Phase 2 Report Water Resources
-
Upload
chase-campbell -
Category
Documents
-
view
63 -
download
2
Transcript of Phase 2 Report Water Resources
Purcell, Goodwyn, & Campbell Lexington, KY 6 May 2015 Sandi Beechez, Chair, UK Master Planning TeamUniversity of Kentucky100 Administration Drive Dear Sandi Beechez,
This letter is in response to your notice to proceed dated 16 April 2015. Our consulting group, Purcell, Goodwyn, & Campbell, has done considerable analysis of the University of Kentucky Master Plan, and determined what we believe to be the best design solution.
This report will cover details within the watershed calculated from a point of interest. This point of interest is located at the intersection of Nicholasville Road and Alumni Drive within the confines of the University of Kentucky’s south campus grounds.
Through the analysis of collected data, we have designed a new detention basin system that we recommend be constructed in the area under consideration. Within this report, we will cover several aspects of the design including pre- and post-development conditions as well as the justification for our design.
Provided here is a summary of our design and the changes that would be necessary for implementation. Please respond to the group’s submission with any inquiries or concerns you may have regarding Phase II.
Sincerely,
Purcell, Goodwyn, & Campbell [email protected]@[email protected]
University of Kentucky’s Mater Plan Drainage, Storm Sewer, and Detention Systems
Phase 2
Lexington, KY 6 May 2015
By:
Macy Purcell
Angela Goodwyn
Chase Campbell
2
Table of Contents
List of Figures……………………………………………………………………………..4
Executive Summary ............................................................................................................5
Introduction .........................................................................................................................7
Identification of Client………………………………………………………………….....7
Site Description and Location Map……………………………………………….............7
Scope………………………………………………………………………………………8
Objectives……………………………………………………………………………........8
Design Analysis…………………………………………………………………………...9
Recommendations .............................................................................................................10
Sources…………………………………………………………………………………...13
Appendix ….......................................................................................................................14
3
List of Figures and Tables
Figure 1: Site Map……………………………………………………………………….14
Figure 2: Site Topographic Map…………………………………………………………14
Figure 3: Pre Development Watershed…………………………………………………..15
Table 1: Pre Development Summary…………………………………………………….15
Figure 4: Junction 1 Pre Development Hydrograph……………………………………..16
Figure 5: Junction 2 Pre Development Hydrograph……………………………………..16
Figure 6: Culvert Pre Development Hydrograph………………………………………...17
Figure 7: Post Development Watershed…………………………………………………17
Table 2: Post Development Summary…………………………………………………...18
Table 3: Post Develop Summary for Reservoirs…………………………………………18
Figure 8: Junction 1 Post Development Hydrograph…………………………………….18
Figure 9: Junction 2 Post Development Hydrograph…………………………………….19
Figure 10: Reservoir 1 Post Development Hydrograph………………………………….19
Figure 11: Reservoir 2 Post Development Hydrograph…………………………………20
Figure 12: Culvert Post Development Hydrograph……………………………………...20
Figure 13: Area of Reservoir 1…………………………………………………………..21
Figure 14: Area of Reservoir 2…………………………………………………………..21
Figure 15: Suggested Basin Locations…………………………………………………...22
4
Executive Summary
Earlier this year, our team was given the opportunity to design a portion of
University of Kentucky’s Master Plan. This portion involved the design of two reservoirs
to collect runoff from a storm we deemed appropriate for the geographical location.
Initially, we spent the majority of our time gathering and analyzing data through the
ARC-GIS computer program to extract explicit information about the watershed we
would be taking into consideration. Once we acquired the necessary data, the next phase
of the plan began.
First, we chose a suitable design storm. The selection of the storm was based on
our engineering judgment, with the knowledge that a less frequent storm would require a
larger and more expensive design. Referencing the U.S. Department of Commerce’s
Rainfall Frequency Atlas of the United States we determined that Kentucky fell within
the boundaries of Type II rainfall distribution. With this information, we saw it
appropriate for our design storm to have a duration of 24-hours and a return period of 25
years. We concluded that having a smaller design storm would not require a significantly
greater expense or waste of space. The design storm produced 5 inches of rainfall, which
we input into the HEC-HMS software to simulate our inflow hydrograph.
Since we were designing two reservoirs, we had to split up the sub-basins
between two junctions connected to a culvert that would eventually feed into them. We
ran the storm through the watershed to acquire pre-development hydrographs and peak
flow for each junction and the culvert, shown in Table 1 & Figures 4-6 in the Appendix.
These peak flows were utilized to help us determine the parameters of each reservoir.
5
We used the AASHTO Method, to determine the design volumes for the
reservoirs, but before we could use this equation, we needed to find tc. To do this, we
used the Watershed Lag Method from the United States Agricultural Department’s
Hydrology National Engineering Handbook in reference to the topographical map shown
in Figure 2. After the design volumes were obtained, it was a trial-and-error process to
determine the right size and fit for the designated locations of the reservoirs, shown in
Figures 13 & 14. We chose to add four orifices to each reservoir. We designed Reservoir
1 to have an outflow of 100cfs and Reservoir 2 to have 250cfs.
Finally, once the reservoirs were added to HEC-HMS, it was necessary to
determine if our design was satisfactory. We ran the storm through our entire system
once more shown in Figure 7, to obtained our final results. The post-development
information is located in Tables 2 &3 as well as Figures 8-12. After analysis, all of the
hydrographs were acceptable, and the outflows for our reservoirs met each of our
designs.
Our final recommendation calls for the construction of two detention basins, one
that covers 5 acres and has a depth of 5 feet, and another that covers 3 acres and is 5 feet
deep. More design specifications can be found in subsequent sections of this report.
6
Introduction
Identification of Client
On February 27, 2015, our client, the University of Kentucky, represented by Ms.
Sandy Beechez contacted us to proceed with Phase 1 of the design for the drainage
system located on south campus.
Site Description and Location Map
The location covers the portion of the University of Kentucky’s south campus,
which includes Alumni Drive, Commonwealth Stadium, the Arboretum, K Lot parking
lot, as well as various buildings. The land in the watershed can be classified as mixed
use. After delineating the watershed, the area was calculated to be 117.89 acres. Figure 1
in the Appendix shows an aerial view of the location, with reference points labeled on the
map.
Figure 15 shows the location map with the placement of our designed basins. In
the figure, Reservoir 1 is shown on the left, and Reservoir 2 on the right. As you can see,
the reservoirs fit nicely within the spaces we used in the design. This means that all of the
current infrastructure on this portion of south campus will not have to be altered very
much. The only alterations that will have to be made would be the uprooting and
replanting of trees and vegetation. Other than the lack of green space, our site is
predominately covered by Commonwealth Stadium and the impervious parking lot that is
connected to it.
7
Scope of Study
In 2006 two women were sucked into a storm drain due to record rainfalls and
drowned at the intersection of Nicholasville Road and Alumni Drive. This tragic event
caused the University of Kentucky to take steps to alleviate flooding in the area. The
University is removing a parking lot at the entrance to the Greg Page Apartments and is
replacing it with a new lot that will be built on top of a water detention basin. The scope
of this portion of the study is to analyze and design an adequate watershed drainage
system.
Objectives
The purpose of this study is to design an adequate drainage system for south
campus of the University of Kentucky. The location of this study is known to have both
drainage and retention problems. The delineation of the watershed has provided
necessary data for the curve number calculations. The objective is to prevent runoff
volumes that are safe to the public and the environment during a storm event. As a
group, we decided it would be feasible to reduce flow from the watershed by 60%.
Because the University holds safety in such high regard, safety will be a key
factor in our decision making process. Overall, the establishment of the drainage system
must enhance the level of safety for locals, students, and the University of Kentucky
Campus as a whole.
8
Design Analysis
Once the watershed information was input into the HEC-HMS software, we tested
the watershed to see its response to 5” of rainfall, or a 24-hour, 25-year storm. Noting the
output data, which can be seen in Table 1 and Figures 4-6, we began the design process
through procedures noted earlier.
Upon completion of our detention basin design, the group considered its
effectiveness. To determine if the design would meet our objectives and fulfill the clients
needs, we analyzed the data output from HEC-HMS.
As noted previously in the Objectives section, one primary goal was to reduce the
outflow from the watershed by 60%. The combined outflows from the watershed before
development totaled just over 1100cfs. Thus, to reduce by 60%, the post-development
outflow would have to be less than or equal to 440cfs.
We determined that our design successfully met this objective. After adding two
detention basins to the watershed model, we once again modeled a 25-year storm using
the design. The HEC-HMS software confirmed our calculations, and showed that our
design performed better than a 60% reduction in flow.
The group also considered the objective to minimize the area devoted to detention
basins. Through several design iterations, the group successfully managed to develop the
final plan which calls for two basins. The combined area of these basins is eight acres.
This represents only 4.5% of the total watershed area. Similarly, since the basins will be
grass-lined, they do not take away green space from an area that has a significant
proportion of open green space.
9
Next, the design does not require the demolition or deconstruction of any existing
infrastructure. The group focused on preventing any unnecessary demolition in order to
decrease construction costs. Construction costs will be reasonably low because of the
location of the planned basins. As can be seen in Figure 13 of the Appendix depicting the
planned locations, the basins border Alumni Drive and the K Lot parking lot on UK’s
campus. Equipment used in construction could be staged in the area already being used
for Commonwealth Stadium renovations, and would not have to travel far to the work
site.
Ultimately, the design successfully fulfilled all of the group’s objectives, and
served the needs of the client.
10
Recommendations
Based on the design analysis, our group recommends the implementation of our
design. Given that the design meets the objectives of the client, we believe that it would
serve their needs well.
Implementation of our design would require the construction of two detention
basins. The first and larger of these basins is to be located between Alumni Drive and the
Greg Page Apartments, and is to cover an area just over 5 acres. The second basin should
be slightly smaller than the first at only 3 acres. It is to be located just past the first basin,
but on the opposite side of the road, bordering the K Lot parking lot. The precise
locations can be seen in Figure 15 of the Appendix.
The larger basin is intended to handle a large majority of the runoff from the
Commonwealth Stadium parking lot and the surrounding parking lots. These lots make
up a large percentage of the watershed, and prevent water from infiltrating. Drains
should be installed in the parking lot and should connect to culverts installed beneath
Alumni Drive to divert water from the lots and into the larger basin. Similarly, 5 32”
culverts should be use to drain the water from the culvert into the existing grass channel
that parallels Alumni Drive. This channel connects to the culvert that lets water out of the
watershed and which serves as the outlet of the watershed.
The smaller basin is designed to handle flows from the open space and
grassy/forested areas. Since these areas allow more water to seep into the ground, the
runoff is less than with the parking lots. Four 24” culverts should allow water to flow out
of the basin.
11
Both basins should have side slopes with one foot of vertical rise to every two feet
of horizontal distance. Thus, the basins should have trapezoidal cross sections. Because
of the irregular shape of the basins, the group found it difficult to calculate the volume of
these odd shapes. Instead, we initially designed these basins with vertical sides, since the
volume could be calculated by multiplying the area by the height. In effect, adding sloped
sides to the basins adds a slight safety factor, because the volume will be greater than
originally designed. This increased volume increases the effectiveness and level of safety
of the basin, without a significant increase in cost.
We recommend that this design be implemented very soon, in order to coordinate
with work that is currently going on. At the time of this report, considerable work is
being done to renovate the parking lot adjacent to the UK Arboretum. If work is started
soon, it would save time, and would prevent possible damage to a completed parking lot
by construction equipment.
Our final recommendation is to use the design presented by this report.
12
SourcesGupta, Ram S. Hydrology and Hydraulic Systems. Long Grove, IL: Waveland, 2008.
Print.
http://www.nws.noaa.gov/oh/hdsc/PF_documents/TechnicalPaper_No40.pdf
https://www.codot.gov/programs/environmental/water-quality/documents/drainage-
design-manual/drainagedesignmanual_chapter12_storagefacilities.pdf
http://directives.sc.egov.usda.gov/OpenNonWebContent.aspx?content=27002.wba
http://www.hec.usace.army.mil/software/hec-hms/documentation.aspx
13
Appendix
Figure 1: Site Map
Figure 2: Site Topographic Map
Alumni Dr.Nicholasville Rd.
14
Figure 3: Pre Development Watershed
Table 1: Pre Development Summary
Peak Outflow (cfs) Total Outflow (in)
Junction 1 449.7 3.79
Junction 2 728.3 4.82
Culvert 1175.7 4.38
15
Figure 4: Junction 1 Pre Development Hydrograph
Figure 5: Junction 2 Pre Development Hydrograph
16
Figure 6: Culvert Pre Development Hydrograph
Figure 7: Post Development Watershed
17
Table 2: Post Development Summary
Peak Outflow (cfs) Total Outflow (in)
Junction 1 449.7 3.79
Junction 2 728.3 4.82
Culvert 317.9 4.38
Table 3: Post Develop Summary for Reservoirs
Peak Storage (AC-FT)
Peak Elevation
(Ft)
Peak Inflow (cfs)
Peak Outflow
(cfs)
Total Inflow
(in)
Total Outflow
(in)
Reservoir 1
8.0 3.9 449.7 105 3.79 3.79
Reservoir 2
11.9 3.7 728.3 213 4.82 4.82
Figure 8: Junction 1 Post Development Hydrograph
18
Figure 9: Junction 2 Post Development Hydrograph
Figure 10: Reservoir 1 Post Development Hydrograph
19
Figure 11: Reservoir 2 Post Development Hydrograph
Figure 12: Culvert Post Development Hydrograph
20
Figure 13: Area of Reservoir 1
Figure 14: Area of Reservoir 2
21
Figure 15: Suggested Basin Locations
22