Phase I Presentation

25
PURDUE UNIVERSITY BASEBALL FACILITY Phase 1 : Conceptual Design and Alternatives Analysis CE 498 -Senior Design - 2009 Team 5

description

 

Transcript of Phase I Presentation

Page 1: Phase I Presentation

PURDUE UNIVERSITY BASEBALL FACILITY

Phase 1 : Conceptual Design and Alternatives Analysis

CE 498 -Senior Design - 2009

Team 5

Page 2: Phase I Presentation

ENGINEERING TEAM

PROJECT MANAGER: Alice Madjani

TRANSPORTATION ENGINEER: Eric Hulme

STRUCTURAL ENGINEER: Matt Murray

ENVIRONMENTAL ENGINEER: Mike Broyles

STRUCTURAL ENGINEER: Ryan Laughlin

2

Page 3: Phase I Presentation

3

Presentation OverviewSite LayoutBaseball FacilitySoccer FacilitySite master planSite AccessWater management

Engineering considerations

Environmental considerations

LEED AccreditationConstructionCost EstimateProject Schedule

Page 4: Phase I Presentation

4

Time for a New FacilityOther Big Ten Facilities

Current Purdue Facility

Page 5: Phase I Presentation

5

Site Layout

Page 6: Phase I Presentation

6

Baseball Facility

Unique FeaturesSeatingGreen SpacesPress BoxHD LightingBerme SeatingOutfield Wall

LayoutGround LevelConcourse LevelPress Box

Page 7: Phase I Presentation

7

Soccer FacilityContinue using the eastern

field for competitionOption of using the west

field for a future men’s teamExpanded SeatingSupport Facilities

Concessions StandRestroomsLocker Room

H.D. LightingOpportunities to share

facilities

Opportunities to share facilities

Page 8: Phase I Presentation

8

Site Master Plan

Page 9: Phase I Presentation

9

Existing Access

Page 10: Phase I Presentation

10

Construction Access

Construction Route from S.R. 26

Construction Route from S.R. 126

Construction Route to US 231

Construction Route to S.R. 26

Construction Exit Route from S.R. 526 to S.R. 126

Construction Route into Site

Construction Route from Site

Construction Route from US 231

Page 11: Phase I Presentation

11

Vehicle Access Intersection Improvements

Intersection Improvements

New Parking Field

New Parking Field

New Parking Field

Perimeter Parkway

Page 12: Phase I Presentation

12

Pedestrian AccessUpper Pedestrian

Corridor

Lower Pedestrian Corridor

Central Pathway

Eastern Pathway

Western Pathway

Bike Path Extension

Page 13: Phase I Presentation

13

Water ManagementStream through the middle of the site

Central Drainage Channel through siteRiparian zone = Storm water pollution prevention

BMP to remove fertilizers and suspended solidsCentral detention basin

Control release rate to Jordan CreekHarvest rain water from basin

Flushing toilets Site irrigation Electronic controls (Supervisory Controls and Data

Acquisition)

Page 14: Phase I Presentation

14

Water Management

Page 15: Phase I Presentation

15

Environmental Considerations

Wetlands U.S. Fish and Wildlife

ServicePEMA: temporary wetland

ContaminationUS-231 Relocation StudyPreviously undeveloped

siteNot classified as a historic

site by DNRNo formal study

Page 16: Phase I Presentation

16

Engineering ConsiderationsFoundation System

Shallow spread footing and continuous wall foundations

Structural SystemSteel frameReinforced concrete slabs and seating structureSteel columns for Press Box supportAwning covering half the seatsCable suspension system for awning and

backstop

Page 17: Phase I Presentation

17

L.E.E.D.LEED Certification and Benefits

Anticipated Certification: Silver (20 points)Sustainable Site Credits: 9Water Efficiency Credits: 3Materials and Resources Credits: 6Innovation & Design Process Credits: 2

Gold Certification Potential

Page 18: Phase I Presentation

18

ConstructionSite management

ZEAL as the constructionmanager

Construction equipment1. Rollers 7. Bobcats

2. Lifts 8. Grader

3. Concrete

pumps9. Excavator

4. Cranes 10. Pavers

5. Front-end

loader

11.

Compactor

6. Dump Trucks 12. Fort lift

Page 19: Phase I Presentation

19

Construction cont’dMaterial

Building Steel framing Reinforced concrete

Parking lot Pervious concrete

Page 20: Phase I Presentation

20

Cost EstimateConceptual cost estimate

Soccer addition

Facility CostBaseball field $1,894,089Building Construction $4,929,922

Site work $5,471,713

Total (89.2% cost reduction) $10,967,786

Administrative $4,240,563

Total project cost $15,208,349

Facility Cost

Soccer addition $592,330

Administrative cost $191,915

Total $784,245

Page 21: Phase I Presentation

21

Construction Scheduling

Page 22: Phase I Presentation

22

SummaryThe FacilitySite LayoutEngineering ConsiderationEnvironmental ConsiderationL.E.E.D. Accreditation Cost EstimateProject Schedule

Page 23: Phase I Presentation

23

References Ashley, Erin. "Using Pervious Concrete to achieve LEED credits." 2008.

Pervious Concrete Pavement. 02 February 2009 <http://www.perviouspavement.org/benefits_LEEDcredit.htm>.

B4UBUILD. A Sample Residential Construction Schedule. 1998 - 2008. 19 February 2009 <http://www.b4ubuild.com/resources/schedule/6kproj.shtml>.

CE 498 - CE Design Project. January 2009. 02 February 2009 <https://engineering.purdue.edu/Courses/CE498>.

Corporation, The Schneider. "Storm Water Analysis." 2007. Google. Google Earth. West Lafayette, February 2009. HNTB. Purdue University - Athletic Facilities Master Plan. Conceptual

master plan. Indianapolis: HNTB, 2007. J&M Equipment Specialist & Salvage Recovery. 2008. 2 February 2009

<jmequipmentspecialist.com/id7.html>. Michigan, University of. Michigan Go Blue. February 2009. February 2009

<http://www.mgoblue.com/facilities/article.aspx?id=28646#>.

Page 24: Phase I Presentation

24

References cont’d Microsoft. Live Search Maps. February 2009. February 2009

<http://maps.live.com/>. Office of the University Architect. "Consultant's Handbook." 2006. Office of

University Architect. 20 January 2009 <http://www.purdue.edu/architect/resources/handbook/index.html>.

Qualite. Design Soccer. 2008. 12 February 2009 <http://www.qualite.com/DesignSoccer.html>.

RS Means. Builiding Construction Cost Data. Kingston, MA: R.S. Means Company, 2009.

The Schneider Corporation. "Report of Geotechnical Engineering Study." 2008.

The Schneider Corporation. "Storm Water Analysis." 2007. U.S. Fish and Wildlife Service. "Viewing Wetland with Google Earth (Plug-in for

Google Earth)." July 2008. U.S. Green Building Council. New Construction Version 2.2 Reference Guide.

Washington, DC: U.S. Green Building Council, 2006. US Green Building Council. 2009. 20 January 2009 <http://www.usgbc.org/>.

Page 25: Phase I Presentation

25

Questions!