Phoenix Convention Center Phoenix, Arizona Evolution of Energy Services Integrated Energy...

8
Phoenix Convention Center • Phoenix, Arizona Evolution of Energy Services Integrated Energy Track Integration of the Energy Industry Nicole Bulgarino Ameresco August 12, 2015

Transcript of Phoenix Convention Center Phoenix, Arizona Evolution of Energy Services Integrated Energy...

Page 1: Phoenix Convention Center Phoenix, Arizona Evolution of Energy Services Integrated Energy TrackIntegration of the Energy Industry Nicole Bulgarino Ameresco.

Phoenix Convention Center • Phoenix, Arizona

Evolution of Energy Services

Integrated Energy Track Integration of the Energy Industry

Nicole BulgarinoAmeresco

August 12, 2015

Page 2: Phoenix Convention Center Phoenix, Arizona Evolution of Energy Services Integrated Energy TrackIntegration of the Energy Industry Nicole Bulgarino Ameresco.

Energy Exchange: Federal Sustainability for the Next Decade2

ThenLong pay-backsAdd into ESPC with buy-down money and bundling

NowStand-alone projects through ESPC and PPAProviding lower cost energy than brown power

FutureFully Integrated Microgrid with onsite energy generation

ESCO Evolution – Renewables

DOE Savannah River Site | 20 MW Biomass Cogeneration Facility

Fort Detrick18.6 MW Solar PV Farm

NASA Wallops Flight Facility752 Tons of Geothermal Heat Pumps

Page 3: Phoenix Convention Center Phoenix, Arizona Evolution of Energy Services Integrated Energy TrackIntegration of the Energy Industry Nicole Bulgarino Ameresco.

Energy Exchange: Federal Sustainability for the Next Decade3

T-12

T-8

Integrated LEDs with Advanced Controls

ESCO Evolution – Energy Efficiency

• Energy Efficiency– Simple replacements to fully

integrated measures

Page 4: Phoenix Convention Center Phoenix, Arizona Evolution of Energy Services Integrated Energy TrackIntegration of the Energy Industry Nicole Bulgarino Ameresco.

Energy Exchange: Federal Sustainability for the Next Decade4

• Initial projects included:– High Efficiency Lighting Retrofit

and some sensor installation– Water Conservation– Compressed Air System Repairs– Equipment Replacement

Typical Initial ESPC Projects

Page 5: Phoenix Convention Center Phoenix, Arizona Evolution of Energy Services Integrated Energy TrackIntegration of the Energy Industry Nicole Bulgarino Ameresco.

Energy Exchange: Federal Sustainability for the Next Decade5

• Hill AFB ESPC• T- 5 Lighting with sensors• Site wide compressed air system

upgrade with tie into central plant• Ventilation improvements• Waste water minimization • 2,250 kW Renewable Landfill Gas to

Energy Plant • 210 kW ground-mounted PV array • Other Facility & Energy System

Improvements

Evolve to Comprehensive Energy Projects

Page 6: Phoenix Convention Center Phoenix, Arizona Evolution of Energy Services Integrated Energy TrackIntegration of the Energy Industry Nicole Bulgarino Ameresco.

Energy Exchange: Federal Sustainability for the Next Decade6

• Utilizing ESPC for deep retrofit of over one million square feet of office space at the New Carrollton Federal Building and the Silver Spring Metro Center 1 building (SSMC 1) in Silver Spring, Maryland.

• Project highlights include: – Complete retrofit of mechanical systems/building

controls– Energy consumption reductions of 60 percent against

baseline usage– 50% water cost reduction against baseline usage– Major chiller plant upgrade and replacement with

geothermal fied– 1 megawatt equivalent of on-site renewable energy, a

geothermal well-field will operate below a parking lot covered by a large-scale solar canopy.

– More than 11,000 new LED lighting fixtures will be controlled by a network of 2,000 occupancy and ambient light sensors

Evolve to Deep Energy Retrofit

Page 7: Phoenix Convention Center Phoenix, Arizona Evolution of Energy Services Integrated Energy TrackIntegration of the Energy Industry Nicole Bulgarino Ameresco.

Energy Exchange: Federal Sustainability for the Next Decade7

• Fort Detrick - 18.6 MW solar project • 25-year electricity purchase agreement

with Fort Detrick and a 25-year land lease with the U.S. Army Corps of Engineers

• The facility is designed to be micro-grid compatible.

• All electricity from the solar facility will be consumed by Fort Detrick.

• Ameresco will build, own, operate and maintain the solar project.

• Ameresco is also building a 1.24 mile 4 kV distribution line to support the PV plant.

• The project is planned to be operational by February 2016.

ESCOs providing Supply-Side Only Projects

Page 8: Phoenix Convention Center Phoenix, Arizona Evolution of Energy Services Integrated Energy TrackIntegration of the Energy Industry Nicole Bulgarino Ameresco.

Energy Exchange: Federal Sustainability for the Next Decade8

Nicole BulgarinoSenior Vice President – Federal [email protected]

Federal.Ameresco.com