PHOBOS TOF Construction Status A.B. Hayes, E.B. Johnson, Robert Pak, R.T.D. Teng, and F.L.H. Wolfs...
-
Upload
adele-harper -
Category
Documents
-
view
213 -
download
0
Transcript of PHOBOS TOF Construction Status A.B. Hayes, E.B. Johnson, Robert Pak, R.T.D. Teng, and F.L.H. Wolfs...
PHOBOS TOF Construction Status
A.B. Hayes, E.B. Johnson,
Robert Pak, R.T.D. Teng,
and F.L.H. Wolfs
University of Rochester
supported by NSF
TAC Review
Brookhaven Nat’l Lab
Nov. 6, 1998
Outline
Detector Configuration:
» Baseline
» TOF Upgrade Components & Assembly Support Structure Readout Electronics Summary
PHOBOS Baseline Design
Multiplicity Array:» Octagon Barrel» Vertex Detector» Ring Counters
Nearly 4coverage
( - 5.4 < < 5.4 ) Spectrometer Arms: Detailed measurement
of ptransverse down to
~ 40 MeV/c for pions.
TOF System Upgrade
Time-of-flight wall
Magnet support structure
Silicon planes
Interaction point
Ring muliplicity counters
Required performance:
» TOF < 100 ps
» Occupancy < 15%
Particle ID with PHOBOS
Baseline design relies solely on energy loss
PID based on dE/dx:» / K : p < 650 MeV/c
» K / p : p < 1.2 GeV/c
PID based on TOF (TOF =100 ps):» / K : p < 1.2 GeV/c» K / p : p < 2.0 GeV/c
1.7 m from interaction point
Physics Impact of PHOBOS TOF
Spectral behavior of ptransverse distributions
Extend pt region for and K interferometry
Precise measurement of K/ ratios as a function of pt
Study pt dependence of meson production
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
Pt
(G
eV/c
)
1.51.00.50.0
y
Time-of-Flight Identification
dE/dx Identification
+, -
Scintillators and Light Guides
Scintillators:» BC-404 fast plastic from Bicron» 8 x 8 x 200 mm3
» Diamond milled surface finish Light Guides:
» BC-800 acrylic dog-leg design » Machined at INP in Krakow
Photomultiplier Tubes & Bases
Hamamatsu R5900-00-M4MOD 12 stage multi-anode PMTs » Minimum gain per any
one channel of 2 x 106 at +800 V
» Maximum variation in gain (uniformity) is less than 50% per any one tube
Quality assurance done
Hamamatsu Gain Vs. Rochester Gain
0.00E+00
2.00E+06
4.00E+06
6.00E+06
8.00E+06
1.00E+07
1.20E+07
1.40E+07
1.60E+07
0.00E+00 5.00E+06 1.00E+07 1.50E+07 2.00E+07
Rochester Gain
Ham
am
ats
u G
ain
Assembly of components
Gluing of light guides to scintillators is completed Wrapping in reflective Al foil and first layer of protective tape is
finished for all 240 detectors
Mounting Fixture
Must precisely align light guides with the face of the PMT
Serve as gluing fixture for PMTs to light guides
Machining at INP in Krakow is completed
Magnetic Shields
TOF detectors must operate unaffected by magnetic fringe fields of at least 100 G
Prototype metal shield has been designed and tested in house
Order completed through Perfection Mica
LED Calibration System
470 nm (blue) LED from Panasonic (P465)
Duplex fiber optic cables from Thomas & Betts carry pulses to each PMT
Pulse width ~ 10 ns out of PMT (at +8 V) and bright enough to drive multiple PMT’s
Light split between fibers and PIN diode reference
LED
Splitter
Fiber Bundle
PIN Diode
(To PMT’s)
LED Calibration System1 mm dia plastic fiber located in “dead-area” at center of PMT
Upper-right light guide removed to show fiber
NIM to TTL converter
Pulser uses transistor in avalanchemode to discharge a capacitorthrough LED
Basic TOF Units
Gluing of PMTs to light guides & fiber optics has begun Final assembly and testing of basic TOF units progressing
well at Rochester (we’re under spec)
Benchtest: Crosstalk
Crosstalk in PMT will not be a problem
TOF Support Structure
Final design of TOF support structure nearly complete AutoCAD picture courtesy of our collaborators at INP
Readout Electronics
Standard modules were chosen to reduce overhead from development of specialized electronics
LeCroy 1458 HV mainframe with ARCNET card sent to BNL for work on Slow Controls
Order placed with LeCroy for HV cards, FASTBUS ADCs and TDCs, and CAMAC discriminators
Cost of PHOBOS TOF Project
Total cost (proposal):
» NSF MRI Grant $328,129.00
» Cost sharing + 245,196.00
$573,325.00
--------------------------------------------------------------------- Actual current expenditures $475,346.80 Proposed current expenditures - 474,271.30
$1,075.50
Summary
Solid progress has been made on all fronts
for the PHOBOS TOF System at Rochester.
The PHOBOS TOF System will be ready on Day 1 of Commissioning Run at RHIC.
Stay tuned: http://teacher.nsrl.rochester.edu/ Research/PHOBOS/Phobos.html