NW direction from the project site, Marine
Sanctuary is about 1 km in NW direction
from the mine working boundary.
Gaga Bird Sanctuary is about 16.55 km in
SW direction from project site.
8. Reserved / ProtectedForest
Nil
9. Nearest Town Bhatia (about 20 km SSE)
10. Toposheet Restricted (41F 7)
11. Seismic Zone Seismic Zone IV as per IS-1893(part-I)-2002
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-7
Figure-1.1Geographical Location of the Project
Project Site
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-8
Figure-1.2Corner co – ordinates of the mine lease area
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-9
Figure-1.3BUFFER Map of the Project
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-10
Figure-1.4Photographs of the Mine Lease Area
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-11
1.3.5 Importance to the Country & Region
Bauxite is a mineral found mostly in a belt around the equator. Bauxite, containing
15-25 percent aluminium, is the only ore that is used for commercial extraction of
aluminium today. It is extremely important economically due to the very widespread
use of aluminum. It is used in almost everything from soda cans to candy wrappers
to cars, aircraft, and boats. It is the most common light weight metal in use.
Resources of bauxite in the country as on 1.4.2010, as per UNFC system, are placed
at 3,480 million tonnes. These resources include 593 million tonnes reserves and
2,887 million tonnes remaining resources. By grades, about 84% resources are of
metallurgical grade. The resources of refractory and chemical grades are limited and
together account for about 4%. By States, Odisha alone accounts for 52% of
country's resources of bauxite followed by Andhra Pradesh (18%), Gujarat (7%),
Chhattisgarh and Maharashtra (5% each) and Madhya Pradesh and Gujarat (4%
each). Major bauxite resources are concentrated in the East Coast bauxite deposits
in Odisha and Andhra Pradesh. (Source: Indian Minerals Yearbook 2013, Part II
http://ibm.nic.in/IMYB%202011_Bauxite.pdf).
1.3.6 Supply and Demand Details
The production of bauxite in India, at 15,360 thousand tonnes in 2012-13 increased
by 11% as compared to the previous year due to better market demand. There were
152 reporting mines in 2012-13 as against 172 in the previous year. Besides,
production of bauxite was reported as associate mineral by 10 mines during the
year. In all, 70 producers reported production of bauxite in 2012-13. Ten principal
producers having 42 mines contributed 86% of the total production. Forty seven
major mines, each producing more than 50 thousand tonnes per annum, together
accounted for 93% of the total production. The share of 18 public sector mines was
about 42% of the total production in 2012-13 as against 43% contributed in the
previous year. About 63% of the total production of bauxite was of 40-45% Al2O3
grade, 15% was of cement grade, 12% was of 45-50% Al2O3 grade, 7% was of below
40% Al2O3 grade, 2% was of Refractory grade, and 1% of production was reported
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-12
together in 50-55% Al2O3, 55-60% Al2O3 Abrasive and Chemical grade during the
year under review. Odisha continued to be the leading producing state accounting
for about 38% production. Next in the order of production were Chhattisgarh and
Maharashtra (13 % each), Gujarat (20%), Jharkhand & Maharashtra (13%) and
Madhya Pradesh 5%. The remaining two percent was produced by Goa, Karnataka
and Tamil Nadu. In 2012-13, reported consumption of bauxite in India was 11.02
million tonnes as compared to 10.37 million tonnes in the previous year.
Alumina/aluminium industry was the principal consumer of bauxite, accounting for
88% consumption in 2012-13 followed by cement (9%) and refractory (2%). (Source:
Indian Minerals Yearbook 2013, Part II http://ibm.nic.in/IMYB%202011_Bauxite.pdf)
1.4 SCOPE OF THE STUDY
In line with the MoEF prescribed Terms of Reference (TOR), the area comprising 10
km radius around the proposed mine lease boundary is considered as the study area.
The EIA/EMP report has been prepared following the generic structure specified in
the EIA Notification 2006 & its amendment thereof. The detailed studies have been
conducted as per prescribed TOR.
The scope also includes all the conditions outlined in the TORs prescribed by MoEF.
TOR conditions and their compliance is given in Table-1.6.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-13
Table-1.6
TOR Compliance
ToRNo.
ToR Points Compliance
1 Year-wise production details since1994 should be given, clearly statingthe highest production achieved in anyone year prior to 1994. It may also becategorically informed whether therehad been any increase in productionafter the EIA Notification, 1994 cameinto force w.r.t. the highest productionachieved prior to 1994.
Year – wise production since 1994 -1995 is givenin Table 1.3 Section 1.2.1, Chapter 1.There was no production till 1998 -99. Highestproduction during 1999 – 2000, was 2007 – 2008.
2 A copy of the document in support ofthe fact that the Proponent is therightful lessee of the mine should begiven.
The Mining Lease was granted over an area of55.2520 ha (Mine working area 37.1670 ha) infavor of M/s Smt, Puspaben Prabhudas.Makhecha, on dated 01-02.1992 and executedon 27.06.1994 for a period 20 years. (Enclosed asAnnexure – I). Lessee has applied for renewal on16.06.2012 (Enclosed as Annexure – II a) andlease is valid as per new MMDR 2015, till26.06.2034. Lessee is an individual. The legalheirs the Late Pushpaben Prabhudas Makhechaare Shri Bharatbhai Makhecha and Shri Nareshbhai Makhecha (The letter is attached asAnnexure – II b).
3 All documents including approvedmine plan, EIA and public hearingshould be compatible with oneanother in terms of the mine leasearea, production levels, wastegeneration and its management andmining technology and should be inthe name of the lessee.
The EIA report is prepared on the basis ofinformation given in the approved mine plan andsupportive documents like lease deed, etc.Public Hearing raised point has beenincorporated in 7.2 in chapter 7.All the documents including approved mine plan,EIA report, lease deed details waste generationand its management are attached in Draft EIAReport.Approved Mine Plan is enclosed as Annexure –X.
4 All corner coordinates of the minelease area, superimposed on a HighResolution Imagery/toposheet shouldbe provided. Such an Imagery of theproposed area should clearly show the
The Corner co – ordinates of the mine lease areaare shown in Figure 1.2 Chapter-1 (Page No. I-8).
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-14
ToRNo.
ToR Points Compliance
land use and other ecological featuresof the study area (core and bufferzone).
5 Does the company have a well laiddown Environment Policy approved byits Board of Directors? If so, it may bespelt out in the EIA report withdescription of the prescribed operatingprocess/procedures to bring into focusany infringement/deviation/violationof the environmental or forest norms/conditions? The hierarchical system oradministrative order of the Companyto deal with the environmental issuesand for ensuring Compliance with theEC conditions may also be given. Thesystem of reporting of non-compliances / violations ofenvironmental norms to the Board ofDirectors of the Company and/orshareholders or stakeholders at largemay also be detailed in the EIA report.
The company has a well laid down EnvironmentPolicy, approved by mine owner. It is shown inAnnexure- V.
6 Issues relating to Mine Safety,including subsidence study, blastingstudy etc. should be detailed. Theproposed safeguard measures in eachcase should also be provided.
All safety measures prescribed under mining lawswill be followed strictly. All workers will bemedically examined in pre placement phase.Periodical medical examination as per Mines Rule1955- will be done every 5 years. The personsworking in dusty environment will be examinedevery year as per the DGMS circular No. 01 of21.01.2010. Medical examination will be as perthe medical fitness prescribed under Form P andP1 of the Mines Rule 1955, amended by Mines(amendment) Rules, 1989.The details of Occupational health impact ofproject and Details of routine checkup, Medicalaid as per ESI Scheme, Training, PPE is describedin Chapter 4, Section 4.12(Page No. IV/33).
7 The study area will comprise of 10 kmzone around the mine lease from leaseperiphery and the data contained inthe EIA such as waste generation etcshould be for the life of the mine /
The study area of 10 km zone around the mine isselected for EIA study. The overburdengenerated (Soil & intercalated waste) will betemporarily stacked and then simultaneouslybackfilled and reclamation will be carried out.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-15
ToRNo.
ToR Points Compliance
lease period.8 Land use of the study area delineating
forest area, agricultural land, grazingland, wildlife sanctuary, national park,migratory routes of fauna, waterbodies, human settlements and otherecological features should beindicated. Land use plan of the minelease area should be prepared toencompass preoperational,operational and post operationalphases and submitted.
Land use of the study area delineating forestarea, agricultural land, grazing land, waterbodies, and human settlements is given in Figure3.6, of Chapter 3( Page No. III/40).Marine National Park and Sanctuary presentwithin Study area. (Distance Certificate fromForest Department is attached as Annexure VI).
9 Details of the land for any Over BurdenDumps outside the mine lease, such asextent of land area, distance frommine lease, its land use, R&R issues, ifany, should be given.
It is a Government Waste Land, granted to Lesseeas Mining Lease. No any OB dumps presentoutside the mine lease. There are no R & R issuesrequired.
10 A Certificate from the CompetentAuthority in the State ForestDepartment should be provided,confirming the involvement of forestland, if any, in the project area. In theevent of any contrary claim by theProject Proponent regarding the statusof forests, the site may be inspected bythe State Forest Department alongwith the Regional Office of theMinistry to ascertain the status offorests, based on which, the Certificatein this regard as mentioned above beissued. In all such cases, it would bedesirable for representative of theState Forest Department to assist theExpert Appraisal Committees.
No forest land is involved. (Distance Certificatefrom Forest Department is attached as AnnexureVI).
11 Status of forestry clearance for thebroken up area and virgin forestlandinvolved in the Project includingdeposition of net present value (NPV)and compensatory afforestation (CA)should be indicated. A copy of theforestry clearance should also befurnished.
No forest land is involved. (Distance Certificatefrom Forest Department is attached as AnnexureVI).
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-16
ToRNo.
ToR Points Compliance
12 Implementation status of recognitionof forest rights under the ScheduledTribes and other Traditional ForestDwellers (Recognition of Forest Rights)Act, 2006 should be indicated.
Not Applicable.
13 The vegetation in the RF/PF areas inthe study area, with necessary details,should be given.
No Vegetation in RF/PF areas in the study area.
14 A study shall be got done to ascertainthe impact of the mining project onwildlife of the study area and detailsfurnished. Impact of the project on thewildlife in the surrounding and anyother protected area and accordinglydetailed mitigative measured required,should be worked out with costimplications and submitted.
The Conservation plan is enclosed as Annexure-VIII.
15 Location of National Parks,Sanctuaries, Biosphere Reserves,Wildlife Corridors, Tiger/ElephantReserves/Critically PollutedAreas/Aravalli (existing as well asproposed), if any, within 10 km of themine lease should be clearly indicated,supported by a location map dulyauthenticated by Chief WildlifeWarden. Necessary clearance, as maybe applicable to such projects due toproximity of the ecologically sensitiveareas as mentioned above, should beobtained from the State WildlifeDepartment/Chief Wildlife Wardenunder the Wildlife (Protection) Act,1972 and copy furnished.
There are Marine National Park and Sanctuarypresent within 5 km in from the site (DistanceCertificate from Forest Department is attached asAnnexure VI).
16 A detailed biological study of the studyarea [core zone and buffer zone (10km radius of the periphery of the minelease)] shall be carried out. Details offlora and fauna, duly authenticated,separately for core and buffer zoneshould be furnished based on suchprimary field survey, clearly indicating
A detailed biological study is discussed underChapter-3, Section 3.12 (Page No. III/45).Thespecies found in the study area are detailedunder Section 3.12 of Chapter 3.One Scheduled - I is found in Study area andconservation plan Will be submitted during FEIAReport. The Conservation plan is enclosed asAnnexure- VIII.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-17
ToRNo.
ToR Points Compliance
the Schedule of the fauna present. Incase of any scheduled-I fauna found inthe study area, the necessary plan fortheir conservation should be preparedin consultation with State Forest andWildlife Department and detailsfurnished. Necessary allocation offunds for implementing the sameshould be made as part of the projectcost.
17 Proximity to Areas declared as‘Critically Polluted’ or the Project arealikely should also be indicated andwhere so required, clearancecertifications from the prescribedAuthorities such as the SPCB or StateMining Dept. should be secured andfurnished to the effect that theproposed mining activities could beconsidered.
No Critically Polluted area is near project site.
18 Similarly, for coastal project, A CRZmap duly authenticated by one of theauthorized agencies demarcatingLTL,HTL,CRZ area location of minelease w.r.t CRZ, coastal features suchas mangroves, if any should befurnished. (Note: The mining projectsfalling under CRZ would also need toobtain approval of the concernedcoastal zone Management Authority).
A CRZ map demarcating LTL, HTL, and CRZ issurveyed and prepared by NCSCM attached asAnnexure – IX).
19 R&R Plan/compensation details for theProject Affected People (PAP) shouldbe furnished. While preparing the R&RPlan, the relevant State/NationalRehabilitation & Resettlement Policyshould be kept in view. In respect ofSCs /STs and other weaker sections of
Not applicable, as the project area is aGovernment Waste Land there is noRehabilitation/Resettlement of any personrequire, due to mining operations.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-18
ToRNo.
ToR Points Compliance
the society in the study area, a needbased sample survey, family-wise,should be undertaken to assess theirrequirements, and action programmesprepared and submitted accordingly,integrating the sectoral programmes ofline departments of the StateGovernment. It may be clearly broughtout whether the village located in themine lease area will be shifted or not.The issues relating to shifting of Villageincluding their R&R and socio-economic aspects should be discussedin the report.
20 One season (non-monsoon) primarybaseline data on ambient air quality(PM10, SO2 and NOx), water quality,noise level, soil and flora and faunashall be collected and the AAQ andother data so compiled presenteddate-wise in the EIA and EMP Report.Site-specific meteorological datashould also be collected. The locationof the monitoring stations should besuch as to represent whole of thestudy area and justified keeping inview the pre-dominant downwinddirection and location of sensitivereceptors. There should be at least onemonitoring station within 500 m of themine lease in the pre-dominantdownwind direction. The mineralogicalcomposition of PM10, particularly forfree silica, should be given.
Primary baseline data on ambient air quality isgiven in Section 3.6 of Chapter 3 (Page No. III/5).Water quality is given in Section 3.8 of Chapter 3.Noise level is given in Section 3.7 of Chapter 3.Soil characteristics are given in Section 3.9 ofChapter 3Lab Reports have been attached as Annexure-XV.Details of flora and fauna are given in Section3.12 of Chapter 3(Page No. III/44).Site-specific metrological data have beencollected, as prescribed, for non monsoon seasonof March 2015 to May 2015 in Table 3.1 Page ofChapter 3.
21 Air quality Modeling should be carriedout for prediction of impact of theproject on the air quality of the area. Itshould also take into account theimpact of movement of vehicles fortransportation of mineral. The detailsof the model used and inputparameters used for modelling should
Details of Air Quality Modeling carried out for airquality of the area has been incorporatedChapter 4, Section 4.2 (Page No. IV/4).
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-19
ToRNo.
ToR Points Compliance
be provided. The air quality contoursmay be shown on a location mapclearly indicating the location of thesite, location of sensitive receptors, ifany, and the habitation. The windroses showing predominant winddirection may also be indicated on themap.
22 The water requirement for theproject, its availability and source to befurnished. A detailed water balanceshould also be provided. Fresh waterrequirement for the project shouldalso be indicated.
Total water requirement is 8 KLD during miningoperation.
23 Necessary clearance from theCompetent Authority for drawl ofrequisite quantity of water for theproject should be provided.
As per the CGWA’s Categorization of Talukas inGujarat (please refer Annexure - XII), KalyanpurTaluka of Devbhoomi Dwarka District, Gujarat isnot falling under any of the three Categories;Semi-critical, Critical and Over-exploited.Therefore Kalyanpur Taluka is considered to be inSafe Zone.Further, on the basis of Guidelines issued byCGWA, NOC for ground water abstraction in SafeCategory areas will be required only if the groundwater abstraction exceeds 1000 m3/day for hardrock areas and 2000 m3/day for alluvial areas.In case of Project mining lease, total waterrequirement will be 8 KLD, which is very less ascompared to the ground water abstraction limitsof CGWA, thus permission from State GroundWater Board for drawing water will not berequired.
24 Description of water conservationmeasures proposed to be adopted inthe Project should be given. Details ofrainwater harvesting proposed in theProject, if any, should be provided.
Rain water will be collected in mined out pits andused for dust supperssion. A part of excavatedarea will be converted into water reservoir. Thedetails are given in Section-4.3 chapter-4(PageNo. IV/9).
25 Impact of the project on the waterquality both surface and groundwatershould be assessed and necessarysafeguard measures, if any required
Surface Water :
There is no permanent surface water bodynearby to mine lease.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-20
ToRNo.
ToR Points Compliance
should be provided. Ground Water :
Ground water pollution can take place only if themining rejects contain chemical substances.However, the deposit does not contain anyharmful ingredients. Hence, no impact ongroundwater quality is envisaged.
26 Based on actual monitored data, itmay clearly be shown whether workingwill intersect groundwater. Necessarydata and documentation in this regardmay be provided. In case the workingwill intersect groundwater table, adetailed hydro geological study shouldbe undertaken and report furnished.Necessary permission from CentralGround Water Authority for workingbelow ground water and for pumpingof ground water should also beobtained and copy furnished.
Mining activity will not intersect the groundwater.
27 Details of any stream if any passingthrough lease area andmodification/diversion proposed, ifany and the impact of the same on thehydrology should be brought out.
No any stream is passing through lease area. Oneseasonal Rani river falls with in 10 km of studyarea. (As fig 1.3 – Study Area map of the Project)
28 , Information on site elevation, workingdepth, groundwater table etc. shouldbe provided both in AMSL and bgl. Aschematic diagram may also beprovided for the same.
The information is given below:
Site elevation (AMSL): 18m to 3m.
Working depth: The minimum and maximumdepth of working is 5.00m depending uponthickness of bauxite bed & topsoil.
Ground water table: The minimum water levelis 12.00m below the general ground level duringthe monsoon period the maximum water level is18.00m below the general ground level duringsummer period.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-21
ToRNo.
ToR Points Compliance
29 A time bound Progressive GreenbeltDevelopment Plan shall be prepared ina tabular form (indicating the linerquantitative coverage, plant speciesand time frame) and submitted.Keeping in mind, the same will have tobe executed up front oncommencement of the project.
The progressive greenbelt development detailsare given in chapter-4, Section 4.10.
30 Quantity of solid waste generation tobe estimated and details for itsdisposal and management should beprovided. The quality, volumes andmethodology planned for removal andutilization (preferably concurrently) oftop soil should be indicated, Details ofbackfilling proposed, if any, should alsobe given. It may be clearly indicatedthat out of the total waste generatedduring the mine life, how muchquantity would be backfilled and howmuch quantity would be disposed offin the form of external dump (numberof dumps, their height, terraces etc. Tobe brought out).
The details of OB generation, disposal andbackfilling details are given in Chapter-4, Section-4.5 (Page No. IV/17).
31 A time bound Progressive GreenbeltDevelopment Plan shall be prepared ina tabular form (indicating the linearand quantitative coverage, plantspecies and time frame) andsubmitted, keeping in mind, the samewill have to be executed up front oncommencement of the project.
The progressive greenbelt development detailsare given in Chapter-4, Section-4.10 (Page No.IV-29).
32 Impact on local transportinfrastructure due to the projectshould be indicated. Project increase intruck traffic as a result of the project inthe present road network (includingthose outside the project area) shouldbe worked out, indicating whether it iscapable of handling the increase load.Arrangement for improving theinfrastructure, if contemplated
The impact of additional trafficis discussed inChapter-3, Section-3.11(Page No. III/42).
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-22
ToRNo.
ToR Points Compliance
(including action to be taken by otheragencies such as State Government)should be covered.
33 Details of the onsite shelter andfacilities to be provided to the mineWorkers should be included in the EIAreport.
Infrastructure facilities to be provided for themine workers are as under:-i. Shelter/rest room.ii. Separate facility for male workers.iii. Medical first aid room.iv. Training center.v. Canteen facilities.
34 Conceptual post mining land use andReclamation and Restoration of minedout areas (with plans and withadequate number of sections) shouldbe given in the EIA report.
Conceptual plans and sections are given inSection-2.10 and Chapter -2 Page No. II/22).The conceptual post mining land use andreclamation and Restoration ofmined out area is tabulated below:-
SI.No.
Particulars Area put on useupto life of mine
(in hectare)1 Pit (Area under
Mining)23.3954
2 Storage Soil 03 Overburden dump 04 Mineral storage 0.05005 Infrastructure 0.00506 Roads
/Rasta(Additional)0.2000
7 Green belt 0.50008 Township Area 09 Railway 010 Tailing Pond 011 Effluent Treatment
Plant0
12 Mineral Separationplan
0
13 Sub grade 0Grand Total 25.1504
35 Phase-wise plan of greenbeltdevelopment, plantation andcompensatory afforestation should becarted clearly indication the area to be
The progressive greenbelt development detailsare given in Chapter-4, Section 4.10 (Page No.IV-28).
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-23
ToRNo.
ToR Points Compliance
covered under plantation and thespecies to be planted. The details ofplantation already done should begiven.
36 Occupational heath impact of projectshould be anticipated and preventionmeasures initiated. Details in thisregard should be proved. Details of preplacement medical examination andperiodical medical examinationschedules should be incorporated inthe EMP.
All safety measures prescribed under mining lawswill be followed strictly. All workers will bemedically examined in pre placement phase.Periodical medical examination as per Mines Rule1955- will be done every 5 years. The personsworking in dusty environment will be examinedevery year as per the DGMS circular No. 01 of21.01.2010. Medical examination will be as perthe medical fitness prescribed under Form P andP1 of the Mines Rule 1955, amended by Mines(amendment) Rules, 1989.The details ofOccupational health impact of project and Detailsof pre placement medical examination andperiodical medical schedules are described underChapter 4, section 4.12( Page No. IV /32).
37 Public health impaction of the projectrelated activities for the population inthe impact zone should besystematically evaluated and theproposed remedial measures shouldbe detailed along with budgetaryallocations.
Public health implications of the project andremedial measures are detailed are given inChapter-4, section 4.12.5 [Page No. IV/34].
38 Measures of socio economicsignificance and influence to the localcommunity proposed to be providedby project proponent should beindicated. As far as possible,quantitative dimensions may be givenwith time frame for implementation.
Measures of corporate social responsibility to thelocal community have been furnished and aregiven in Chapter 7, section 7.11(Page No. VII/40).
39 Details environmental managementplan to mitigate the environmentalimpacts which, should inter-alia alsoinclude the impact due to change ofland use, due to loss of agriculturalland and grazing land, if any,occupational health impacts besidesother impacts of the projects.
The details are given in Chapter9.
40 Public hearing points raised and All the points raised during public hearing have
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine Working Area 37.167 ha)Chapter-1Introduction
I-24
ToRNo.
ToR Points Compliance
commitment of the project proponenton the same along with time boundaction plan to implement the sameshould be provided and alsoincorporated in the final EIA/EMPReport of the Project.
been incorporated in chapter VII.
41 Details of litigation pending against theproject, if any, with direction / orderpassed by any Court of Law against theproject should be given.
There is no litigation pending against this project.
42 The cost of the project (capital costand recurring cost) as well as the costtowards implementation of EMPshould clearly be spelt out.
The sum of Rs 23.98 Lakh is kept under this head.The detailed Environmental Management Plancost is discussed under Chapter 9, Section-9.7Table 9.4 (Page No. IX/11).
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-1
CHAPTER-2
PROJECT DESCRIPTION
INDEX
SI.NO CONTENT PAGE NO
2.0 PROJECT DESCRIPTION II/2
2.1 Type of Project II/2
2.2 Need of the Project II/2
2.3 Status of Regulatory Clearances of the Project II/2
2.4 Size/Magnitude of Operation II/3
2.5 Land Requirement II/3
2.6 Physiography II/5
2.7 Geology II/7
2.8 Mineable reserve II/15
2.9 Anticipated life of the mine for Bauxite mining II/16
2.10 Conceptual Mining Plan: II/18
2.11 Post mining land use II/20
2.12 Generation of Waste II/20
2.13 Drilling & Blasting II/23
2.14 Water Requirement II/14
2.15 Power Supply II/25
2.16 Proposed Manpower II/25
2.17 Characteristics of Ore II/25
2.18 Use of Mineral II/26
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-2
2.0 PROJECT DESCRIPTION
2.1 Type of Project
The proposed project is an opencast manual cum semi mechanized with theproduction 1, 51,875 TPA with mining working area 37.1670. The details of theproject are given in Table-2.1.
Table-2.1Details of the project
Sr. No. Parameter Description1 Total ML area 55.2520 ha2. Mine working area 37.1670 ha2 Production level Bauxite 1,51,875 TPA4 Mine technology semi mechanized open cast5 Name of the lessee Smt. Pushpaben P. Makhecha
2.2 Need of the Project
Gujarat is the second largest producer and produces over 15 per cent of the totalbauxite of India. The total reserves are estimated at 87.5 million tonnes mainly foundin Jamnagar, Junagadh, Kheda, Kuchchh, Sabarkantha, Amreli and Bhavnagar. Themost important deposits occur in a belt which is 48 km long and 3 to 4.5 km widelying between the Gulf of Kachchh and the Arabian Sea through Bhavnagar,Junagadh and Amreli districts.
2.3 Status of Regulatory Clearances of the Project
The Modified Mine Plan has been approved by IBM vide letter 682(23) (M.P. –522/2009-II MCCM (N) Udaipur dated 03.09.2015. The earlier details of mine aregiven in Table-2.2.
TABLE-2.2DETAILS OF THE MINE
S.No Particulars Details1 Lease Execution The mining lease was granted over an area of
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-3
Particulars 55.2520 ha in favor of Smt, Pushpaben P.Makhecha, on dated 01-02-1992 andexecuted on 27.06.1994.
2 Date of mineopening
During 1992
5 Modified Mining Planfor Reduced AreaApproved by IndianBureau of Mines
IBM vide letter 682 (23)(M.P.- 522/2009 – IIMCCM (N) Udaipur dated 03.09.2015.
6 Validity period ofpresent Mining plan 20 years
2.4 Size/Magnitude of Operation
The salient features of the project are presented in Table-2.3.
TABLE-2.3DESCRIPTION OF THE MINE
Sr.No.
Parameter Description
1. Production 1,51,875 TPA of Bauxite2. Category of mineral
resource Proved (111)
3. Mineable reserves 629323 Tonnes of Bauxite,4. Expected life of mine 5 years (as per as present level of
exploration)5. Method of mining semi mechanized open cast6. Mechanization semi mechanized7. Bench Height 4.5m8. Bench Width 10 m9. soil thickness 0.40 M10. Bauxite thickness 4.5 M11. Stripping ratio 1:0.8 (Bauxite to Overburden)
2.5 Land Requirement
The land use pattern around village is Government Waste Land interspersed withbarren Government Waste Land. The land ownership of the mine lease is given in
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-4
Table-2.4. The area plan is shown in Figure-2.1. Marine National Park & MarineSanctuary is about more than 1 Km in N from the site.
TABLE-2.4LAND OWNERSHIP DETAILS OF THE MINE LEASE
Government Waste land 55.2520 Ha
G.W. Land (Public) NILRaiyati NILTotal 55.2520 Ha
Existing Land use pattern:
The land Use Pattern at present exists in the mine is as under:
SI. No. Particulars Present land use pattern (ha)
1 Pit (Area under Mining) 19.4402
2 Storage Soil 0
3 Overburden dump 0
4 Mineral storage 0.0500
5 Infrastructure 0.0050
6 Green Belt 0.0100
7 Road/Rasta(Additional ) 0.0460
8 Township Area 0
9 Railway 0
10 Tailing Pond 0
11 Effluent TreatmentPlant
0
12 Mineral SeparationPlan
0
13 Sub grade 0
Grand Total 19.5512
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-5
2.6 Physiography
The leasehold area is covered by soil in peneplained terrain without any major
topographical relief. The mining lease area is government waste land. The lease area is in
irregular shape. Bauxite can be seen in working pits in all the blocks. No cultivation is being
done in leasehold area. Bajra and jawar are MC main crops of the region, which are grown
on the cultivable land outside mine lease in the area.
There is no river or nala crossing in the lease area. The rainy water follows the natural slope
of the area. In general the area is having slope in eastern direction. Rainy water of region
ultimately goes into Arabian Sea. However in general water flow in eastern direction. The
temperature reaches up to 450C during summer and minimum up to 120C in the winter. The
average rainfall of the region is 400 mm per year. Except small bushes no tree can be seen in
the area. There is no reserve or protected forest in the area. There is no village within lease
area. The nearest village is Virpur, Mewasa & Kenedy.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-6
FIGURE-2.1SURFACE PLAN OF THE MINE LEASE AREA
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-7
2.7 Geology
The area around Mewasa, Kenedy, Nandana, Mota Asota, Ran &Virpur village exposesbauxite as segregated pocket within laterite or horizontal bedded bauxite deposit withinlaterite or altered clay. The other rock type exposed in the region are trap rocks, limestoneand lithomergic clays. The limestone belonging to gaj beds series is overlying the laterites.The sequence of formation ranges from early Eocene to recent in age. The generalizedstratigraphic sequence of the region is given below:-
Sequence AgeSand dunes, Ran clays and aluminum Sub recent to recent
Gaj Beds
Agrillacems Limestone
Calcareous clays
Concretionary limestone Lower Miocene
Calcareous Grit,
Conglomerate
Laterite with bauxite upper Eocene
Pockets Super trappeans
(Other Lithomarge puplebrown clay)
Deccan trap Lower Eocene to late cretaceous
2.7.1 Local Geology
It has been observed that the lease area is covered with topsoil. The thickness ofoverburdens various from place to place. The bauxite is exposed in working pit. Thethickness of bauxite zones is 4.5m. In general recovery of high grade bauxite is Nil; low grade
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-8
95% of ROM bauxite (up to 35% Al2O3) and 5% mineral waste (below 35% Al2O3). Therecovery percentage of bauxite is 95% of ROM based on the result of excavation done so farin the area.
Formation Thickness in Meter
Soil 0.40m
Bauxite 4.5m
Lithomarge Clay -
Geological and mineable reservesCategory Geological Reserves Mineable Reserves
Proved 36,80,826 MT 6,29,323 MT
PRODUCTION PARAMETERSYear Total
tentativeExcavation
(Cum)
TOPSoil(Cum)
OB/SB/IB(Cum)
ROM(cum) MineralRejectin M3
ROM/WasteRatio
Ore(Cum) Mineralreject(Cum)
(15-16) 41994 Nil Nil 41994 2100 2100 1:0.8(16-17) 65905 5380 Nil 60525 3026 3026 1:0.8(17-18) 67150 5400 Nil 60750 3038 3038 1:0.8(18-19) 65768 5369 Nil 60399 3020 3020 1:0.8Total 240817 16149 Nil 223668 11184 11184 1:0.8
The detailed geological plan is given in Figure 2.3.
2.7.2 Details of Exploration: -
In the proposed mining, the Mining work will be carried out from southern part of the leasearea during modified mining plan period in one shift only.Soil will be first scraped/excavated and stacked near pit temporary. It will be spread overstatutory barrier. Bauxite present in the area with a thickness of 4.5 will be mined out byforming one bench of 4.5m each with the help of excavator- tipper combination. Initially abox cut is made for formation of RAMP with 1:16 in gradient to reach the pit bottom of the
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-9
one bench. The bauxite will be transported to porbandar by hired truck. The existing fairweathered road will be used as approach road to connect village.
Geometry of bench:-The height of bench will be 4.5m and the width of benches will be 10m and slope of benchwill be maintained 700 from vertical.In the next five years the mining will be done by semi mechanized open cast method (OTFM)by using excavator and tippers. The width of bench will be kept 10m and height of benchwill be of 4.5m. The blasted bauxite will be sorted manually on pit surface. The slope of theface will be maintained 700 from vertical during mining operation.In general bauxite of the area is soft in nature & major part of it can be excavated withoutuse of drilling & blasting. However Drilling will be done in hard compact part of bauxite bed.Drilling will be carried out with the help jack hammer. Blasting will be done by qualifiedblaster under supervision of mining mate / Mines Manger. All precaution as will be takenduring blasting operation.Based on experience gain from the lease area in past, recovery of bauxite from ROM is 95%,rest 5% in waste. Bauxite of the area is of low grade category. The waste generated duringmodified mining plan period will be stacked at pit floor.The bench wise reserves are calculating as under:-
BL x BW x BH x Sp. Gr. x RF = R (T)BL = Bench length in MeterBW = Bench width in MeterBH = Bench height in MeterSp. Gr. = Specific GravityR (T) = Reserves in tones
2.7.3 Indicate Year wise tentative Excavation in cubic meters indicating development,ROM, pit wise as in table below: -As mining lease is having working pits, in the proposed mining plan no development work isproposed. During the proposed mining plan period bauxite will be excavated after removalof soil, for tonnage calculation specific gravity is considered as 2.5 MT/M3. During planperiod work will be carried out in south part of the area.The recovery factor of bauxites from Rom is considered as 0.95 (95% for ROM because lowgrade bauxite upto 35% (Al2O3) will be used & sold as non plant grade (Low grade).During the modified mining plan period, the bauxite mineral left out in working pit will alsobe excavated. The total area (other than already mined out area) of each year to be minedin next four year will be as under:
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-10
Year Area to be mined out (M2)2015 – 16 (At pit floor) 41994M2 (Pit no. 3& 4)August 15 to March 16)2016-17 13450 M2
2017-18 13500 M2
2018-19 13422 M2
2.7.4 Year wise production for the ensuring four year of modified mining plan period:-In the proposed mining plan. The mining will be started in south part of lease area. It isproposed to undertake mining work systematically, so as to improve effective supervision,better quality & economic work of the mines. As mentioned above overburden is consistingof soil. Bauxite horizon occurs 0.4m thin cover of soil. Bauxite mineral will be excavated byforming single bench of 4.5m height as the thickness of bauxite zone is 4.5m. The width ofbench will be kept 10k. Drilling & Blasting will be done for bauxite only if required.It is proposed during modified mining plan period; the soil will be scraped & stackedtemporally near pit/ statuary boundary. No bench of soil/ OB will be formed. Bauxitespresent in the area is about 4.5m thick & will be excavated by forming one bench of 4.5 mheight. The width of bench will be kept as 10m minimum.Initially a box cut is made for formation of RAMP with 1:16 gradient to reach pit bottom ofthe ROM bench. The bauxite present in the area is low grade. The recovery of saleablebauxite is 95% of ROM. The 5% of ROM will be generated as waste. The waste generatedduring modified mining plan will be stacked at pit floor.
Second Year (August 15 to March 16) (2015-16): -
During the second year of plan period, mining will be carried out in south part of lease areaat pit floor pit no. 3 & 4 as shown in year wise development plan plate no. VI controlled bysection M-M’. As shape of lease area is very irregular. Hence orientations of face will changefrequently as shown over year wise development plan. Bauxite present at pit floor of 1.00mthickness will be scraped. No soil will be scraped during second year.The strip is located in southern part of area and controlled by section M-M.For pit no. 3In general the strip parameters are as under: -1. Area of strip at pit floor: 29694 m2
2. Average thickness of bauxite at pit floor: 1.0 m3. Average thickness of soil: NilMining of Soil/ Bauxite for pit no. 3Bench No. Area in M2 * Height M = Volume in M3
Bauxite at pit floor 29694 * 1.0 = 29694 M3
Bauxite at pit floor of pit no. 3 = 29694 M3
For Pit no.In general the strip parameters are as under: -
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-11
1. Area of strip at pit floor = 12300 M2
2. Average thickness of bauxite at pit floor = 1.0m3. Average thickness of soil = Nil
Mining of Soil/ Bauxite for Pit no. 4Mining of Soil/ Bauxite for pit no. 3Bench No. Area in M2 * Height M. = Volume in M3
Bauxite at pit floor 12300 * 1.0 = 12300 M3
Bauxite at pit floor of pit no. 4 = 12300 M3
Total bauxite of pit 3 & 4 = 29694 M3 +12300 M3
= 41994 M3 / 104985 MTThird Year (2016 -17):-During the third year period, mining will be carried out south east part of lease areacovering area around pit no. 2 as shown over year wise development plan & sectioncontrolled by section N-N’. Soil will be scraped first & bauxite will be excavated by formingone bench of 4.5m height. The orientation of face will be east – west advancing easterly.The propose area fall between gride S- 236 to S-457 & E 300 to E 479.The strip is located in central part of area and controlled by section N-N’.In general the strip parameters are as under: -Area of strip = 13450m2
Average thickness of bauxite = 4.5m.Average thickness of soil = 0.40mMining of soil / Bauxite: -Bench No. Area in M2 * Height M. = Volume in M3
Soil 13450 * 0.40 = 5380 M3
1 Bauxite 13450 * 4.5 = 60525 M3
Total Bauxite ROM = 60525 M3
Total Bauxite in MT = 151312 MTForth Year (2017 – 18): -During the fourth year of plan period, mining will be carried out in south part lease areacovering area in and around pit no.3 as shown over year wise development plan & sectioncontrolled by section M-M’. The face formed at the end of 3rd year will be advance innortherly. The proposed area fall between gride S-383 to S-744 & E 150 to E 370. Soil will bescraped first, than bauxite will be produced by forming one bench of 4.5m height.The strip is located in south part of lease area and controlled by section M-M’.In general the strip parameters are as under: -1. Area of strip 13500m2
2. Average thickness of bauxite 4.5m3. Average thickness of soil 0.40mMining of Soil / Bauxite: -
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-12
Bench No. Area in M2 * Height M. = Volume in M3
Soil 13500 * 0.40 = 5400 M3
1 Bauxite 13500 * 4.5 = 60750 M3
Total Bauxite ROM = 60750 M3
Total Bauxite in MT = 151875 MTFifth Year (2018-19):-During the fifth year period, the face formed at the end of fourth year will be advancewesterly, as shown over year wise development plan section controlled by section M-M’.Soil will be scraped first & bauxite will be excavated be forming one bench of 4.5m height.Face form at the end of 4th year shall be further advance in north direction covering pit no. 7also. The area falls in two strip which falls between gride S – 430 to S- 774 & E 50 – E 172and second strip between S416 to S 484 & W 78 to W 180.The strip is located in south west part of lease area and controlled by section M-M’.
In general the strip parameters are as under: -1. Area of strip 13422m2
2. Average thickness of bauxite 4.5m3. Average thickness of soil 0.40mMining of Soil / Bauxite: -Bench No. Area in M2 * Height M. = Volume in M3
Soil 13422 * 0.40 = 5369 M3
1 Bauxite 13422 * 4.5 = 60399 M3
Total Bauxite ROM = 60399 M3
Total Bauxite in MT = 150998 MT
The Insitu Tentative Excavation is as under:
Year Totaltentative
Excavation(Cum)
TOPSoil(Cum)
OB/SB/IB(Cum)
ROM(cum) MineralRejectin M3
ROM/WasteRatio
Ore(Cum) Mineralreject(Cum)
(15-16) 41994 Nil Nil 41994 2100 2100 1:0.8(16-17) 65905 5380 Nil 60525 3026 3026 1:0.8(17-18) 67150 5400 Nil 60750 3038 3038 1:0.8(18-19) 65768 5369 Nil 60399 3020 3020 1:0.8Total 240817 16149 Nil 223668 11184 11184 1:0.8
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-13
Year wise production during four years modified mining plan period:The year wise details of volume bauxite ore to be excavated & the production tonnage ofconsidering the recovery percentage of all grade bauxite are as under:-
Year (a) Volume M3 Tonnage ofROM(d)
Recovery ofBauxite 95%ROM in MT d* 0.95 (e)
Waste 5 %of ROMM.T.D * 0.05(mineralwaste)(f)
Low grade100% ofproduction inMT e *Abrasives &refractorygrade(g)
Soil (b) ROM(c )
(15 -16)August15 toMarch16)
Nil 41994 104985 99736 5249 99736
(16-17) 5380 65905 151312 143746 7566 143746
(17-18) 5400 67150 151875 144281 7594 144281
(18-19) 5369 65768 150998 143448 7500 143448Total 16149 240817 559170 531211 27959 531211
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-14
FIGURE-2.2GEOLOGICAL PLAN OF THE MINE LEASE AREA
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-15
2.8 Mineable reserve
The mineable reserve estimated on the basis of measured and indicated category isas tabulated in Table-2.5.
Table-2.5Mineable reserve details
Classification Code Reservesestimation(Quantity intones)
Grade
TOTAL MINERAL RESERVES Bauxite
A. Mineral1. Proved MineralReserves.
111 629323 MT Low Grade
2. Probable MineralReserves.
122 --
Total 629323 MTB. Remaining Resources3. Feasibility MineralResources
211
4. Pre – feasibility mineralresources
221 3051503 MT Low Grade
5.Measured MineralResources
331 -
6. Indicated MineralResources
332 -
7. Inferred MineralResources
33 -
8. ReconnaissanceResources.
334 -
Total 3051503 MT
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-16
Grade of the reserves:-
One the basis of the mining experience of the lessee in the lease area the bauxiteavailable in the lease area is of High Grade and low – grade bauxite only. Grade wiseDemonstrated reserves could be summarized as under:-
S. No. Category of Reserves Recovery1 High grade (Abrasive grade & refractory
grade) Al2O3 > 50%)Nil
2 Low grade (upto 35% Al2O3) (Cement andother grade)
95% of production
3 Waste grade 5% of ROM
In all 629323 MT mineable reserves of bauxite has been estimated of approximately1, 40,000 MT of bauxite is produced every year, then the life of mine is 5 years. Itmay be increased after further exploration.
2.9 Anticipated life of the mine for Bauxite mining
The life of the mine would be about 5 years.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-17
FIGURE-2.3GEOLOGICAL SECTION OF THE MINE LEASE AREA
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-18
FIGURE-2.4Year wise development Plan
2.10 Conceptual Mining Plan:
It is proposed to put three trial pits during modified mining plan period.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-19
Year No. of trial pits No.of pits, dimension and volume
(2016 -17)August 15 to March 16
One 5m*5m
2017 – 18 One 5m * 5m2018 – 19 One 5m * 5m
The life of the mine is 5 years. During coming 5 years the entire mineralized area leaving allstatutory barriers and eco sensitive zone. Based on the present available mineable reserves& proposed annual production plan, it is expected that complete bauxite ore will beexcavated by open cast mining method within 5 years period. The conceptual plan has beenprepared up to life of the mine because the life of the mine is 5 years only. The lease areawill be converted into one pit having dimension varies from place to place depending uponshape & size of lease area and average depth will be about 4.5 m.
SI. No. Particulars Presentland usepattern(In Ha)
Area put on useupto end ofmining planperiod (inhectare)
Area put on useupto life ofmine (inhectare)
1 Pit (Area underMining)
19.4402 23.4774 23.3954
2. Storage Soil 0 0 03. Overburden dump 0 0 0
4. Mineral storage 0.0050 0.0500 0.0500
5. Infrastructure 0.0050 0.0050 0.00506. Green Belt 0.0100 0.3100 0.20007. Road/Rasta(Additional
)0.0460 0.0460 0.5000
8. Township Area 0 0 0
9. Railway 0 0 010 Tailing Pond 0 0 0
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-20
11 Effluent TreatmentPlant
0 0 0
12 Mineral SeparationPlan
0 0 0
13. Sub grade 0 0 0Grand Total 19.5512 23.8884 25.1504
The past experience of mining activity in the ML as the details of maturity of voids aftermining marked out in the present mining plan have shown that the voids created by miningwill be much larger and the waste rocks and soil left out will be insufficient for backfillingpurpose. Therefore complete backfilling of the mined out area upto original ground level isnot possible. Therefore the mined out will be used as water reservoir as shown inconceptual plan. In the water reservoir the higher benches of excavated mining pit shall beterraced and plantation will be done for stabilizing the slope. The slope of higher bencheswill be made gradual & gentle for easy accessibility by local people to pond water andfencing will be carried out around the water reservoir as required.The waste generated (5% of ROM) will be stacked at pit floor in systematic manner afterexcavation of fall thickness of bauxite.
2.10.2 (B) Afforestation programme upto end of conceptual mining plan period: -It is proposed to undertake plantation programme in the lease area. Plantation work will becarried out along statutory barrier and on backfilled area so that a green belt can bedeveloped. 150 saplings will be planted during modified mining plan period and upto life ofthe mined and 750 plants will be upto life of the mine.
2.11 Post mining land use:-Part of the area will be backfilled and other part of the area will be used as water reservoir.The basic requirement of local community is storage of rain water therefore the mined outarea will be used as water reservoir. In the water reservoir the higher benches on theexcavated pit shall be terraced and plantation will be done for stabilization the slope. Theslope of higher benches will be made gradual and gentle for easy accessibility by localpeople to pond water and fencing will be carried out around the water reservoir.
2.12 Generation of Waste(a) Nature and quantity of top soil, overburden/ waste and mineral reject:
In the proposed mining plan topsoil will be generated but no OB will be generatedthe 5% ROM will be generated as mineral waste.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-21
The waste that is likely to be generated will be in the form of associated clay with thebauxite horizon as mineral reject, which is below the threshold grade, and has nosale value & of no use. Hence considered as a waste.The yearly rate of generation of the waste has been described in detail in the miningchapter and the date given there is presented in a tabular from below. For the soiland waste the expansion factor considered is 1.3.Top soil will be generated during modified mining plan period.A tabular statement shoeing volume of soil, OB mineralized waste:-
Year Top Soil(cum) Mineral waste (cum)Reuse/Spreading
Storage Backfilling Storage Blending Beneficiation
(2015 – 16 )August 15to March
16)
Nil Nil Nil 2100 Nil Nil
2016 – 17 5380 Nil Nil 3026 Nil Nil2017 -18 5400 Nil Nil 3038 Nil Nil2018 - 19 5369 Nil Nil 3020 Nil Nil
Total 16149 Nil Nil 11184 Nil Nil
Waste generated during production of mineral bauxite will be stacked in pit floorafter excavation of bauxite upto full thickness. Top soil will be spread over statuarybarrier for plantation.(b) Proposed dumping area: -In the proposed modified mining plan. It is proposed that waste generated duringmining plan period will be stacked at pit floor after excavation of bauxite. Soil will bespread over statuary area for plantation. Part of mined out land will be used as waterreservoir.(c) Disposal of waste, configuration & sequence of year wise build up of dumps &protective measures:-No Backfilling will be done in the area after complete extraction of full thickness ofbauxite. The waste generated during modified mining plan period will be stacked inthe pit floor. As volume of voids (area to be worked) is much more than materialavailable for backfilling, entire mined out area up to original ground level will notpossible. Therefore mined out lease area will be used as water reservoir. Fencing willbe carried out around the water reservoir.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-22
FIGURE-2.5CONCEPTUAL PLAN & SECTION
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-23
2.13 Drilling & Blasting: -
The bauxite horizon being of compact formation, required drilling and blasting in the 30 % of
bauxite zone for this purpose 2.00m deep hole will be drilling by jack hammer and will be
blasted by the 25mm dia and 250mm long explosive available in the region. The spacing and
burden will be kept as 1M.
The broad parameters are as under:
1. Spacing : 1.5M
2. Burden : 1.5M
3. Depth : 2.0M
4. Diameter of hole : 30MM
5. Explosive per wise hole : 1.6 Kg/
6. Power factor : 7MT/Kg
7. No of holes blasted per round : 10holes as per round
8. Maximum hole blasted per day : 10holes as per round
The blasted material from the bauxite horizon will be broken and sorted manually. About 25
holes will be required daily and 30 kg. Gelatin, 255 detonator and 62.5m fuse coil will be
required daily.
The blasting will be done by qualified blaster. The magazine of M/s Prabhudas Vithaldas
situated at Block A of Virpur Kenedy bauxite. The explosive will be transported from the
magazine.
Precautions to be observed during drilling & blasting: -
During drilling, for the safety of the workers ear muff are provided to the workers to protect
them from the effect of noise created by blasting. Prior to blasting people are posted are
posted at appropriate distance at all safety points around the lease area to prevent the
vehicle as well as pedestrians entering the area.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-24
1. Loading Equipment: -
S.No Type Nos. Bucket
capacity in
M3
Make Motive
power
HP
1 Excavator One 1.0 M3 Tata Diesel 250
Haulage and transport equipment
2. Haulage with in the mining lease hold:-
S.No Type Nos. Size
capacity in
tonnes
Make Motive
power
HP
1 Tippers Two 10MT Tata - -
1. Drilling Machine: -
S.No Type Nos. Diameter
of hole in
MM
Make Motive
power
HP
1 Jack hummar (RH
658/42)
One 32MM Atlas
Capco
- -
2 Compressor one 100cft/m Atlas
Capco
- -
Water Pump –One 5HP
2.14 Water Requirement:-
Water for drinking and operations is required to be 8.0 KLD. It is proposed to obtain water
for drinking from nearby villages.
The breakup of total water requirement of the mines is given in Table-2.6.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-25
TABLE-2.6WATER REQUIREMENT
Sr. No. Water Requirement Quantity (m3/day)1 Drinking/Domestic use 2.0
2 Water sprinkling to suppress dust at loading face,Wet drilling, Spraying on Haul roads and
plantation etc.
3.0
3 Greenbelt 3.0
Total 8.0
2.15 Power Supply
If any, as per requirement.
2.16 Proposed Manpower
The lessee is having mining leases in this area and has employment quite a number ofqualified mining engineers and geologist who are already in charge of these working.
ORGNISATION CHARTDesignation Number of Employees
Full time Mining Engineer cum MinesManager -(As per rule 42 of MCDR 1988)
1
Geologist 1Mines Mates Cum blaster 1Excavator operator 2Tippers Operator 6Driller 2Helpers 10Man power required for sorting 20
Other 5Total Manpower Requirement 48
2.17 Characteristics of Ore
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Taluka Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-2Project Description
II-26
Bauxite is one of the most important industrial minerals and it being the aluminum ore, is
the principal raw material for the production of alumina. Bauxite is formed by lateralization
of various silicate rocks such as granite, gneiss, basalt, syenite and shale. The bauxite rock
usually includes other materials such as iron hydroxides, clay, silt and free silica. It most
often occurs as a residual soil material in tropical and subtropical areas. It is the primary
source of aluminum.
2.18 Use of Mineral
a. End use industry (Physical & Chemical Composition):-i. End use of mineral:The bauxite produced in the mining lease falls under low category only.The low grade category of bauxite is used in the manufactures of cement and which isexported to Middle East countries.
Physical specification for abrasives and ceramic grade bauxite: -The bauxite to be used in the abrasive grains manufactures and in the manufacture of HighAlumina refractory bricks should be in lump form and the size of the lumps should not beless than 10 cm.Physical specification for cement grade bauxite: -In the case of bauxite used in the manufacture of cement, the lumps can be less than 10cmin size.
(b) Intermediate Industries involved in up gradation of mineral before end use:-There is no industry involved in up gradation of mineral bauxite before its end use. Onlymanual hands sorting of lateritic clay & laterite which are very low is Al2O3 is high in Fe2O3 &SiO2 is being done.(c) Detail requirement of other industries, captive consumption export:-Low grade bauxite is sold to other parties.(d) Physical & Chemical specification of buyers : -Physical & chemical specification of low grade bauxite used in cement manufacture is asunder:-Al2O3 : upto 30 %SiO2 :10 %( max)(f) Proposal for up gradation of ROM:-Except hand sorting (removal of lateritic clay & lateritic) no up gradation is required.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-1
CHAPTER- 3
DESCRIPTION OF ENVIRONMENT
INDEX
SI.NO CONTENT PAGE. NO
3.0 Description of the environmental III/2
3.1 Baseline environmental status III/2
3.2 Study area III/2
3.3 Study period III/2
3.4 Meteorology/Approach III/2
3.5 Meteorological Conditions III/3
3.6 Air environment III/5
3.7 Noise levels III/11
3.8 Water environment III/14
3.9 Soil characteristics III/35
3.10 Land use/land cover mapping III/39
3.11 Traffic analysis III/41
3.12 Biological environment III/44
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-2
3.0 DESCRIPTION OF THE ENVIRONMENTAL
3.1 Preamble
Baseline environmental status in and around the mining lease area depicts theexisting environmental conditions of air, noise, water, soil, biological and socio-economic environment. The project as a center, a radial distance of 10 km isconsidered as study area for baseline data collection and environmental monitoring.The data was collected for various environmental attributes so as to compute theimpacts that are likely to arise due to proposed development activity by Grass RootsResearch & Creation India (P) Ltd. recognized by MoEF as per Environment(Protection) Act, 1986 & NABL through it Laboratory.
The main aim of the impact assessment study depends mainly on two factors. One isthe estimation of impact from proposed project on the environment and second oneis the assessment of the environmental condition. Both are key factors to arrive atthe post project scenario. The estimated impact due to the mine lease area can besuperimposed over the existing conditions to arrive at the post project scenario. Thescope of the baseline studies includes detailed characterization of followingenvironmental components:
Metrological conditions Ambient Air Quality Noise levels Water Quality (Surface + Ground water) Soil Quality Biological Environment
3.2 STUDY AREA
The project as a center, a radial distance of 10 km is considered as study area forbaseline data collection and environmental monitoring.
3.3 STUDY PERIOD
The baseline environment quality was carried out over a radial distance of 10 kmaround the mine during pre- monsoon season of 2015 covering the months of March2015 to May 2015.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-3
3.4 METHODOLOGY / APPROACH
3.4.1 Methodology of EIA
Environmental Impact Assessment study has been conducted within an area of 10km radius around the ML area. The various steps involved in the study for thisproject are divided into three following phases.
• Identification of significant environmental parameters and assessing thebaseline status within the study area and assessment of pollutants envisageddue to proposed activities and the polluting activities in the study area onvarious environmental parameters.
• Perdition of impacts after superimposing the predicted pollution load over thebaseline condition.
• Prepare Environmental Management Plan for mitigation of impacts onenvironment arising out of the proposed activity.
3.4.2 Approach
Environmental monitoring in order to establish the baseline environmental status ofthe study area for Ambient air, Water, Soil, Land use, ecology, etc.
• Collection of site specific meteorological data at the mine site.• Carrying out a detailed biological study for the Core and Buffer Zone.• Literature review that includes identification of relevant data and articles
from various publications, various government agencies and other sourcesfor socio-economy, demography, meteorology, land use, ecology, etc.
• Identify various existing pollution loads due to mining and domesticactivities in the buffer zone.
• Evaluate the predicted impacts on the various environmental attributes inthe study area by using scientifically developed and widely acceptedEnvironmental Impact Assessment (EIA) Methodologies.
• Preparation an Environmental Management Plan (EMP) outlining themeasures for improving the environmental quality.
3.5. METEOROLOGICAL CONDITIONS
Meteorology is the key to understand the air quality. The essential relationshipbetween meteorology and atmospheric dispersion involves the wind in the broadestsense. Wind fluctuations over a very wide range of time, accomplish dispersion andstrongly influence other processes associated with them.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-4
A meteorological station was set up at the proposed mine lease. Meteorological datawas generated during the pre monsoon March – May 2015 monitoring period andshown in Table-3.1.The following parameters were recorded at hourly intervals continuouslyduring monitoring period, except rainfall which was recorded on daily basis.
Wind speed Wind Direction Air Temperature Relative Humidity Rainfall
Figure 3.1The wind-rose diagram (Mar – April, 2015)
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-5
Table-3.1Summarized Project site Meteorological Data for Post-Monsoon
MonthWind Speed (km/h) Temperature (°C)
Rainfall(mm)
Relative Humidity (%)
Max AvgCalm(%)
Max Min Avg Max Min Avg
March2015 18.2 8.9 25 34.8 19.1 46.9 0.1 63.7 15.1 37
April2015 24 13.3 21 40.1 24.4 32.3 0.0 73.8 12 40.2
May2015 26.5 16.2 19 42.2 25.8 34.0 0.19 79.4 11.74 44.7
3.6 AIR ENVIRONMENT
3.6.1 Ambient Air Quality
The ambient air quality was monitored in the impact area as per MoEF guidelines.The study area represents mostly rural environment. The prime objective of thebaseline air quality study was to assess the ambient air quality of the mining leasearea.
3.6.2 Methodology Adopted for the Study
The baseline status of the ambient air quality has been assessed through ascientifically designed ambient air quality network. The design of monitoringnetwork in the air quality surveillance programme has been based on the followingconsideration.
Meteorological parameters. Topography of the study area. Representative of regional background air quality for obtaining baseline status
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-6
Representative of likely impact areas.
Ambient Air Quality Monitoring (AAQM) stations were set up at 7 locations with dueconsideration to the above mentioned points. AAQM locations were selected indownwind and upwind direction of the proposed mining lease area covering coreand buffer zones taken unit consideration of the converge factor. Monitoringlocation at 500m in downwind direction is also considered. The details of themonitoring stations are given in Figure 3.2.
Ambient air quality monitoring was carried out twice a week with a frequency of 24hours for 12 weeks during the study period. The common air pollutant namelyParticulate Matter-10 (PM10), Sulphur-dioxide (SO2) and Oxides of Nitrogen (NOX) hasbeen measured through a planned field monitoring.The baseline values of the air pollutants of concern are presented in Tables belowstatistical parameters like minimum, maximum, average and 98th percentiles havebeen computed from the observed field data for all sampling stations and are givenTable-3.3, Table-3.4, and Table-3.5. These are compared with the standardsprescribed by Central Pollution Control Board (CPCB) for industrial, residential andrural zone.
Table-3.2Location of Ambient Air Quality Monitoring Stations
Locations Code LocationsDistance wrt tothe mine (km)
Direction wrt tothe mine
Core Zone
AQ1 Project Site 0 0Buffer Zone
AQ2 500 mtr from project 500m EAQ3 Mota Asota 5 NEAQ4 Harbardi 6 SEAQ5 Mewasa 5 SAQ6 Mahadeviya 8 SWAQ7 Pindara 7 WSW
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-7
Table-3.3
Ambient Air Quality in the Study Area PM10
Location PM10 (µg/m3 )
Code Name of theStation
Min Max Average 98th
percentilesAAQ-1 Project Site
(Virpur) 86.2 139.4 103.6 130.7AAQ-2 500m project
site. 88.0 104.0 96.8 103.8AAQ-3 Mota & Asota 53.7 83.8 65.3 83.1AAQ-4 Habaradi 50.5 64.2 56.5 63.3AAQ-5 Mevasa 62.5 90.5 73.8 89.4AAQ-6 Mahadeviya 64.1 99.7 77.3 97.4AAQ-7 Pindara 72.8 90.8 84.0 90.2
Table-3.4
Ambient Air Quality in the Study Area SO2
Location SO2 (µg/m3 )
Code Name of theStation
Min Max Average 98th
percentilesAAQ-1 Project Site
(Virpur) 5.1 6.8 5.8 6.8AAQ-2 500m from
project site <5 6.8 5.9 6.8AAQ-3 Mota & Asota 5.1 6.8 5.9 6.7AAQ-4 Habaradi <5 6.2 5.7 6.2AAQ-5 Mevasa <5 6.2 5.6 6.2AAQ-6 Mahadeviya <5 6.6 6.0 6.6AAQ-7 Pindara <5 6.6 5.9 6.6
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-8
Table-3.5
Ambient Air Quality in the Study Area NOx
Location NOx (µg/m3 )Code Name of the
StationMin Max Average 98th
percentilesAAQ1 Project Site
(Virpur) 10.1 13.8 11.9 13.7
AAQ2500m fromproject site 9.4 15.3 12.7 15.1
AAQ3 Mota & Asota 8.5 13.6 10.8 13.3AAQ4 Habaradi 7.2 14.9 9.7 13.9AAQ5 Mevasa 9.2 14.8 12.9 14.7AAQ6 Mahadeviya 7.4 12.7 10.5 12.7AAQ7 Pindara 6.5 14.3 10.4 13.6
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-9
Figure 3.2Ambient Air Monitoring Locations
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-10
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-11
3.6.3: Baseline Scenario
a) Particulate Matter (PM10)
Particulate matter in general terms is the particulate matter in ambient air. Itincludes dust, smoke etc. In general some of the important sources of suspendedparticulate matter are mines. The following sources of suspended particulate matterin the study area are identified:
o Emission due to vehicular movemento Dust generation from ground or other mining operations
The minimum and maximum concentration of PM10 recorded within the study areawas 50.5 µg/m3 to 139.4 µg/m3 with the 98th percentile ranging between 63.3µg/m3 to 130.8 µg/m3.
The 24 hourly average values of PM10 were compared with the National Ambient AirQuality Standards (NAAQS) and found that some sampling stations recorded in thestudy area are above the applicable limits i.e., 100 µg/m3 for PM10.
b) Sulfur Dioxide (SO2)
Sulfur dioxide gas is an inorganic gaseous pollutant. Sulfur dioxide emissions areexpected to be emitted wherever combustion of any fuel containing sulfur takesplace. The sulfur in the fuel will combine with oxygen to form sulfur dioxide. Thefollowing sources of sulfur dioxide in the study area are identified:
Emissions from domestic/consumption of fuel (coal, diesel, etc) Emissions from DG sets used by mining activity and local residents
Sulfur dioxide in atmosphere can combine with water (moisture) in the air to formsulphuric acid aerosols that can corrode metal surfaces, fabrics and the leaves ofplants. Sulfur dioxide is an irritant to the eyes and respiratory system. Excessiveexposure to sulfur dioxide can cause bronchial asthma and other breathing relateddiseases as it affects the lungs.
The minimum and maximum concentration of SO2 recorded within the study areawas <5 to 6.8 µg/m3 with the 98th percentile ranging between 6.2 µg/m3 to 6.8µg/m3.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-12
The 24 hourly average values of SO2 were compared with the National Ambient AirQuality Standards (NAAQS) and it was found that all sampling stations recordedvalues are below the applicable limits 80 µg/m3.
c) Oxides of Nitrogen (NO2)
The important sources of oxides of Nitrogen are from utilities and auto exhaust dueto vehicular movement in mine lease area. The following sources of oxides ofnitrogen in the study area are identified.
o Emissions from field burning of coal.o Emissions from vehicular movements in the study area.
Oxides of Nitrogen in the presence of sunlight will undergo reactions with a numberof organic compounds to produce all the effects associated with photochemicalsmog. NOX has inherent ability to produce deleterious effects by themselves liketoxicity. It causes asphyxiation when its concentration is great enough to reduce thenormal oxygen supply from the air.
The minimum and maximum concentration of NOx recorded within the study areawas 6.5 µg/m3 to 15.3 µg/m3 with the 98th percentile ranging between 12.7 µg/m3to 15.1 µg/m3.
The 24 hourly average values of NO2 were compared with the National Ambient AirQuality Standards (NAAQS) and it was found that all sampling stations recordedvalues are below the applicable limits 80 µg/m3.
3.7 NOISE LEVELS
Noise is one of the most undesirable and unwanted by-products of our modern lifestyle. It may not seem as insidious or harmful as air and water pollutants but itaffects human health and well-being and can contribute to deterioration of humanwell-being in general and can cause neurological disturbances and physiologicaldamage to the hearing mechanism in particular. It is therefore, necessary tomeasure both the quality as well as the quantity of noise in and around theproposed site.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-13
3.7.1 Source of Noise
The main sources of noise in the study area are domestic activities, industrialactivities and vehicular traffic. The main occupation of the villagers in the study areais agriculture and business.
3.7.2 Noise Level in the Study Area
The baseline noise levels have been monitored at 7 locations within the study zone,using a sound level meter and noise level measurement locations were identified forassessment of existing noise level status, keeping in view the land use pattern,industrial area, Silence Zone, residential areas in villages etc., if available within 10km radius of the study area. The day levels have been monitored during 6.00 AM to10.00 PM and night noise levels, during 10.00 PM to 6.00 AM. The noise monitoringstations are shown in Figure 3.3 and represented in Table 3.6. The results arepresented in Table 3.8.
Figure 3.3Noise monitoring stations
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-14
Table 3.6Noise Level Monitoring Stations in the Study Area
Locations Code Locations Distance wrt tothe mine (km)
Direction wrt tothe mine (km)
Core Zone
NQ1 Project Site 0 0Buffer Zone
NQ2 500m from project site W 500MNQ3 Mota Asota NE 5NQ4 Harbardi SE 6NQ5 Mewasa S 5NQ6 Mahadeviya SW 8NQ7 Pindara WSW 8
Table 3.7
Hourly Leq Noise Level in the Study Area (March 2015 to May 2015)
SI. No. Locations Equivalent Noise Level, dB (A)Observed Value, dB (A) Prescribed Limit,
dB(A)Day Night Day, Night
Core Zone1. NQ1 Industrial Area 68.4 53.2 75 70Buffer Zone2. NQ2 Industrial Area 66.5 54.6 75 703. NQ3 Residential
Area52.7
43.255 45
4. NQ4 ResidentialArea
54.244.5
55 45
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-15
5. NQ5 ResidentialArea
53.143.2
55 45
6. NQ6 ResidentialArea
52.742.3
55 45
7. NQ7 Silence Area 46.3 38.1 50 40
3.7.3 Ambient Noise Standards
Ministry of Environment Forests & climate change has notified the noise standards videgazette notification dated February 14, 2000 for different zones under the EnvironmentProtection Act (1986). These standards are given in Table-3.8.
Table 3.8
Ambient Quality Standards in respect of Noise
Area Code Category of Area Noise dB (A) Leq
Daytime* Night time*A Industrial Area 75 70B Commercial Area 65 55C Residential Area 55 45D Silence Zone 50 40
Note:1. Daytime is from 6.00am to 10.00 pm and Nighttime is from 10.00 pm to
6.00 am.2. Silence zone is defined as area up to 100 meters around premises of hospitals,
educational institutions and courts. Use of vehicle hours, loud speakers and burstingof crackers are banned in these zones
3.7.4 Baseline Scenario
The values of noise observed in some of the areas are primarily owing to vehiculartraffic and other anthropogenic activities. Assessment of night time Leq (Ln) variesfrom 38.1 to 54.6 dB (A) and the daytime Leq (Ld) varies from 46.3 to 68.4 dB (A)within the study area.
The status of noise quality within the 10 km zone of the study area is, therefore,within the MoEF standards.
3.8 WATER ENVIRONMENT
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-16
3.8.1 Water Quality
Water quality assessment is one of the essential components of EIA study. Suchassessment helps in evaluating the existing health of water body and suggestingappropriate mitigation measures to minimize the potential impact fromdevelopment projects. Water quality of surface and ground water has been studiedin order to assess proposed water-uses in construction, drinking, cooling andhorticulture purpose.
The water quality at the site and other locations within the 10 km impact zone wasmonitored during March – May 2015. The water sampling locations marked withinthe study are presented in Table 3.10 and Figure 3.4 and the result of themonitoring and analysis are presented in the Table 3.11 to Table 3.16 showingWater Quality Monitoring Locations marked within the Study Area.
Table 3.9Location of Water Sampling Sites
GW-Ground water, SW-Surface water
Location Code. Sample collected fromGround Water Samples
GW – 1 Project SiteGW – 2 Mota AsotaGW –3 MewasaGW-4 PindaraGW -5 Mahadeviya
Surface Water SamplesSW – 1 Ran RiverSW – 2 Pindara BaySW-3 Ni pall pond
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-17
Figure 3.4Water Quality Monitoring Location
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-18
Table 3.10
Surface water Sample Analysis Results during March -2015S.No. Parameter Unit S.W. 1 S.W. 2 S.W. 3
ran River Pindara Bay Ni Pall pond1 pH - 8.09 8.2 7.862 Dissolved Oxygen mg/l 7.5 6.5 6.73 BOD (3 Days at 27 °C) mg/l 4 1.2 54 Free Ammonia (as N) mg/l <0.1 <0.1 <0.15 Sodium Adsorption Ratio - 4.13 19.58 1.286 Boron mg/l 0.2 1.2 0.47 Conductivity µmhos/cm 950 71004 4508 Temperature (°C) 24 25 269 Turbidity NTU 10 10 12
10 Magnessium Hardness ( as CaCO3) mg/l 58 5440 4811 Total Alkalinity (as CaCO3) mg/l 162 4210 13812 Chloride (as Cl) mg/l 146 18038 4213 sulphate (as SO4) mg/l 67 2650 2014 Nitrate (as NO3) mg/l 0.4 0.8 0.515 Fluoride (as F) mg/l 0.8 1.1 0.816 Sodium (as Na) mg/l 121 7434 3517 Potassium (as K) mg/l 14 342 4
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-19
18 TKN mg/l 1.8 1.5 1.619 Total Phosphorous (as P) mg/l 0.03 0.06 0.0220 COD mg/l 12 6 1021 Phenolic compounds (as C6H5OH) mg/l <0.001 <0.001 <0.00122 Lead (as Pb) mg/l <0.01 <0.01 <0.0123 Iron (as Fe) mg/l 0.11 0.16 0.1024 Cadmium (as Cd) mg/l <0.01 <0.01 <0.0125 Zinc (as Zn) mg/l 0.07 0.07 0.0626 Arsenic (as As) mg/l <0.01 <0.01 <0.0127 Mercury (as Hg) mg/l <0.001 <0.001 <0.00128 Chromium (as Cr) mg/l <0.01 <0.01 <0.0129 Nickel (as Ni) mg/l <0.01 <0.01 <0.0130 TDS mg/l 570 42602 270
Bacteriological parameter1 Total Coliform MPN/100ml 1900 180 24002 Faecal Coliform MPN/100ml 210 45 300
NR - No Relaxation
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-20
Table 3.11Surface water Sample Analysis Results during April -2015
S.No. Parameter Unit S.W. 1 S.W. 2 S.W. 3ran River Pindara Bay Ni Pall pond
1 pH - 8.2 8.12 7.867.782 Dissolved Oxygen mg/l 6.8 6.5 6.33 BOD (3 Days at 27 °C) mg/l 4.6 1.2 4.24 Free Ammonia (as N) mg/l <0.1 <0.1 <0.15 Sodium Adsorption Ratio - 4.2 19.56 1.296 Boron mg/l 0.3 1.2 0.347 Conductivity µmhos/cm 993 70889 4968 Temperature (°C) 24 22 279 Turbidity NTU 12 8 13
10 Magnessium Hardness ( as CaCO3) mg/l 60 5400 5311 Total Alkalinity (as CaCO3) mg/l 167 4000 14312 Chloride (as Cl) mg/l 152 18038 48
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-21
13 sulphate (as SO4) mg/l 72 2750 2614 Nitrate (as NO3) mg/l 0.32 0.6 0.2815 Fluoride (as F) mg/l 0.6 1.3 0.916 Sodium (as Na) mg/l 125 5637 3717 Potassium (as K) mg/l 16 340 618 TKN mg/l 2 1.5 1.819 Total Phosphorous (as P) mg/l 0.04 0.07 0.0320 COD mg/l 13.2 5 12.821 Phenolic compounds (as C6H5OH) mg/l <0.001 <0.001 <0.00122 Lead (as Pb) mg/l <0.01 <0.01 <0.0123 Iron (as Fe) mg/l 0.12 1.15 0.1324 Cadmium (as Cd) mg/l <0.01 <0.01 <0.0125 Zinc (as Zn) mg/l 0.08 0.07 0.0726 Arsenic (as As) mg/l <0.01 <0.01 <0.0127 Mercury (as Hg) mg/l <0.001 <0.001 <0.00128 Chromium (as Cr) mg/l <0.01 <0.01 <0.0129 Nickel (as Ni) mg/l <0.01 <0.01 <0.0130 TDS mg/l 595 42533 297
Bacteriological parameter1 Total Coliform MPN/100ml 2000 210 2600
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-22
2 Faecal Coliform MPN/100ml 220 60 310NR - No Relaxation
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-23
Table 3.12Surface water Sample Analysis Results during May -2015
S.No. Parameter Unit S.W. 1 S.W. 2 S.W. 3ran River Pindara Bay Ni Pall pond
1 pH - 7.86 8.16 7.72 Dissolved Oxygen mg/l 6.3 6.5 6.03 BOD (3 Days at 27 °C) mg/l 4 1.2 3.54 Free Ammonia (as N) mg/l <0.1 <0.1 <0.15 Sodium Adsorption Ratio - 4.2 26.5 1.296 Boron mg/l 0.4 1.2 0.37 Conductivity µmhos/cm 958 71900 5028 Temperature (°C) 28 25 309 Turbidity NTU 11 7 12
10 Magnessium Hardness ( as CaCO3) mg/l 58 5460 5611 Total Alkalinity (as CaCO3) mg/l 160 4500 14012 Chloride (as Cl) mg/l 148 18060 5013 sulphate (as SO4) mg/l 69 2750 2814 Nitrate (as NO3) mg/l 0.34 0.65 0.2915 Fluoride (as F) mg/l 0.7 1.3 0.816 Sodium (as Na) mg/l 123 7460 3917 Potassium (as K) mg/l 15 580 8
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-24
18 TKN mg/l 2.3 1.5 219 Total Phosphorous (as P) mg/l 0.05 0.08 0.0620 COD mg/l 16 4 1821 Phenolic compounds (as C6H5OH) mg/l <0.001 <0.001 <0.00122 Lead (as Pb) mg/l <0.01 <0.01 <0.0123 Iron (as Fe) mg/l 0.12 0.15 0.1324 Cadmium (as Cd) mg/l <0.01 <0.01 <0.0125 Zinc (as Zn) mg/l 0.09 0.07 0.0726 Arsenic (as As) mg/l <0.01 <0.01 <0.0127 Mercury (as Hg) mg/l <0.001 <0.001 <0.00128 Chromium (as Cr) mg/l <0.01 <0.01 <0.0129 Nickel (as Ni) mg/l <0.01 <0.01 <0.0130 TDS mg/l 575 43148 301
Bacteriological parameter1 Total Coliform MPN/100ml 2150 270 33002 Faecal Coliform MPN/100ml 250 60 350
NR - No Relaxation
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-25
Table 3.13Groundwater Sample Analysis Results during March -2015
S.No Parameter Unit Limit (IS-10500:2012) GW1 GW2 GW3 GW 4 GW 5
Desirable PermisibleVirpur NearProject site Mota Asota
MewasaPindara Mahadeviya
1 Colour Hazen 5 15 <5 <5 <5 <5 <52 Odour - oderless oderless oderless oderless oderless oderless oderless3 Taste - UnAgreeable UnAgreeable UnAgreeable UnAgreeable UnAgreeable UnAgreeable UnAgreeable4 Turbidity NTU 1 5 1 2 2 6 15 pH -
6.5-8.5No
Relaxation 7.64 7.75 7.62 7.88 7.816 Total Hardness (as
CaCO3)mg/l
200 600 410 478 1380 980 4307 Iron (as Fe) mg/l
0.3No
Relaxation 0.08 0.06 0.09 0.11 0.068 Chlorides (as Cl) mg/l 250 1000 790 550 1520 950 11509 Fluoride (as F ) mg/l 1 1.5 1.8 0.97 1.1 0.7 0.9
10 TDS mg/l 500 2000 2015 1668 4205 2321 263411 Calcium(as Ca2+) mg/l 75 200 98 114 332 235 10312 Magnesium (as Mg2+) mg/l 30 100 40 46 132 95 4113 Copper (as Cu) mg/l 0.05 1.5 <0.01 <0.01 <0.01 <0.01 <0.0114 Manganese(as Mn) mg/l 0.1 0.3 0.05 0.04 0.04 0.13 0.03
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-26
15 Sulphate (as SO4) mg/l 200 400 140 135 154 148 14516 Nitrate(as NO3) mg/l
45No
Relaxation 22 18 26 20 2117 Phenolic Compounds
(as C6H5OH)mg/l
0.001 0.002 <0.001 <0.001 <0.001 <0.001 <0.00118 Mercury (as Hg) mg/l
0.001No
Relaxation <0.001 <0.001 <0.001 <0.001 <0.00119 Cadmium (as Cd) mg/l
0.003No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0120 Selenium ( as Se ) mg/l
0.01No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0121 Arsenic (as As) mg/l 0.01 0.05 <0.01 <0.01 <0.01 <0.01 <0.0122 Cyanide (as CN ) mg/l
0.05No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0123 Lead (as Pb) mg/l
0.01No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0124 Zinc (as Zn) mg/l 5 15 0.4 0.06 0.07 0.17 0.1025 Anionic Detergent (as
MBAS)mg/l
0.2 1 <0.01 <0.01 <0.01 <0.01 <0.0126 Chromium (as Cr6+) mg/l
0.05No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0127 Mineral oil mg/l
0.5No
Relaxation <0.1 <0.1 <0.1 <0.1 <0.1
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-27
28 Alkalinity as CaCO3 mg/l 200 600 358 434 1160 368 33829 Aluminum (as Al) mg/l 0.03 0.2 0.3 0.4 0.3 0.2 0.430 Boron (as B) mg/l 0.5 1 0.2 0.3 0.3 0.4 0.5
Microbiological Parameter1 Total Coliform MPN/100ml Shall not be detectable ND (<2) ND (<2) ND (<2) ND (<2) ND (<2)2 E.coli E.coli
/100ml Shall not be detectable Absent Absent Absent Absent AbsentNR - No Relaxation
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-28
Table 3.14Groundwater Sample Analysis Results during April -2015
S.No Parameter Unit Limit (IS-10500:2012) GW1 GW2 GW3 GW 4 GW 5
Desirable PermisibleVirpur NearProject site Mota Asota
MewasaPindara Mahadeviya
1 Colour Hazen 5 15 <5 <5 <5 <5 <52 Odour - Agreeable Agreeable oderless oderless oderless oderless oderless3 Taste - Agreeable Agreeable UnAgreeable UnAgreeable UnAgreeable UnAgreeable UnAgreeable4 Turbidity NTU 1 5 2 3 2 4 25 pH -
6.5-8.5No
Relaxation 7.82 7.65 7.73 7.98 8.026 Total Hardness (as
CaCO3)mg/l
200 600 421 481 1388 988 4397 Iron (as Fe) mg/l
0.3No
Relaxation 0.07 0.05 0.1 0.13 0.078 Chlorides (as Cl) mg/l 250 1000 810 562 1531 962 11659 Fluoride (as F ) mg/l 1 1.5 2 1.1 1.2 0.8 1.1
10 TDS mg/l 500 2000 2062 1706 4249 2361 267511 Calcium(as Ca2+) mg/l 75 200 101 115 333 237 10512 Magnesium (as
Mg2+)mg/l
30 100 40 47 134 96 4213 Copper (as Cu) mg/l 0.05 1.5 <0.01 <0.01 <0.01 <0.01 <0.0114 Manganese(as Mn) mg/l 0.1 0.3 0.04 0.05 0.04 0.13 0.03
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-29
15 Sulphate (as SO4) mg/l 200 400 142 138 156 151 14716 Nitrate(as NO3) mg/l
45No
Relaxation 23 20 28 23 2317 Phenolic Compounds
(as C6H5OH)mg/l
0.001 0.002 <0.001 <0.001 <0.001 <0.001 <0.00118 Mercury (as Hg) mg/l
0.001No
Relaxation <0.001 <0.001 <0.001 <0.001 <0.00119 Cadmium (as Cd) mg/l
0.003No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0120 Selenium ( as Se ) mg/l
0.01No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0121 Arsenic (as As) mg/l 0.01 0.05 <0.01 <0.01 <0.01 <0.01 <0.0122 Cyanide (as CN ) mg/l
0.05No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0123 Lead (as Pb) mg/l
0.01No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0124 Zinc (as Zn) mg/l 5 15 0.6 0.08 0.1 0.16 0.1425 Anionic Detergent (as
MBAS)mg/l
0.2 1 <0.01 <0.01 <0.01 <0.01 <0.0126 Chromium (as Cr6+) mg/l
0.05No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0127 Mineral oil mg/l
0.5No
Relaxation <0.1 <0.1 <0.1 <0.1 <0.1
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-30
28 Alkalinity as CaCO3 mg/l 200 600 366 445 1180 381 34829 Aluminum (as Al) mg/l 0.03 0.2 0.3 0.41 0.33 0.023 0.4330 Boron (as B) mg/l 0.5 1 0.4 0.3 0.5 0.5 0.3
Microbiological Parameter1 Total Coliform MPN/100ml Shall not be detectable ND (<2) ND (<2) ND (<2) ND (<2) ND (<2)2 E.coli E.coli
/100ml Shall not be detectable Absent Absent Absent Absent AbsentNR - No Relaxation
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-31
Table 3.15Groundwater Sample Analysis Results during May -2015
S.No Parameter Unit Limit (IS-10500:2012) GW1 GW2 GW3 GW 4 GW 5
Desirable
Permisible
VirpurNear
Projectsite
MotaAsota
Mewasa Pindara Mahadeviya
1 Colour Hazen 5 15 <5 <5 <5 <5 <52 Odour - Agreeabl
eAgreeable oderless oderle
ssoderle
ssoderless oderless
3 Taste - Agreeable Agreeable
UnAgreeable
UnAgreeable
UnAgreeable
UnAgreeable
UnAgreeable
4 Turbidity NTU 1 5 3 2 4 3 45 pH -
6.5-8.5No
Relaxation 7.83 7.76 7.78 8.04 8.216 Total Hardness (as
CaCO3)mg/l
200 600 426 484 1367 994 4467 Iron (as Fe) mg/l
0.3No
Relaxation 0.08 0.07 0.12 0.15 0.098 Chlorides (as Cl) mg/l 250 1000 816 569 1539 972 11709 Fluoride (as F ) mg/l 1 1.5 2.1 1.2 1.3 0.9 1.2
10 TDS mg/l 500 2000 2089 1737 4281 2398 2704
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-32
11 Calcium(as Ca2+) mg/l 75 200 102 116 328 238 10712 Magnesium (as Mg2+) mg/l 30 100 41 47 132 96 4313 Copper (as Cu) mg/l 0.05 1.5 <0.01 <0.01 <0.01 <0.01 <0.0114 Manganese(as Mn) mg/l 0.1 0.3 0.05 0.06 0.07 0.12 0.0415 Sulphate (as SO4) mg/l 200 400 146 142 160 154 15116 Nitrate(as NO3) mg/l
45No
Relaxation 25 20 30 24 2417 Phenolic Compounds
(as C6H5OH)mg/l
0.001 0.002 <0.001 <0.001 <0.001 <0.001 <0.00118 Mercury (as Hg) mg/l
0.001No
Relaxation <0.001 <0.001 <0.001 <0.001 <0.00119 Cadmium (as Cd) mg/l
0.003No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0120 Selenium ( as Se ) mg/l
0.01No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0121 Arsenic (as As) mg/l 0.01 0.05 <0.01 <0.01 <0.01 <0.01 <0.0122 Cyanide (as CN ) mg/l
0.05No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0123 Lead (as Pb) mg/l
0.01No
Relaxation <0.01 <0.01 <0.01 <0.01 <0.0124 Zinc (as Zn) mg/l 5 15 0.7 0.1 0.12 0.18 0.1625 Anionic Detergent (as
MBAS)mg/l
0.2 1 <0.01 <0.01 <0.01 <0.01 <0.01
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-33
26 Chromium (as Cr6+) mg/l0.05
NoRelaxation <0.01 <0.01 <0.01 <0.01 <0.01
27 Mineral oil mg/l0.5
NoRelaxation <0.1 <0.1 <0.1 <0.1 <0.1
28 Alkalinity as CaCO3 mg/l 200 600 375 456 1190 394 36029 Aluminum (as Al) mg/l 0.03 0.2 0.4 0.32 0.37 0.21 0.4630 Boron (as B) mg/l 0.5 1 0.5 0.2 0.4 0.6 0.4
Microbiological Parameter1 Total Coliform MPN/100
mlShall not bedetectable ND (<2)
ND(<2)
ND(<2) ND (<2) ND (<2)
2 E.coli E.coli/100ml
Shall not bedetectable Absent Absent Absent Absent Absent
NR - No Relaxation
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-34
Sampling Frequency and Sampling Techniques
Parameters for analysis of water quality were selected based on the utility of the particularsource of water as per MoEF guidance. Hence quality of ground water was compared withIS: 10500: 1991 (Reaffirmed 1993 With Amendment NO -3 JULY 2010) for drinking purposes.Surface water quality was monitored for parameters as per Methods of Monitoring &Analysis published by CPCB and it was rated according to the CPCB Water Quality Criteriaagainst A, B, C, D & E class of water. Water samples were collected as Grab water samplefrom sampling location in a 5 liter plastic jerrycan and 250 ml sterilized clean glass/petbottle for complete physico-chemical and bacteriological tests respectively. The sampleswere analyzed as per standard procedure / method given in IS: 3025 (Revised Part) andstandard method for examination of water and wastewater Ed.21st, published jointly APHA,AWWA and WPCF.The surface water quality is compared with CPCB water quality criteria mentioned in Table3.16 below:
Table 3.16Water Quality Criteria as per Central Pollution Control Board
Designated-Best-Use Class ofwater
Criteria
Drinking Water Sourcewithout conventionaltreatment but afterdisinfection
A Total Coliforms Organism MPN/100ml shallbe 50 or lesspH between 6.5 and 8.5Dissolved Oxygen 6mg/l or moreBiochemical Oxygen Demand 5 days 20°C2mg/l or less
Outdoor bathing (Organized) B Total Coliforms Organism MPN/100ml shallbe 500 or less;pH between 6.5 and 8.5;Dissolved Oxygen 5mg/l or moreBiochemical Oxygen Demand 5 days 20°C3mg/l or less
Drinking water source afterconventional treatment anddisinfection
C Total Coliforms Organism MPN/100ml shallbe 5000 or less;pH between 6 to 9;Dissolved Oxygen 4mg/l or moreBiochemical Oxygen Demand 5 days 20°C3mg/l or less
Propagation of Wild life andFisheries
D pH between 6.5 to 8.5Dissolved Oxygen 4mg/l or more Free
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-35
Ammonia (as N) 1.2 mg/l or lessIrrigation, Industrial Cooling,Controlled Waste disposal
E pH between 6.0 to 8.5Electrical Conductivity at 25°C micromhos/cm Max.2250Sodium absorption Ratio Max. 26Boron Max. 2mg/l
Below-E Not Meeting A, B, C, D & E Criteria
As per the standard practice, one sample from each station was taken each month inthe study period. Sampling was done by standard sampling technique as per theStandard Methods. Necessary precautions were taken for preservation of samples.
3.8.2 Result & Conclusion:
The pH limit fixed for drinking water samples as per IS-10500 Standards is 6.5to 8.5 beyond this range the water will affect the mucus membrane and orwater supply system. During the study period, the pH was varying for groundwaters from 7.62 to 8.21 & pH was varying for surface waters from 7.7 to8.16. The pH values for all the samples collected in the study area duringstudy period were found to be within the limits.
The desirable limit for total dissolved solids as per IS-10500 Standards is 500mg/l where as the permissible limits in absence of alternate source is2000mg/l, beyond this palatability decreases and may cause gastro intestinalirritation. In ground water samples collected from the study area, the totaldissolved solids are varying from 1668 mg/l to 4249 mg/l the TDS of thesamples above the permissible limit of 2000 mg/l.
The desirable limit for chlorides is 250 as per IS-10500 Standards where aspermissible limit of the same is 1000 mg/l beyond this limit taste, corrosionand palatability are affected. The chloride level, in ground water samples 550mg/l to 1539 mg/l. & for surface water it is 42 mg/l to 18060 mg/l thechloride samples are within the above limits.
The desirable limit as per IS-10500 Standards for hardness is 300 mg/l whereas the permissible limit for the same is 600 mg/l beyond this limitencrustation in water supply structure and adverse effects on domestic usewill be observed. In the ground water samples collected from the study area,the hardness is varying from 410 mg/l to 1388 mg/l.
Fluoride is the other important parameter, which has the desirable limit of1mg/l and permissible limit of 1.5 mg/l. however the optimum content offluoride in the drinking water is 0.6 to 1.5 mg/l. if the fluoride content is less
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-36
than 0.6 mg/l it causes dental carries, above 1.5 mg/l causes flurosis. In theground water samples of study area the fluoride value were in the range of0.7 mg/l to above limit in surface water it varies from 0.6 mg/l to 1.3.
Overall all the samples collected from the study area were found to be forconsumption, Most of ground water samples limits. Most of the heavy metals in allsamples are below detectable limits.
3.9 Soil Characteristics
The composite soil samples were collected from site and the study area and wereanalyzed for characterization. The locations of the monitoring sites are depicted inFigure 3.5 and given in Table 3.17 Showing Soil Sample Collection Points markedwithin the Study Area.
3.9.1 Methodology
The soil samples were collected in the month of April - 2015. Soil samples werecollected from 7 locations, at each of these locations, the sub-locations wereidentified randomly from where soil was collected from 30 cm below the surface.The final samples represent homogenously mixed soil from these sub-locations foreach location. The samples were filled in polythene bags, labeled in the field withnumber and site name and sent to laboratory for analysis. The test results are givenin Table-3.18.
Particulars DetailsFrequency One grab sample from each station– once during the Study
PeriodMethodology Composite grab samples of the topsoil were collected from 3
depths, and mixed to provide a representative sample foranalysis. They were stored in airtight Polythene Bags andanalyzed at the laboratory
Table 3.17
Soil Sample Collection Points
Code Location Direction wrt to the mine (km) Distance wrt to the mine (km)
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-37
Figure 3.5Soil Sample Collection Points
Core ZoneSQ- 1 Project Site - -
Buffer Zone
SQ2 500m fromproject site W 500m
SQ3 Mota Asota NE 5SQ4 Harbardi SE 6SQ5 Mewasa S 5SQ6 Mahadeviya SW 8SQ7 Pindara WSW 8
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-38
Table 3.18Phyisco-Chemical Properties of Soil
S.No Parameter Unit SQ-1 SQ-2 SQ-3 SQ-4 SQ-5 SQ-6 Sq-7Project
siteVirpur
500MtrFrom
Project site
Mota Asota Harbardi Mewasa Mahadeviya Pindara
1Texture -
sandyLoam
Sandy ClayLoam
Sandy ClayLoam
SandyLoam
Sandy ClayLoam Sandy Loam
Sandy ClayLoam
Sand % 66.8 53.6 51.7 62.1 58.3 61.7 55.7Silt % 15.6 22.3 23.2 20.5 19.1 18.5 23.9Clay % 17.6 24.1 25.1 17.4 22.6 19.8 20.4
2 pH (1:2) - 7.46 7.86 7.51 7.46 7.62 7.89 7.51
3Electrical Conductivity(1:2) µmhos/cm 241 365 432 305 285 336 330
4Cation exchangecapacity
meq/100gm 15.3 21.0 22.7 17.2 19.2 17.1 16.5
5 Potassium mg/kg 93 168 135 142 175 161 1546 Sodium mg/kg 102 125 106 126 123 106 1137 Calcium mg/kg 2419 3152 3326 2658 2869 2546 2533
11 Magnesium mg/kg 305 512 626 365 469 416 422
8Sodium AbsorptionRatio - 0.52 0.54 0.44 0.61 0.56 0.51 0.55
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-39
9Water HoldingCapacity % 25.3 29.4 30.5 26.3 28.3 27.1 29.3
10 Porosity % 40.3 35.6 34.5 39.2 37.2 38.1 36.5
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-40
3.9.2 Results of Analysis of the Soil
Physical characteristics of soil were characterized through specific parameters vizbulk density, porosity, water holding capacity, pH, electrical conductivity andtexture. Soil pH plays an important role in the availability of nutrients. Soilmicrobial activity as well as solubility of metal ions is also dependent on pH. In thestudy area, variations in the pH of the soil were found to be Neutral (7.46 to 7.86).Electrical conductivity (EC) is a measure of the soluble salts and ionic activity inthe soil. In the collected soil samples the conductivity ranged from 241-432µmhos/cm.
The soils with low bulk density have favorable physical condition where as thosewith high bulk density exhibit poor physical conditions for agriculture crops.
3.10 Land Use/Land Cover Mapping
To assess the land use pattern surrounding the 10 km radius of the site, a detailedstudy was carried out. The land use pattern study reveals that the 10 km environs ispredominantly settlement area in the East while the entire West is occupied bysome Agriculture and Reserved or protected forest land. The landuse details aregiven in Table- 3.19 and shown in Figure-3.6.
Table 3.19The land use of the study area
SI. No Description Area (ha)1 Settlement 16.132 Ocean 12225.773 Open Land 3189.644 Open Scrub 314.545 River 56.896 Salt Waste 2393.127 Water Bodies 1950.118 Agricultural Land 14734.36
Total 34880.56
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-41
Figure 3.6Land use delineation of 10 km radius area
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-42
3.11 Traffic Study
Traffic study is carried out by understanding the existing carrying capacity of theroad near to the project site and connecting main roads in the area. Then dependingon the capacity of the mine, the number of truck that will be added to presentscenario will be compared to the carrying capacity. The existing volume of trafficand, the Level of Service are given in Table-3.20.
Table 3.20 Existing Traffic Scenario & LOS
V= Volume in PCU’s/day & C= Capacity in PCU’s/ day
The existing Level of Service near Village is “A” i.e. excellent and at highway is “A”i.e. excellent when compared with LOS recommended by IRC, as given in Table-3.22.
Total Capacity of mine : 1, 51,875 TPA
No. of working days : 302 days
Average Production per day : 502 tonnes
Truck Capacity : 20 tonnes approx.
No. of trucks trips /day : 25 truck approx
No. of truck trips per day to & fro : 25*2 = 50
Increase in PCU per day : 200
Table 3.21 Additional Traffic Scenario & LOS due to proposed project
Road V(PCU/day) C(PCU/day) Modified V/CRatio
LOS
Virpur Village 200+90=290 1800 0.16 A
NH - 974 200+500=700 6000 0.11 A
Road V(PCU/day) C(PCU/day) Existing V/C Ratio LOS
Vicinity of site 90 1800 0.05 A
Road towardsVirpur
500 6000 0.08 A
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-43
Traffic study is carried out by understanding the existing carrying capacity of the road nearto the project site and connecting main roads in the area. Then depending on the capacityof the mine, the number of truck that will be added to present scenario will be compared tothe carrying capacity. The existing volume of traffic and, the Level of Service are given inTable-3.22.
Table 3.22 (V/C Ratio & LOS)
Level ofService
Definition Volume to capacityratios PerformanceFreeways All other
roadways
AConditions of free flow; speed is controlledby driver’s desires; speed limits, or physicalroadway conditions.
0.0-0.34 0.0-0.34 Excellent
B
Conditions of stable flow; operating speedsbeginning to be restricted; little or norestriction on maneuverability from othervehicles.
0.35-0.54 0.35-0.50 Very Good
C
Conditions of stable flow; speeds andmaneuverability more closely restricted;occasional backups behind left-turningvehicles at intersections.
0.55-0.77 0.51-0.74Good /
Average /Fair
D
Conditions approach unstable flow;tolerable speeds can be maintained buttemporary restrictions may cause extensivedelays; little freedom to maneuver; comfortand convenience low; at intersections, somemotorists, especially those making leftturns, may wait through one or more signalchanges.
0.78-0.93 0.75-0.89 Poor
EConditions approach capacity; unstable flowwith stoppages of momentary duration;maneuverability severely limited.
0.94-0.99 0.90-0.99 Very Poor
Note: Capacity as per IRC: 64-1990From the above analysis it can be seen that V/C ratio is “excellent” in the vicinity area,whereas for the road approaching Virpur is also “excellent”. As per the classification theadditional load on the carrying capacity of the concerned roads will not have any significantchange.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-44
Figure 3.7: Transportation Route Map
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-45
3.12 BIOLOGICAL ENVIRONMENT
3.12.1 Introduction
Biodiversity reflects the potential of a regional ecosystem. Biota of a particular area is
considered as indicators of the environment as they quickly respond not only to one
environmental factor but also an interactive group of factors. These communities influence
and react sensitively to changes in the balance of environmental stresses.
Biological diversity comprises the variability of genus, species and ecosystems and is very
crucial for maintaining the basic processes on which the life depends. On the basis of
biological physiology biodiversity broadly can be divided into two category i.e. the floral
diversity and faunal diversity. Conservation of the biodiversity is essential for the
sustainable development as it not only provides the food, fodder and medicine, but also
contributes to improvement of essential environmental attributes like air, water, soil, etc.
Before starting any Environmental Impact Assessment study, it is necessary to identify the
baseline of relevant environmental parameters which are likely to be affected as a result of
the operation of the proposed project. A similar approach has been adopted for conducting
the study on Biological Environment for this Project. Both terrestrial and aquatic ecosystems
have been studied to understand the biological environment nearby the project site.
The study was conducted in the project area to assess all possible consequences on the
biological environment. Flora and fauna surveys and data collection conducted for assessing
the biological diversity and its status over a period of time that forms an integral part of
Impact Assessment Techniques. The present study is highlighting the various issues
pertaining to floristic diversity and the faunal wealth in the core area i.e. Virpur (Gunawali)
Bauxite Mine, District Devbhoomi Dwarka (Gujarat) and buffer zone i.e. area within 10 km
radius.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-46
3.12.2 Description of Study
Virpur (Gunawali) Bauxite Mine is situated near the Virpur village which is spread over an
area of 55.2520 ha and located in the Devbhoomi Dwarka district of Gujarat near the
Kalyanpur tehsil.
Devbhoomi Dwarka District is located in the North West of Gujarat. It is bounded partly by
Gulf and partly by the desert of Kutch in the North, Porbandar district in the South, Jamnagar
district in the East and Arabian Sea in the West. The District has a geographical area of
40, 51 sq. km. Devbhoomi Dwarka district is situated under the Seismic Zone-IV as per IS-
1893 (part-1)-2002. The district has a hot semi-arid tropical climate. The district has
maximum agricultural land out of its total geographical area. The district is not enriched
with forest. The forest of Devbhoomi Dwarka district comprises of tropical deciduous
vegetation due to high temperature and humidity.
Present mining lease area (Gunawali) is located on the barren land in the Devbhoomi
Dwarka district near the Sea shore. There is no any agriculture land nearby the mining lease
area. Some agriculture land is present away from the mining lease area. The main crop of
the buffer area is Cotton (Gossypium herbaceum)followed by Castor (Ricinus communis), Ground
nut (Arachis hypogaea), Bajra (Pennisetum typhoides), Jowar (Sorghum bicolor), Jeera/Jeeru
(Cumium cyminum), Wheat (Triticum aestivum), Tuver (Cajanus cajan), Mug (Magna radiate),
Mango (Mangifera indica) and Chikko (Manikara zapota).
As an Eco-Sensitive zone, Marine National Parks and Sanctuary, Jamnagar is situated at the
distance of 1 km away in north-West direction (Fig. 1).
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-47
Fig. 1: Location map of Gunawali (Virpur) Bauxite Mine, District Devbhoomi Dwarka
3.12.3 Climate:
The Devbhoomi Dwarka district has a dry climate except in the monsoon seasons. The cold
season lasts for about three and a half months from November to the end of February. The
period from April to the end of June constitutes the hot seasons. The monsoon season
starts in the middle of July. The average maximum temperature was recorded 47° C during
summer months while minimum of 6° C was recorded in winter months. The district
Jamnagar receives average annual rainfall in the region is 400 mm.
3.12.4 Soil:
Most of the land of Devbhoomi Dwarka district is saline as it is well connected to the coastal
area,. The eastward and westward region of the district is fertile. The soil of the Devbhoomi
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-48
Dwarka district is characterized by sandy alluvial, medium black and hilly & forest soils. These
soils ranges in depth from shallow to 60 cm deep with lime concretion or lime encrusted
gravels at varying depths.
3.1.5 Drainage
The district Devbhoomi Dwarka has no major perennial flowing rivers, but the seasonal
Rani River, Paul River and Godhka River has their existence in the district. These all lotic
habitats are seasonal. Besides these, district has also some other seasonal streams and
considered as the small canals in comparison to the large rivers.
3.12.1 Methodology
3.12.1.1 Period of Sampling
The ecological survey has been conducted during Post monsoon season for the collection ofprimary data of flora-fauna, vegetation, soil and other environmental observations. Thedetails are given as below:
Post-monsoon: October to December
Core zone : At the project site
Buffer zone : Around 10 km radius of the project site
3.12.1. 2 Mode of Data Collection
Detailed survey was conducted to evaluate floral and faunal composition of the study area.
Primary data on floral and faunal composition was recorded during site visit and secondary
data was collected from the Forest Department and published relevant literature. Inventory
of flora and fauna has been prepared on the basis of collected data. The mode of data and
parameters considered during field investigations is given in Table 3.1.
Table 3.1: Mode of Data Collection & Parameters Considered During the survey
Aspect Data Mode of data collection Parameters MonitoredTerrestrial
EcologyPrimary datacollection By field survey Floral and Faunal diversity
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-49
Secondarydata collection
* Department of Forest Gujarat
* Marine National Park & WildlifeSanctuary, Jamnagar, Gujarat
Floral and Faunal diversity,Types of vegetation, foresttype, Importance etc.
3.12.2 Component of Biological Environment of Core Zone
3.12.2.1 Flora: During the present study, major tree was not observed in the core area of
the Virpur (Gunawali) mine lease area while thick patches of Prosopis Juliflora were
recorded at the core zone. Besides this, patch of small size Savidora persicaandZizyphussp. Were
also observed.
3.11.2.2. Fauna: Core zone of the proposed mine area is situated on barren land having
some shrub patches which does not support permanent habitats for any animal. On the
other hand, bird’s nest was also not observed due to the lack suitable habitats.
3.12.3 Biological Component of Buffer Zone
3.12.3.1 Forests
The forest area in this district is negligible as only 10% land of the district is covered with
forest. The timber and fuel wood is major produce while gum, grass, mower flowers, timroo
platy etc. are the minor produces. The district has 17360 Sq. km forest cover area (23.5 % of
total geographical area) which comprises of tropical deciduous vegetation due to high
temperature and humidity. As per “Wildlife (Protection) Act-1972”, there is an eco-sensitive
zone has been declared as Marine National Parks and Sanctuary, Jamnagar which is in 10 km
radius of study area of proposed mining area.
In the buffer zone several scrubs vegetation documented were Prosopis Juliflora, Salvadora oleiodes,
Zizyphus nummularia, Calotropis procera, Capparis decidua, Acacia eburnean, Acacia sp., Acacia nilotica,
Acacia Senegal, Dichrostachys cinerea, Maytenus emarginata and Balanites aegyptiaca. Whereas,
some common trees were species were Prosopis cineraria, Acacia leucophloea and Azadirachta
indica.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-50
3.12.3.2 Vegetation in and around Human Settlement
There are several villages are under the buffer zone of Virpur (Gunawali) Bauxite Mine. The
common species grown near villages observed were Abutilon fruticosum, Acacia chundra,
Acacia nilotica, Azadirachta indica, Clerodendrum phlomidis, Calotropis gigantea, Capparis
decidua, Diospyros melanoxylon, Dichrostachys cinerea, Emblica officinalis, Euphorbia
tirucalli, Madhuca indica, Mangifera indica, Mitragyna sp., Opuntia elatior, Solanum indicum
and Zizyphus nummularia.
3.12.3.3 Terrestrial Flora of the Buffer Zone
Buffer zone of Virpur (Gunawali) Bauxite Mine are mainly agriculture and barren land.
During the present investigation of buffer zone of present study area a large number of
flowering plants were recorded. Plant species comes under the RET (Rare, Endangered and
Threatened) category were not observed from the both the study area. Buffer area of
Gunawali block area has different flora and fauna on account of presence of the Marine
National Park and Sanctuary, Jamnagar and mangroves. Lists of flora of Gunawali blocks are
given in Table 3.2 and Table 3.3.
Table 3.2: List of Flora present in Gaga Wildlife Sanctuary(Marine National Park and Sanctuary) of Gunawali Mine
Sl. No. Botanical Name Family Types of Plant1 Abutilon glaucum Malvaceae Herb2 Acacia nilotica Minosaceae Tree3 Achyranthes aspera Amaranthaceae Herb4 Agave americana Liliaccae Herb5 Aleuropus lagopoides Poaceae Herb6 Aloe barbadensis Liliaccae Herb7 Alysicarois scariosus Fabaceae Herb8 Ammania braccifera Lythraceae Herb9 Apluda mutica Poaceae Herb
10 Aristida funiculata Poaceae Herb11 Blepharis repese Acanthaceae Herb12 Bothriochloa pertusa Poaceae Herb
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-51
13 Chorcorus tenas Malvaceae Herb14 Clorish barbata Poaceae Herb15 Clorish spathacea Poaceae Herb16 Coccinia arandis Cucurbitaceae Herb17 Coccinia indica Cucurbitaceae Herb- climber18 Commelina forskoali Commelinaceae Herb19 Cressa cretica Convolvulaceae Herb20 Crozophora prostrata Euforbiaceae Herb21 Cyperus sp. Cyperaceae Herb
22Dactyloctiniumaegypticum Poaceae Herb
23 Dicathium annulatum Poaceae Herb24 Digera muricata Amaranthaceae Herb25 Digitaria ciliaris Poaceae Herb26 Eclipta alba Astcraccae Herb27 Eleocharis sp. Cyperaceae Herb28 Enicostemma littorale Fabaceae Herb29 Eragrostis ciliaris Poaceae Herb30 Eragrostis tenella Poaceae Herb31 Halopyrum mucronatum Poaceae Herb32 Haylandia latebrosa Fabaceae Herb33 Indigofera oblongifolia Fabaceae Herb34 Launea resedifolia Astcraceac Herb35 Ludwigia perenis Onagraceae Herb36 Marsilea minuta Marsileaceae Herb37 Merremia gangatica Convolvulaceae Herb38 Mukia madaraspatena Cucurbitaceae Herb- climber39 Najas spicata Hydrocharitaceae Herb-Aquatic40 Panicum sp. Poaceae Herb41 Paspalum scorbiculatum Poaceae Herb42 Pentatropis capensis Asclepiadaceae Herb43 Phoenix sylvestris Palmae/Arcecaceae Tree44 Phragmites karka Poaceae Herb45 Phyla nodiflora Verbenaceae Herb46 Phyllanthus amarus Phyllanthacea Herb47 Pithecellobium dulce Minosaceae Tree48 Pristrophe bicalycaulata Acantheceae Herb49 Prosopsis juliflora Minosaceae Tree50 Pulicaria wightianct Asteraceac Herb
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-52
51 Rhyncosia minima Fabaceae Herb- climber52 Ruellia prostrate Acantheceae Herb53 Rupia maritima Ruppiaceae Herb54 Salvadora persica Salvadoraceae Herb55 Senra incana Malvaceae Herb56 Sporobolus sp. Poaceae Herb57 Suaeda maritima Amaranthaceae Herb58 Suaeda nudiflora Amaranthaceae Herb59 Taverniera cuneifolia Fabaceae Herb60 Tephrosia strigosa Fabaceae Herb61 Teramnus labialis Fabaceae Herb- climber62 Tomarix troupi Tamaricaceae Herb63 Triumffeta rotundifolia Malvaceae Herb64 Typha angustifolia Typhaceae Herb65 Vernonia cinerea Asteraceac Herb
Source: GRC survey data supported by Data of Department of Forest, Jamnagarand Marine National Park, Jamnagar, Gujarat
Table 3.3: Terrestrial Flora Present in Buffer zone of Gunawali Mine (Virpur)Sl.No. Botanical Name Family Local Name
Trees1 Acacia catechu Mimosaceae Khair2 Acacia leucophloea Mimosaceae Rojjh3 Adina cordifolia Rubiaceae Haldu4 Aegle marmelos Rutaceae Billi5 Albizzia labbeck Mimosaceae Siris (Kala)6 Albizzia procera Mimosaceae Khadi (Safed
Siris)7 Anogeissus latifolia Combretaceae Dhaura8 Anogeissus pendala Combretaceae Dhokra9 Azadirachta indica Meliaceae Neem
10 Balanites aegyptica Asclepiadiaceae Hingoca11 Bauhinia racemosa Caesalpiniaceae Jhingha12 Bombax cieba Bombacaceae Semal13 Boswellia serrata Burseraceae Salar14 Butea monosperma Fabaceae Dhola15 Cassia fistula Caesalpiniaceae Amaltas16 Cassia fistula Fabaceae Mokua
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-53
17 Dichrostachys cinerea Cyperaceae Goya Khair18 Diospyrus melanoxylon Ebnaceae Tendu19 Emblica officinalis Euphorbiaceae Amla20 Ficus bengalensis Moraceae Bad21 Ficus cordifolia Moraceae Paras papal22 Ficus racemosa Moraceae Gular23 Ficus religiosa Moraceae Pipal24 Flacourtia indica Flacourtiaceae Kakon25 Holoptelea integrifolia Moraceae Churel26 Lannea coromandelica Lamiaceae Gurjan27 Madhuca indica Sapotaceae Mahua28 Mangifera indica Anacardiaceae Aam29 Me'lotus philipinensis Euphorbiaceae Umbia30 Mitragyna parvifolia Rubiaceae .Kada31 Moringa oleifera Moringaceae Serjna32 Pterocarpus massupium Fabaceae Bija33 Soymida febrifuga Meliaceae Rohan34 Sterculia urens Sterculiaceae Karaya35 Syzygium cumini Sterculiaceae Jamun36 Tamarindus indica Caesalpiniaceae Imli37 Terminalia arjuna Combretaceae Kohra38 Terminalia bellerica Combretaceae Bahera39 Terminalia tomentosa Combretaceae Sadera40 Wrightia tinctoria Apocynaceae Khirni41 Zizyphus mauratiana Rhamnaceae Bor42 Zizyphus xylocarpa Rhamnaceae Ghat ber
Shrubs and Herbs1 Carissa spinarum Apocyanaceae Karonda2 Cassia auriculata Fabaceae Anwal3 Cassia tora Fabaceae Panwar4 Cuculigo orchioides Hypoxidaceae Dholi musli5 Dendrocalamus strictus Poaceae Bans6 Euphorbia hirta Euphorbiaceae Dudhi7 Ipomoea fistula Apocyanaceae Besharam8 Lantena camera Lamiaceae Jhurmari9 Olerodendron viscorun Asteraceae Amia
10 Scilla spinarum Liliaceae Koli Kandi
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-54
11 Temarix dioca Tamaricaceae Jhan12 Zizyphus mumuleria Rhamnaceae Jhasber
Climbers1 Abrus precatorius Fabaceae Chirmu2 Asparagus dumosus Liliaceae Narkanta3 Butea superba Fabaceae Palasbel4 Crotolaria orisensis Fabaceae Aonl bel5 Cryptolepis buchanani Periplocaceae Bichhubel6 Ichnocarpus frutescens Asteraceae Dudhi7 Momordica charantia Cucurbitaceae Kakoda8 Mucuna prarita Fabaceae Kenwach9 Tinospora cordifolia Tiliaceae Neemgiloy
Grasses1 Alphuda mutica Poaceae Polda2 Aristida depressa Poaceae Lampals3 Aristida setacea Poaceae Garra4 Aseilema laseum Poaceae Gandel5 Cenchrus setigerus Poaceae Bharut6 Chrysopogon fulvus Poaceae Seran7 Dactyloctenium aglypticum Poaceae Makra8 Dichanthium annulafum Poaceae Karad9 Eremopogon foreolatus Poaceae Buhari
10 Heteropogon contortus Poaceae Surwala11 Imperata cylindrica Poaceae Dab12 Sorghum habepensa Poaceae Baru13 Themeda quadrivalvis Poaceae Ratda
Source: GRC survey data supported by Department of Forest, Gujarat
3.12.3.4 Aquatic Flora of the Buffer Zone
Aquatic plants are plants that have adapted to living in aquatic environments. They are also
referred to as macrophytes (Hydrophytes). Aquatic plants can only grow in water or
in soil that is permanently saturated with water. During the present investigation some
macrophytic vegetation were collected near by the some small aquatic habitats present in
the buffer area were Anagallis arvensis, Azolla pinnata, Ceratophyllum demersum, Cyperus
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-55
alopecuroides, Phragmites australis, Ipomoea aquatica, Ludwigia sp., Parthenium
hysterosphorus, Polygonum glabrum and Utricularia aurea.
3.12.3.5 Fauna of the Buffer zone
The major parts of buffer area of the study area lies under forest cover and agriculture field.
There is a no any permanent habitats was observed in the core zone of the proposed mine
area. A list of animals of the buffer area has been prepared on the basis of local inquiry from
the village people and from the available published literatures. The animals thus recorded
were cross checked with Wildlife (Protection) Act, 1972 for their schedule. The fauna of
study area can be grouped in to aquatic and terrestrial animals.
3.12.3.6 Mammals
Devbhoomi Dwarka district has several mammal species. As per the local people, movement
of schedule-I category animals have not been seen in the buffer zone of Virpur (Gunawali)
mine except Peafowl which is present in the buffer zone. On the basis of local survey and
inquiry some domesticated animals such as Cow, Goat and Buffalo and some wild animals
such as Nilgai, Jackal etc. has been recorded from the buffer zone of Virpur (Gunawali) mine
blocks. List of mammalian species of both the blocks are given in Table 3.4.
Table 3.4: List of Mammals recorded from Buffer Zone of Virpur (Gunawali) MineSl. No Scientific name Common Name Schedule Status
1 Boselaphustragocamelus
tragocamelus
Blue bull / Nilgai III2 Canis aureus Jackal III3 Felis chaus Jungle Cat II4 Funambulus pennanti Five striped Palm
squirrelIV
5 Herpestes edwardsii Common Mongoose IV7 Mus booduga Indian field mouse V8 Rattus rattus Common House Rat V9 Sus scrofa Indian Wild Boar III
10 Lepus nigricollis Indian Hare -11 Hemiechinus auritus
HedgehogHedgehog IV
12 Hyaena hyaena Indian Hyena III13 Vulpes bengalensis Common Fox II14 Hystrix indica Porcupine IV
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-56
15 Mellivorinae mellivora Honey badger -16 Viverricula indica Small Indian civet -17 - Flying squirrels Squirrel -
Source: GRC Data supported by Data of Department of Forest, GujaratGujarataaaaGujataRajasthan
3.12.3.7 Reptiles
The reptile diversity in Devbhoomi Dwarka district included several species of lizards and
snakes. As per the Wildlife (Protection) Act, 1972, lizard and snakes was observed among
avian fauna in the buffer zone of both the blocks. Details of Reptiles species present in the
buffer zone of Gunawali Mine area, Devbhoomi Dwarka is given in Table 3.5.
Table 3.5: Reptile of recorded from Buffer Zone of Virpur (Gunawali) Mine
Sl. No. Scientific Name Common Name Schedule Status1 Bungarus caeruleus Common Indian Krait IV2 Calotes versicolor Common garden lizard -3 Daboia russelii Russell's viper II4 Echis carinatus Saw-scaled viper -5 Hemidactylus flaviviridis House Gecko III6 Mabuya carinata Skink -7 Naja naja Indian Cobra II8 Ptyas mucosus Rat Snake II9 Sitana pondcenana Fan-Throated Lizard -
Source : GRC Survey Data supported by Data of Department of Forest, Gujarat
3.12.3.8. Avian Fauna
Total 28 species bird species were recorded from the buffer zone of Gunawali mine. No
bird’s habitats like nesting, breeding and forging patterns are noticed in the core zone. Local
birds are noticed in the buffer zone of the study area. No fixed pattern in migratory
behavior is noticed. As per the Wildlife (Protection) Act, 1972, Indian Peafowl were
observed as schedule-I species among avian fauna in the buffer zone of Virpur (Gunawali)
Mine. List of avian fauna present in the buffer zone of Gunawali (Virpur) mine is given in
Table 3.6.
Table 3.6: List of Avian Fauna of Buffer Zone of Virpur (Gunawali) Mine
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-57
SL. No English Name Scientific Name Schedule Status(WPA, 1972) IUCN
1 Jungle Myna Acridotheres fuscus IV LC2 Common Myna Acridotheres tristis IV LC3 Common Kingfisher Alcedo atthis IV LC4 House Swift Apus nipalensis IV LC5 Ashy Wood swallow Artamus fuscus IV LC6 Spotted Owlet Athene brama IV LC7 Purple Sunbird Cinnyris asiaticus IV LC8 Rock Pigeon Columba livia IV LC9 Jungle Crow Corvus macrorhynchos IV LC
10 House Crow Corvus splendens IV LC11 Common Quail Coturnix coturnix IV LC12 Common Cuckoo Cuculus canorus IV LC13 Indian Cuckoo Cuculus micropterus IV LC14 Black Drongo Dicrurus macrocercus IV LC15 Red Jungle fowl Gallus gallus IV LC16 Great Barbet Megalaima virens IV LC17 White Wagtail Motacilla alba IV LC18 House Sparrow Passer domesticus IV LC19 Jungle Bush Quail Perdicula asiatica IV LC20 Rose-ringed Parakeet Psittacula krameri IV LC21 Red-vented Bulbul Pycnonotus cafer IV LC22 Spot-winged Starling Saroglossa spiloptera IV LC23 Grey Bushchat Saxicola ferreus IV LC24 Oriental Turtle Dove Streptopelia orientalis IV LC25 Common Babbler Turdoides caudata IV LC26 Jungle Babbler Turdoides striata IV LC27 Common Hoopoe Upupa epops IV LC28 Indian Peafowl Pavo cristatus I
Source : GRC Survey Data supported by Data of Department of Forest, GujaratLC: Least Concern,: Not Evaluated, EN: Endangered, NT: Near Threatened
3.12.3.9. Aquatic Fauna
i. Amphibian: Amphibians are commonly at the places along the margin of aquatic and
terrestrial systems. Due to presence of water bodies like seasonal streams, nalas and ponds
in the study area is providing shelter to many amphibian species. Some of the commonly
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-58
reported species from the Gunawali mine area were Bufo melanostictus (common Indian
toad), Euphlyctis cyanophlyctis (Indian skipper frog) and Hoplobatrachus tigerinus (Indian
bull frog) etc.
ii. Fishes: Several seasonal lentic and lotic water bodies situated in the buffer zone of
Virpur (Gunawali) Mine and they support few fish species. During the present study, total
of 9 fish species were observed from different location while collecting by local fisherman.
List of recorded fishes is given in Table 3.7.
Table-3.7: Diversity of Fishes presents in Buffer Zone of Virpur (Gunawali) Mine
Sl. No. Name of the Taxa Schedule (WPA,1972)& IUCN Red status
Family-Cyprinidae1 Puntius ticto LRnt2 Puntius sophore LRnt3 Puntius sarana VU4 Catla catla VU5 Labeo rohita LRnt
Family-Bagridae6 Mystus cavasius LRnt
Family-Chandadae7 Channa punctatus LRnt8 Channa marulius VU
Family-Belonidae9 Xenentodon cancila LRnt
Source: GRC Survey DataEN : Endangered, VU : Vulnerable, Rnt: Lower risk near threatened,Lrlc : Low risk least concern
3.12.4 Agricultural landThe economy of Gujarat is predominantly agricultural and rural in nature, with wide
fluctuations in the growth rate due to uncertainties in agricultural production.
Agriculture in Devbhoomi Dwarka district is primarily rain-fed. The irrigation from the
mining pit is observed in many localities. It is observed that these mining pits are acting as
an option for rainwater harvesting in this water scarcity region.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-59
Maximum area of buffer zone (within 10 km radius of the site) is covered with agricultural land.
The crops grown in Devbhoomi Dwarka district as well as buffer zone of Gunawali Mine
(Virpur) were Cotton (Gossypium herbaceum), and Castor (Ricinus communis) and during monsoon
period, Ground nut (Arachis hypogaea), Bajra (Pennisetum typhoides), and Jowar (Sorghum bicolor)
among major crops. While, minor crops practiced in this region during monsoon are Jeera/Jeeru
(Cuminum cyminum) and Ground nut (Arachls hypogaea). Minor crops practiced in this region during
winter are Wheat (Triticum aestivum) and Til (Sesamum indicum). Some others crop such as Tuver
(Cajanus cajan) and Mug (Magna radiate),Mango (Mangifera indica) and Chikko (Manilkara zapota)
plantation were also observed in the few villages in the buffer area. In Devbhoomi Dwarka
district has 62% land as cultivable land of its total Geographical area.
3.12.3.1 Fishery
In Gujarat, village ponds are very good resource to undertake effective fish culture which
can generate employment at village level. For the financial and administrative support of
fisherman, Gujarat Fisheries Central Co-operative Association Limited (GFCCA) has been
established which is an apex cooperative body of the fishermen cooperatives in the State of
Gujarat. The Devbhoomi Dwarka district is endowed with some dams, ponds and canal
which support fisheries activities. Besides, this a large number of private pond aquaculture
practice are continued by local fisherman communities.
Some common fish species present in all the water bodies of Gujarat are as Catla catla,
Cirrhinus cirrhinus, Labeo rohita, Mystus Cavasius, Glossogobius giuris, Mastacembelus
armatus and Puntius sp.
3.12.4 Occurrence of Schedule-I and Rare, Endangered and Threatened (RET) Species
Overall, studies of the buffer zone of both Virpur (Gunawali) Bauxite Mine reveal that plant
species under the category of RET have not been observed. Among Fauna, Indian Peafowl
(Pavo cristatus) is documented as schedule-1 species. There is no any other species belongs
any other class were observed under schedule category from both the respective buffer
zone. However, all care will be taken for protection of others flora & fauna also, if any in the
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-3Description of Environment
III-60
leasehold area. Conservation plan for above mentioned species is attached along with the
report.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-1
CHAPTER-4
ANTICIPATED ENVIRONMENTAL IMPACT AND MITIGATION MEASURESINDEX
SI.NO. CONTENTS Page No.
4.1 Details of the Investigated Environmental Impacts IV/2
4.2 Air Environmental IV/4
4.3 Water Environment IV/9
4.4 Impact on Land Use IV/12
4.5 Impacts due to disposal of Overburden IV/17
4.6Impact on Air Quality IV/18
4.7Proposed Mitigation Measures for Dust Suppression IV/20
4.8Noise Environment IV/21
4.9Impact due to Ground Vibrations IV/25
4.10 Greenbelt and Plantation IV/29
4.11Biological Environment IV/30
4.12 Occupational Health (Impacts and Mitigation Measures) IV/32
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-2
4.0 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
4.1 Details of the Investigated Environmental Impacts
This chapter provides a brief overview of the potential impacts on variousenvironmental components due to the proposed semi mechanized open cast miningactivities.
The opencast mining operations in general cause environmental degradation and ifadequate control measures are not taken to prevent/mitigate the adverseenvironmental impacts, these operations may cause irreversible damage to the eco-system. The environmental parameters most commonly affected by mining activitiesare:
Topography and drainage Air quality Noise levels and ground vibrations Water resources and quality Landuse Pattern Soil quality Flora and Fauna Socio-Economic conditions; and Occupational Health
Various environmental impacts, which have been identified due to the miningactivities, are discussed in the following sections and mitigation measures aresuggested.
4.1.1 Impact on Topography and Drainage
(a) Topography: - The Topography of the terrain around Virpur (Gunawali), Mewasa,Mota Astota and other village is marked low lying narrow winding latertte ridgeswith intervening broad flat and undulating valley gradually sloping towards the coastin the west to south westerly direction. Being a drought prone area, the rain fall isscanty and hence there are no perennial rivers. The nallas and rivers which remainsmostly dry during major part of the year show a dendritic drainage pattern. Thenarrow winding ridges normally show a low dip slope towards east – north – eastand relatively escarpment slope towards west- south – west.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-3
The general topography of the lease area is relatively a flat terrain having very lowSlop. The highest RL is 26 m RL in south part of the lease area and lowest RL is 10.53m RL in north part of the lease area. Drainage of the lease area is towards north intonatural drainage course.
(b) Drainage Pattern: - There is no river or nalla or well exist in the lease in the leasearea. There is no fix drainage pattern Rain fall in the area is Scanty. During rains,water flows higher elevation to lower elevation in all direction. Part of rain water isalso collected in working pits, which are soon dried up as rains are not regular. Thereis a natural drainage system within the lease area. The drainage system in the arearemains from south to north direction.
Figure-4.1Drainage map
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-4
4.2 AIR ENVIRONMENT
4.2.1 Anticipated Impacts
The mining will be carried out by opencast other than fully mechanized method. The air
borne particulate matter generated by ore and handling operations and transportation of ore is
the main source of air pollutant. The dumpers and HEMM will emit smoke and noxious gases
and un-burnt hydrocarbons.
The emissions of Sulphur dioxide (SO2), Oxides of Nitrogen (NO
2) contributed by diesel
operated excavation/loading equipment and vehicles plying on haul roads are marginal.
Prediction of impacts on air environment has been carried out taking into consideration
proposed production and net increase in emissions.
Air pollution sources in the operating mine have been classified into three categories:
i. Drilling and Blasting operations
ii. Excavation and Loading of ore
iii. Transportation of ore on the haul road
Water tankers with spraying arrangement will be used for regular water sprinkling on the haul
roads to ensure effective dust suppression. The dumpers are well maintained so that exhaust
smoke does not contribute abnormal values of noxious gases and un-burnt hydrocarbons.
In order to assess the impact due to Bauxite production of 500 TPD on air environment,
prediction has been carried out.
4.2.4 Air Pollution Impact Prediction through Dispersion Modeling
Prediction of impacts on air environment has been carried out by employing Industrial
Source Complex Short Term (ISCST3) dispersion model.
The ISC area source model is used to simulate the effects of fugitive emissions from sources
such as topsoil, OB and ore loading and unloading and blasting, and transportation. The ISC
models use a numerical integration approach for modeling impacts from area sources. The
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-5
ISC models accept rectangular areas that may also have a rotation angle specified relative to a
north-south orientation.
The dust dispersion modeling requires the following data: Micro – meteorological data Mining data Dust concentration data
The impact has been predicted over a 10 km radius area with mining area as the centre. To
obtain greater resolution, the receptors are defined with respect to 500 x 500 m grid point to
have better results. GLC have been calculated at every 500 m grid point to have better results.
4.2.2 Emissions Details
Blasting, loading - unloading and transportation of ores and overburden will be the main
polluting source in the proposed mining activities releasing Particulate Matter (PM10)
affecting Ambient Air of the area. Emission during Blasting, Loading and unloading was
calculated by the area sources. Transportation of the ore by tucks on the haul road was
calculated by the area source which was combination of line sources with each truck loaded
with ore transported over the haul road of the mining area.
The open pit mining involves the following general processes:
• Removal of the vegetable layer (top soil)
• Removal of overburden
• Removal of the useful geological material
• Hauling of the useful geological material
Each one of these mining operations is, in turn, divided into various different activities, that
depend on the technologies used. Each activity is an emission source. The Table - 4.1 shows
the emission factors considered for modeling exercise.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-6
Table-4.1 Emission Factors
Activity type Emission
Soil Loading & Unloading 7.85 x 10-6 kg PM10/t
Soil Transportation 1.47 kg PM10/VKT
OB Loading & Unloading 7.85 x 10-6 kg PM10/t
OB Transportation 19.87 kg PM10/VKT
Blasting 2.57 x 10-2 kg PM10/blast
Mineral loading 2.56 x 10-3 kg PM10/t
Mineral unloading 7.85 x 10-6 kg PM10/t
Mineral Transportation 2.88 x 10-1 kg PM10 VKT
Emission was calculated with the help of emission factor calculated by formula given below
E=TP X EF
Where E= Emissions (tonnes/year)
TP= Annual Throughput
EF= Emission Factor
4.2.5 Meteorological parameters
The meteorological data file for the Short Term model normally consists of meteorological
data, beginning with hour 0.1:00 of March 1, 2015 and ending with hours 24:00 of May 31,
2015. The hourly meteorological data recorded continuously at site for the same period. The
mean meteorological data recorded at the site has been used for the modelling. In absence of
site specific mixing heights, mixing heights published in IMD Publication “Atlas of Hourly
Mixing Height and Assimilative Capacity of Atmosphere in India” by S.D. Attri, Siddhartha
Singh, B. Mukhopadhyay, and A.K. Bhatnagar (2008) has been used.
After processing of area source data in ISCST3, isopleths for fugitive dusts (Line Source +
Area Source) is generated, this is presented in figure 4.2. The software selects the
meteorological data of the worst day which is different from the seasonal wind rose.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-7
Fig 4.2: Wind Rose Diagram
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-8
4.2.6 Modeling Results
4.2.6.1 Predicted Ambient Particulate Concentrations
A summary of the PM10 concentrations predicted for the proposed mine are presented in
Table 4.2.
Table 4.2: PM10 Contribution at the Nearby Locations
Location Code Locations Direction Distance(km)
Backgroundvalue
(98 percentile)in µg/m3
CumulativeIncremental
GLC inµg/m3
TotalPredictedGLC inµg/m3
AQ-1 Project site Center - 130.7 9.48 140.2
AQ2 500 m fromproject E 500m 103.8
1.6 105.4
AQ3 Mota Asota NE 5 83.1 <0.01 83.1AQ4 Harbardi SE 6 63.3 <0.01 63.3AQ5 Mewasa S 5 89.4 <0.01 89.4AQ6 Mahadeviya SW 8 97.4 <0.01 97.4AQ7 Pindara WSW 7 90.2 <0.01 90.2
The excess of the 24-hour PM10 standards is observed. The 24-h maximum incremental GLC
of PM10 9.48 µg/m3 occurred at the center of the mine site. The value of PM10 at the project
site was 140.2 µg/m3observed after superposition of base-line value of 130.7 µg/m3 on the
incremental GLC of 9.48 µg/m3 under combined impact of loading, unloading, transportation
of ore by trucks over haul road and blasting at the mining area.
Contours of the maximum predicted 24-hour average PM10 concentrations (Figure 4.2)
indicate that 9.48 µg/m3 are predicted to occur within mine site from the mining operations.
However, at the receptors of 500m downwind from project site the contour of 1.5 µg/m3 has
occurred and at the rest of the receptors in 10 km radius there is no effect of mining and the
PM10 concentrations well within the PM10 standards. Hence peak concentrations are
localised to operations.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-9
Figure 4.3: Isopleths for fugitive dusts (Area source + Line Source)
4.3 Water Environment
4.3.1 Impact on Water Resources
The mining activities will not produce any kind of pollutants. So, there is no any bad impactwill be introduces on local surface water. On the other hand, ground water will also be safeand not disturbed as ground water table in this area. There is no river or nala crossing in the
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-10
lease area. The rain water follows through the natural slope in eastern direction of the area.Rain water of the region ultimately goes into the Arabian Sea.
4.3.2 Impact on Water Quality
Water is required for mining operations mainly for sprinkling on haulage roads and at openfaces during mining for suppression of dust. Around 8.0 kld of water is required for miningactivities. Arabian Sea is near from the lease area. There will be insignificant impact on thesurface water resources due to withdrawal of water required for mining operations.
Impact on Surface Water Quality and Sediment Load
Mining activity increases sediment load and total dissolved solids in streams due toerosional activity of overburden dump and loosened soil by blasting activity. Thefollowing measures will be taken up by project authorities to reduce this load.
1. Dense plantation.2. Construction of siltation ponds/tanks.3. Construction of Garland drains.
Physico-chemical characteristics of surface water samples collected from rivers andnalas in the buffer zone are under the desirable limits. Except, water of Pindara Bayrecorded higher values for Conductivity, Chloride, Sulphate, Sodium and Potassiumas compared to Ran River and Ni-Pal Pond. The higher values documented onaccount of higher salinity and hardness.
No wastewater generation is envisaged due to the mining operations. The sanitarywastewater will be sent to septic tanks. No impact of wastewater generation on thesurface water is envisaged, as there is no discharge into surface water resources.
Impact on Ground Water Quality
Ground water pollution can take place only if the mining rejects contain chemicalsubstances. However, the deposit does not contain any harmful ingredients. Hence,no impact on groundwater quality is envisaged.
4.3.3 Wastewater Generation, Treatment & Disposal
The wastewater generation in the mining process is not envisaged. The sanitarywaste will be routed to septic tanks followed by soak pits. The sump also behaves asprimary settling tanks for the mine water. Thereby, the suspended solids, the major
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-11
contaminant added to the mine water inflow, would settle down and clean tappedwater will be discharged on to the surface.
4.3.3.1 Measures for Minimizing Adverse Impacts
Mine Drainage
The following facilities will be provided for proper mine drainage:
The garland drains will be developed in advance for each mine stage so thatwater is collected in these garland drains and discharged properly outside the pit.
Working faces will be laid such that the water from the working areas will flowinto the sump by gravity from where it will be pumped out.
Face pumps of adequate capacity will be provided at working faces to keep thesedry.
Slurry pumps will be provided to deal with slurry formed during rainy season. Surface Water Pollution Control Measures
Retaining walls of adequate dimensions will be provided at the toe of dumps andthe unstable OB benches within the mine to prevent wash off from dumps andsliding of material from benches. This will help in preventing silting of waterdrains/channels;
The water channels/drains carrying the rain water from the mine will be providedwith baffles and settling pits to arrest the suspended solids, if any, present in thiswater;
The worked out slopes will be stabilized by planting appropriate shrub/grassspecies on the slopes. This will help in preventing wash-off of ore from theseslopes;
The mine water will be regularly tested for presence of any undesirable elementsand appropriate measures will be taken in case any element is found exceedingthe limits prescribed by CPCB.
Ground Water Pollution Control Measures
The domestic sewage from the canteen and toilets will be routed to septic tanks.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-12
Regular monitoring of water levels and quality in the existing open wells andbore wells in the vicinity will be carried out. If found necessary, additionalobservation wells will be sunk for monitoring the water levels and quality aroundthe mine representing both upstream and downstream conditions.
Artificial Recharge and Rain Water Harvesting
For reducing the impact of lowering of water level and pollution level in thesurroundings of the proposed opencast workings, the following methods of artificialrecharge and rain water harvesting methods will be adopted.
1. There is no major roof top area is present in lease area. Only small office ispresent at mine lease. Rain water will be collected and recharge in mined out pitsthrough garland.
2. Rain water which flows away from the area as runoff will be accumulated inmined out pit through garland drain. Water stored in mined out pits inducesgroundwater recharge.
3. Rain water and sump water.4. No STP plant is require at mining lease because very small quantity waste water
will be generated from domestic uses water. Waste water will be collected insoak pit and utilize for dust suppression and green belt development.
The project will through these actions enhance the water levels in the area.
4.4 Impact on Land Use
The proposed opencast mine will result slight change and disturbance of the land usepattern of the Mine Lease area. The land degradation is expected during miningactivities like excavation, overburden dumping, soil extraction etc. Land requirementfor the project has been assessed considering functional needs. The lease area is of55.2520 ha (Mine working area 37.167 ha) Fertility of land is very poor. Within theproposed area the pre-mining break up of land is as follows:
Existing Land Use:
Agriculture land and govt. wastelands cover the terrain surrounding ML area. Apartfrom this, quite a number of mining leases area also found all around the ML.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-13
Existing land Use Pattern in the mine
SI. No. Particulars Present land usepattern(In Ha)
1 Pit (Area under Mining) 19.4402
2. Storage Soil 03. Overburden dump 0
4. Mineral storage 0.0500
5. Infrastructure 0.00506. Green Belt 0.01007. Road/Rasta(Additional ) 0.0460
8. Township Area 09. Railway 010 Tailing Pond 011 Effluent Treatment Plant 012 Mineral Separation Plan 0
13. Sub grade 0Undisturbed Area 19.5512
Post mining reclamation of the area in the form of creation of reservoir, plantations,recreation spots etc are presented in Table-4.3.
TABLE-4.3STAGE-WISE LAND USE PATTERN
All values are given in HectareSI. No. Particulars Present
land usepattern(In Ha)
Area put on useupto end ofmining planperiod (inhectare)
Area put on useupto life ofmine (inhectare)
1 Pit (Area underMining)
19.4402 23.4774 23.3954
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-14
2. Storage Soil 0 0 03. Overburden dump 0 0 0
4. Mineral storage 0.0500 0.0500 0.0500
5. Infrastructure 0.0050 0.0050 0.00506. Green Belt 0.0100 0.3100 0.20007. Road/Rasta(Additional
)0.0460 0.0460 0.5000
8. Township Area 0 0 0
9. Railway 0 0 010 Tailing Pond 0 0 011 Effluent Treatment
Plant0 0 0
12 Mineral SeparationPlan
0 0 0
13. Sub grade 0 0 0Total 19.5512 23.8884 25.1504
At the conceptual stage, about 23.3954 ha area will be disturbed on account ofmining activities. A part of excavated area will be converted into water reservoir. Inaddition to this, about 19.5512 ha of undisturbed area will also be covered underafforestation and 0.0100 ha area will be utilized for Roads.
In mining operation, neither toxic effluent nor toxic solid waste will be generated.Hence, the soil quality in the vicinity is not expected to be adversely affected due tomining operation.
Hazard and Risk Assessment of OB Dumps
Hazard of OB dump failure is mainly governed by following factors:
1. Height of benches
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-15
2. Slope of benches3. Nature of material4. Slope of foundation rock5. Nature of foundation rock6. Drainage of foundation7. Depth of ground water table
The following precautions will be taken to reduce the risk of dump failure:
1. OB benches will be of <30m height in each tier.2. The angle of repose of3. OB benches will be around 37o.4. The soil from the foundation ground will be scrapped before starting OB
dumping.5. Drainage control structure like garland drain will be made around OB dump area
to avoid water flow during monsoon below the OB dump.6. Levelling, grading and drainage arrangement for top of OB dumps.7. Technical & Biological reclamation.No adverse impact is anticipated on land use of buffer zone associated due to theproposed mining operations, as all the activities will be confined within the projectsite only.
Rehabilitation and reclamation is an integral part of the environmental managementplan, Figure-4.4 reflects this aspect.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-16
FIGURE- 4.4Environmental Management Plan
4.5 Impacts due to disposal of Overburden
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-17
In the proposed mining plan topsoil will be generated but no OB will be generatedthe 5% ROM will be generated as mineral waste.The waste that is likely to be generated will be in the form of associated clay with thebauxite horizon as mineral reject, which is below the threshold grade, and has nosale value & of no use. Hence considered as a waste.The yearly rate of generation of the waste has been described in detail in the miningchapter and the date given there is presented in a tabular from below. For the soiland waste the expansion factor considered is 1.3.Top soil will be generated during modified mining plan period.A tabular statement showing volume of soil, OB mineralized waste:-
Year Top Soil(cum) Mineral waste (cum)Reuse/Spreading
Storage Backfilling Storage Blending Beneficiation
(2015 – 16 )August 15to March
16)
Nil Nil Nil 2100 Nil Nil
2016 – 17 5380 Nil Nil 3026 Nil Nil2017 -18 5400 Nil Nil 3038 Nil Nil2018 - 19 5369 Nil Nil 3020 Nil Nil
Total 16149 Nil Nil 11184 Nil Nil
Waste generated during production of mineral bauxite will be stacked in pit floorafter excavation of bauxite upto full thickness. Top soil will be spread over statuarybarrier for plantation.(b) Proposed dumping area: -In the proposed modified mining plan. It is proposed that waste generated duringmining plan period will be stacked at pit floor after excavation of bauxite. Soil will bespread over statuary area for plantation. Part of mined out land will be used as waterreservoir.(c) Disposal of waste:-No Backfilling will be done in the area after complete extraction of full thickness ofbauxite. The waste generated during modified mining plan period will be stacked inthe pit floor. As volume of voids (area to be worked) is much more than materialavailable for backfilling, entire mined out area up to original ground level will notpossible. Therefore mined out lease area will be used as water reservoir. Fencing willbe carried out around the water reservoir.
4.6 Impact on Air Quality
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-18
Air pollution sources at the mining area can be classified into three categories, viz.,area sources, line sources and instantaneous point sources. Extraction of Bauxite byvarious activities in mining area is considered as an area source. Blasting is the mainsource of instantaneous point sources. Majority of the heavy machinery is operatedon diesel. The mining activity is likely to contribute Suspended Particulate Matter(SPM), Dust from area sources and Oxides of Nitrogen (NOx) and hydrocarbons fromautomobile exhaust. The existing baseline concentrations of pollutants are withinthe limits prescribed by CPCB. The sources of pollutants from mining activities aregiven in Table-4.4.
TABLE-4.4SOURCES OF POLLUTANTS
Sr. No. Source Type of Pollutant1 Mining activity (drilling, blasting, loading) SPM, NOx2 Transport of Overburden or soil for dumping/
backfill and bauxite to sorting/sizingSPM
3 Dumping of waste SPM4 Sorting of bauxite and loading SPM5 Transportation of sorted bauxite SPM, NOx
Impacts from Area Sources
The area sources include mine pit and its activities covering drilling, blasting, hauling,loading/unloading and stockpiles.
The dust emissions from the above areas will be fugitive in nature and maximumduring summer season (when the wind velocities are likely to be high) and almost nilduring the monsoon season. The dust emissions are likely to be confined to the minepremises only.
Impacts from Line Sources
The proposed plant activities will involve transport of ore from the site. The totalproposed traffic details due to the project are given in Table-4.5. The trucks will beadequately covered/ bagged; hence the fugitive emissions will be avoided.
TABLE – 4.5PROPOSED TRAFFIC DUE TO THE PROJECT
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-19
Material Modeof
transport(%)
Quantity
(TPA)
Quantity
(TPD)
Quantity byRoad(TPD)
Capacity ofvehiclecarryingmaterial(Tonnes)
Number ofdaily vehicles
plying
Number of
vehicles
plying/h
Bauxite Road(100)
1,51,875
502 502 20 25 50
The transportation of raw materials will involve generation of additional traffic ofabout 25 trucks per hour. Compared to the existing traffic on highway, theincremental traffic density due to the proposed plant (25 trucks per hour) will benegligible.
The annual and 24-Hr average concentrations of PM10 are lower than the NAAQS atmining and residential places. In order to reduce the effect of PM10 a few additionalmeasures may be implemented.
Restriction of trucks/dumpers speed and overhauling, and regular road cleaning areessential in order to control dust pollution from transportation, together with waterspraying on roads. Washing of dumpers/ trucks’ wheels/body at an appropriatedistance from site entrance, loading and unloading in area protected from wind,minimization of drop heights, use of sheet or cover on loaded vehicles andapplication of water sprays to moisten transported material is also essential.Installation of sprinkling system along with application of binding agents, chemicalson unpaved roads are required. In addition, unpaved roads should be converted toblack topped roads, with regular maintenance/ repair of roads to maintaincompactness, gradient and drainage, sweeping of unpaved roads and the impositionof speed limits on trucks and other vehicles. A Green belt should be developedhaving plants with thick foliage, which will effectively attenuate the dustconcentration.
4.7 Proposed Mitigation Measures for Dust Suppression
Bauxite is a hydrated oxide of aluminum. It is a mixture of two or more hydroxidescorresponding to Gibbsite (Al2O3.3H2O) and Boehmite (Al2O3.H2O). The moisturecontent in Bauxite is around 3% to 7%. Therefore emissions due to mineral handling
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-20
during mining operation are not much and restricted to the lease area only. Airpollution is caused mainly due to dust generation added with gaseous emission fromtransportation activities along with mining operation like drilling, dozing, blasting,loading, haulage etc. Proper mitigation measures will be practiced during miningactivities to control air pollution load below the prescribed limits.
In the proposed project, drilling will be done with latest drill machines with vacuumsuction for dust extraction thus the likelihood of dust emission from drilling activities isnegligible. The burden and spacing for the hole will be 2m and 3m for effective depthof 6.00m. The power factor per Kg. will be 8.00 MT. About 50% of ROM bauxiteneeds blasting therefore about 110Kg. explosive will be required per day. 14 or 15holes will be required daily.
Blasting is the main source of instantaneous point sources. Blasting is usually carriedout by deep holes. SPM and NOx emissions are envisaged during the blasting andtransportation operations. The large quantity of dust will be wind borne due toblasting but due to the proposed greenbelt around the mine, the spread of dust willbe arrested. But these are kept under control by monitoring regularly the emissionsfrom exhaust and using appropriate control measures by sprinkling of water on haulroads etc. The gaseous emissions like Oxides of Nitrogen from the blasting activity willbe instantaneous and will prevail for shorter duration. The blasting will be carried outonly between 2 pm to 3 pm during noon when normally low wind conditions prevailand temperature inversions are not likely to occur.
In addition to the above the production of blast fumes containing noxious gases willbe reduced by the following methods:
Blasting will be carried out only during the daytime Controlled blasting will be practiced Mitigative measures for control of ground vibrations and to arrest fly rocks and
boulders will be implemented Proper and proportionate mixing of fuel oil with ammonium nitrate to ensure
complete detonation Use of adequate booster/primer: and Proper stemming of the blast hole.
Fugitive Emissions
Fugitive dust emissions from the proposed project would be significant as there willbe air pollution due to activities like transport of bauxite and overburden and
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-21
generally due to the movement of vehicles on the roads. The proposed greenbeltand regular water sprinkling will help reduction in fugitive emissions.
Automatic water sprinklers will be installed in the mine. Pressurized water will besprinkled. Dust generation is reduced by using sharp teeth for shovels.
With the proposed control measures, the fugitive emissions will be insignificant interms of their impact on environment.
The proposed air pollution mitigation measures are as follows:
• Regular water sprinkling on haul roads, loading and unloading points and transferpoints will be carried out.
Wet drilling of mine to reduce the dust generation from the drilling operations; Water spraying on mine faces to control dust emanated from loading and
handling operations; Water spraying over the muck pile to be loaded in order to reduce dust
generation during loading operations; Bauxite will be transported by tarpaulin covered vehicles and not overloaded to
avoid dust emission; Vehicular emissions will be kept under control and regularly monitored. Measures will be taken for maintenance of vehicles used in mining
transportation of mineral Extensive Plantation of trees of different variety in Bauxite storage yard; Dust masks to all workers working in dusty atmosphere; A good housekeeping and proper maintenance which will help in controlling
pollution; and• Periodical monitoring of air samples at various locations, and it will be ensure
that the ambient air quality parameters conform to the norms prescribed by theCPCB/SPCB in this regard.
4.8 Noise Environment
4.8.1 Noise Impact on Working Environment
Mining operations will be the main sources of noise pollution. Noise due to vehicularmovement will be intermittent, but will also add to the background noise level.
Once the mine becomes operational, there will be the following sources of noise inthe area:
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-22
Drilling; Blasting; Operation of HEMM; and Vehicular Movement.
It has been observed that mechanization of mine generally leads to higher noiselevels if not properly controlled. Operation of drills, shovels, dumpers, pay loadersand dozers involve noise generation above 90 dB (A), which is the prescribedThreshold Limit Value. However, the expected noise levels are not likely to have anyeffect from the occupational health point of view.With the mining operations, due to the deployment of machinery, drilling andblasting for mine development, excavation, and transportation of bauxite and men,it is imperative that noise levels would increase. However, as the mine leaseboundary is located 1.0-km away from the nearest settlement, the expected noiselevels will not have significant effect on the community.
Noise Generated due to Drilling
The drilling operations in mine will be carried out by using 6” dia rotary percussivedrills. The typical Noise levels due to drilling at1-m distance will be about 85 – 90 dB (A). However, it is proposed to provide inbuiltcabin for drill operators with ear muffs/ear plugs.
The mine site where heavy earth moving machinery will operate, noise level will bemore than the stipulated 90 dB (A) norm of DGMS. The noise level will be within thetolerance limit at a distance of 15 to 20 m. The protection measures for theoperators of the equipment will reduce the impact.
The noise produced by blasting will be for extremely short duration of around 0.5seconds, though with a high intensity. The impacts over the surrounding habitat canbe minimized by adopting adequate precautions during blasting and also by properlyscheduling it as indicated in the management plan. Development of greenbelt alongthe periphery of the mine site is expected to act as an effective barrier against itspropagation of sound waves towards the nearby human settlements.
4.8.2 Noise Generated Due to Blasting
Noise generated from blasting is always instantaneous. It takes less than 5 secondsto occur. Noise of blast is site specific and depends on type, quantity of explosives,dimensions of drill holes, degree of compaction of explosive in the hole and rock.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-23
The noise levels during blasting operations are likely to be in the range of 120-140 dB(A) at 50-200 m distance from the blast site. The noise levels tend to decrease withdistance. Blasting will be carried out maximum two times per week between 12.00Noon to 2.00 PM. As the blasting is likely to last for very short duration depending onthe charge, the noise levels over this time will be instantaneous and short induration.
The noise levels in many situations will be above Threshold Limit Value. Exposure tonoise levels, above Threshold Limit Value may have detrimental effect on theworkers' health. Mine workers working for more than 4 to 4.5 hours per shift will begreatly affected, unless suitable mitigatory measures are taken. The adverse effectsof high noise levels on exposed workers may result in:
Annoyance; Fatigue; Temporary shift of threshold limit of hearing; Permanent loss of hearing; and Hypertension and high blood cholesterol, etc.
Noise pollution poses a major health risk to the mine workers. When noise in theform of waves impinges the eardrum, it begins to vibrate, stimulating other delicatetissues and organs in the ear. If the magnitude of noise exceeds the tolerance limits,it is manifested in the form of discomfort leading to annoyance and in extreme casesto loss of hearing. Detrimental effects of noise pollution are not only related tosound pressure level and frequency, but also on the total duration of exposure andthe age of the person.
Frequency levels and associated mental and physical response of humans are givenin Table-4.6.
TABLE-4.6NOISE EXPOSURE LEVELS & ITS EFFECTS
Noise Levels dB(A) Exposure Time Effects85 Continuous Safe
85-90 Continuous Annoyance and irritation90-100 Short term Temporary shift in hearing
threshold, generally withcomplete recovery
Above 100 Continuous Permanent loss of hearing
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-24
Noise Levels dB(A) Exposure Time EffectsShort term Permanent hearing loss can be
avoided100-110 Several years Permanent deafness110-120 Few months Permanent deafness
120 Short term Extreme discomfort140 Short term Discomfort with actual pain
150 and above Single exposure Mechanical damage to the earSource: Hand Book of EIA, Rao & Wooten
It is a well accepted fact that noise pollution causes fatigue to operating personnel.Provision will be made to keep down the noise level to the extent it is feasible.
4.8.3 Noise Generated due to Excavation and Transportation
Typical noise levels generated during excavation, loading and transportationactivities of the mining activities are presented in Table-4.7.
TABLE-4.7TYPICAL NOISE GENERATION DUE TO EXCAVATION/LOADING/TRANSPORTATION
EQUIPMENT
Sr. No. Name of the Equipment Nos. Noise at Source dB(A)1 Near Tipper (at full race) 2 75 - 902 Excavators 4 75–90
The total noise from all of the above equipments occurs only when all theequipments operate together and simultaneously, which is a remote possibility.
It is proposed to provide air conditioned cabins in Excavators and Tippers to reducenoise impact to the operators.
Noise Dispersion from the Mine
The noise generation from the mine will be from various sources, which will beoriginating from various locations within the Mines. For the purpose of noisedispersion, it is assumed that all the noise generating sources from the mine as onesource. The dispersion of this noise is computed by using the model.
4.8.4 Mitigation Measures
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-25
The noise level control measures at various stages of the mining will be as givenbelow:
Use of Hydraulic drills with in-built cabin; Proper maintenance and lubrication of all moving parts of machines; Non-moving parts of machine will be properly fastened; Blasting will be well designed and arranged in such a way that only one or two
holes are blasted at a time with the use of short delay detonators in combinationwith sequential blasting machine;
No trunk line of detonating fuse will be used on surface (Even if detonating fuseis used as trunk line with cord relays, then it is covered with clay properly);
Primary blasts will be designed such that boulder generation will be minimum; Secondary blasting will be avoided; Explosives will be blasted into confined stage or optimum stemming column will
be maintained for holes during charging of hole; Blasting will be done only during afternoon hours when temperature inversions
are not likely to be there and air density is less; Blast of optimum size will be taken to keep noise level of blasting within 130
dB(A); No blasting will be done when the sky is cloudy because cloud cover can cause
reflection of pressure wave block to the ground at some distance from blast; Non-electric down-the-hole detonators will be used thus reducing noise level
during blasting operation
4.8.5 Occupational Exposure Mitigation Measures
Cabins will be provided for hydraulic drill machines; Earmuffs / ear plugs will be provided to personnel to abate noise; Silencers are provided to modulate the noise generated by machines; and Reducing the exposure time of workers to the higher noise levels.
4.9 Impact due to Ground Vibrations
Ground vibration, fly rock, air blast, noise, dust and fumes are the deleterious effectsof blasting on environment. The explosive energy sets up a seismic wave in theground, which can cause significant damage to structures and disturbance to humanoccupants. It causes major damages to the pit configuration too.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-26
When an explosive charge is fired inside the blast hole, it is instantly converted intohot gases, which exert intense pressure on the blast hole walls. High intensity shockwaves propagate radially in all directions and cause the rock particles to oscillate.This oscillation is felt as ground vibration. The proposed mining operations usingdeep hole drilling and blasting using delay detonators are bound to produce groundvibrations.
Blasting, in addition to easing the hard strata, generates ground vibrations andinstantaneous noise. Ground vibration from mine blasting is expressed by amplitude,frequency and duration of blast. The variables, which influence ground vibrations arecontrollable and non-controllable. The non-controllable variables include generalsurface terrain, type and depth of overburden and wind. Similarly, the controllablevariables include type of explosives, charge per delay, delay interval, direction ofblast progression, burden, spacing and specific charge and coupling ratio.
The oscillation of rock particles is called Particle Velocity and its maximum value iscalled Peak Particle Velocity (PPV), which is measured in millimeter per second. Thestandards for safe limit of PPV are established by Director General of Mines Safetyfor safe level criteria through Circular No. 7 dated 29/8/1997. The safe level criteriaPPV as mentioned in Circular No. 7 of DGMS is presented in Table-4.8.
TABLE-4.8PERMISSIBLE PEAK PARTICLE VELOCITY (mm/s)
Type of Structure Dominant ExcitationFrequency
<8 Hz 8 – 25 Hz >25 HzA] Buildings/structures not belonging to the owner
Domestic houses/structures (Kuchha brick andcement)
5 10 15
Industrial Buildings (RCC and framed structures 10 20 25Objects of historical importance and sensitivestructures
2 5 10
A] Buildings belonging to the owner with limited life spanDomestic houses/structures (Kuchha brick andcement)
10 15 25
Industrial buildings (RCC & framed structures) 15 25 50Source: DGMS Circular No. 7 dated 29/08/1997
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-27
As the distance increases, the PPV value is likely to reduce. The ground vibrationsgenerated by blasting during the mining operations will be well within the standardsprescribed by DGMS by controlled blasting. Ground vibrations are not likely to affectthe structures in the vicinity of mine lease area.By adopting controlled blasting, the problems will be greatly minimized at mines. Theimpacts are also minimized by choosing proper detonating system, optimizing totalcharge and charge/delay. Noiseless trunk delays to minimize the noise due to airblast, non-electric (NONEL) system of blasting for true bottom whole initiation,muffling mats to arrest the dust and fly rock will be adopted. Hence, the impact dueto ground vibration will be significantly reduced.
4.9.1 Vibration Abatement
The blasting operations are proposed to use deep hole drilling and blasting usingdelay detonators which are bound to reduce the ground vibrations. Further, theground vibrations will be controlled by using modern shock tubes with delay non-electric (nonel) detonators. The following mitigation measures should continue to bepracticed.
State of the art technology of non-electric initiation system; Free face is kept sufficiently long and care is taken to ensure that effective
burden is not excessive; Firing of maximum number of blast holes towards free face will be carried out; Number of blast holes per delay will be kept as one; Proper stemming of holes will always be carried out; Blasting will be avoided during foggy wealth and when wind velocity is more than
25 km/hour; Blasting will be performed strictly as per the guidelines specified under blasting
technology; Overcharging will be avoided; Blasting operations will be carried out only during day time as per mine safety
guidelines; A safe distance of about 500 m from center of blasting will be maintained; During blasting, other activities in the immediate vicinity will be temporarily
stopped; Drilling parameters like over burden, depth, diameter and spacing will be
properly designed to give proper blast; The mesh ratio S/B will always be more than unity; S/B >1 S = hole spacing, B = distance between rows (burden); Effective stemming of the explosives will be done in the drill holes;
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-28
The explosives will be selected such that they have:
A high velocity of detonation; A density suited to its particular application; Good fume characteristics; Good water resistance; and Good storage qualities and resistance to atmospheric parameters.
Further, the afforestation programme will reduce the noise and vibration level. A 50m wide belt of trees of increasing height will be provided, which act as an acousticbarrier and reduces noise levels by 20-30 decibel.
In order to reduce ground vibrations caused by blasting the following additionalprecautions will be taken:
a) To provide proper free face to each hole to keep maximum charge per delaywithin limit, holes will be blasted with a combination of short delay detonatorsand sequential blasting machine;
b) To minimize vibration level, burden of first row as well as effective burden forother holes will be kept optimum;
c) Holes will be drilled at 10 degree inclination from vertical so more explosiveenergy is utilized in productive way as in vertical hole only 50% of energy isutilized in productive way;
d) Holes will be charged with proper quantity of explosives instead of excessivecharging;
e) Keep coupling ratio (ratio of charge diameter to hole diameter) minimum forhigh strength booster explosives;
f) Larger column of hole will be charged with low-density explosives i.e., ANFO etcinstead of high-density explosives column to reduce loading density;
g) Total number of holes per blast will be designed properly;h) Blasts will be only once or twice a week; andi) Peak particle velocity will be according to vibration study.
4.10 Greenbelt and Plantation
Proposed Plantation at the Mine Site
The main aim of plantation in the mined out areas is to stabilize the land to protect itfrom rain and wind erosion. The plantation scheme broadly covers the followingareas:
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-29
Greenbelt around peripheral portions of the ML; and Afforestation on top soil dumps and either sides of the haul roads.
Full fledged horticulture department under the guidance of the experiencedhorticulturist will carry out the Greenbelt development programme.
Plantation will be raised in the 7.5 m wide green belt in the safety zone around themining lease by planting the native species around ML area, backfilled and reclaimedarea, around water body, roads etc. in consultation with the local DFO/Agriculturedepartment. The density of the trees will be around 2500 plants per ha.
Greenbelt Development in ML area
It is given immense importance to develop green cover in ML area. About 0.0100 haof land will be brought under green cover development in first five years ofoperation. Area available for afforestation and green belt in mine lease at the end ofmine life is 0.2000 ha in addition to 19.5512 ha of backfilled and reclaimed withplantation area.
It is also proposed to develop wide Greenbelt around peripheral portions of the ML,afforestation on top soil dumps and either side of the haul roads.
Plantation Species
The suggested species for plantation are given in Table-4.9. The plantation species isconsidered based on the following:
Adoption to the geo-climatic conditions of the area; Mix of round, spreading, oblong and conical canopies; Different heights ranging from 4 m to 20 m; Preferably evergreen trees; Fast growing type; A thick canopy cover; Preferably of native origin; and Having large leaf area index.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-30
TABLE-4.9SPECIES SUGGESTED FOR PLANTATION
Sl. No. Botanical name Commonname Uses
1 Actinodaphne obovata Pajihuta Timber, fuel-wood3 Albizia lebbeck Siris Timber, fuel4 A. lucida Moz Timber, fuel5 Altingia excelsa Singri Timber6 Artocarpus lacucha Deb chali Timber; fruits edible7 Bauhinia variegata Kanchon Flower bud edible, fodder8 Castanopsis indica Hingori Nuts edible; Timber,9 Engelhardtia spicata Tongtamasok Timber, fuel
10 Juglans regia Thitcha Seeds, Timber, medicinal11 Kydia calycina Pichola Timber, fuel, ornamental12 Lannea coromandelica Jia Timber, fuel, ornamental13 Magnolia grandiflora Boromthuri Ornamental14 Mesua assamica Sia-Nahar Ornamental15 Morus alba Sahtut Fodder, fuel, ornamental16 Phoebe hainesiana Bola Bonsum Timber17 Pinus wallichiana Blue pine Timber, fuel, ornamental18 Pterospermum acerifolium Hathipayle Timber, fuel, ornamental19 Schima wallichii Chilone Timber, fuel, ornamental20 Terminalia myriocarpa Panisaz Timber, fuel, ornamental
4.11 Biological Environment
There are few forest patches and reserved and protected forests in study area.Marine National Park is about 4.12km, Marine Sanctuary is about 0.521km & GagaBird Sanctuary about 16.55km of the study area.No loss of forest resource is envisaged due to the project. The impacts on flora arebriefly described in the following sections:
4.11.1 Impact on Terrestrial Ecology
Flora
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-31
There is no forest area in the core zone, although there are few reserved andprotected forests in the buffer zone. As the mining activity is in the core zone noimpact on the flora of the buffer zone due to the proposed mining of bauxite isanticipated.
The impact on terrestrial ecology will be due to emission of gaseous pollutant likeNOx. The pollutant at a very low dose acts as an atmospheric fertilizer for thevegetation. However, at higher doses, they are injurious to both vegetation as wellas animals.
Extensive plantation comprising of pollutant resistant trees is undertaken, which willserve not only as pollution sink but also as a noise barrier. It is expected that with theadoption of these mitigatory measures, the impact due to operation of the mine willbe minimal on the terrestrial ecosystem.
Fauna
The adverse impacts on fauna would be mainly due to:
Human activity; Noise; and Land Degradation.
The impact on the fauna of the buffer zone due to the mining activity will bemarginal as minimum disturbance will be there outside the mine lease area. Theproposed progressive mine closure, plantation and pollution prevention and controlover a period of time will create conditions favourable for fauna.
4.11.2 Impact on Aquatic Ecology
No wastewater generation is envisaged from the mining operations. The domesticsewage is sent to septic tank followed by soak pit. The rainwater and seepage watercollected in the sumps will be re-used for dust suppression and for greenbelt. Hence,no impact is envisaged from the mining operations on aquatic bodies.
4.11.3 Mitigation Measures
No impact is envisaged on biological environment of the area. However, extensivegreenbelt / green cover will be developed in and around ML area.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-32
4.12 Occupational Health (Impacts and Mitigation Measures)
The project proponent has concern and takes full responsibility for the protection ofthe workers against sickness, disease and injury arising out of their employment andhave adopted certain principles with regard to occupational health services, likeestablishing and maintaining a safe and healthy working environment which willfacilitate optimal physical and mental health in relation to work.
Project proponent also adopts following occupational health measures
(a) Identification and assessment of the risks from health hazards in the workplace;(b) Surveillance of the factors in the working environment and working practices
which may affect workers' health, including sanitary installations, canteens andhousing; and
(c) Advice on planning and organization of work, including the design of workplaces,on the choice, maintenance and condition of machinery and other equipmentand on substances used in work.
4.12.1 SafetySafety of employees during blasting operation and maintenance of miningequipment and handling of explosive materials is to be taken care of as per the MineRegulations, 1961 and Circulars of DGMS. To avoid any adverse effects on the healthof workers due to dust, heat, noise and vibration, sufficient measures have beenproposed in the EMP. These include:
Provision of wet drilling /or dust collectors; Provision of rest shelters for mine workers with amenities like drinking water,
fans, toilets etc. Provision of personnel protection devices for the workers; Rotation of workers exposed to high noise areas; First-aid facilities.
Occupational Health Survey VARADA of the employees will be carried out at regularintervals.
4.12.2 Identification of Work Related Health Hazards
Details of the periodical check up as per guidelines are given in Table-4.10.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-33
TABLE-4.10PROPOSED PERIODICAL CHECK UP FOR EMPLOYEES
Particular DescriptionFrequency of check up Pre/Post employment check-up
For mines employees = once in 5 year.Test to be conducted Haematological Test, Biochemical Test,
Urine R/M, ECG, Spirometry, Audiometry,Chest X-Ray, Colour Vision, Health reviewSystem, Medical Fitness from FMO
Medical report of each employee will be maintained and will be updated withfinding.
4.12.3 Ranking of Risks to Public Health
Most common diseases in the region are common cold, cough, malaria, flue, entericfever like typhoid which will be prevalent amongst the mine workers.
The operations in the mine can lead to release of the pollutants to the atmosphere,as given in Table-4.11. Adequate mitigation measures are in place to prevent therelease of the pollutants to the atmosphere.
TABLE-4.11POSSIBLE POLLUTANTS FROM DIFFERENT OPERATIONS
Pollutant Source of mine operationDust Drilling, Blasting, Material HandlingNoise Blasting, Drilling, HEMMVibrations Drilling, BlastingCO2 , N0x , SO2, HC HEMM operation at mines
4.12.4 Assessment of Risks
Risks will be assessed through impact severity and probability studies. In addition tothe air & water quality monitoring, soil analysis and vibration studies will be carriedout.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka , Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-4ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
IV-34
4.12.5 Measures to Communicate Risks for Prevention and Control
Measures will be taken to communicate risks before starting of mining to generalpeople. This will be done through proper training and conducting safety talks forawareness of risks involved and correct practices communication by ways of displayboards and safety meets. Procedures and work instructions will be displayed andcommunicated to all on regular basis.
With the proposed mitigating steps, the impacts can be minimized and theoccupational health impacts are insignificant.
Working of mine will be done as per approved mining plan and environmental plans.
TABLE-4.12Budget for Occupational Health
Particulars Capital Cost (Rs.) Recurring Cost (Rs.)
For routine checkup 40,000 50,000
Medical aid as per ESIScheme
20,000 50,000
Training 15,000 20,000
PPE 40,000 50,000
Total 1,15,000 1,70,000
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, District JDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-5Analysis of Alternative Technology & Site
V-1
CHAPTER-5
ANALYSIS OF ALTERNATIVES (TECHNOLOGY & SITE)
INDEX
SI.NO CONTENTS PAGE NO.
5.1 Analysis of Alternatives Technology V/2
5.2 Analysis of Alternative Site V/2
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, District JDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-5Analysis of Alternative Technology & Site
V-2
5.0 ANALYSIS OF ALTERNATIVE TECHNOLOGY AND SITE
5.1 Site Alternatives under Consideration
No alternative mining method has been proposed.
The mining projects are site specific as such alternate sites is not considered.
5.2 Analysis of Alternative Technology
5.2.1 Choice of Method of Mining
Factors in the choice of an actual mining method for a given deposit are depositcharacteristics, percentage recovery, requirement of health and safety andenvironmental concerns, production, scheduling scope of mechanization andautomation, workforce requirements wage rates, land reclamation, operating andcapital cost estimates. The selection of the mining method (development andextraction) is a key decision to be made in the opening up of a mine.
Surface or open pit mining is used for large, near-surface deposits is drilled, blasted,loaded into trucks, and hauled to a facility where it is crushed and ground to auniform size for further processing. Surface mining requires the removal and disposalof layers of top soil and underlying rock commonly called the overburden. The ore isbroken into pieces that can be easily transported and moved to a crushing plant forfurther processing. Mining must be planned so that the combine of miningprocessing and reclaiming the land is taken up concurrently.
The Semi Mechanised opencast mining method will be adopted because of thefollowing reasons:
The Semi Mechanised opencast mining operations ensure higher mineralconservation.
The method used for mining is efficient for Bauxite mining, so no alternative miningmethod has been proposed.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)
Chapter-6Environmental Monitoring Program
VI-1
CHAPTER 6- ENVIRONMENTAL MONITROING PROGRAM
6.1 Introduction VI/2
6.2 Implementation Schedule of Mitigation Measures VI/2
6.3 Environment Monitoring Programme VI/5
6.4 Reporting Schedules VI/5
6.5 Cost Estimates VI/8
6.6 Corporate Environmental Policy VI/9
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)
Chapter-6Environmental Monitoring Program
VI-2
6.0 ENVIRONMENTAL MONITORING PROGRAMME
6.1 Introduction
The Environment Monitoring Programme is required to ensure sustainabledevelopment in the study area (10 km) of the project site, hence it needs to be an allencompassing plan for which the plant authorities, Government, Regulating agencieslike Pollution Control Board etc. working in the region and more importantly theaffected population of the study area need to extend their co-operation andcontribution.
6.2 Implementation Schedule of Mitigation Measures
The mitigation measures suggested in Chapter-4 will be implemented so as to reducethe impact on the environment due to the operations of the proposed project.Implementation schedule of mitigation measures is given in Table-6.1.
TABLE-6.1 IMPLEMENTATION SCHEDULE
Sr. No. Recommendations Time Requirement Schedule
1 Air pollution control
measures
Before commissioning of
proposed mining
Immediate
2 Water pollution control
measures
Before commissioning of the
mine
Immediate
3 Noise control measures Along with the commissioning
of the mine
Immediate
4 Ecological preservation
and up gradation
Stage-wise implementation Immediate
&
Progressive
Administrative Aspects & Environmental Monitoring Program
Regular monitoring programme of the environmental parameters is essential to takeinto account the changes in the environmental quality.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)
Chapter-6Environmental Monitoring Program
VI-3
Institutional Arrangements for Environment Protection and Conservation
The mine will be supervised and controlled by Mines Manager supported by adequateteam of technically and statutorily qualified personnel apart from the operating staffof skilled, semi-skilled, unskilled and other categories.
The organizational structure for Environment Cell for mining operations is shown inFigure-6.1. This Environment Cell is responsible for the management andimplementation of the environmental control measures.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)
Chapter-6Environmental Monitoring Program
VI-4
Figure-6.1 Organization Structure for Environment Management
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)
Chapter-6Environmental Monitoring Program
VI-5
Basically, this department will supervise the reclamation planning & management, air& water pollution control management, Liasoning with State & Central Statutoryagency & Committee.
In case the monitored results of environmental pollution are found to exceed theallowable limits, the Environment Management Cell will suggest remedial action andget these suggestions implemented through the concerned authorities.
The Environment Management Cell will also co-ordinate all the related activities suchas collection of statistics of health of workers and population of the region,afforestation and greenbelt development. The Environment Management Cell willreview Corporate Environmental performance along with the reporting of non-compliances.
6.3 Environment Monitoring Programme
Monitoring shall confirm that commitments are being met. This may take the form ofdirect measurement and recording of quantitative information, such as emissions andwastes, for measurement against corporate or statutory standards, consent limits ortargets. It may also require measurement of ambient environmental quality in thevicinity of a site using ecological/biological, physical and chemical indicators.Monitoring may include socio-economic interaction, through local liaison activities oreven assessment of complaints.
The environmental monitoring will be conducted in the mine operations as follows: Air quality; Water quality; Noise levels; Soil Quality; and Greenbelt DevelopmentThe details of post project monitoring is presented in Table 6.2
6.4 Reporting Schedules
Post project monitoring will be carried out as per conditions stipulated inenvironmental clearance letter issued by MOEF, consent issued by SPCB as well asaccording to CPCB guidelines. The project site is considered as core zone and the arealying within 10 km radius from the mine site is considered as buffer zone, where someimpacts may be observed on physical and biological environment. In the buffer zone,slight impact may be observed and that too is occasional, table below showing thedetails of post Project Monitoring programme.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)
Chapter-6Environmental Monitoring Program
VI-6
Table-6.2 Post Project monitoring programme
Attributes Sampling MeasurementMethod
Test ProcedureNetwork Frequency
A. Air EnvironmentMeteorological· Winddirection· Relative
humidity· Rainfall
Minimum1 sitein the projectimpact area
Regularly inoneseason byWeatherMonitoringStation
Mechanical/automaticweather station
-
PollutantsPM10
7 locations inthe projectimpact area(Minimum 2locations inupwind side,2 sites indownwindside / impactzone and 1 incore zone)
Once in aseason.
Gravimetric method -Gravimetric method -
SO2 EPA Modified West &Geake method
Absorption inPotassium TetraChloromercuratefollowed byColorimetricestimation usingP-RosanilinehydrochlorideandFormaldehyde(IS:5182 Part - II).
NO2 Arsenite modifiedJacob & Hochheiser
Absorption indil. NaOH andthen estimatedcolorimetricallywithsulphanilamideand N (I-Nepthyle)EthylenediamineDihydrochlorideand HydrogenPeroxide(CPCB Method).
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)
Chapter-6Environmental Monitoring Program
VI-7
B. Water EnvironmentpH, Turbidity,Colour, Odour,Taste,TDS, TotalHardness,Calciumhardness,Magnesiumhardness,Chloride,Fluoride,Sulphate,Nitrates,Alkalinity,Iron, Copper,Manganese,Mercury,Cadmium,Selenium,Arsenic,Cyanide, Lead,Zinc,Chromium,Aluminum,Boron,PhenolicCompounds
Set of grabsamplesduring preand post-monsoonforground andsurfaceWater in thevicinity.
Diurnal andSeason wise
As per IS 10500 Samples forwaterquality shouldbecollected andanalyzedas per :IS : 2488 (Part 1-5)methods forsamplingand testing ofIndustrialeffluentsStandardmethods forexamination ofwaterand wastewateranalysispublished byAmerican PublicHealthAssociation.
C. NoiseNoise levels atDay & nighttime -Leq dB (A)
MineBoundary,High noisegeneratingareas withinthe lease
Quarterly /Halfyearly
As per CPCB norms As per CPCBnorms
D. SoilpH, BulkDensity, Soiltexture,Nitrogen,AvailablePhosphorus,
7 locationsin the projectimpact area
Yearly/halfyearly
As per USDAMethod
As per USDAMethod
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)
Chapter-6Environmental Monitoring Program
VI-8
Potassium,Calcium,Magnesium,Sodium,ElectricalConductivity,Organic Matter,ChlorideE. Socioeconomic· Demographicstructure· Infrastructureresource base· Economicresource base· Health status:Morbiditypattern· Cultural andAestheticattributes· Education
Socioeconomicsurvey is basedonproportionate,stratified andrandomsamplingmethod
Minimumfor twophases ofthe project
Primary datacollection throughQuestionnaire
Secondary datafrom censusrecords,statistical hardbooks, toposheets, healthrecords andrelevant officialrecords availablewith Govt.agencies
6.5 Cost Estimates
The details of the cost to be incurred for successful monitoring of environmentalparameters and implementation of control measures are given in Table-6.3.
TABLE-6.3COST OF ENVIRONMENTAL PROTECTION MEASURES
(Rs. in Lakhs)SI. No. Measures Capital cost
(in Rs.)Annual recurring cost
(in Rs.)Proposed Proposed
1 Pollution Controli) Dust Suppressionii) Garland drain & grounddump
25,00025,000 50,000
2 Pollution Monitoringi) Air pollutionii) Water pollution
25,00025,000
30,00030,000
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)
Chapter-6Environmental Monitoring Program
VI-9
3 Reclamation &RehabilitationGreen Belt
25,000 30,000
4 Others (Environmentalstudy, Statutory compliance,etc.)
50,000 30,000
Total 1,75,000 1,80,000
6.6 Corporate Environmental Policy
The project proponent commits to contributing towards a clean and sustainableenvironment and continually enhancing our environmental performance as an integralpart of our business philosophy and values.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-1
CHAPTER 7- ADDITIONAL STUDIES
S.No. Content Page No.
7.0 Public ConsultationVII/2
7.1Risk Assessment & Occupational Health & Safety andDisaster Management
VII/12
7.2 Occupational Health – Proposal for SurveillanceVII/14
7.3 Plan of evaluation of health of workersVII/10
7.4 Disaster Management PlanVII/21
7.5 Major Hazards and their ControlVII/23
7.6 Disaster Preventive MeasuresVII/25
7.7The responsibility of the members of the Disaster ControlTeam
VII/31
7.8 Disaster due to Natural Calamity and External FactorsVII/34
7.9 ConclusionVII/35
7.10 Contact DetailsVII/39
7.11 Socio-Economic Impact Assessment of Virpur GunawaliBauxite Mining Project, Jamnagar, Gujarat
VII/39
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-2
ADDITIONAL STUDIES
7.0 Public Consultation:
The public hearing for the Virpur (Gunawali) Bauxite mine for 1, 51,875 TPA capacity
with semi mechanized open cast method in Virpur (Gunawali) village, Kalyanpur
Tehsil, Devbhumi Dwarka District, Gujarat was conducted on 29.03.2016, as per the
Environment Impact Assessment Notification dated 14th September 2006. The public
hearing details are summarized in the Table-7.1.
Table-7.0 Public Hearing Details
Particular DescriptionAdvertisement for Public Hearing
Date of Advertisement inNewspapers
Name of Newspapers
25.02.2016
Gujarat SamacharIndian Express Editions
Date of Public Hearing 29.03.2016 at 10.30A.MVenue Virpur (Gunawali) Bauxite Mine Area,
Virpur ( Gunawali) Block, Survey No. 142,Village : Virpur, Tehsil : Kalanpur, District :Devbhoomi Dwarka, Pin code : 361315
Members Shri RR. Raval (G.A.S), District Magistrate,Devbhoomi Dwarka.P.U. Dave Regional Officer, GPCB Jamnagaras representative of the Member Secretary,GPCB
The press notification indicating the date and venue of the public hearing was issued inprominent news papers Viz. Gujarat Samachar , Indian Express Editions with project detailsinviting suggestions, views, comments and objections from the public regardingestablishment of 1,51,875 TPA capacity semi mechanized open cast method in Virpur(Gunawali) village, Kalyanpur Tehsil, Devbhumi Dwarka District, Gujarat. Public hearingmeeting was convened by P.U. Dave Regional Officer, GPCB Jamnagar along with Shri RR.Raval (G.A.S), District Magistrate, Devbhoomi Dwarka.Around 74 people attended the public hearing.The public hearing proceedings & related papers are attached as Annexure- XIII.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-3
The Technical Consultant briefed the public about the purpose of organizing the hearing and
asked the project proponent to explain the salient features of project and specific reference to
the impacts on environment, its management and social welfare measures including
community development activities proposed.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-4
7.0.1 Issues Raised during Public Hearing and Commitment
Sr. No. Name and Address Point Represented Replies from projectproponent
Action Plan Time Frame FinancialAllocation
1. Shri KachrabhaiBhimabhai Kambariya,Sarpanch, Village :Virpur
From company my village is gettinglivelihood and surrounding villagesalso get livelihood.
We get free Doctor Service fromcompany.
People who willwork in miningoperation lesseewill provideDoctor facility toemploy miningoperation duringmining operation.
After obtainingEnvironmentalClearance.
A sum of Rs. 2.40Lakhs has beenallocated for CSRpurpose.
2. Shri KambariyaJagdishbhai Village :Virpur
Progress of this village andsurrounding villages is through thecompany.
Company is working that’s whyvillages are happy.
There is no rain for years, inspite ofthat villagers need to go outside forlivelihood. Job of own choice isavailable at door step.
This company is a big tree underwhich nearby villager’s sleep, if thisbig tree is cut then everybody face
7.5 m barrier zonewill be madeduring miningoperationPlantation will bedone as perguidelines forcontrol pollution& dustsuppression.It is ensure that Ifthere is anydamage to cropdue to miningactivity;
Green belt willdeveloped in 7.5mbarrier zone at theend of mine andentire area will bereclaimed byAfforestation
A sum of Rs. 2.40Lakhs has beenallocated for CSRpurpose.
A sum of Rs.25,000 has beenallocated Greenbelt purpose as acapital costhowever sum of30,000 forrecurring cost forgreen beltdevelopment.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-5
trouble.The company may cause 5% harm
but on other side benefits are 95 %.
Company is giving some fund toGaushala, conducts Medical Campsand also sprinkling water on roads.
The Company has mined out, sea, ifthis water is stored then in thecoming years when will be no orless rain this water can be used byvillagers and animals.
Company is carrying out plantationbut it should be increased as more aspossible then, the barren landbecome fertile and useful to all.
Compensationwill be given afterthe survey withlocal authority.
3. Shri NagabhaiNebhabhai GadherVillage : Mewasa
The suggestions given to thecompany are correct, they shouldproperly implement.
All the nearby villages surroundingthe project are getting livelihood,nobody has objection.
Somewhat difficulties of 5 % facedby villagers has to be addressed andthere are no any other problem.
4. Shri BharatbhaiNebhabhai Varvariya,
This is Gunawali mines, as perenvironmental, have you seen any
Representative of theproject informed that
Road will bemaintained after
After obtainingEnvironmental
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-6
Village : Mewasa trees.Work is prohibited in 10km rangefrom the sea then also many minesare working.
Here babools are planted, have youseen any tree planted.
Company is breaking the roads andcreating big dumps.
Contractors are opposing that’s whynot speaking more. Mewasa villagemeeting is tomorrow, that time willspeak.
this area is 55 ha out ofwhich area for mining is37 ha and, 18 ha fallsunder Eco Sensitivezone, where in miningactivity is stopped.
He again informed that,you talked about 10km,for that Government hasnotified 1km EcoSensitive zone. As perthe notification dated22.08.2013 the area ismarked and 18 ha isreduced from it.
starting miningoperation.
It is ensured thatPlantation will bedone as perguidelines forcontrol pollution& dustsuppression.
Clearance.
A sum of Rs.25,000 has beenallocated Greenbelt purpose as acapital costhowever sum of30,000 forrecurring cost forgreen beltdevelopment.
5. Shri KumbhabhaiBoghabhai KambariyaVillage: Virpur
Trees are planted at Gunawali areafew are small, few are big.
Water sprinkling is carried outregularly.
Labours and tractor owners aregetting livelihood.
Regularly getting salary.
Everything is good.
It is ensured thatwater sprinklingwill be providedfor dustsuppression.
After obtainingEnvironmentalClearance.
6. Shri KarshanbhaiDeveshibhai Madan
In any field, if such good companyis exist and doing good work then
Representative of theproject informed that
It is ensured thatPlantation will be
After obtainingEnvironmental
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-7
Village: Pindara public and surrounding 10 villagesget livelihood. Plants may beplanted. Care for environment maybe taken.
Company is not carrying out loadingon dedicated road. Loading iscarried out in surrounding villagesand on any road.
Village representations are notbeing heard.
On allotted road loading should becarried out.
Water sprinkling is not reachingupto village road. Your trucks arepassing through surroundingvillages in all directions; at howmany places you will sprinkle water.You may be trying but you may notsprinkle water on all roads. Yourstrucks should not be passed on anyroads.
Due to your loading on VirpurGunawali road during croppingseason, crops get damage. If youpass through given road, thennobody face problem.
our production is upto 1,51,000 MT. productionsfor one day isapproximately 500tonnes.
Approximate 25 truckswill be passing per day.
In addition he informedthat Bypass road isdeveloped for trucks.
He further informed thatcompany is regularlysprinkling water on theroad where trucks arepassing.
done as perguidelines forcontrol pollution& dustsuppression.
Road will bemaintained duringStart miningoperation.
It is ensured thatwater sprinklingwill be providedfor dustsuppression.
Clearance.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-8
7. Shri GirishbhaiMakwana,Village: Nandana
I am working at pushpabenPrabhudas Makhecha company andhumbly requesting to start pushabenprabhudas Makhech mine
8. Shri RamjibhaiDevshibhai Village:Pindara
I am doing service at company. 25to 30 boys are working from myvillage in company, the boys aregetting livelihood.
If 25 to 30 boys are working, andone person from one family, then 8to 10 persons depend on him.
If 5% damage due to company thenon other hand 95% benefits arethere.
25 to 30 boys are working inGunawali bauxite mine. Companystarts working then livelihood wewill get.
There is no any industry in this areaother than Bauxite.
9. Shri BharatbhaiNebhabhai LagariyaVillage: Mewasa
Company is BML, Ashapura isworking as a contractor.
Which lease is of Ashapura in
Regional officer, GPCB,Jamnagar andrepresentative of theMember Secretary,
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-9
Virpur, Mewasa and Mota Asota? GPCB informed that thispublic hearing is forpushpaben PrabhudasMakhecha project, sosubmit yourrepresentation for that,and requested not togive other representationhere For otherrepresentation contactthe GPCB office. Therepresentation related topushpaben prabhudasMakhecha will beincluded in the Minutesof this public hearing.
10. Shri Parbatbhai LagariyaVillage: Virpur
I am working in this company.
Company is obeying all rules ofmining.
Water sprinkling is being carried outwhere trucks are passing.Providing fund for fodder inGaushala.
The development of this companywill held in getting livelihood. 8 to10 villages will be benefitted.
11. Shri NebhabhaiMurabhai Kambariya
My age is 35 year. Bauxite is since50 years and will be for 100 years.
Representative ofproject informed that,
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-10
Village : VirpurIf this company would not comevillage would not be developed.
Before 10 years, in 2001 there wereno houses to stay.
There are benefits due to companyarrival. Now it is Ram Raj.
there will be benefits tothe people through thiscompany.He informed thatGovernment will get Rs.1.82 crore as a Royalty,approx Rs. 5 croreincome as taxes and forconservation plan Rs.17.83 lakh is proposed,which will beimplemented throughforest department.
12. Shri NathubhaiDevabhai MatangVillage: Bhatia
I am working in company.
Continuation of the company will bebenefited to the people.
Agriculture is irregular so, ifcompany presents then people getlivelihood.
There is little loss but benefits topoor people.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-11
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-12
7.0.2 Conclusion on Public Hearing
As there is no further representation from the Public present during public hearing,
P.U. Dave Regional Officer, GPCB Jamnagar summed up the Proceedings of the
Public hearing and declared the Public Hearing as over. The details of people
attended, representations received in writing during the public hearing are enclosed
along with the minutes of the public hearing as Annexure XIII.
7.1 Risk Assessment & Occupational Health & Safety and Disaster Management
Mining by open cast method involves dust generation by excavation, loading and
transportation of mineral. At site, during blasting, excavation and loading activity,
dust is main pollutant which affects the health of workers whereas environmental and
climatic conditions also generate the health problems.
Addressing the occupational health hazard means gaining an understanding of the
source (its location and magnitude or concentration), identifying an exposure pathway
(e.g. a means to get it in contact with someone), and determination of likely a receptor
(someone receiving the stuff that is migrating).
Occupational hazard due to mining mainly comes under the physical hazards.
Possible physical hazards are as below mentioned:-
7.1.1 Physical Hazards due to Mining Operations:
Following health and safety related physical hazards were identified due to mining
operations to the workers:-
1. Light: - The workers may be exposed to the risk of poor illumination during
evening hours or excessive brightness during day times. The effects are eye strain,
headache, eye pain and lachrymation, congestion around the cornea and eye fatigue.
2. Heat and Humidity: - The most common physical hazard is heat as working is
done in open sun light without any shed. The direct effects of excessive heat exposure
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-13
in summer season areas are burns, heat exhaustion, heat stroke and heat cramps; the
indirect effects are decreased efficiency, increased fatigue and enhanced accident
rates. Heat and humidity are encountered in hot and humid condition when
temperatures and air temperatures may exceed 480C in the mining area.
3. Eye Irritation: - During the high windy days in summer the sandstorms could be
the problems for eyes like itching and watering of eyes.
4. Respiratory Problems: - Large amounts of dust in air with possibility to have free
crystalline quartz can be a health hazard, exacerbating respiratory disorders such as
asthma and irritating the lungs and bronchial passages. However, this can be easily
controlled by water sprinkling.
5. Noise Induced Hearing Loss: - Vehicles and Machinery is the main source of noise
pollution at the mine site, though they are not significant
6. Insect and snake bites: These are possible as their habitations below boulders, if
any, may be disturbed during mining.
7. Approaching areas having deep pits unknowingly: These are possible if there is
any such site nearby and no warning sign boards are provided.
Safety in the workplace is critical to the success of running a business, no matter what size it
is. As a small business owner one has certain rights and responsibilities regarding health and
safety in the workplace. Even without any employees, one must ensure that the business does
not create health and safety problems for the customers and the general public.
All safety gears will be provided to workers and care will be taken by the Management that
these are used properly by them. All safety norms will be followed.
The Management, however small it may be, will form a policy and methods to execute them
as given in Fig. 7.1.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-14
Fig. 7.1: Occupational Health – Policy and Methods
7.2 Occupational Health – Proposal for Surveillance
The choice and the implementation of specific measures for preventing workplace injury and
ill health in the work-force of the proposed mining project are due to operations like blasting,
excavation, mining machineries, loading and transportation of materials in open areas without
any shed and exposure to unexpected and natural weather conditions. Below are the most
common causes of injury and illness in the mining industry:
Slips, trips and falls on the same level, falls into pits, unguarded machinery, falling
objects while loading;
Moving machinery, on-site transport, loaders and trucks/dumpers;
Exposure to uncontrolled solar heat, exposure to minerals and inhalable agents (fine
dusts );
Manual handling and repetitive work;
Lack of OSH training, poor work organization;
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-15
Inadequate accident prevention and inspection, inadequate emergency first-aid and
rescue facilities, lack of medical facilities and social protection;
Mining industry generates dust during its operation and transportation. Dust may enter
into the systemic circulation and thereby reach the essentially all the organs of body
and affects the different tissues.
Continuous working and improper working position leading to pain & exhaustion.
7.2.1 The OHS system:
The entire OHS system will be designed as per Fig. 7.2.
Fig. 7.2: OHS system
7.2.2 Personal Protective Equipment (PPE)
General Provisions
As a supplementary protection against exposure to hazardous conditions in the mining
projects where the safety of workers cannot be ensured by other means, such as eliminating
the hazard, controlling the risk at source or minimizing the risk; suitable and sufficient PPEs,
having regard to the type of work and risks, and in consultation with workers and their
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-16
representatives, shall be procured and used by the workers and provided and maintained by
the employer, without cost to the workers.
Items of PPE provided shall comply with the relevant BIS standards and criteria
approved or recognized by the competent authority. Where BIS standards are not
available, PPEs meeting international standards may be procured.
Those responsible for the management and operation of the personal protection
programme shall be trained in the selection of the proper equipment, in assuring that
it is correctly fitted to the people who use it, in the nature of the hazards the
equipment is intended to protect against, and provide adequate comfort, and in the
consequences of poor performance or equipment failure.
PPEs shall be selected considering the characteristics of the wearer and additional
physiological load or other harmful effects caused by the PPEs. It shall be used,
maintained, stored and replaced in accordance with the standards or guidance for
each hazard identified at the facility and according to the information given by the
manufacturer.
PPEs shall be examined periodically to ensure that it is in good condition.
Different PPEs & their components shall be compatible with each other when worn
together.
It shall be ensured that the procured PPEs are ergonomically designed and, to the
extent practicable, should not restrict the user’s mobility or field of vision, hearing or
other sensory functions.
Employer shall ensure that the workers who are required to wear PPEs are fully
informed of the requirements and of the reasons for them, and are given adequate
training in the selection, wearing, maintenance and storage of this equipment.
When workers have been informed accordingly, they shall use the equipment
provided throughout the time they may be exposed to the risk that requires the use of
PPEs for protection.
The PPEs shall not be used for longer than the time indicated by the manufacturer.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-17
Workers shall make proper use of the PPEs provided, and maintain it in good
condition, consistent with their training and be provided with the proper means for
doing so.
PPEs procured shall not contain hazardous substances, such as asbestos.
7.2.3 Head Protection:
Helmets intended for use in industry shall be subjected to a test for resistance to
falling objects while loading.
Any helmet that has been submitted to a heavy blow, even if there are no evident
signs of damage, shall be discarded.
If splits or cracks appear, or if a helmet shows signs of ageing or deterioration of the
harness, the helmet shall be discarded.
Helmets for persons working overhead shall be so procured that they shall be
provided with chin straps.
In addition to safety, consideration shall also be given to the physiological aspects of
comfort for the wearer.
The helmets shall be so procured that they shall be as light as possible, the harness
should be flexible and should not irritate or injure the wearer and a sweatband should
be incorporated.
All protective headgear shall be cleaned and checked regularly.
7.2.4 Face & Eye Protection:
Face shields or eye protectors shall be used to protect against flying particles and dust
storms.
Goggles, helmets or shields that give maximum eye protection shall be worn by
operators and their helpers.
With the use of face and eye protectors, due attention shall be paid to greater comfort
and efficiency in consultation with workers.
The protectors shall be fitted and adjusted by a person who has received training in
this task.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-18
7.2.5 Respiratory Protective Equipment:
When effective engineering controls are not feasible, or while they are being
implemented or evaluated, masks, appropriate to the hazard and risk in question, shall
be used to protect the health of the worker working in dusty conditions.
7.2.6 Hearing Protection:
Noise pollution is not a major issue in the project except while working near a
blasting site and noisy mining machinery. However, the following measures shall be
taken if anybody is to work in a noisy area:
When effective engineering controls are not feasible or while they are being
implemented or evaluated, hearing protection shall be used to protect the health of
workers.
Hearing loss of speech frequencies may occur with elevated long-term exposure to
noise. The use of hearing protectors gives the best results to users who are well
informed of the risks and trained in their use. If earplugs are used, special attention
shall be paid to the proper fitting technique.
Hearing protectors shall be so procured that they are comfortable, and the users shall
be trained to use them properly. Special attention shall be paid to possible increased
risk of accidents due to the use of hearing protectors. Earmuffs reduce the capacity to
locate sound sources and prevent warning signals from being heard. This is especially
true for workers with considerable hearing loss.
No model is suitable for all persons. Those wearing hearing protectors shall be able to
choose from alternative products that meet the attenuation criteria. Earplugs shall not
be the only solution as not all people can wear them.
Hearing protectors shall be evaluated through an audiometric test programme for
exposed workers.
7.2.7 Protection from fall:
In mining projects, workers are exposed to working at uneven sites with pits and
slopes not properly designed.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-19
Devices like fencings and warning signboards shall be provided to prevent workers
from falling to the extent possible.
Appropriate and timely rescue shall be provided.
7.2.8 Protection from flying rock and blast vibration:
Though the blasting will be controlled and only to loosen the rock, flying rock
elements may reach habitations and injure persons.
Blasting will be done on schedule times with proper information by public
announcement system to warn workers and nearby villagers.
The area to be blasted will be fenced temporarily.
Charge amount and delay per charge will be controlled to limit vibration within CMRI
limits and USBM Model will be run to predict peak particle velocity (ppv) and safe
distance from blasting site where ppv will be within limits.
FIGURE-7.3
IDENTIFICATION OF HAZARDS IN OPEN CAST MINE
OPEN CAST MINE
EXPLORATIONOF ORE
DRILLING ANDBLASTING
DUSTECOLOGICAL RISK(LAND, AIR, WATER NOISE
TRANSPORTATIONORE
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-20
7.3 Plan of evaluation of health of workers
By pre-designed format during pre-placement and periodical examinations.
Proper schedule will be devised and followed with help of occupational health experts
and doctors.
7.3.1 Schedule of medical check-up during operational phase:
Comprehensive Pre-employment medical checkup for all employees
General check up of all employees once every year.
Local hospitals and Govt. health monitoring system will be engaged.
Dispensary and ESI facility will be provided to all workers as applicable
7.3.1.1: Medical Examination Schedule:
All workers will be subjected to Initial Medical Examination as per Mines Rule 1955
at the time of appointment. Periodical Medical Examination will be conducted at least
once in a year. Immediate action will be taken if any worker is found to exhibit signs
of heat stroke or dehydration or snake bites etc. by signing a contract with a nearby
hospital and shifting him there.
Medical camps will be organized. The detail of health check up and periodical
medical examination schedule is given in Table 7.1. The period mentioned here are
assuming a 3 year lease. In case the lease is of longer duration, the period will increase
accordingly. √ in a cell indicates action.
Table 7.1: Medical Examination Schedule
S.No Activities 1st Year 2 nd Year 3 rd Year
Initial Medical Examination (Mine Workers)
1 Physical Check -up √
2 Psychological Test √
3 Audiometric Test √
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-21
4 Respiratory Test √
5 Eye check up √
Periodical Medical Examination (Mine Workers)
1 Physical Check -up √ √ √
2 Psychological Test √ √ √
3 Audiometric Test √ √ √
4 Respiratory Test √ √ √
5 Eye check up √ √ √
Medical Camp (Mine Workers & Nearby
Villagers
√ √ √
Training (Mine Workers) √ √ √
7.4 Disaster Management Plan
7.4.1 Introduction
Even with all precautions, disasters may take place. As such, an Emergency Plan has been
formulated to take care of any disaster in the project and surrounding areas and is detailed
here.
In order to prevent occurrence of any disaster, the project will be provided with
various safety measures as described. However, in case of failure of safety measures or due
to natural calamity or sabotage, disaster may happen. Therefore, it is necessary to provide
disaster control facilities to minimize losses due to disaster. Normally, in the project, no
major disaster affecting nearby population areas are foreseen. However, accidents inside
the project affecting workplace in vicinity cannot be ruled out.
7.4.2 Definition of disasters
A situation will be called a `Disaster' if it entails any one or more of the following factors:
Risks of loss of human lives - ten or more in one single situation.
Loss of property as a consequence of the incident is over Rs.1 Crore and/or bears a
potential to the above.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-22
A situation which goes beyond the control of the available resource of the project.
A situation apparently may not have much loss but its long-term severity can affect
loss of life, production and property.
7.4.3 Type of disasters:
The types of possible disaster in the project are given below:
i) Disaster due to failure of safety measures on account of:
- Fire and explosion
- Pressure wave transmission due to blasting or explosion
- Collapse of mine wall and dump slope
- Accidents due to mining equipment and trucks/dumpers
ii) Disaster due to natural calamity on account of:
- Flood
- Earth quake / cyclone / Storm / Cloud burst / Lightning
iii) Disaster due to external factors on account of:
- Food poisoning / Water poisoning
- Sabotage
- Quick sand conditions
7.4.4 Objectives:
Objectives of the disaster control/management plan for the proposed project are:
i. To identify type of major disasters that may occur in the project.
ii. To collect data on type of disasters, which had happened already in other mining projects.
iii. An action plan to handle disaster.
7.4.5 Identification of Hazardous Process/Area: The entire area is prone to hazard.
7.4.6 Level of Accident:
If there is any disaster in any part of the project /work place due to any reason, the area which
may be affected can be classified in the following four classes:
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-23
1. Level I - Operator level
2. Level II - Local/community level
3. Level III - Regional/ national level
4. Level IV - International level
Level I class of accidents have been considered for the project.
Level I
Under this level, disasters may happen due to fire and explosion, accidents due to traffic, falls
on uneven areas and pits, toxic gas release, pressure wave transmission due to blasting or
explosion, flash floods, inundation, cyclones, cloud burst, collapse of dumps and earthquake.
This level has probability of occurrence affecting persons inside the project site-may be
workers or any visitor including stray animals who have strayed into the site as the site has no
protective boundary of its own due to its nature unlike an industrial plant. Moreover, as the
project, other than controlled blasting, has no source of fire, explosion, or toxic gas release,
the effect will not reach nearby community.
7.5 Major Hazards and their Control:
Fire and Explosions:
The mining machineries use diesel and these may be stored at site. The fuel oil storage areas
may face fire and explosion problems if the Hazardous Materials Act is not complied with.
Fire protection facilities will be provided as mentioned under Disaster Control Team
responsibilities to handle Fire and explosion.
Fall in pits:
The entire work area is unprotected worked out area. The levels are not uniform having pits
and slopes. There are every possibility of workers, visitors and stray cattle to fall in pits.
Fencing will be provided wherever is practicable as complete fencing of pits is not
practicable.
Failure of Pit Slope
Pit will be created of limited depth with bench heights not exceeding 3m and a slope of 450.
Thus the chance disaster during collapse of pits or failure of pit slope is under control.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-24
Failure of Waste Dump
Rolling of stones from dump may pose severe chances of injury. However, as all dumps will
have adequate slope, chances are minimized. However, bund walls of 3m height will be
created around dumps to catch rolling objects. Also, during heavy rains, dump slide may take
place which will be contained by these bund walls.
Explosion, Fire
The operation needs only controlled blasting and hence any major fire or explosion disaster is
not anticipated.
Accidents from Trucks/Dumpers
Movement of trucks and dumpers inside the lease area and accident during loading and
transportation of minerals/overburden may cause accidents.
Measures to Prevent Accidents Due to Trucks/Dumpers
All transportation within applied mining lease working shall be carried out directly under
the supervision and control of the management.
The vehicles will be maintained in good condition and checked thoroughly and vehicles
without fitness certificate or PUC Certificate will not be allowed. In case of doubt, vehicles
will be inspected by a competent person authorized for the purpose by the management.
Road signs will be provided along the evacuation route showing maximum speed limit,
school sites, market places, hospital sites or any other sites where crowds are anticipated en
route and at each and every turning point up to the main road (wherever required).
To avoid danger while reversing the equipment’s/ vehicles especially at the working place /
loading points, stopper shall be posted to properly guide reversing/ spotting operating,
otherwise no person shall be allowed within 10 m radius of machine except operators.
Flash Floods:
As the project site has many deep pits, it has probability of getting affected by flash floods in
case of excessive rains, if the workers remain uninformed. They may be severely affected
leading to wash away in the stream.
Insect and Snake Bites:
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-25
The area of mining is broken areas and pits having good habitation of benthic organisms,
insects and snakes. During working, they may feel disturbed and there are possibilities of
insect and snake bites. Anti venom injections will be kept at site and at contracted hospitals
nearby and this will be administered only by a qualified doctor as mentioned in the Disaster
Control Team responsibilities.
7.6 Disaster Preventive Measures
Alarm System – an effective control system:
In case of mining projects, where maximum chances of disaster are due to uninformed
blasting, flash floods and inundation due to anthropogenic or natural activities, a proper
communication and alarm system is the first requirement. The alarm system can be activated
during each disaster as per the protocol and for natural calamities like heavy rain or flood in
the adjoining river, if any, only if the Safety Officer is communicated the same from upstream
sources on time. There is a time lag between the occurrence of the situation at source and it’s
reaching the site, which are some distance away. If the source is due to anthropogenic
reasons, the information must be communicated to downstream areas so that they can take
preventive measures on time. In case the source is due to natural disasters, then also its effect
will take some time to reach the project site and there is sufficient time to take preventive
actions. To develop and operate such a communication system during natural calamities is the
responsibility of the state government. The responsibility of the project is to develop links
with nearby villagers to warn them before blasting and the state government, specially the
irrigation department during flash floods, so that they can receive such communications on
time and translate into actions. The project shall develop its own communication and alarm
system which will work as follows:
Whereas for blasting, the alarm will be initiated as per protocol and during flash floods, on
receiving the message of `Disaster’ from upstream sources, the Safety Executive, will instruct
Commanding Officer Security services to sound SIREN WAILING TYPE FOR 5
MINUTES. On receiving the message of “Emergency Over” from Safety Executive All Clear
Signal by Sounding Siren straight for two minutes will be given. The features of the alarm
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-26
system will be explained to one and all to avoid panic or misunderstanding during disaster.
7.6.1 Project layout:
Provision of adequate access ways for the movement of equipment and personnel are
kept.
Minimum two numbers of escape routes for escape during disaster shall be identified
and informed.
Siting of fuel oil storage for mining machineries, if any, shall be in protected fenced
area inside tank bund located on the shore and not in river bed.
7.6.2 Fire Fighting
The proposed project will be provided with fire protection systems as given in Table 7.2.
Table 7.2: List of Fire Extinguishers Required at Different Locations
Name of site Type
Fuel Tank Area CO 2 Foam type
Dry Chemical type
Sand Baskets
In project office Dry Chemical powder type
However, prior to installation of fire station & safety equipment, an experienced and
qualified Fire Officer as per Factories Act will be engaged to carry out in-depth study and
advise on the selection of equipment.
7.6.3 Safety
The proposed project will have a Safety Executive who will be an experienced and qualified
staff whose main job will be to bring about safety consciousness amongst the work force in
the project. The Safety Executive will conduct regular safety awareness courses/drills by
organizing training of the personnel among the various working levels.
Safety awareness will also be created by the various posters highlighting the safe working
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-27
practices in working area, public places and roads etc. Report will be given to Management
for corrective measures to improve the safety conditions.
7.6.4 Training
Management will arrange training on safety accident prevention, first aid, hazard control,
housekeeping and environmental management. Special emphasis with mock drills in disaster
control will also be planned.
7.6.5 Communication
In the proposed project, there will be up-to-date communication facilities with
telecommunication and mobile phones, walkie-talkies, loud speakers to warn workers in case
of an accident.
Contingency Plan and formation of Disaster Control Team
The contingency plan has been prepared from the experiences of accidents that have occurred
in various other mining projects. The contingency plan being a dynamic plan will need
periodical reviews and modifications with new experiences. Even with all precautionary
measures taken to avoid disaster, disaster may occur. To tackle situations during and after
disaster, a well-defined contingency plan and persons responsible to execute it is a must. The
management will form a Disaster Control Team which will be headed by a Safety Executive,
who is a senior full time employee of the company well qualified in Risk Management and
Safety. The Safety Executive will be made responsible to handle disaster. On getting
information about any accident, the officer will perform the following tasks:
verify from the affected project site
Inform the Management or other nominated coordinators immediately.
To be responsible for planning and provisions of assistance from local authorities.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-28
To keep higher authorities informed about the situation.
The decision of the Safety Executive on any matter to meet the objective of disaster
control plan will be final.
To identify persons from within the organization or outside local persons and form a
Disaster Control Team.
To convey message to his Disaster Control Team after consulting Management.
Disaster Control Team will report to the Safety Executive and will consists of
members from Casualty services, Rescue services, Fire fighting services, Traffic
control, Training services, Depot and Transport services, Supply Services, Salvage
service, Welfare services, Security services and Public Relation Service.
All the services will be headed by respective Commanding Officers.
To consult between themselves on matters related to more than one service and to
decide on the action to be taken.
In effect, it is to optimize operational efficiency to rescue rehabilitation and render
medical help and to restore normalcy.
Emergency Organization
It is recommended to setup an Emergency Organization. A senior executive (Mine
Manager) who has control over the affairs of the mine will be heading the Emergency
Organization. He will be designated as Site Controller. As per the General Organization
chart, in the mines, the Mines Manager will be designated as the Incident Controller.
The Incident Controller will be reporting to the Site Controller.
Each Incident Controller, for himself, organizes a team responsible for controlling the
incidence with the personnel under his control. Shift In-charge will be the reporting
officer, who will bring the incidence to the notice of the Incidence Controller and Site
Controller.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-29
Emergency Co-coordinators’ will be appointed who will undertake the responsibilities
like fire fighting, rescue, rehabilitation, transport and provide essential and support
services. For this purposes, Security In-charge, Personnel Department, Essential services
personnel will be engaged. All these personnel will be designated as key personnel.
In each shift, electrical supervisor, electrical fitters, pump house in-charge and other
maintenance staff will be drafted for emergency operations. In the event of power or
communication system failure, some of staff members in the mine offices will be drafted
and their services will be utilized as messengers for quick passing of communications.
All these personnel will be declared as essential personnel.
Emergency Communication
Whoever notices an emergency situation such as fire, growth of fire etc will inform his
immediate superior and Emergency Control Center. The person on duty in the
Emergency Control Center will appraise the Site Controller. Site Controller verifies the
situation from the Incident Controller of that area or the Shift In-charge and takes a
decision about an impending On Site Emergency. This will be communicated to all the
Incident Controllers, Emergency Co-ordinators. Simultaneously, the emergency warning
system will be activated on the instructions of the Site Controller.
7.6.6 Emergency Facilities
Emergency Control Center (ECC)
For the time being, Mine Office Block is identified as Emergency Control Center. It will
have external Telephone, Fax, Telex facility. All the Site Controller/ Incident Controller
Officers, Senior Personnel will be located here. Also, it will be an elevated place.
The following information and equipment are to be provided at the Emergency Control
Center (ECC):
Intercom, telephone;
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-30
P and T telephone;
Safe contained breathing apparatus;
Fire suit/gas tight goggles/gloves/helmets;
Hand tools, wind direction/velocities indications;
Public address megaphone, hand bell, telephone directories;
Internal P and T, factory layout, site plan;
Emergency lamp/torch light/batteries;
Plan indicating locations of hazard inventories, sources of safety equipment, work
road plan, assembly points, rescue location vulnerable zones, escape routes;
Hazard chart;
Emergency shut-down procedures;
Nominal roll of employees;
List of key personnel, list of essential employees, list of Emergency Co-ordinators;
Duties of key personnel;
Address with telephone numbers and key personnel, emergency coordinator, essential
employees; and
Important address and telephone numbers including Government agencies,
neighboring industries and sources of help, outside experts, population details around
the Mine.
7.6.7 Assembly Point
Number of assembly depending upon the mine location will be identified wherein
employees who are not directly connected with the disaster management will be
assembled for safety and rescue. Emergency breathing apparatus, minimum facilities
like water etc. will be organized.
In view of the size of mine, different locations will be ear marked as assembly points.
Depending upon the location of hazard, the assembly points are to be used.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-31
7.6.8 Emergency Power Supply
Mine facilities are connected to power supply from the State Electricity Board. In the
event of any grid supply failure, Diesel Generator will be provided at the mine, which is
operated as soon as any power failure occurs. Thus water pumps, mine lighting and
emergency control center, administrative building and other auxiliary services are
connected to emergency power supply. In all the blocks flame proof type emergency
lamps will be provided.
7.7 The responsibility of the members of the Disaster Control Team
7.7.1 Casualty services
Casualty Services will be manned by a local Medical Officer or an appointed Medical Officer
nominated as a member of Disaster Control Team. His functions will include:
First aid service by first aid parties on the spot.
Ambulance service for transport of casualties from the spot to nearest hospital.
The Member Casualty Services will look after the following things:
7.7.1.1 Procedure for treatment
On getting a signal from the Safety Executive or information on telephone or hearing siren,
the Member of the Casualty service and first aid personnel will report to Safety Executive.
The Ambulance with the driver will report to site. First aid parties will render first aid to
casualties at the place of occurrence and those requiring further treatment would be
transported to the nearest hospital by ambulance. In case of extra help being required from
outside Safety Executive will initiate for help in:
Evacuating the casualties
Essential assistance in first aid.
Extra medical helps from neighboring hospital or main hospital.
7.7.1.2 First Aid
It is necessary to give first aid to the persons injured in disaster. First aid post will be set up.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-32
At the post 1 first aid personnel shall be kept in rotating shifts of 8 hours.
7.7.1.3 Fire fighting services
The functions of the fire fighting group will be:
To enforce all regulations for prevention of fire.
To co-ordinate fire fighting activities
To request neighboring industries and District Authority for rendering services of their
fire fighting crew under mutual aid schemes, if necessary.
7.7.2 Traffic control services
The free movement of the fire vehicles and ambulance at the scene of fire/emergency is very
important and therefore the security personnel on duty must ensure that all the roads at the
scene of fire/emergency are kept clear and fire/emergency must not park their vehicles within
100 meters of fire, at road junction and at access roads. The ignition key should be left in the
vehicles.
7.7.3 Training services
The responsibilities of the training department in the context of disaster management shall be
as given below.
The faculty will consist of Safety Executive and all members of the Disaster Control
Team
To arrange training of volunteers/employees nominated by Safety Executive.
To arrange refresher training courses once in a year.
To arrange mock drills, twice in a year.
To make a list of employees trained in various specialized disasters so that they can be
easily contacted to handle a particular type of disaster. The person concerned will
immediately report to Safety Executive.
7.7.4 Welfare services
Management of proposed project will nominate one person from administration side as the
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-33
Commanding Officer of welfare services.
Emergency camps will be set up only in exceptional cases on available area. For this purpose
necessary materials will be brought from nearby market. The function of the welfare officer
will include:
To provide shelters to affected persons.
To arrange enough stock of essential commodities
To arrange clothing and medicines to affected persons.
To arrange drinking water, if supply is disrupted, with the help of District
Authorities.
7.7.5 Security services
Chief Security Officer will be Commanding Officer, Security Services. Security services will
be primarily responsible for the security of the project. His functions will include:
To control the vehicular traffic inside the project.
To help local police in patrolling the area of project and outside the battery area, if
necessary.
To assist various services in removing people from inundated areas, areas which have
faced disaster and fighting fires.
To assist in transporting injured persons.
One jeep and one motor cycle will always be kept as reserve to cope with emergency
demand and immediate mobility of security personnel.
7.7.6 Public Relation Services
A senior officer from the organization will look after Public Relation Services as PRO. His
responsibilities are:
To consult Management before communication, if required with outside agencies.
PRO will be the official spokesman for the proposed project with outside agencies.
PRO will arrange for photography and filming of the whole disaster as photography
and filming of such incidents are of immense value for the purpose of investigation,
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-34
training and education.
7.7.7 Food poisoning
In case of food poisoning the following actions will be taken:
SAFETY EXECUTIVE will contact District Authorities and seek their help, if
necessary.
Security Personnel and employees will help in transporting the affected people to
various hospitals.
7.8 Disaster due to Natural Calamity and External Factors
Most of the measures and processes shall be same as given under in-house disaster except that
the Safety Executive will contact the State/ District authorities for necessary instructions to
co-ordinate with them.
7.8.1 Cloud burst/lightning
Cloud burst/lightning may lead to a situation which can lead to minor to major emergency in
mining projects due to flash flood and submergence. In such emergency, actions indicated
under Disaster due to Natural Calamity and External Factors will be initiated
7.8.2 Fire and Explosion
Chances of fire and explosion from the project exist due to storage of fuel and in case of
uncontrolled blasting. Following contingency plans have been made:
Safety Executive along with Commanding Officers takes overall charge of the
situation
Safety Executive will assess the situation for possible after effects of the fire in the
project and the surrounding areas likely to get affected
Safety Executive will inform local authorities to send fire tenders, if necessary
Safety Executive will inform the people of likely affected areas through
communication system to leave the area and move to other areas earmarked, if
necessary
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-35
Safety Executive will inform coordinator, external services to inform the District
authorities of the disaster and request them for help.
To evacuate people from the affected areas outside the project.
To control the traffic and maintain law and order.
To arrange medical aid for the affected people.
Safety Executive will arrange inspection of affected areas to get firsthand knowledge
of damages occurred.
7.9 Conclusion:
In view of the imperative need to meet the gigantic challenge posed by natural hazards, the
successes achieved, the experience garnered and the onerous task ahead to secure safety and
Disaster-free functioning of the industry, whether small or big, in the larger interests of the
society and the people envisages an entire gamut of issues connected with mainstreaming
disaster management concerns in the developmental efforts at all levels and across a spectrum
of sectors. The main themes to be addressed are
Ensuring that existing and upcoming industrial assets and infrastructure are disaster-
resistant.
Ensuring proper siting of industrial establishments considering hazard parameters.
Making industrial processes and procedures inherently safe.
Development of on-site and off-site DM plans by mining industries in association
with the District Administration.
Conducting mock-drills at regular intervals to determine the efficacy of the DM plans.
Preparation of inventory of corporate resources and uploading them on the IDRN –
India Disaster Resource Network.
Large-scale association with awareness generation initiatives aimed at building the
knowledge, attitude and skills of the common people for a safer habitat.
To move away from relief-centric approach to a pro-active assault on vulnerabilities
through risk management measures and capacity building of industrial personnel.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-36
Mainstreaming private sector participation in disaster management.
Establishing linkages between private sector and the community.
Networking knowledge on best practices and tools for effective disaster management.
Development and implementation of appropriate risk transfer mechanisms.
For any type of above disaster, a rescue team will be formed by training the mining
staff with specialized training. The proposed project involves Bauxite mining, the
anticipated risks are mentioned below:
SI.
No
Hazard
Identification
Risk Recommendations for
Mitigations
1 Drilling Risk of Accidental Injury, Vibration,
Noise. Dust Risk of Flying rock projectile
injury to eyes
Use of PPE/PPA.
2 Blasting Risk Flying rock projectile
Blasting Dust &noise. Projectile Impact
Work as per SOP with
due safety precautions
3 Overburden
handling
Risk of Landslides, loss of life and
property,
Siltation of surface water run off
Implementations of
material Handling SOP
4 Heavy
Machinery
Risk of Accidents/injuries
during handling of dumpers, trucks,
proclains, ripper dozers etc.
Use of PPE/PPA &work
permit system
5 High tension
line
Risk of accident during movements of
trucks and mining activity.
Leaving a barrier zone
from electric line and
taking precautionary
measures to prevent
from any accident
FIGURE-7.4
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-37
ON-SITE EMERGENCY PLAN
Operator
Shift Incharge
Safety Officer
Site ControllerRoom
Emergency Control
Emergency Co-ordinator Emergency Co-ordinator(Medical,Mutual,Aid
Rehabilitation,Transportand Communication)
(Rescue,Fire Fighting)
Electrician, First Aid,Transport-Driver
Telephone-Operator
ElectricianPump Operator
Emergency Co-ordinator(Essential Services)
Pump Operator
Shift Incharge
Incident Controller
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-38
FIGURE-7.5
OFF-SITE EMERGENCY PLAN
7.10 Contact Details:
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-39
The DMP will be circulated to each and every member of the project by the Association withall contact details. However, only the Safety Executive is allowed to call CommandingOfficers. All the Commanding Officers are provided with phone numbers of persons fromwithin the organization and outside, whom they need to contact in case of a disaster. All theemployees are strictly advised not to contact Commanding Officers of various services in caseof Disaster as it will create confusion and may be misused to create panic. These are as givenin Table 7.3.
Table 7.3: Contact Details
Sl.No
Designation Phone number
1 Safety Executive (0286 – 22444288)2 Commanding Officer, Casualty services will be
exhibited at siteoffice
3 Commanding Officer ,Rescue services4 Commanding Officer, Fire fighting services5 Commanding Officer ,Traffic control6 Commanding Officer ,Transport services7 Commanding Officer ,Salvage service8 Commanding Officer ,Supply Services,9 Commanding Officer ,Welfare services10 Commanding Officer ,Security services11 Commanding Officer ,Public Relation
Services
7.11 Socio – Economic Impact Assessment of virpur Gunawali Bauxite Mining Project,Jamnagar, Gujarat:
IntroductionIn this section of the EIA Report an attempt has been made to assess the Socio-Economic
Impact of the proposed Bauxite Mining Project at village Virpur, Taluka Kalyanpur, District
Devbhumi Dwarka, Gujarat.
Socio-Economic Impact Assessment (SEIA) refers to the systematic analysis of various social
and economic characteristics of the human beings living in a given geographical area during
the period of study. The geographical area is called Study Area or Impact Area. SEIA is
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-40
carried out separately but concurrently with Environment Impact Assessment (EIA). The
study area consists of core area where the project is located and a buffer area encircling the
project area with a radius of 10 km from the periphery of the core area. The Socio-
Economic Impact Assessment focuses on the likely effect of the project on social and
economic well-being of the community. The impact may be direct or indirect, positive or
negative.
Objective of the StudyThe Socio-Economic Impact Assessment focuses the effect of the project on social and
economic well-being of the community. The above analysis relies on both quantitative and
qualitative measures of impacts. The impacts are evaluated in terms of changes in
community demographics, housing, employment & income, market effects, public services,
retail business, quality of life and artistic qualities of the community. Qualitative assessment
of community perceptions about development is also an important measure of
development impacts. Assessing proposed developments in socio-economic context will
help the community leaders and local people identify potential social equity issues,
evaluate the adequacy of social services and determine whether the project has adverse
effects on overall social well-being.
Scope of the Study
The scope of the study is as follows:
To collect Baseline Data of the study area.
To comprehend Socio-economic status of the people living in the study area.
To assess probable impact of the project on social and economic aspects in the study
area.
To evaluate the likely impact of the project on Quality of Life of the people living in
the study area.
To ensure sustainability of the positive impact.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-41
To suggest mitigation measures and agency responsible for taking action in case of
adverse impact.
Methodology
For Socio-Economic Impact Assessment of the proposed project, GRC India carries out
systematic analysis of the various socio-economic characteristics, both in terms of quality
and quantity. Accordingly, both qualitative and quantitative data was collected from
secondary sources. The secondary data was collected from the published data/information
of the Census Authority. Records of the state and district administration were also referred
to.
For collection of primary data, a sample survey was conducted in the study area. In each
selected habitation, a specified number of representative households were selected
scientifically for collection of information through face to face interviews with head of the
household or any responsible member of the family.
Census-cum-Sample Survey in the Core Area
As the likely impact of the project will be greatest in the core area and it diminishes
progressively when move away from the core area to the periphery of the study area, a
Census-cum-Sample Survey was conducted in the core area for the collection of socio-
economic data. It is treated as a census survey because all the habitations located in the
core area were surveyed for the collection of information. Further, in each habitation a
household survey was conducted by drawing representative samples from a list of
households prepared. Since, collection of information from all the households in a
habitation is time consuming and expensive, the sample survey approach was adopted for
collection of information from the selected households in the village(s).
Sample Survey in the Buffer Area
In the buffer area, where the impact of the project progressively reduces with the distance
from the project area, two stage sample design was adopted. The first stage units were
census village(s) and the ultimate stage units were households.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-42
Sample Design
Two-Stage Sampling Design was adopted in the study area. The First Stage Units were Census
village(s) and the Ultimate Stage Units were households in the selected village(s).
Method of selection of First Stage Units:
Probability Proportional to Size without Replacement (PPSWOR) was adopted to select the
habitations from the list of Census villages.
Method of selection of Ultimate Stage Unit:
The Circular Systematic Sampling was adopted in each habitation to select the households from
a list of households prepared after complete listing. The household were selected at an interval
(K) calculated by dividing the population (N) by sample size (n).
Sample Size
The sample size at each level (village and household) was decided by using the formula =
√ {(1.96 *σ)/Δ}; where = Sample Size, 1.96 is the Table Value of Confidence Limit, σ =
Standard Deviation and Δ = Degree of Precision.
Survey Instruments
The following Schedules/Questionnaires were developed for collection of Primary Data:
Questionnaire 1: Village Particulars
The village Questionnaire was developed for collection of village particulars like
Demographic details of the village, Infrastructure and other facilities available in the village
from the Sarpanch or other village officials.
Questionnaire 2: Household Particulars
The Household Questionnaire was developed to collect information on various parameters
from the selected households.
Each Schedule/Questionnaire is divided into several blocks and there are both open-ended
and closed-ended questions.
Chronology of various steps to prepare the SEIA Report is as under:
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-43
Study Area
The project site is located at village Virpur, Taluka Kalyanpur, District Devbhoomi Dwarka
Gujarat. In the study area, there are only nine identified habitations. All habitations are
falling under rural category. The habitations are spread over in different taluka namely
Okhamandal, Kalyanpur, Khambhalia and Kalavad of the district Jamnagar.
The land use pattern of the study area is presented in the table below:
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-44
It may be seen from the above table that 55.8 per cent of the total geographical area is
cultivable land whereas 15.0 per cent is forest land, 9.0 per cent is cultivable waste land and
the remaining 20.2 per cent is barren or fallow land. Of the total cultivable land, 23.8 per
cent is irrigated land and the remaining 76.2 per cent is un-irrigated land.
Baseline Data of the Study Area
The baseline data with respect to population and basic amenities in the study area is as
under:
I. Demographic Particulars/Population Details:
Table: Land Use Pattern of the Study AreaS. No. Land Use Pattern % to the Total
1. Forests Land 15.0
2. Cultivable Land 55.8
2(a). Irrigated Land (23.8)
2(b). Un-irrigated Land (76.2)
3. Cultivable Waste Land 9.0
4. Barren/Fallow Land/Area not available for Cultivation 20.2
Total 100.0
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-45
Table: Demographic Particulars/Population Details of the Study AreaDescription Number Percentage to
Respective TotalGender wise Total Population 21281 100.0Male 10957 51.5Female 10324 48.5
Sex Ratio 942Gender wise Total Population(0-6 age group)
3013 100.0
Male 1554 51.6Female 1459 48.4
Sex Ratio 939Number of Households 3891
Average Household Size 5Highest Avg. Household Size 6Lowest Avg. Household Size 5Total Population of Scheduled CasteCommunity
1345 100.0
Male 721 53.6Female 624 46.4
Sex Ratio 865Total Population of Scheduled TribeCommunity
11 100.0
Male 5 45.5Female 6 54.5
Sex Ratio 1200Total Population of GeneralCommunity (including OBC)
19925 100.0
Male 10231 51.3Female 9694 48.7
Sex Ratio 948Total Literates 11646 100.0Male 7040 60.4Female 4606 39.6
Overall Literacy Rate 63.8Male 74.9Female 52.0Gender Gap in Literacy Rate 22.9Total Workers 8695 100.0
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-46
Male 6142 70.6Female 2553 29.4Gender Gap in Work Participation Rate 41.2
9 Total Main Workers 6772 100.0Male 5844 86.3Female 928 13.7
Gender Gap in Work Participation Rate 72.610 Total Marginal Workers 1923 100.0
Male 298 15.5Female 1625 84.5Gender Gap in Work Participation Rate -69.0
11 Total Household Industrial Workers 43 100.0Male 36 83.7Female 7 16.3
12 Total Agricultural Workers 7721 100.0Male 5320 68.9Female 2401 31.1
13 Total Cultivators 5814 100.0Male 4258 73.2Female 1556 26.8
14 Total Agricultural Labour 1907 100.0Male 1062 55.7Female 845 44.3
15 Total ‘Other Workers’ 931 100.0Male 786 84.4Female 145 15.6
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-47
II. Basic Amenities:
Table: Basic Amenities Available in the Study Area1. EDUCATION
EducationalInstitutions
TypePrimary SchoolMiddle SchoolSecondary School
2. HEALTH
Health Facilities
Allopathic HospitalAllopathic DispensaryFamily Welfare CentrePrimary Health CentrePrimary Health Sub-Centre
3. WATER
Drinking Water
Means of Drinking Water AvailableWellsTube wellsHand pumpsTanksTap
4. ELECTRICITY
Electricity SupplyType of Electricity SuppliedPower for Domestic UsesPower Agriculture Uses
5. ROAD
Approach Road
Types of Road(s) AvailablePaved RoadsMud RoadsFoot Roads
Source: Primary Research
Socio-Economic Impact Assessment of the Project
Impact on Demographic Composition:
The impact of the proposed mining project on demographic composition will be marginal as
there will be no major immigration of people from distant areas and mainly local people will
be recruited for employment. The migrants from distant places will be kept bare minimum.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-48
Hence, there will be no significant impact on the population composition in the study area.
After expansion of the existing unit the increase in population will be marginal. Since there
will be no significant change in population, the overall sex ratio will remain more or less
same.
Impact on Employment Opportunities:
The greatest impact of the proposed project is employment opportunities for the local
people. The proposed project will provide employment to the local people up to the
maximum extent. It has estimated that 65 people will get direct employment in this mining
project. Besides the above the project is expected to generate some indirect employment
also. Creation of employment opportunities is a positive impact of the project on socio-
economic aspects of people living in the study area.
Impact on Agriculture:
No negative impact on agricultural production in the study area is anticipated due to mining
activities of the proposed project. The lease area is a plateau and there is no vegetation.
Hence no agriculture is possible in the lease area due to its barrenness, pits and quarries.
Impact on Industrial Activity:
The Industrial activity in the study area is expected to get a boost due to proposed mining
project. It is expected that in the near future few micro and small scale industrial units may
come up in the vicinity offering employment opportunities to many people.
Impact on Road Development:
Movement of trucks and other vehicles to and fro the quarry is expected to increase
substantially. Hence, there is ample scope for road development in and around the mining
areas.
Impact on Consumption Pattern of the Local People:
Increased household income due to employment opportune in the mining operation may
change the consumption pattern of the study area.
Impact on Health:
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-49
To resolve any kind of health hazard and accident in the mining area there are many safety
guards for the workers. For protection from blasting at the mining place, dust and other
materials it may be made compulsory for all workers to wear helmet, masks and gloves
while working in the mining site. There will also be a well-developed medical unit with
trained MBBS doctors and other medical staffs at the mining site.
Impact on Law & Order:
As local people will be employed to run the quarry, no law & order problem is envisaged. It
is expected that the workers will attend to their duties from their residence and return to
their homes after the day’s work is over. However, to meet any untoward incident one
police post may be set up closed to the project area.
Corporate Social Responsibility
As per the section 135 of the Companies Act, 2013 Corporate Social Responsibility (CSR) is
mandatory part of any development project.
As per the guidelines issued on dated 27th Feb, 2014 (Schedule-VII) by the Ministry of
Corporate Affairs, Government of India the suggested ten major CSR activities by giving
importance to the corporate philosophy with the objective to improve the quality of life
and socio-economic scenario with special attention to the people residing in the study area
are given below:
I. Hunger, Poverty and Malnutrition, Promoting Preventive Health Care and Sanitation
and making available Safe Drinking Water.
II. Promoting Education, including Special Education and Employment Enhancing
Vocation Skills Especially among Children, Women, Elderly, and the Differently-Able
and Livelihood Enhancement Projects.
III. Promoting Gender Equality, Empowering Women, setting up Homes and Hostels for
Women and Orphans, setting up Old Age Homes, Day Care Centers and such other
Facilities for Senior Citizens and measures for Reducing Inequalities faced by Socially
and Economically Backward Groups.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-50
IV. Ensuring Environmental Sustainability, Ecological Balance, Protection of Flora and
Fauna, Animal Welfare, Agro-forestry, Conservation of Natural Resources and
Maintaining Quality of Soil, Air and Water.
V. Protection of National Heritage, Art and Culture Including Restoration of Buildings
and sites of Historical Importance and Works of Art, setting up Public Libraries,
Promotion and development of Traditional Arts and Handicrafts.
VI. Measures for the benefit of Armed Forces Veterans, War Widows and their
Dependents
VII. Training to Promote Rural Sports, Nationally Recognized Sports, Paralympics sports
and Olympic sports.
VIII. Contribution to the Prime Minister's National Relief Fund or any other fund set up
by the Central Government for socio-economic development and relief and welfare
of the Scheduled Castes, the Scheduled Tribes, other backward classes, minorities
and women.
IX. Contributions or funds provided to technology incubators located within academic
institutions which are approved by the Central Government.
X. Rural Development Projects.
Based on the above suggested activities by the Government of India, the project proponent
may set out to do the following CSR activities by giving importance to their corporate
philosophy in order to achieve the objective to improve the quality of life and socio-
economic scenario with special attention to the people residing in the study area:
1. In support of Health-
Health Checkups and Medical Camps in the project village and other part of
the study area.
Providing free medicines and medical equipments to the Primary Health
Centers falling under the study area.
2. In support of Education-
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-51
Spreading the light of Education by providing sponsorship or financial
assistance to underprivileged children and meritorious students
Providing uniforms and books to the school children.
A certain part (5%) of budgetary amount i.e., approximately Rs. 2.40 Lakh of the project has
been decided to spend during next three years after commencement of the project in
support of the above mentioned CSR activities.
The estimated budgetary allocation of the amount for these above activities is given in the
table below:
Table: Fund for the various CSR ActivitiesS. No. Activities Allocation of Fund (Rs.
Lakhs)1. In support of Health 1.20
2. In support of Education 1.20Total 2.40
Conclusion
The implementation of the project will increase employment opportunities to the local
people. The mining operation will not only fetch income to the state exchequer but also
ensure healthy development of bauxite mining in the state of Gujarat. The project will
provide impetus to industrialization of the area. It is likely the intending entrepreneurs will
venture to set up micro and small scale units in the near future making the area a mixed
society, associated with industry, trade and business. With the implementation of the
mining project the occupational pattern of the people in the area will change making more
people engaged in industrial and business activities.
In the study area, there is large scope of improving health and educational facilities. It is
expected that same will improve with opening of the project and promoting the CSR &
other associated industrial & business activities by the project proponent. It can be
expected from the project that it may also give some value addition directly or indirectly in
the field of agriculture and agro-based activities in the study area.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-7Additional Studies
VII-52
The overall impact of the project is expected to be positive for the habitants of the area,
the government and the persons associated with the project.
*****
EIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-8PROJECT BENEFITS
VIII-1
CHAPTER 8- PROJECT BENEFITS
8.0 Project benefits VIII/2
8.1 Improvement in the Physical Infrastructure VIII/2
8.2 Improvement in the Social Infrastructure VIII/2
8.3 Employment Potential VIII/2
EIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-8PROJECT BENEFITS
VIII-2
8.0 PROJECT BENEFITS
8.1 Improvement in the Physical Infrastructure
The impact on the civic amenities after the commencement of mining activities islikely to be substantial. The basic requirements of the community needs will bestrengthened by extending health care, educational facilities developed in thetownship for the community, providing drinking water to the villages,building/strengthening of existing roads in the area. The proponent will initiate theabove amenities either by providing or by improving the facilities in the area, whichwill help in uplifting the living standards of local communities.
Medical facilities will be provided in the form of first-aid facility at the mine. Thesemedical facilities will also be available to local people in the surrounding in case ofemergencies.
8.2 Improvement in the Social Infrastructure
Generation of employment and improved standard of living; Increased revenue to the State by way of royalty, taxes and duties; and Superior communication and transport facilities etc.
In addition to above, due to increase in purchasing power of local habitants: There will be significant change in the socio-economic scenario of the area. The proposed project will enhance the prospects of employment. Recruitment
for the unskilled and semiskilled workers for the proposed project will be fromthe nearby villages.
The development of the basic amenities viz. roads, transportation, electricity,drinking water, proper sanitation, educational institutions, medical facilities,entertainment, etc. will be developed as far as possible.
Overall the proposed project will change living standards of the people andimprove the socio-economic conditions of the area.
8.3 Employment Potential
Future production planning does not indicate some change from present, in theemployment. The number of unskilled labour may increase depending on thequantum of overburden removal. The lessee has employed 43 miners for raising ores
EIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-8PROJECT BENEFITS
VIII-3
& 5 unskilled workers for removal of overburden, quarry cleaning & road repairing.The details of employment are given in Chapter-2.
The employment of local people in primary and secondary sectors of project willupgrade the prosperity of the region. These will in-turn improve the socio-economicconditions of the area. The total manpower required for the proposed mining projectunder various categories is 48 persons and persons will be mainly sourced from localcommunity in and around mining project and few technical persons will beemployed during operational phase from local and also from outside area. Inaddition to the above, contractual labour and indirect employment opportunities willalso be getting benefited after installation of mining project.
************
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-1
CHAPTER- 9
ENVIRONMENT MANAGEMENT PLAN
SI.
NO.
CONTENTS Page No.
9.0 ENVIRONMENT MANAGEMENT PLAN IX/2
9.1 AIR QUALITY MANAGEMENT IX/2
9.2 NOISE POLLUTION CONTROL IX/3
9.3 WATER QUALITY MANAGEMENT IX/4
9.4 WASTE MANAGEMENT IX/4
9.5 GREENBELT AND PLANTATION IX/4
9.6 BIOLOGICAL MANAGEMENT MEASURES IX/5
9.7 OCCUPATIONAL HAZARDS AND SAFETY IX/8
9.8 SOCIO ECONOMIC MEASURES IX/10
9.9 POLICY AND ACTION PLAN ON SOCIAL RESPONSIBILITY IX/11
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-2
9.0 ENVIRONMENT MANAGEMENT PLAN
The environmental management plan consists of the set of mitigation, management,
monitoring and institutional measures to be taken during the implementation and operation of
the project, to eliminate adverse environmental impacts or reduce them to acceptable levels.
The present environmental management plan addresses the components of environment,
which are likely to be affected by the different operations in a mine area.
The aims of EMP are:
• Overall conservation of environment.
• Minimization of waste generation and pollution.
• Judicious use of natural resources and water.
• Safety, welfare and good health of the work force and populace.
• Ensure effective operation of all control measures.
• Vigilance against probable disasters and accidents.
• Monitoring of cumulative and long time impacts.
• Ensure effective operation of all control measures.
9.1 Air Quality Management
Emissions due to mineral handling, during mining operations are not much and restricted to
the lease area only. Air pollution is caused mainly due to dust generation added with gaseous
emission from transportation activities along with mining operation like drilling, blasting,
loading, haulage etc.
9.1.1 Control of Fugitive Emissions
• Wet drilling arrangements will be made.
• Use of Personal Protection Equipments (PPE) like dust masks, ear plugs etc. by the
mine workers.
• Rock breaker will be used for breaking over size boulders in order to reduce dust and
noise generation, which otherwise would be generated due to secondary blasting.
• Controlled blasting and optimization of use of explosive energy will help in reducing
the above emissions.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-3
• Regular water sprinkling on haul roads & loading points will be carried out.
• Development of green belt/plantation around the lease boundary, roads, dumps etc.
• Ambient Air Quality Monitoring will be conducted on regularly basis to assess the
quality of ambient air.
9.1.2 Prevention and control of Gaseous Pollution
• In mining activities, the sources of gaseous emissions would be blasting
• Blasting of explosive results in the increase of nitrogen oxides, which get diluted by
the wind. Controlled blasting and optimization of use of explosive energy will help in
reducing the above emissions.
• Proper maintenance of machines improves combustion process & makes reduction in
the pollution. Good maintenance and monitoring of fuel and oil will not allow
significant addition in the gaseous emission.
9.2 Noise Pollution Control
9.2.1 Noise Abattement and Control
• Proper maintenance, oiling and greasing of machines at regular intervals will be done
to reduce the generation of noise.
• Adequate silencers will be provided in all the diesel engines.
• Blast holes will not be overcharged.
• Plantation along the sides of approach roads and mine area will be done to minimize
the propagation of noise.
• Personal Protective Equipments (PPE) like earmuffs/earplugs will be provided to all
operators and employees working near mining machineries or at higher noise zone.
• Periodical noise level monitoring will be done.
9.2.2 Protective measures for ground vibrations / fly rocks caused by blasting
• Innovations like shelter plantation would be carried around the mine for minimizing
adverse impact of blasting along with following measures will be adopted at mine to
reduce ground vibration, fly rocks, dust generation, noise generation, etc.
• Overcharging will be avoided;
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-4
• Supervision of drilling and blasting operations to ensure design blast geometry;
• Blasting operations will be carried out only during day time as per mine safety
guidelines;
• Proper warning signals will be used;
• By optimization of drilling – blasting parameters i.e. burden, spacing, depth of hole,
etc.
• By using Control Blasting
• By avoiding secondary blasting with the help of rock breaker.
9.3 Water Quality Management
Adequate control measures will be adopted to check not only the wash-off from soil erosion
but also uncontrolled flow of mine water.
9.4 Waste Management
9.4.1 Nature of waste: They shall be used for backfilling. The quantum of waste to be
removed is given below:
Year Top Soil(cum) Mineral waste (cum)Reuse/Spreading
Storage Backfilling Storage Blending Beneficiation
(2015 – 16 )August 15 to
March 16)
Nil Nil Nil 2100 Nil Nil
2016 – 17 5380 Nil Nil 3026 Nil Nil2017 -18 5400 Nil Nil 3038 Nil Nil2018 - 19 5369 Nil Nil 3020 Nil Nil
Total 16149 Nil Nil 11184 Nil Nil
There is soil will be utilized for preparation of protective bund during 5 years and then
or leveling and topping of backfilled area so that plantation can be done on it.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-5
9.5 Greenbelt and Plantation:
So far as Afforestation is concerned, saplings will be planted in pits of 50 cm to 40 cm dia
and about 0.5m deep would be dug. Depending upon the type of soil and type of plant
species, listed in this chapter in Table 9.2, the interval between the pits would be kept. The
hole will be filled with mixture of soil and manure fertilizer. Local species will be planted in
the area as per availability. A table showing year wise Afforestation scheduled
It was proposed to plant 150 sampling every year during plan period. The lessee has taken up
Afforestation work.
Table 9.1 Afforestation scheduled
All plants could not survive due to scarcity of water and low fertile land.
The following characteristics should be taken into consideration while selecting plant species
for green belt development and tree plantation.
• They should be fast growing and tall trees.
• They should be perennial and evergreen.
• They should have thick canopy cover.
Strip No.Year
Number of saplings
to be plantedArea in ML
I 2015 -2016
(August 15 to March 16)150 750
II 2016 – 2017 150 750
III 2017 – 2018 150 750
IV 2018 - 2019 150 750
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-6
• Plantation should be done in appropriate alternate rows around the proposed site to
prevent lateral pollution dispersion.
• The trees should maintain regional ecological balance and conform to soil and
hydrological conditions. Indigenous species should be preferred.
9.6 Biological Management Measures
There is a requirement to establish a stable ecosystem with both ecological and economic
returns. Minimization of soil erosion and dust pollution enhances the beauty of the core and
the buffer zone. To achieve this, it is planned to increase plantation activities. The basic
objectives of plantation are as follows:-
Improvement of Soil quality
Quick vegetative cover to check soil erosion
Improvement in mining site stability
Conservation of biological diversity
As dust receptor which likely to produce during mining
9.6.1 Greenbelt Development Plan
Green belt is plantation of trees for reducing the pollution as they absorb both gaseous and
particulate pollutant, thus removing them from atmosphere. Green plants form a surface
capable of absorbing air pollutants and forming sinks for pollutants. It improves the aesthetic
value of local environment. Under present project, green belts and shelter plantation have
been planned with emphasis on creating biodiversity; enhance natural surroundings and
mitigating pollution. The greenbelt development plan aims to overall improvement in the
environmental conditions of the region. The plan with a five-fold objective addresses issues
such as providing sink for air pollutants likely to emitted from the project; enhancing the
forest cover for increasing the biodiversity of the region; providing aesthetic value to the
project area enhancing the ecological equilibrium of the area; and to a large proportion in
combating soil erosion.
Afforestation on degraded forest area, forest protection / conservation will be
carried out every year by the mine owner.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-7
This activity will promote the emergence of the primary succession species,
hence it will be a silvicultural operation, extremely important for maintaining
ecology and environmental health of the area.
This helps in regeneration & establishment of pioneer plant species saving
expose land & land cutting.
Afforestation will be done along the boundary barrier and quarry roads. Considering a grid of
2.5m x 2.0m about 0.5 hectares area, Numbers of plants of different species will be planted.
The plants recommended for afforestation are as per Guidelines for Developing Greenbelts,
CPCB, March 2000 and listed in Table 9.2
Table 9.2 species recommended for greenbelt development
SI.
No.
Name Botanical Name Status
1 Gulmohar Delonixregia Tree
2 Neem Azadirachtaindica Tree
3 Bargad Ficusbenghalensis Tree
4 Gulmohar Delonixregia Tree
5 Emli Tamarindusindica Tree
6 Babul Acacia arabica Tree
7 Khair Acacia catechu Tree
8 Achar Buchananialatifolia Tree
9 Bakain Meliaazedarach(L.) Tree
10 Aam Magiferaindica Tree
11 Jamun Syzygiumcumini Tree
12 Subabul Leucaenaleucocephala Tree
13 Semal Bombaxceiba(L.) Tree
14 Bakain Meliaazedarach(L.) Tree
15 Nagphani OpuntiaelatiorMill. Tree
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-8
16 Jamun Syzigiumcumini(L.) Tree
17 Kath Jamun Eugenia heyneana. Wall Shrub
Table 9.3 key suggestive measures under EMP
Impact Predicted Suggestive measure
Disturbance of free
movement/living of wild
fauna
Awareness camps will be conducted for labours to make
them aware about sensitivity and importance of forest
No tract or new road for movement of labours or
vehicles be laid in forest area, this will prevent forest
fragmentation, encroachment and human – animal
encounter
Care will be taken that noise produced during vehicles
movement for carrying ore materials are within the
permissible noise level. Higher noise level in the forest
area will lead to restless and failure in detection of calls
of mates and young ones
Care will be taken that no hunting of animals carried out
by labours
If wild animals are noticed crossing the core zone, it will
not be disturbed at all
Labours will not be allowed to discards food, plastic
etc., which can attract animals near the core site
Only low polluting vehicle will be allowed for carrying
ore materials. All vehicles allowed in the project site
area will have to provide pollution under control
certificate at the end of three months
No honk will be allowed in the forest area, noise level
will be within permissible limit (silent zone-50dB
during day time) as per noise pollution (regulation and
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-9
control), rules, 2000, CPCB norms
Harvesting of flora No tree cutting, chopping, lumbering, uprooting of
shrubs and herbs should be allowed
No pilling of ore material should in any green area.
Collections of economically important plants will be
fully restricted.
9.7 Occupational Hazards and Safety
Occupational safety and health is very closely related to productivity and good employer-
employee relationship. The factors of occupational health in proposed Mining project are
mainly dust and land degradation. Safety of employees during operation and maintenance etc.
shall be as per Mines Rules and Regulations.
To avoid any adverse effect on the health of workers due to various pollutants, sufficient
measures relating to safety and health will also be practiced:
• Provision of rest shelters for mine workers with amenities like drinking water etc.
• All safety measures like use of safety appliances, such as dust masks, helmets, shoes,
safety awareness programs, awards, posters, slogans related to safety etc.
• Training of employees for use of safety appliances and first aid in vocational training
center.
• Regular maintenance and testing of all equipment as per manufacturers’ guidelines.
• Periodical Medical Examination (PME) of all workers by a medical Officer
• First Aid facility is provided at the mine site.
• Close surveillance of the factors in working environment and work practices which
may affect environment and worker’s health.
• Working of mine as per approved mining plan and environmental plans.
9.7.1 Organizational Setup
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-10
In order to develop and implement the environmental monitoring and management plan,
proposed mine is having an Environmental Cell, headed by the environmental officer
reporting to head of the project. Their activities will be as follows:
Regular environmental monitoring as stipulated by the regulatory authorities
Preparation and submission of environmental report to the regulatory authorities
Compliance management with all environmental legislation
Implementation of various environmental management programs and reporting the
performance to the top management.
Co-coordinating the environmental related activities within the project as well as with
outside agencies.
Green belt development, etc.
9.7.2 Budget
It is necessary to include the environmental cost as a part of the budgetary cost component.
The project authorities propose to undertake the following environmental works to achieve
the environmental quality as desired. Also the project cost of the project is Rs 23.98 lakhs its
breakup is given in Table 9.4 and for environment protection its breakup is given in Table
9.4.
Table 9.4 Project Cost Bifurcation
S.No. Description Cost in lakhs
1 Land Cost Expenditure NIL
2 Cost of Infrastructure site facilities + Vehicles Rs. 20.98 Lakhs
3 Environmental Protection and implementation cost Rs. 1.75 Lakhs
4 Green belt development Cost Rs.1 .25 Lakhs
Total Rs 23.98 Lakhs
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-11
Table 9.5: Budget for Environmental Protection
SI. No. Measures Capital cost(in Rs.)
Annual recurring cost(in Rs.)
Proposed Proposed1 Pollution Control
i) Dust Suppressionii) Garland drain & grounddump
25,00025,000 50,000
2 Pollution Monitoringi) Air pollutionii) Water pollution
25,00025,000
30,00030,000
3 Reclamation &RehabilitationGreen Belt
25,000 30,000
4 Others (Environmentalstudy, Statutory compliance,etc.)
50,000 30,000
Total 1,75,000 1,80,000
9.8 Socio Economic Measures
The lessee will provide financial assistance for the development of social infrastructure of the
area.
Following measure will be taken to improve the Social infrastructure of the study area:
• Preventive medical care and educational facilities for rural population shall be
promoted.
• Priority will be given to local people for employment. Indirect employment through
contractual services shall be provided.
• Extending general benefit by way of development work in the villages through
respective Gram Panchayat.
• Supplementing Govt. efforts in health monitoring camps, social welfare and various
awareness programmes among the rural population.
• Assisting social forestry programme.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-12
9.9 Policy and Action Plan on Social Responsibility
A detailed Community Social Responsibility plan has been prepared and the details of
the report are given below.
CORPORATE SOCIAL RESPONSIBILITY :
As per the section 135 of the Companies Act, 2013 Corporate Social Responsibility (CSR) is
mandatory part of any development project.
As per the guidelines issued on dated 27th Feb, 2014 (Schedule-VII) by the Ministry of
Corporate Affairs, Government of India the suggested ten major CSR activities by giving
importance to the corporate philosophy with the objective to improve the quality of life and
socio-economic scenario with special attention to the people residing in the study area are
given below:
I. Hunger, Poverty and Malnutrition, Promoting Preventive Health Care and Sanitation
and making available Safe Drinking Water
II. Promoting Education, including Special Education and Employment Enhancing
Vocation Skills Especially among Children, Women, Elderly, and the Differently-
Able and Livelihood Enhancement Projects
III. Promoting Gender Equality, Empowering Women, setting up Homes and Hostels for
Women and Orphans, setting up Old Age Homes, Day Care Centers and such other
Facilities for Senior Citizens and measures for Reducing Inequalities faced by
Socially and Economically Backward Groups
IV. Ensuring Environmental Sustainability, Ecological Balance, Protection of Flora and
Fauna, Animal Welfare, Agro-forestry, Conservation of Natural Resources and
Maintaining Quality of Soil, Air and Water
V. Protection of National Heritage, Art and Culture Including Restoration of Buildings
and sites of Historical Importance and Works of Art, setting up Public Libraries,
Promotion and development of Traditional Arts and Handicrafts
VI. Measures for the benefit of Armed Forces Veterans, War Widows and their
Dependents
VII. Training to Promote Rural Sports, Nationally Recognized Sports, Paralympics sports
and Olympic sports
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-13
VIII. Contribution to the Prime Minister's National Relief Fund or any other fund set up by
the Central Government for socio-economic development and relief and welfare of
the Scheduled Castes, the Scheduled Tribes, other backward classes, minorities and
women
IX. Contributions or funds provided to technology incubators located within academic
institutions which are approved by the Central Government
X. Rural Development Projects.
Based on the above suggested activities by the Government of India, the project proponent
may set out to do the following CSR activities by giving importance to their corporate
philosophy in order to achieve the objective to improve the quality of life and socio-economic
scenario with special attention to the people residing in the study area:
1. In support of Health-
Health Checkups and Medical Camps in the project village and other part of
the study area
Providing free medicines and medical equipments to the Primary Health
Centers falling under the study area
2. In support of Education-
Spreading the light of Education by providing sponsorship or financial
assistance to underprivileged children and meritorious students
Providing uniforms and books to the school children.
The estimated budgetary allocation of the amount for these above activities is given in the
Table 9.5.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-9ENVIRONMENT MANAGEMENT PLAN
IX-14
Table: 9.5 Fund for the various CSR ActivitiesS. No. Activities Allocation of Fund (Rs.
Lakhs)1. In support of Health 1.20
2. In support of Education 1.20Total 2.40
9.9.2 Conclusion
As discussed, it is safe to say that the project is not likely to cause any significant
adverse impact on the ecology of the area, as adequate preventive measures will be
adopted to contain the various pollutants within permissible limits. Green belt
development around the area will also be taken up as an effective pollution mitigative
technique, as well as to control the pollutants released from the premises of the
Bauxite Mine.
************
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-1
CHAPTER-10 SUMMARY & CONCLUSION
10.0 INTRODUCTION X/2
10.1 ENVIRONMENTAL CLEARANCE X/2
10.2 PROJECT DESCRIPTION X/3
10.3 BASELINE ENVIRONMENTAL STATUS X/6
10.4 Cost Estimates X/8
10.5 ADDITIONAL STUDIES X/9
10.6 PUBLIC CONSULTATION X/10
10.7 PROJECT BENEFITS X/10
10.8 CONCLUSIONS X/10
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-2
10.0 SUMMARY & CONCLUSION
10.1 INTRODUCTION
The mining Lease was granted over an area of 55.2520 ha in village virpur, Taluka Kalyanpur
and Dist : Devbhumi Dwarka, in favor of Smt, Pushpaben P. Makhecha, on dated 01-02-1992
and executed on 27.06.1994 for a period 20 years.(Enclosed as Annexure – I). Lessee has
applied for renewal on 16.06.2012 (Enclosed as Annexure – II a) and lease is valid as per
new MMDR 2015 By Government of India. The lessee Smt, Pushpa Ben P. Makhecha expired
on 5.04.2012. The legal heirs the Late Pushpaben Prabhudas Makhecha are Shri Bharatbhai
Makhecha and Shri Naresh bhai Makhecha (The letter is attached as Annexure – II b). The
lease period has been increased as per norms. Modified mine plan has been approved by
IBM vide letter 682(23) (M.P. - 522/2009-II MCCM (N) Udaipur dated 03.09.2015 (Enclosed
as Annexure -X) As per Modified mining plan production capacity is revised as 1, 51,875 TPA
with mining working area 37.1670 ha as block falling in the ECO Sensitive Zone as per the
notification issued by MOEF & CC dated 22.08.2013 has been enclosed. The estimated
project cost is Rs. 23.98 Lakh. The project proponent has informed that the baseline
monitoring has been conducted for summer season March to May – 2015 based on ToR
conditions and the same is informed to the ministry vide letter no. PPM/MoEF &CC/15-
16/300 dated 22.04.2015. Ministry has accorded ToR to the project vide letter no. J-
11015/120/2013-IA-II (M) dated 04.02.2015 (Enclosed as Annexure – IV a). The PP has
request to amend the ToR with respect to proposed production capacity 8, 18,418 TPA
(ROM) to 1, 51,875 TPA (ROM) of Bauxite, area 55.2520 ha with mining working area
37.1670 as per Modified Mine Plan (Letter is attached as Annexure – IV b). The expected life
of mine is 5 years (as per as present level of exploration). The amended ToR was received
vide letter No. J-11015/120/2013-IA.II (M) dated 4th December, 2015.
The Environmental Impact Assessment (EIA) study report is prepared for obtaining
Environmental Clearance (EC) from the Ministry of Environment and Forests (MOEF),
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-3
Governmental of India, New Delhi for proposed Virpur (Gunawali) Bauxite mine Marine
National park & Marine Sanctuary is present within 5 km of the study area as per ESZ
Notification issued on dated 22nd August, 2013. It is classified as “Category – A” as per the
EIA notification dtd 14th September 2006.
10.1.1 IDENTIFICATION OF PROJECT & PROJECT PROPONENT
Identification of Project
The Mining Lease was granted over an area of 55.2520 ha in Village: Virpur, Tehsil:Kalyanpur, and Dist: Devbhumi Dwarka.
Project Proponent
Address of the applicantName of the Mine : Virpur (Gunawali) Bauxite MineLessee : Smt. pushpaben Prbhudas MakhechaAddress : Opp Circuit Villa, Chopati Road, Porbandar (Gujarat)District : PorbandarState : GujaratPhone : 0286 – 22444288
10.1.2 BRIEF DESCRIPTION OF PROJECT
Nature of the Project
The proposed Virpur (Gunawali) Bauxite mine lease extends over an area of 55.2520ha (mine working area 37.167 ha), as the proposed mine lease area is within 5 kmfrom Marine National Park/Marine Sanctuary, it is classified as “CATEGORY-A”, as perthe EIA notification dtd 14th September 2006 & its amendment.
Size of the Project
The Mining Lease was granted over an area of 55.2520 ha in Village: Virpur, Taluka:Kalyanpur, and Dist: Devbhumi Dwarka.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-4
10.1.3 Anticipated Life of Project and Cost of the Project
The projected life of the mine is 5 years. The cost of mining land and miningmachinery for the present mining lease area is about Rs. 23.98 Lakh and the breakupof the EMP cost are given in Table 1.4.
10.1.4 Location of the Project
The proposed Virpur (Gunawali) Bauxite mine lease comes under Village: Virpur,Taluka: Kalyanpur, and Dist: Devbhumi Dwarka. Geo-graphically the ML area extendsfrom East Longitude 69°17'43.6" to 69°18'25.5” E and North Latitude 22°15'38.7" to22°16'17" N.
10.2 PROJECT DESCRIPTION
10.2.1 Size/Magnitude of Operation
The salient features of mine lease are given below:
Sr. No. Particulars in 10 km Details
1. State Highway SH- 25 about 10 km away in South directionfrom the site. A mettaled road passing nearto the sight, leads to Ran.
2. LatitudeLongitude
22°15'38.7" to 22°16'17" N.69°17'43.6" to 69°18'25.5” E
3. National Highway NH 8E about 29 km away in South Westdirection from the site.
4. State, National Boundaries Nil in 10 km
5. Railway station Bhopalka railway station about 17 km in SSE
direction from the site.
Bhatiya railway Station about 20 kms in SSWdirection from the site.
6. Airport Porbandar Airport about 75 km away in SSEdirection from the site.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-5
Sr. No. Particulars in 10 km Details
7. Ecological Sensitive Areas(Wildlife Sanctuaries)
Marine National Park is about 4.12 Km. in
NW direction from the project site, Marine
Sanctuary is about 1 km in NW direction
from the mine working boundary.
Gaga Bird Sanctuary is about 16.55 km inSW direction from project site.
8. Reserved / ProtectedForest
Nil
9. Nearest Town Bhatia (about 20 km SSE)
10. Toposheet Restricted (41F 7)
11. Seismic Zone Seismic Zone IV as per IS-1893(part-I)-2002
10.2.2 Mineral Reserves
The mineable reserve estimated on the basis of measured and indicated category isas tabulated in Table-10.1.
Table-10.1Mineable reserve details
Classification Code Reservesestimation(Quantity intones)
Grade
TOTAL MINERALRESERVES
Bauxite
A. Mineral1. Proved MineralReserves.
111 629323 MT Low Grade
2. Probable MineralReserves.
122 --
Total 629323 MTB. Remaining Resources
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-6
3. Feasibility MineralResources
211
4. Pre – feasibility mineralresources
221 3051503 MT Low Grade
5.Measured MineralResources
331 -
6. Indicated MineralResources
332 -
7. Inferred MineralResources
33 -
8. ReconnaissanceResources.
334 -
Total 3051503 MT
10.2.3 Mine Development and Production
The mine is already fully developed and the rate of Bauxite production will bearound 1, 51,875 tonne per annum from fifth year onwards.The Bauxite production target for the next four years is as given in Table-10.2.
Table-10.2Bauxite production
Year TotaltentativeExcavation(Cum)
TOPSoil(Cum)
OB/SB/IB(Cum)
ROM(cum) MineralRejectin M3
ROM/WasteRatio
Ore(Cum) Mineralreject(Cum)
(15-16) 41994 Nil Nil 41994 2100 2100 1:0.8(16-17) 65905 5380 Nil 60525 3026 3026 1:0.8(17-18) 67150 5400 Nil 60750 3038 3038 1:0.8(18-19) 65768 5369 Nil 60399 3020 3020 1:0.8Total 240817 16149 Nil 223668 11184 11184 1:0.8
10.3 BASELINE ENVIRONMENTAL STATUS
10.3.1 Soil Quality
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-7
Eight soil samples were collected in and around the mine lease area to assess thepresent soil quality of the region. The pH of the soil indicates that the soil is slightlyto moderately alkaline in nature. The nitrogen, phosphorous, potassiumconcentrations were observed to be in the range of less to more than sufficientcategory.
Based on the results, it is evident that the soils are not contaminated by anypolluting sources.
10.3.2 Meteorology
Meteorological data at the site was monitored during 1st March to 31st May 2015representing winter season. It was observed that the during study period,temperature ranged from 19.10C to 42.20C. During the same period of observations,the relative humidity recorded was ranged from 12% to 79.35% A total of 0.19-mmrainfall was recorded during the study period.
10.3.3 Ambient Air Quality
Ambient Air Quality Monitoring (AAQM) has been carried out at seven locations with afrequency of two days per week for three months during summer season of 2015. Theminimum and maximum concentration of PM10 recorded within the study area was50.5 µg/m3 to 139.4 µg/m3 with the 98th percentile ranging between 63.3 µg/m3 to130.7 µg/m3. The minimum and maximum concentration of SO2 recorded within thestudy area was <5 to 6.8 µg/m3 with the 98th percentile ranging between 6.2 µg/m3to 6.8 µg/m3. The minimum and maximum concentration of NOx recorded withinthe study area was 6.5 µg/m3 to 15.8 µg/m3 with the 98th percentile rangingbetween 12.7 µg/m3 to 15.6 µg/m3. The minimum and maximum concentration ofPM10 recorded within the study area was 50.5 µg/m3 to 139.4 µg/m3 with the 98thpercentile ranging between 63.3 µg/m3 to 130.7 µg/m3.
10.3.4 Water Quality
To assess the physical and chemical properties of water in the region, water samplesfrom seven locations were collected from various water sources around the mine leasearea.
The pH limit fixed for drinking water samples as per IS-10500 Standards is 6.5to 8.5 beyond this range the water will affect the mucus membrane and orwater supply system. During the study period, the pH was varying for ground
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-8
waters from 7.62 to 8.21 & pH was varying for surface waters from 7.7to8.16. The pH values for all the samples collected in the study area duringstudy period were found to be within the limits.
The desirable limit for total dissolved solids as per IS-10500 Standards is 500mg/l where as the permissible limits in absence of alternate source is2000mg/l, beyond this palatability decreases and may cause gastro intestinalirritation. In ground water samples collected from the study area, the totaldissolved solids are varying from 1668 mg/l to 4249 mg/l the TDS of thesamples were below the desirable limit but within the permissible limit of2000 mg/l.
The desirable limit for chlorides is 250 as per IS-10500 Standards where aspermissible limit of the same is 1000 mg/l beyond this limit taste, corrosionand palatability are affected. The chloride level, in ground water samples 550mg/l to 1539 mg/l. & for surface water it is 42 mg/l to 18060 mg/l thechloride samples are within the desirable limits.
The desirable limit as per IS-10500 Standards for hardness is 300 mg/l whereas the permissible limit for the same is 600 mg/l beyond this limitencrustation in water supply structure and adverse effects on domestic usewill be observed. In the ground water samples collected from the study area,the hardness is varying from 410 mg/l to 1388 mg/l.
Fluoride is the other important parameter, which has the desirable limit of1mg/l and permissible limit of 1.5 mg/l. however the optimum content offluoride in the drinking water is 0.6 to 1.5 mg/l. if the fluoride content is lessthan 0.6 mg/l it causes dental carries, above 1.5 mg/l causes flurosis. In theground water samples of study area the fluoride value were in the range of0.7 mg/l to 2.1 & in surface water it varies from 0.6 mg/l to 1.3.
Overall all the samples collected from the study area were found to be fit forconsumption, Most of ground water samples are well within the permissible limits.Most of the heavy metals in all samples are below detectable limits
10.3.5 Noise Levels
Ambient noise levels were measured at seven locations around the proposed minesite. Assessment of night time Leq (Ln) varies from 43.2 to 54.6 dB (A) and thedaytime Leq (Ld) varies from 46.3 to 68.4 dB (A) within the study area.
10.3.6 Ecological Environment
Based on the field studies and review of published literature, it is studied of thebuffer zone of both Virpur (Gunawali) bauxite mine reveal that plant species under
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-9
the category of RET have not been observed. Among Fauna, Indian Peafowl (Pavocristatus) is documented as schedule-1 species. There is no any other speciesbelongs any other class were observed under schedule category from both therespective buffer zone. However, all care will be taken for protection of others flora& fauna also, if any in the leasehold area. Conservation plan for above mentionedspecies is attached along with the report. There is an Eco-Sensitive zone, MarineNational Parks is about 4.12km, Marine Sanctuary is about 1km and Gaga BirdSanctuary is about 16.55km of the study area.
10.3.7 Social Environment
The study area (10-km radius) area has a total population of 94,918 according to2011 census. Total male population is about 51% and total female population isaround 49%. The average literacy rate is ‘less’ to ‘moderate’ in the region.
10.4 Cost Estimates
The details of the cost to be incurred for successful monitoring of environmentalparameters and implementation of control measures are given in Table-10.3.
TABLE-10.3COST OF ENVIRONMENTAL PROTECTION MEASURES
SI. No. Measures Capital cost(in Rs.)
Annual recurring cost(in Rs.)
Proposed Proposed1 Pollution Control
i) Dust Suppressionii) Garland drain & grounddump
25,00025,000 50,000
2 Pollution Monitoringi) Air pollutionii) Water pollution
25,00025,000
30,00030,000
3 Reclamation &RehabilitationGreen Belt
25,000 30,000
4 Others (Environmentalstudy, Statutory compliance,etc.)
50,000 30,000
Total 1,75,000 1,80,000
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-10
10.4.1 ADMINISTRATIVE ASPECTS
Environmental Management Cell will be headed by the agent of mine and willconstitute Manager (Mines), Environmental Engineer, Scientists and supervisor.
10.5 ADDITIONAL STUDIES
10.5.1 Risk Assessment and Disaster Management Plan
The complete mining operation will be carried out under the management controland direction of a qualified mine manager holding a First Class Manager’s Certificateof competency to manage a metalliferous mine granted by the Directorate Generalof Mines Safety (DGMS), Dhanbad. The DGMS have been regularly issuing standingorders, model standing orders and circulars to be followed by the mine managementin case of disaster, if any. Moreover, mining staff will be sent to refresher coursesfrom time to time to keep them alert.
10.5.2 Disaster Management Plan
Emergency preparedness is an important aspect in the planning of DisasterManagement. Personnel would be trained suitably and prepared mentally andphysically in emergency response through carefully planned, simulated procedures.Similarly, the key personnel and essential personnel shall be trained in the operations.
10.6 PUBLIC CONSULTATION
10.6.1 Public Hearing
The draft EIA is prepared and submitted to Pollution Control Board for Public Hearing.The public hearing for the Virpur (Gunawali) Bauxite mine for 1, 51,875 TPA capacitiesby semi mechanized open cast method in Virpur (Gunawali) village, Kalyanpur Taluka,Devbhumi Dwarka District, Gujarat was conducted on 29.03.2016, as per theEnvironment Impact Assessment Notification dated 14th September 2006. The publichearing proceedings & related papers are attached as Annexure- XIII.
10.7 PROJECT BENEFITS
The proposed project also benefits in improving the physical infrastructure of thestate. The social infrastructure of the area will also be developed.
FEIA for the Proposed Virpur(Gunawali) Bauxite Mine at village Virpur, Tehsil Kalyanpur, DistrictDevbhumi Dwarka, Gujarat (55.2520 ha) (Mine working area 37.167 ha)Chapter-10SUMMARY & CONCLUSION
X-11
The project also benefits the employment potential of the area by providingemployment to the nearby population (directly and indirectly) during constructionalas well as operational phases of the project.
10.8 CONCLUSIONS
The mining operations will meet the compliance requirements of SPCB/MoEF;
Community impacts will be beneficial, as the project will generate significanteconomic benefits for the region;
Adoption of Best Available Technology and Best Management Practices withmore environmental friendly process; and
With the effective implementation of the Environment Management Plan (EMP)during the mining activities, the proposed project can proceed without anysignificant negative impact on environment.
1
CHAPTER-XI
DISCLOSURE OF CONSULTANTS ENGAGED
The EIA/EMP Report for Virpur (Gunawali) Bauxite lease 55.2520 ha (Mine Working area37.167 ha) for a Peak Production of 1, 51,875 TPA at Village Virpur, Tehsil Kalyanpur,District: Devbhumi Dwarka, Gujarat (55.2520ha) Mine working area (37.167ha) hasbeen prepared by Grass Roots Research & Creation India (P) Ltd.
Name of the Consultant
Address
Grass Roots Research &
Creation India (P) Ltd.
F:374- 375, Sector: 63, Noida,
India
ISO 9001: 2008 (QMS),
14001:2004 (EMS) &
OHSAS 18001: 2007
Certified Co.
Accredited by QCI/NABET.
Name of the Laboratory
Address
GRC India Training and
Analytical Laboratory
F- 375, Sector: 63, Noida,
India
NABL Accredited
Laboratory,
Recognized by MoEF under
Environment (Protection)
Act, 1986.
A unit of GRC India (P) Ltd.
2
The following Coordinator & Functional Area Experts were involved in the preparationof the EIA/EMP Report:
FAE- AP Mr. K D Choudhury
FAE- WP Dr. P R Chaudhari
FAE- SHW Mr. Rajesh B.
FAE- EB Dr. P R Chaudhari
FAE-SE Mr. K N Dutta
FAE- AQM Dr. Ms. C Mary Sukanya
FAE- LU Mr. P Radhakrishnamoorthy
FAE- HG Dr. Tapan Majumder
FAE- G Dr. Tapan Majumder
FAE- RH Mr. K D Choudhury
FAE- SC Dr. S R Maley
FAE- NV Mr. K D Choudhury
The following team was involved under the guidance of experts for preparation of thereport:
Personnel involved in
Preparation of EIA/EMP
report as Team Member
Mr. Varun Bhardwaj (AFAE)
Dr. C Mary Sukanya (Team Member & Proposed FAE)
Mr. P. R. Chaudhary (Team Member - EB)
Mr Rahul Kumar (Team Member)
3
Accreditation from Quality Council of India, QCI NABET
Grass Roots Research & Creation India (P) Ltd. has got the Initial accreditation from QCINABET and has undergone Surveillance Assessment as well. The result of continuedaccreditation is published on the QCI website as SAAC 69th and subsequent Minutes ofMeeting in the year 2013-14.
As per the recently published QCI NABET ‘List of Accredited ConsultantOrganizations/Rev. 32/July 06, 2015’, listed in as accredited consultant, Category ‘A’ Sl. No.74. The list of accredited consultants is published on QCI NABET and MoEF websites aswell.
For reference, a snapshot of first page of the accredited list along with the list where GRCIndia’s name is listed is pasted below:
4
************