Phase IV Presentation Group 7 Thomas Kudej Marko Sutovic Timothy Smith.
-
date post
22-Dec-2015 -
Category
Documents
-
view
215 -
download
2
Transcript of Phase IV Presentation Group 7 Thomas Kudej Marko Sutovic Timothy Smith.
WHISPER 200 ANALYSIS AND REMEDIATIONPhase IV Presentation
Group 7Thomas KudejMarko SutovicTimothy Smith
GROUP MEMBERSAdvisor
Professor Basu
Timothy Smith Marko Sutovic
Thomas Kudej
Presentation OutlineProject ObjectiveBackground Phase I-IIIPhase IV
Monitoring System Parts Ordered Programming Needed
Power Transformation SystemHeight Increasing Base
BudgetGantt ChartNugget ChartQuestions?
Project ObjectivesTo design a monitoring system to record data from
the wind turbine and use this data to improve on the power generation .
Design and build a foundation to raise the height of the turbine over any further obstacles and bring it closer to the recommended height.
Use the monitoring system to observe vibrations transmitted by the turbine into the roof slab.
Design the foundation in response to vibrations analysis
Analyze the data to study trends of a wind turbine in an urban environment
BackgroundPrevious design group placed
Whisper 200 on Babbio roofThey incorrectly assumed
wind readings from buoy on Hudson river and other local weather stations were similar to Babbio roof conditions
Local wind measurements were needed of potential locations on campus for the Whisper 200
BackgroundA repeatable experiment
was executed at 8 locations on Stevens Campus
Measured wind speeds and direction.
Repeated on three different days
Sample was taken at Babbio Location A (original location) on Day 1 between 1:35pm and 1:45pm.
0
2
4
6
8
10
12
1:36
:57 P
M1:
37:2
4 PM
1:37
:37 P
M1:
38:1
3 PM
1:38
:23 P
M1:
38:3
1 PM
1:39
:07 P
M1:
39:2
0 PM
1:39
:32 P
M1:
39:5
8 PM
1:40
:17 P
M1:
40:3
9 PM
1:40
:50 P
M1:
41:0
2 PM
1:42
:01 P
M1:
42:1
4 PM
1:42
:35 P
M1:
43:0
1 PM
1:43
:12 P
M1:
43:3
4 PM
1:43
:48 P
M1:
43:5
7 PM
1:44
:12 P
M1:
44:2
9 PM
1:44
:39 P
M1:
44:4
7 PM
1:45
:02 P
M1:
45:1
6 PM
1:45
:34 P
M1:
45:5
0 PM
1:45
:58 P
M1:
46:0
7 PM
Speed
BackgroundSample was taken at CPA
Location B (optimal location) on Day 1 between 3:00pm and 3:10pm.
Average Wind Velocity was measured to be 4.0408m/s.
Wind Direction was conclusively consistent.
After analysis, this location was chosen as the most optimal for the Whisper 200, due to its constant wind direction and reliable wind velocity.
Background Whisper 200 moved to CPA location B
Monitoring SystemLive remote
monitoringVibrationPower
productionWind behaviorVideo feed
Store data to create archive of Whisper 200 performance characteristics
Post results on website
Monitoring SystemParts Ordered
2 AccelerometersUSB data loggerUSB to Ethernet Microserver
Programming NeededLabview
Sensors signal processingWebsite
Easy display of data Live video feed
Power Transformation SystemCurrent systemWhisper Link – Rectifies the
3 phase AC out of the turbine and supplies the inverter with a DC output voltage.
Windy Boy Inverter convertsDC input into single phase 120V/60Hz AC into the electrical grid
Windy Boy Grid Tie InverterPower Curve OperationTurbine mode of operation draws power
based upon the DC voltage seen at the input terminal. •Maximum power output
1800W•When start voltage is reached, the inverter waits 10 seconds•If voltage remains above start point , inverter will synchronize the power and export it.•If voltage drops below set point ,inverter will have a zero power output for 120 seconds before shutting down.
Issue with InverterVoltage start point set by manufacturer =
190VdcCurrently the wind turbine needs an increase
in the amount of wind speed in order to reach this point.
Inverter SolutionInverter can be adjusted with software
provided by manufacturer and purchased connecter cable.
Software allows for adjustments to the slope of the power curve
Able to reprogram voltage start and max point in range of 155 – 375 Vdc
By reducing start and max point, you reduce the maximum power output
Possible extensionsStorage Battery systemWhen output DC voltage
does not reach inverterstart point and during periods of low wind, discharge minorgenerated voltage into batteries
Batteries charge to capacity then discharge into the inverter
DownsidesLogisticsCostVoltage losses
Possible ExtensionsMinor battery systemInstall 2-3 batteriesStore energy when Vdc start point is not metUse stored power in batteries to boost the
input DC voltage past the start point when it is close
DownsidesCostLogisticsFeasibility