Phase 1:- Phase 2:- -...
Transcript of Phase 1:- Phase 2:- -...
Proposed installation of Unit II – 500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125
KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW,
1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Pre Feasibility Report
M/s Om Sons Marketing Private Limited 1
PRE - FEASIBILITY REPORT
1.0 EXECUTIVE SUMMARY
(I) Introduction
Om Sons Marketing Private Limited is proposing installation of Unit II – 500 KLPD Ethanol/RS
Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain Based and 125
KLPD Molasses based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I)
and (1x15 MW, 1x5 MW in Phase II)} in Existing Distillery Plant at Village Sangat, Tehsil & District
Bathinda, Punjab.
The unit will be installed in two phases as mentioned below:-
Phase 1:-
a) 250 KLPD Ethanol/RS Industrial/ENA/SDS Plant Grain Based
b) 20 MW Co- Generation power plant
Phase 2:-
a) 125 KLPD Grain Based Ethanol/RS Industrial/ENA/SDS Plant
b) 125KLPD Molasses based Ethanol/RS Industrial/ENA/SDS Plant
c) 1 X 15 MW, 1 X 5 MW Co- Generation power plant
Grain will be used as a raw material in grain based operation which is easily available from the
local market. Molasses will also be used as a raw material in molasses based operation which is
available from nearby sugar mills.
As per EIA Notification dated 14th Sep., 2006 as amended from time to time; the project falls in
Category ‘A’, Project or Activity - 5(g).
TABLE – 1
SALIENT FEATURES OF THE PROJECT
S.
NO.
PARTICULARS DETAILS
A. Nature & Size of the Project
Units Capacity
PHASE I
Grain based Ethanol/RS
Industrial/ENA /Denatured Spirit
Unit
250 KLD
Co-Generation Power 20 MW
CO2 Plant 112.5 TPD
DDGS/ Cattle Feed/ Poultry Feed 150 TPD
PHASE II
Grain based Ethanol/RS 125 KLPD
Proposed installation of Unit II – 500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125
KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW,
1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Pre Feasibility Report
M/s Om Sons Marketing Private Limited 2
Industrial/ENA /Denatured Spirit
Unit
Molasses based Ethanol/RS
Industrial/ENA / Denatured Spirit
Unit
125 KLPD
Co-Generation Power 1 x 15 MW & 1x 5 MW
CO2 Plant 112.5 TPD
DDGS/ Cattle Feed/ Poultry Feed 75 TPD
B. Category of the Project As per EIA Notification dated 14th Sep., 2006 as amended from time
to time; the project falls in Category ‘A’, Project or Activity - 5(g).
C. Location Details
Village Sangat Kalan
Tehsil Bathinda
District Bathinda
State Punjab
Latitude 30˚ 03’ 47.8” N to 30˚ 04’ 03.85” N
Longitude 74˚ 51’ 15.77” E to 74˚ 51’ 31.13”” E
Toposheet No. H43116 & H43013
D. Area Details
Total Project Area 8.8 Ha (22.0 Acres)
Greenbelt/Plantation Area
(ha)
2.9 ha (~33 % of the total project area) has been proposed as Green
belt/Plantation
E. Environmental Setting Details (with approximate aerial distance & direction from project site)
1. Nearest Village Sangat Kalan (1.5 km in NW direction)
2. Nearest Town/City Bathinda City (17.5 km in NNE direction)
3. Nearest National Highway /
State Highway
NH-64 (0.5 km in South direction)
4. Nearest Railway station Sangat Mandi Railway Station (3.0 km in NW direction)
5. Nearest Airport Sri Guru Ram Dass Jee International Airport, Amritsar (180 km in
North direction)
6. National Parks, Wildlife
Sanctuaries, Biosphere
Reserves, Tiger/ Elephant
Reserves, Wildlife Corridors
etc. within 10 km radius
No National Parks, Wildlife Sanctuaries, Biosphere Reserves, Tiger/
Elephant Reserves, Wildlife Corridors etc. lies within 10 km radius of
the project site.
7. Reserved Forests (RF) /
Protected Forests (PF) etc.
within 10 Km. radius
No Reserved Forests (RF) / Protected Forests (PF) etc. lies within 10
Km. radius of the project site.
8. River / Water Body (within 10
km radius)
� Lower Lassara Nallah (0.7 km in SE direction)
� Canal (1.0 km in SSW direction)
� Sirhind Canal (5.0 km in SE direction)
F. Cost Details
1. Total Cost of the Project Rs. 566 Crores
Proposed installation of Unit II – 500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125
KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW,
1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Pre Feasibility Report
M/s Om Sons Marketing Private Limited 3
2. Cost for Environment
Management Plan
o Capital Cost - Rs. 56 Crores
o Recurring Cost - Rs. 10.0 Crores / annum
G. Basic Requirements for the project
Water Requirement (KLD) Phase I:
250 KLPD Grain Based Distillery - 2501 KLPD
Phase II:
125 KLPD Grain Based Distillery - 1027 KLPD
125 KLPD Molasses Based Distillery – 1039 KLPD
Total water requirement (500 KLPD) – 4567 KLPD
Source: Canal Water
Power Requirement (MW) 9.0 MW
Source: Proposed 40 MW Captive Power Plant & D.G. Sets- 3 x 1000
KVA (for Back-up purpose only)
Man Power Requirement 800 persons
Source: Unskilled / Semi-Skilled - Local Area; Skilled- Local & Outside
H. Working Days for Distillery 350 days/ annum
I. Product Ethanol/RS Industrial/ENA/SDS Plant
1.1 ENVIRONMENTAL MANAGEMENT PLAN FOR UNIT II
Particulars DETAILS
Air Quality Management
Possible Sources Boilers (Power Plant), Transportation vehicles, D.G. Sets etc.
Emissions � ESP will be installed with the proposed boilers.
� Adequate boiler stack height will be maintained.
� DG Sets will also have adequate stack of height as per CPCB guidelines.
� Adequate measures for Fugitive Dust Emissions will be taken.
� All the internal roads will be asphalted.
� Development of green belt around the periphery & within the premises of the plant
will help in attenuating the pollutants emitted by the plant.
Monitoring Ambient air quality and stack emission will be regularly monitored to ensure that
ambient air quality standards and suggested limits on stack emission loads would be
met honestly at all the time.
Water Management
Management � The project will be based on “Zero Effluent Discharge”.
� Fresh water requirement of the project will be met by ground water& Canal Water.
Efforts will be made to conserve as much water as possible by recycling and reuse.
� Record of wastewater returned back to process for utilization in
Fermentation/cooling tower and to gardening will be kept.
� Process condensate from MEE will be recycled back to the process for grain
dilution and cooling tower make up.
� Spent lees generation from distillation column will be recycled partly to the
columns for dilution and balance will be used for cooling tower make up.
Proposed installation of Unit II – 500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125
KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW,
1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Pre Feasibility Report
M/s Om Sons Marketing Private Limited 4
� Grain: - DWGS is dried and final product DDGS will be sold as cattle feed.
� Molasses: The spent wash from molasses will be sent to MEE for concentration and
the concentrated spent wash will be mixed with fuel and will be burnt in the
incinerator boiler.
� The waste water generated from the sanitary blocks will be disposed off via septic
tank followed by soak Pit.
Noise Management
Management � Proper maintenance, oiling and greasing of machines at regular intervals.
� PPEs like earplugs and earmuffs to the workers exposed to high noise level.
� Development of green belt/plantation for 33% of the total project area.
� Regular monitoring of noise level will be done.
� D.G sets will be provided with acoustic enclosures to control the noise level within
the prescribed limit.
Monitoring Regular monitoring of noise levels will be carried out and corrective measures in
concerned machinery will be adapted accordingly to the possible extent.
Solid Waste Management
Management � Grain Operation - Solid waste from the grain based operations generally comprises
of fibres and proteins in the form of DDGS, which will be ideally used as cattle feed.
� Molasses operation - Concentrated spent wash will be mixed with fuel and will be
burnt in the incinerator boiler.
� Ash from the boiler will be sold to brick manufacturers.
� Used oil & grease generated from plant machinery/gear boxes as hazardous waste
will be sold out to the CPCB authorized recyclers.
Green belt Development/ Plantation
Management � 33% of total project area will be developed under green belt/plantation.
� All the barren areas will be vegetated.
� Native plant species will be planted in consultation with local horticulturist.
� Green belt development along with the road & plant boundary will attenuate noise
level arrest dust and improve the environment in surrounding.
Odour Management
Management � Odour will be primarily controlled at source by good operational practices,
including physical and management control measures.
� Better housekeeping will be maintained with good hygiene condition by regular
steaming of all fermentation equipment.
� Use of efficient biocides to control bacterial contamination.
� Control of temperature during fermentation to avoid in-activation / killing of yeast.
� Avoiding staling of fermented wash.
� Regular use of bleaching powder in the drains to avoid generation of putrefying
micro-organisms.
Proposed installation of Unit II – 500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125
KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW,
1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Pre Feasibility Report
M/s Om Sons Marketing Private Limited 5
2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
(i) Identification of Project and Project Proponent
The Oasis Group has Hotels of star category at Mussoorie and Delhi under the world known
management group Carlson and brand name Country Inn & Suites by Carlson”
The group is also in luxury goods business under the brand name of “Dillano Luxurious
Jewels” which caters to the niche business class and participates in elite jewellery exhibitions
such as Wedding Asia etc.
Oasis Group, India Based Group are well known and highly reputed in the Luxury/hospitality
liquor/ business. The Group has wide distribution network for both Indian and foreign made
liquor in number of states. They have been engaged with this activity for more than 5 decades.
At present the group owned five running Distilleries, two bottling Units and expanding and
diversifying into different business at fast pace.
The Oasis Group is a highly reputed conglomerate with diverse interests that include Distillery,
Liquor Retailing, Hotels and Constructions. The Group’s rapid growth on Indian corporate
scene rests on its strong foundation of professional management and astute collective
enterprises. Over the last 15 years, the Malhotra Group has grown into a diversified
business and industrial house with a high growth rate and a total commitment to persistent
growth.
The group was founded by Shri Om Prakash Malhotra. It is his foresight and vision that has
promoted the organization to take its present shape. Its present Chairman and Director, Mr.
Deep Malhotra, a second-generation entrepreneur, carries with him rich experience coupled
with sharp commercial acumen. The Group has a team highly qualified, experienced, trusted
persons with a right mix of technocrats, Finance Experts and management professionals.
Group Companies:-
1. Country Inn & Suites By Carlson (A Unit of Diamond Resorts Pvt. Ltd.), Mussoorie
2. Oasis Resorts Pvt. Ltd., Delhi
3. Dillano Luxurious Jewels Ltd., Delhi
4. Oasis Commercial Pvt. Ltd., Haryana
5. Oasis Overseas Pvt. Ltd., Haryana
6. Malbros International Pvt. Ltd, Punjab
7. Oasis Distilleries Ltd, Indore
8. Gauravh Wines Pvt. Ltd., Punjab
9. Om Sons Marketing Pvt. Ltd, Punjab
10. Malbros Enterprises Pvt. Ltd, Delhi
Proposed installation of Unit II – 500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125
KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW,
1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Pre Feasibility Report
M/s Om Sons Marketing Private Limited 6
11. Calx Paper Pvt. Ltd, Delhi
12. Gee Emm Bros. Distributors Pvt. Ltd., Delhi
13. Vijeta Beverages Pvt. Ltd., Rajasthan
14. Gautam Wines Pvt. Ltd., Punjab
ALCOHOL MANUFACTURING: - The Alcohol Distillation Unit has been designed as per multi
pressure distillation technology which gives maximum of output which minimum of input
energy. The ENA being made at our Plant meets best industrial specifications.
(ii) Brief description of nature of the project
Om Sons Marketing Pvt. Ltd. is proposing Unit II – 500 KLPD Ethanol/RS Industrial/ENA/SDS
Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain Based and 125 KLPD Molasses
based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I) and (1x15 MW, 1x5
MW in Phase II)} in Existing Distillery Plant at Village Sangat, Tehsil & District Bathinda, Punjab.
Grain/Molasses will we used at raw material which is easily available local market/neighbour
state.
As per EIA Notification dated 14th Sep., 2006 as amended from time to time; the project falls in
Category ‘A’, Project or Activity - 5(g).
(iii) Need for the project and its importance to the country and or region
Advancement in science and technology has created so many products that have enhanced
the quality of human life in every passing year. The human race is largely dependent on
industrialization for up gradation in quality of life. Progress of the nation is judged through its
economic growth which is largely dependent on industrial productivity. In Indian economy
(which is agro based) many industries are dependent over agricultural produce for production
of luxury and need based commodities. Alcohol has assumed a very important place in the
Country’s economy. It is a vital raw material for a number of chemicals. It has been a source of
revenue by way of excise duty levied by the State Government on alcohol liquors. The use of
alcohol for the purpose of potable liquor is as high as its use for industrial purposes.
According to analysts, the Indian Ethanol industry is expected to witness accelerating growth
in coming years. Ethanol is an alcohol fuel that is added to petrol in some countries to lower
cost to the consumer, reduce consumption of oil, and lessen the environmental impact of
transportation. Mixed fuels are rated by the amount of ethanol contained; for example,
common blends are E10, which contains 10% ethanol, and E15, which contains 15% alcohol.
Another common blend is E85, also known as flex fuel, in which the ethanol ranges from 51% in
winters to 83% in summers.
Proposed installation of Unit II – 500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125
KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW,
1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Pre Feasibility Report
M/s Om Sons Marketing Private Limited 7
In addition, though ethanol reduces air particulate pollution, its production results in fairly high
greenhouse gas emissions and negates any the environmental benefit of the shift from fossil
fuel.
The biggest concern with the addition of ethanol to India's fuel supply is that it will take up
scarce land set aside for grazing and other crops to grow fuel. With the demand likely to be
huge, there is bound to be a shift in land use from food crops to fuel crops. Agriculture will
become even more intensive. Without adequate reforms and education in the agricultural
sector to increase productivity, the shift to fuel crops will result in food price inflation. The
savings from reduced oil imports will be spent instead on subsidies and higher food prices.
Furthermore, technology can improve at two ends - energy efficiency at the EV end and
greater storage capacity at the EVB end. The latter would translate into better performing
vehicles without the consumer having to regularly upgrade his EV.
In the path of company’s growth and development this proposed project will serve as yet
another milestone.
(iv) Demand- Supply Gap
Not required in this Project. This depends on Excise department.
(v) Import vs. Indigenous Production
Indian market could not meet present alcohol demand. So they import alcohol 5-7% of total
demand. As far as Ethanol production is concerned, Indian market play a vital role at both
domestic & international level. So they require produce the more alcohol to meet the demand.
(vi) Export Possibility
The possibility of alcohol export is very good. So Indian industries export alcohol in African,
Europe & Asian countries which is very profitable now days. After setup of this type of alcohol
industries government can collect more revenue.
(vii) Domestic / Export Markets
Presently the big Indian players in alcohol production and bottling are United Spirits Ltd, ABD
Pvt Ltd, Radico khaitan Ltd, Globus Spirits Ltd etc. So they try to fulfil the current requirement
of alcohol in domestic as well as export market.
(viii) Employment Generation (Direct and Indirect) due to the project
Direct and indirect employment will be generated due to the proposed project. During
construction phase, employment opportunity to approximately 1000 persons is estimated.
The total manpower requirement for the proposed project will be 800 persons (inclusive of on
roll employees and on contract employees).
Proposed installation of Unit II – 500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125
KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW,
1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Pre Feasibility Report
M/s Om Sons Marketing Private Limited 8
3.0 PROJECT DESCRIPTION
(i) Type of Project including interlinked and independent projects, if any.
No, this project is not an interlinked project.
(ii) Location (map showing general location, specific location, and project boundary &
project site layout) with coordinates
Proposed installation of Unit II – 500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125
KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW,
1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Pre Feasibility Report
M/s Om Sons Marketing Private Limited 9
Figure - 1: Location Map
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-
generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Pre Feasibility Report
M/s Om Sons Marketing Private Limited 10
(iii) Key Plan
Figure - 2: Key Plan
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 11
(iv) Details of alternative sites consideration and basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted.
No alternative site has been taken into consideration.
Following factors were considered while selecting the site:-
� Suitable source of raw material.
� Location in rural area ensures adequate availability of manpower at marginally
lower rates, compared to metro cities of India.
� Nearness to NH-64 which makes it easier to transport raw materials & Products.
� There is no National Park, Biosphere Reserves, Tiger Reserves, Reserved / Protected
Forests within 10 km radius of study area.
(v) Size or magnitude of operation
M/s Om Sons Marketing Private Limited is proposing installation of Unit II – 500 KLPD
Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain
and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW
in Phase I) & (1 x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant at Village Sangat
Kalan, Tehsil Bathinda, District Bathinda, Punjab.
The process includes basic raw material requirement, sizing of equipment, utilities &
services, infrastructure facilities & sources of waste generation, their quantity, treatment
& safe disposal of the waste.
S. No. Units Capacity
1. Ethanol/RS Industrial/ENA/SDS unit 500 KLPD
Phase 1:-
250 KLPD Grain Based Unit
Phase 2:-
a) 125 KLPD Grain Based Unit
b) 125KLPD Molasses based Unit
2. Co-Generation Power Plant 40 MW
Phase 1:- 20 MW
Phase 2:- 1 X 15 MW and 1 X 5 MW
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 12
(vi) Project Description with Process Details (a schematic diagram/flow chart showing
the project layout, components of the project etc. Should be given)
Process Description
Distillery Unit - Production from Grain:
• Grain storage
• Grain cleaning, milling and flour handling
• Slurry preparation & liquefaction
• Multi pressure alcohol distillation
• Alcohol daily receivers & bulk storage
• MEE & Dryer
MAIN PLANT & MACHINERY
1. Grain Storage :
Grains are procured from various sources, such as FCI Storage godowns through agencies
and are unloaded into large Storage Silos after Pre-Cleaning. Storage Silos are specially
designed to keep the Grains in good condition for longer durations and also avoid its
deterioration and theft, etc. It is being proposed to have 30 – 45 days of Grain Storage
facility in the Distillery.
2. Grain Cleaning, Milling and Flour Handling :
The grain is lifted in bucket elevators, screened followed by removal of stones and iron
matter. Cleaned Grains are then milled using dry milling process in Hammer Mills. The
flour is fed through the bucket elevator and conveyed to the Batch Tipping Machine
through a Screw Conveyor. The flour addition is metered through the Batch Tipping
Machine with load cell arrangement, before transferring the flour to the Slurry Tank
through another Screw Conveyor (pre-masher) for slurry preparation process. It is being
proposed to have 4 x 16 TPH as milling paraphernalia for this Distillery.
3. Slurry Preparation & Liquefaction :
Grain flour and process water is fed at controlled rate to Initial Liquefaction tank. Mixed
slurry is taken to the Initial Liquefaction Tank where additional quantity of water is added
as per requirement. Viscosity reduction Enzyme and stabilizing chemicals and a portion of
liquefying enzyme are also added at this stage. This slurry is then “cooked” in the jet
cooker.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 13
The slurry is continuously pumped to a steam jet cooker where high-pressure steam
rapidly raises the slurry temperature. The mixture of slurry and steam is then passed
through the Retention Vessel. The retention vessel has sufficient capacity to provide the
desired retention time at a given flow rate. The cooked mash is discharged to a Flash
Tank.
The cooking process, accomplished in the above manner, converts the slurry into a
hydrated, sterilized suspension and is therefore susceptible to enzyme attack for
liquefaction.
The gelatinized mash from the Flash Tank is liquefied in the Final Liquefaction Tank where
liquefying enzyme (alpha-amylase) is added. The liquefied mash is cooled in Mash Cooler
and transferred to Saccharification cum fermentation section. This process initiates the
formation of sugar.
The gelatinized mash from the Flash Tank is liquefied in the Final Liquefaction Tank where
liquefying enzyme (alpha-amylase) is added. The liquefied mash is cooled in Mash Cooler
and transferred to Saccharification cum Fermentation section.
4. Hiferm-Nm Saccharification and Instantaneous Fermentation:
Yeast Activation:
Yeast seed material is prepared in water-cooled Yeast Activation Vessel by inoculating
sterilized mash with Active Dry Yeast. Optimum temperature is maintained by cooling
water. The contents of the Yeast Activation Vessel are then transferred to Fermenter.
Saccharification & Instantaneous Fermentation:
The Liquefied starch slurry comprising Dextrins is partly taken for Yeast development in
Yeast Activation vessel and majorly transferred into the Fermenter. Amyloglucozydase
and other nutrient Enzymes are first added to Saccharify the Starch Slurry causing
formation of Sugars. Immediately, the Active Yeast is introduced in the system for
simultaneous Fermentation. The process of fermentation is to convert the fermentable
substrate into alcohol. To prepare the mash for fermentation, it may have to be diluted
with water. The pH of the mash is adjusted by the addition of acid. Yeast is available in
sufficient quantity to initiate fermentation rapidly and complete it within the cycle time.
At the start of the cycle, the fermenter is charged with mash and contents of the Yeast
Activation Vessel. Significant heat release takes place during fermentation. This is
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 14
removed by passing cooling water through the Fermenter PHE’s to maintain an optimum
temperature. The recirculating pumps also serve to empty the fermenters into Beer Well.
After the fermenters are emptied, they are cleaned with water and caustic solutions and
sterilized for the next batch. The carbon dioxide evolved during the process is vented to
atmosphere after recovery of alcohol in a scrubber.
5. Ethannol Distillation :
Fermented wash from wash holding tank T-01 is pumped by wash feed pump P-01 to the
top of degassing column (C-2) after preheating the same in beer heater E-02 and spent
wash heat exchanger E-01. The vapors along with non-condensable gases from the top of
degassing column (C-02) are rectified in Heads column (C-03), to expel the high volatiles,
technically known as heads. Bottom liquid from the degasser flows into analyzer column
(C-01) where alcohol is stripped from the liquid. The liquid from bottom of analyzer
column (C-01) is completely stripped of alcohol and is pumped out by thick slop discharge
pump P-02 through heat exchanger E-01 where it preheats the fermented wash before it
enters degassing column. The slop from the analyser column will be feed in to
decanter.The dilute alcohol vapors from near the top of analyzer column (C-01) are
condensed first in beer heater (E-02) while exchanging heat with wash feed and then in
analyzer condenser (E-03). Degasser and analyzer operate under vacuum. The
condensate from E-02 and E-03 is collected in Rectifier Feed Tank V-02. The vapors for
stripping alcohol are generated from analyzer column bottom liquid in the analyzer
column re-boiler (E-04) by using the rectified column top vapors, as discussed
subsequently.
Vapors from the top of heads column (C-03) are condensed in heads column condenser
(E-06) and then in head column vent condenser (E-07). Part of the condensate is returned
to column C-03 as reflux while a small portion is taken out as an impure spirit cut. Liquid
from bottom of C-03 is also taken into Rectified feed tank V-02.
Dilute alcohol water mixture from rectifier feed tank (V-02) are pumped by rectifier feed
pump (P-04) through rectifier feed pre-heater E-11 in to rectifying column (C-04). Rectifier
and its associated equipment work under pressure so that these vapors can supply the
necessary heat for generating the vapors.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 15
The condensate from E-04 is then pumped as Reflux to rectifying column C-04. Rich
alcohol vapors at a concentration of 95.5% v/v from top of rectifying column (C-04) are
condensed first in Analyzer (E-04) and then in Reflux Vent Condenser (E-05). The liquid
from E04 and E-05 are collected in Rectifier Reflux Tank (V-01). Part of the liquid from E-
05 may be drawn off as impure spirit. The impure spirit cut will be maintained as little as
possible to maintain aldehyde levels to meet the required limits in Absolute Alcohol.
Liquid from the reflux tank (V-01) is pumped by Product Pump (P-03) partly as product
and partly as reflux to the top of the Rectifying Column (C-04). The necessary rectifying
vapors to C-04 are generated by boiling the C-04 bottom liquid in Rectifier Column Re-
boiler E-08 using medium pressure steam. Some side streams are drawn from rectifier
column as light and heavy fractions of higher alcohols called fusel oils and cooled in fusel
oil coolers E-09 and E-10 and are mixed with water and allowed to separate out in fuel oil
separator F-01. All vents from E-03, E-07, V-02 and E-05 are connected to Vent Gas
Absorber (C-05) where the vent gases are scrubbed with water to recover entrained
alcohol. The scrubber water is used for washing the fuel oils in fuel oil separator to
recover alcohol from the fuel oil fractions. The absorber vent is connected to vacuum
pump (G-01) which is used to create vacuum in the analyzer and degasser.
Absolute alcohol is manufactured by dehydration of Rectified Spirit. The process adopted
here is based on Pressure Swing Adsorption (PSA) system using Molecular Sieves (3-A).
The flow scheme is shown in above referred flow diagram.
Rectified spirit, after preheating by waste hot streams, is vaporized and superheated in E-
03 and E-04 by using medium pressure steam at 6 Kg/cm2g pressure. Hot vapors at
kg/cm² g pressure and 130° C temperature pass through PSA column S-01A/S-01B where
the water vapors are retained while water free alcohol is released as vapors. The vapors
are condensed in E-07 and E-08 and collected as Absolute Alcohol. When the molecular
sieve bed is saturated with water the alcohol vapors are shifted to the other tower and
the first tower is taken for regeneration. Regeneration is done first by pressure releasing
and creating vacuum and then by elutriating with dehydrated alcohol vapors from the
tower in dehydration operation. The vapors are condensed in E-06 and E-05 and the vent
vapors are recovered through scrubber C-02. Vacuum can be created vacuum by P-04.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 16
(Eductor may also be considered for this duty). Product is cooled in E-09 and transferred
to Absolute Alcohol receiving tank and then on to storage tank.
6. Alcohol Daily Receivers & Bulk Storage :
Alcohol is first taken to Daily receiver storage tanks, which is based on the State Excise
laws, storage for three days considering the weekly holidays of two days. Thereafter, the
alcohol is transferred to Bulk Storage Tanks after taking the daily receiver Dip. This is
transferred using flameproof pumps. Final dispatch of alcohol is metered and again is
carried out using special flameproof pumps. The Bulk Spirit Storage is proposed to be set
up for 30 days.
EFFLUENT HANDLING SECTION
1. Decantation Section:
Decantation section comprises of Centrifuge Decanters, operating at high rpm which are
used for separation of suspended solids from Spent Slops coming out of Distillation
section. The Wet cake thus separated has 30-35% w/w solids, as removed from bottom of
Decanters. This is directly loaded on the trolleys parked below. Thin slops coming out of
Decanter are collected in a tank and are transferred for part recycle & further for
Evaporation into thick syrup.
2. Integrated Evaporation Section:
The suggested treatment scheme is a 2 FF + Finisher Evaporation Plant for Thin Slops
Evaporation. The following points will elucidate the basic working principle:
� Shell & Tube type Evaporators with highly efficient liquid distributor working on the
principle of Falling Film Evaporation have been used, with Plate type Preheaters for
preheating of FEED stream which serves the purpose of energy conservation.
� Analyzer vapour is fed to the first effect evaporator shell side at the given pressure
and temperature as the heating medium.
� The Feed from the Feed balance tank is taken to the PHCOND to make the best
heat recovery.
� The Feed after getting heated to the predetermined temperature in preheater is
fed from the first effect evaporator which is Falling Film Evaporator -1
� The flow path is given below.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 17
INLET FEED - pH cond – E1 – E2 – OUTLET PRODUCT
� Vapours generated in 1st effect VLS (Vapour Liquid Separator) are used as heat
source in the 2nd effect.
� The product at the desired concentration of TS is obtained at the outlet of the
second effect, which is a Falling Film evaporator.
� A Shell & tube type Multi-pass Surface condenser is employed for condensing the
shell side vapours.
� The Pure and the process condensate are collected in receiving vessels.
� Highly efficient operating pumps will be provided for pumping the required fluid.
� The operation of the plant will be under vacuum. Vacuum is created with the help
of a water ring vacuum pump.
� The plant will have high level of automation to get consistent output at required
concentration.
� The system operates under vacuum. Water-ring vacuum pumps are used to
maintain a desired vacuum.
� Cooling water from cooling tower is used in the surface condensers for condensing
the vapours.
CONCLUSION
The thick syrup thus obtained is mixed with the Wet Cake obtained from Decanter
Centrifuges using specially designed Ribbon type mixer and this enriches the protein
content in the fibrous suspended solids separated earlier in Decanter. This Protein & Fibre
rich DWGS is directly sellable as Cattle / Poultry Feed. However, in order to increase the
shelf life of such by-product, it is necessary to dry the product, with minimum possible
moisture content.
SYSTEM DESCRIPTION FOR DWGS DRYER
Wet distiller’s grains shall be fed into the dryer housing at controlled rate through a
suitable feeding system. The Rotary Tube Bundle is enclosed in an insulated dryer housing
and on its outer flights is fixed. Dry saturated steam is to be supplied to the tube bundle
through rotary joint at one end & the condensate is discharged through rotary joint
mounted at other end.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 18
During the course of rotation, these flights pick up the material and shower them on to
the tube bundles. The heat transfer is primarily by conduction. The water vapours are
exhausted through an Exhaust Blower & passed through a cyclone separator for
separating fines.
Dry product partially recycled back to Feed conditioner for feed conditioning through
Product Screw & Recycle Conveyor.
Entire operation of the Dryer is controlled through Control panel.
SYSTEM DESCRIPTION FOR COOLING & CONVEYING
� DWGS below product screw is discharged into charging hopper of pneumatic
conveying system.
� Rotary feeder feeds it into the conveying line.
� Ambient air is used for conveying.
� The material gets conveyed to product collector & discharged from rotary
discharge valve.
� Exhaust air is vented to atmosphere.
� The conveying system is lean phase suction type, using centrifugal blower as prime
mover. The conveying air quantity is designed considering cooling requirement & to
cool the product before discharge.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 19
Figure - 3: Process flow chart For Grain Based Distillery
FOR MOLASSES BASED OPERATION
i) Molasses Unloading and Storage
Molasses from tankers will be unloaded at unloading point and transfer in to
molasses storage tank.
ii) Hiferm-Nm Saccharification and Instantaneous Fermentation:
Yeast Activation:
Yeast seed material is prepared in water-cooled Yeast Activation Vessel by inoculating
sterilized mash with Active Dry Yeast. Optimum temperature is maintained by cooling
water. The contents of the Yeast Activation Vessel are then transferred to Fermenter.
Fermentation:
The Molasses from storage tank to be pumped to Dilutor installed in Fermentation
section and diluted with water. The diluted Molasses called Wort will be feed into Pre
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 20
Fermenter for activation of Yeast. The activated yeast from the Yeast activation vessel
transfer into pre fermenter.
Once the yeast activated in Pre fermenters it will be transfer in to fermenters and diluted
molasses to be add The process of fermentation is to convert the fermentable substrate
into alcohol. The pH of the wort is adjusted by the addition of acid. Yeast is available in
sufficient quantity to initiate fermentation rapidly and complete it within the cycle time.
At the start of the cycle, the fermenter is charged with wort and contents of the Yeast
Activation Vessel. Significant heat release takes place during fermentation. This is
removed by passing cooling water through the Fermenter PHE’s to maintain an optimum
temperature. The recirculating pumps also serve to empty the fermenters into Beer Well.
After the fermenters are emptied, they are cleaned with water and caustic solutions and
sterilized for the next batch. The carbon dioxide evolved during the process is vented to
atmosphere after recovery of alcohol in a scrubber.
iii) Ethanol Distillation:
Fermented wash from wash holding tank T-01 is pumped by wash feed pump P-01 to the
top of degassing column (C-2) after preheating the same in beer heater E-02 and spent
wash heat exchanger E-01. The vapours along with non-condensable gases from the top
of degassing column (C-02) are rectified in Heads column (C-03), to expel the high
volatiles, technically known as heads. Bottom liquid from the degasser flows into analyzer
column (C-01) where alcohol is stripped from the liquid. The liquid from bottom of
analyzer column (C-01) is completely stripped of alcohol and is pumped out by thick slop
discharge pump P-02 through heat exchanger E-01 where it preheats the fermented wash
before it enters degassing column. The slop from the analyser column will be feed in to
decanter. The dilute alcohol vapours from near the top of analyzer column (C-01) are
condensed first in beer heater (E-02) while exchanging heat with wash feed and then in
analyzer condenser (E-03). Degasser and analyzer operate under vacuum. The
condensate from E-02 and E-03 is collected in Rectifier Feed Tank V-02. The vapours for
stripping alcohol are generated from analyzer column bottom liquid in the analyzer
column re-boiler (E-04) by using the rectified column top vapours, as discussed
subsequently.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 21
Vapours from the top of heads column (C-03) are condensed in heads column condenser
(E-06) and then in head column vent condenser (E-07). Part of the condensate is returned
to column C-03 as reflux while a small portion is taken out as an impure spirit cut. Liquid
from bottom of C-03 is also taken into Rectified feed tank V-02.
Dilute alcohol water mixture from rectifier feed tank (V-02) are pumped by rectifier feed
pump (P-04) through rectifier feed pre-heater E-11 in to rectifying column (C-04). Rectifier
and its associated equipment work under pressure so that these vapours can supply the
necessary heat for generating the vapours.
The condensate from E-04 is then pumped as Reflux to rectifying column C-04. Rich
alcohol vapors at a concentration of 95.5% v/v from top of rectifying column (C-04) are
condensed first in Analyzer (E-04) and then in Reflux Vent Condenser (E-05). The liquid
from E- 04 and E- 05 are collected in Rectifier Reflux Tank (V-01). Part of the liquid from E-
05 may be drawn off as impure spirit. The impure spirit cut will be maintained as little as
possible to maintain aldehyde levels to meet the required limits in Absolute Alcohol.
Liquid from the reflux tank (V-01) is pumped by Product Pump (P-03) partly as product
and partly as reflux to the top of the Rectifying Column (C-04). The necessary rectifying
vapours to C-04 are generated by boiling the C-04 bottom liquid in Rectifier Column Re-
boiler E-08 using medium pressure steam. Some side streams are drawn from rectifier
column as light and heavy fractions of higher alcohols called fusel oils and cooled in fusel
oil coolers E-09 and E-10 and are mixed with water and allowed to separate out in fuel oil
separator F-01. All vents from E-03, E-07, V-02 and E-05 are connected to Vent Gas
Absorber (C-05) where the vent gases are scrubbed with water to recover entrained
alcohol. The scrubber water is used for washing the fuel oils in fuel oil separator to
recover alcohol from the fuel oil fractions. The absorber vent is connected to vacuum
pump (G-01) which is used to create vacuum in the analyzer and degasser.
Absolute alcohol is manufactured by dehydration of Rectified Spirit. The process adopted
here is based on Pressure Swing Adsorption (PSA) system using Molecular Sieves (3-A).
The flow scheme is shown in above referred flow diagram.
Rectified spirit, after preheating by waste hot streams, is vaporized and superheated in E-
03 and E-04 by using medium pressure steam at 6 Kg/cm2g pressure. Hot vapours at
kg/cm² g pressure and 130° C temperature pass through PSA column S-01A/S-01B where
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 22
the water vapours are retained while water free alcohol is released as vapours. The
vapours are condensed in E-07 and E-08 and collected as Absolute Alcohol. When the
molecular sieve bed is saturated with water the alcohol vapours are shifted to the other
tower and the first tower is taken for regeneration. Regeneration is done first by pressure
releasing and creating vacuum and then by elutriating with dehydrated alcohol vapours
from the tower in dehydration operation. The vapours are condensed in E-06 and E-05
and the vent vapours are recovered through scrubber C-02. Vacuum can be created
vacuum by P-04. (Educator may also be considered for this duty). Product is cooled in E-
09 and transferred to Absolute Alcohol receiving tank and then on to storage tank.
iv) Alcohol Daily Receivers & Bulk Storage:
Alcohol is first taken to Daily receiver storage tanks, which is based on the State Excise
laws, storage for three days considering the weekly holidays of two days. Thereafter, the
alcohol is transferred to Bulk Storage Tanks after taking the daily receiver Dip. This is
transferred using flameproof pumps. Final dispatch of alcohol is metered and again is
carried out using special flameproof pumps. The Bulk Spirit Storage is proposed to be set
up for 30 days.
B) EFFLUENT HANDLING SECTION
i) Evaporation Section:
The spent wash coming from Distillation section will be fed in to first calendria of the
evaporator section. There will be five calendria will be installed as per design to
concentrate the dissolved solids .suggested treatment scheme is a four FF + Finisher
Evaporation Plant for spent wash Evaporation. The following points will elucidate the
basic working principle:
� Shell & Tube type Evaporators with highly efficient liquid distributor working on
the principle of Falling Film Evaporation have been used, with Plate type
Preheaters for preheating of FEED stream which serves the purpose of energy
conservation.
� Analyzer vapour is fed to the first effect evaporator shell side at the given
pressure and temperature as the heating medium.
� The Feed from the Feed balance tank is taken to to make the best heat recovery.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 23
� The Feed after getting heated to the predetermined temperature in preheater is
fed from the first effect evaporator which is Falling Film Evaporator -1
� Vapours generated in 1st effect VLS (Vapour Liquid Separator) are used as heat
source in the 2nd effect. and from 2nd to third and so on.
� The product at the desired concentration of TS is obtained at the outlet from the
final effect,
� A Shell & tube type Multi-pass Surface condenser is employed for condensing the
shell side vapours.
� The Pure and the process condensate are collected in receiving vessels.
� Highly efficient operating pumps will be provided for pumping the required fluid.
� The operation of the plant will be under vacuum. Vacuum is created with the help
of a water ring vacuum pump.
� The plant will have high level of automation to get consistent output at required
concentration.
� The system operates under vacuum. Water-ring vacuum pumps are used to
maintain a desired vacuum.
� Cooling water from cooling tower is used in the surface condensers for
condensing the vapours.
ii) Incinerator boiler:
The concentrated effluent is mixed with bagasse/coal and dried in a Rotary Dryer to
generate mixed fuel. This mixed fuel/biogas is burnt in Incinerator boiler of 40 TPH to
generate high pressure steam
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 24
Figure - 4: Process flow diagram of Molasses Based Distillery
Power Co-generation 40 MW {(20 MW in Phase I) and (1x15 MW, 1x5MW in Phase II)}
The unit proposes to set-up boiler and power turbine. 1 Nos. x 100 TPH, 1 x 60TPH Boilers
for Coal/Rice Husk/Pet Coke/ Biomass/Natural Gas as available fuel options and 1x40TPH
Boiler cum Incinerator will be installed for slop as available fuel options. This Boiler will
operate mainly to feed steam to grain based / molasses based operations and {40 MW (20
MW in Phase I) and (1x15 MW, 1x5MW in Phase II)} power generations from Turbine.
Proposed {40 MW (20 MW in Phase I) and (1x15 MW, 1x5MW in Phase II)} co-generation
plant consists of a high pressure water tube steam boiler extraction cum condensing
steam turbine. Fuel in the steam boiler will be burnt with the help of air in the boiler
furnace. Water will be circulated in the boiler drum and tubes thus getting heated by the
flame burning in the boiler furnace. Water comes out of the boiler drum located at the
top of the boiler as steam. Flue gases rise in the boiler furnace and come in contact with
the steam coming out of boiler drum. Steam after coming in contact with flue gases gets
heated up further thus getting superheated. Super-heated steam leaves the boiler in a
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 25
pipe. Flue gases after super heating the steam pass through economizer where they pre-
heat the boiler feed water before it enters the boiler drum. After economizer, flue gases
pass through air pre-heaters where they heat the air which is fed to the boiler furnace for
burning the fuel. After air pre heaters flue gases pass through ESP where the dust
particles are collected. The dust is collected from here.
High pressure superheated steam from boiler is passed through a steam turbine, which is
used for distillery process operations. While passing through the turbine, the high
pressure and temperature steam rotates the turbine rotor and an electric alternator
mounted on the same shaft. Electric power is generated by the alternator. This electric
power generated is consumed in house i.e. for running the distillery and utilities like
boilers auxiliaries etc.
Figure 5: Process flow chart for Co-generation Power Plant
(vii) Raw material required along with estimated quantity, likely source, marketing
area of final products, mode of transport of raw material and finished product.
(a) Raw Material Requirements
The raw materials required for the distillery can be broadly categorized as follows:
• Grain & Molasses
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 26
• Enzymes & Chemicals
• Steam
• Fuel
• Power, etc.
The basic raw material for the manufacturing will be Grain & Molasses. In the present
scenario, grains with different starch content are used like damaged grain feed stock,
nakku kinki, maize, bajra, sorghum, barley etc. The process requires the above grains to
be milled into specific flour size. Small quantity of sulphuric acid is sometimes required.
The raw material for the boiler fuel will be Coal, Rice Husk, Pet Coke, Bio Mass, Natural
Gas etc.
Table 2
RAW MATERIAL REQUIREMENT FOR GRAIN BASED DISTILLERY
S.
No.
Particular Requirements Source of the Raw
Material & Mode of
Transportation
1. Grain
(Damaged grain feed stock, nakku kinki,
maize, bajra, sorghum, barley etc.)
900-1000 TPD Nearby area and
states, by road or
Railway
2. Molasses 500-600 TPD Nearby Sugar Mills
3. Chemicals Quantity (TPD)
Sodium Hydroxide (Caustic) 2.0
Enzymes 1.0
Nutrients 2.0 – 3.0
Antifoam Agent 0.5 – 0.6
Yeast (Active Dry Yeast/Distiller’s Yeast 0.25 – 0.35
(b) Fuel Requirement
Table 3
RAW MATERIAL REQUIREMENT FOR GRAIN BASED DISTILLERY
Name of Raw Material Quantity (MT per day) Mode of transportation
Coal, Pet Coke 500-750 TPD By Railway
Rice Husk, Bio Mass 1000-1200 TPD Nearby Road
Slop From Molasses
Evaporator
300-350TPD@55-60%
Solids Pipe Line
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 27
(viii) Resources optimization/ recycling and reuse envisaged in the project, if any, should
be briefly outlined.
Water as a resource will be recycled at each possible step of the process and latest
technology and methodology will be adopted to conserve and reuse the resources.
(ix) Availability of water it’s source, energy /power requirement and source should be
given.
(a) Water Requirement and Source
The total fresh water requirement for this proposed project will be 4567 m3/day.
Source of Water: Canal Water.
Phase Mode of Operation and capacity Total Fresh
water
Phase I 250 KLPD Grain Based Distillery 2501
Phase II 125 KLPD Grain Based operation 1027
125 KLPD Molasses Based Operation 1039
Total 4567
Phase I - Water Requirement for Grain Based Operation - 250 KLPD
The total water requirement for the Grain based (250 KLPD Operation Phase I)
process is estimated at 2501 KLPD, worked out as per details given below:
TABLE - 4 (A) Total Water Input
S. No. Section Water Quantity (KLD)
1. Process water in Liqn 801
2. Boiler feed water 2287
3. DM water for Distillation 275
4. Soft water for Cooling Tower 2250
5. Soft water Distillation 325
6. Soft water pumps sealing 63
7. Fermenter washing 70
8. Floor washing 109
9. Domestic consumption 25
Total 6206
TABLE - 4 (B)
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 28
Total Water Output
S. No. Section Water Quantity (KLD)
1. Steam condensate 1309
2. Spent lees PR 313
3. Spent lees Rectifer 275
4. Spent wash (Grain slops) 402
5. Water in DDGS Dryer 425
6. CT Evaporation & Drift Losses 2250
7. Pump Sealing 63
8. Process Condensate 1012
9. Boiler Blow down 38
10. DM Plant Regeneration 120
Total 6206
TABLE - 4 (C) Total Water Recycle
S. No. Section Water Quantity (KLD)
1 Steam Condensate 1309
2 Thin Slops 402
3 R/E to Distillation 234
4 PR Lees to Fermentation 70
5 Pump Sealing 63
6 Boiler Blow down 38
7 Process Condensate 1012
8 Floor Washing 109
9 Prec Lees to CT 133
10 R/E to Less to CT 41
11 CT Blow down 174
12 DM Plant Regeneration 120
Total Recycling / Reutilization of water per day 3705
TOTAL FRESH WATER INPUT 2501
Hence, fresh water Requirement is 2501 KLPD. Water requirement for first run
would be 6206 KLPD.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 29
Figure – 6: Water balance Diagram 250 KLPD Grain Based Distillery
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 30
Phase II - Water Requirement for Grain Based Operation - 125 KLPD
The total water requirement for the Grain based (125 KLPD Operation Phase II)
process is estimated at 1027 KLPD, worked out as per details given below:
TABLE - 5 (A)
Total Water Input
S. No. Section Water Quantity (KLD)
1. Process water in Liqn 397
2. Boiler feed water 1139
3. DM water for Distillation 138
4. Soft water for Cooling Tower 938
5. Soft water Distillation 163
6. Soft water pumps sealing 31
7. Fermenter washing 39
8. Floor washing 55
9. Domestic consumption 6
Total 2904
TABLE - 5 (B)
Total Water Output
S. No. Section Water Quantity (KLD)
1. Steam condensate 676
2. Spent lees PR 156
3. Spent lees Rectifer 138
4. Spent wash (Grain slops) 201
5. Water in DDGS Dryer 189
6. CT Evaporation & Drift Losses 938
7. Pump Sealing 31
8. Process Condensate 506
9. Boiler Blow down 19
10. DM Plant Regeneration 50
Total 2904
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 31
TABLE - 5 (C)
Total Water Recycle
S. No. Section Water Quantity (KLD)
1 Steam Condensate 673
2 Thin Slops 201
3 R/E to Distillation 117
4 PR Lees to Fermentation 39
5 Pump Sealing 31
6 Boiler Blow down 19
7 Process Condensate 506
8 Floor Washing 55
9 Prec Lees to CT 63
10 R/E to Less to CT 21
11 CT Blow down 100
12 DM Plant Regeneration 50
Total Recycling / Reutilization of water per day 1877
TOTAL FRESH WATER INPUT 1027
Hence, fresh water Requirement is 1027 KLPD. Water requirement for first run
would be 2904 KLPD.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 32
Figure – 7: Water balance Diagram 125 KLPD Grain Based Distillery
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) &
(125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1
x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 33
Phase II - Water Requirement for Molasses Based Operation - 125 KLPD
The total water requirement for the Molasses based (125 KLPD Operation Phase II)
process is estimated at 1039 KLPD, worked out as per details given below:
TABLE - 6 (A) Total Water Input
S. No. Section Water Quantity (KLD)
1. Process water in Fermentation 798
2. Boiler feed water 731
3. DM water for Distillation 313
4. Soft water for Cooling Tower 1125
5. Soft water Distillation 200
6. Soft water pumps sealing 88
7. Fermenter washing 28
8. Floor washing 159
9. Domestic consumption 13
Total 3454
TABLE - 6 (B) Total Water Output
S. No. Section Water Quantity (KLD)
1. Steam condensate 453
2. Spent lees PR 188
3. Spent lees Rectifer 256
4. DM Plant Regeneration 50
5. CT Evaporation & Drift Losses 1125
6. Pump Sealing 88
7. Process Condensate 1280
8. Boiler Blow down 15
Total 3454
TABLE - 6 (C) Total Water Recycle
S. No. Section Water Quantity (KLD)
1 Steam Condensate 453
2 R/E to Distillation 256
3 PR Lees to Fermentation 28
4 Pump Sealing 38
5 Boiler Blow down 15
6 Process Condensate 1280
7 Floor Washing 159
8 R/E to Less to Treatment Plant 56
9 CT Blow down 80
10 DM Plant Regeneration 50
Total Recycling / Reutilization of water per day 2415
TOTAL FRESH WATER INPUT 1039
Hence, fresh water Requirement is 1039 KLPD. Water requirement for first run would be 3454 KLPD.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain and 125 KLPD Molasses Based in Phase II)} & 40 MW
Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW, 1 x 5 MW in Phase II)} in Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 34
Figure – 8: Water balance Diagram 125 KLPD Molasses Based Distillery
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain and
125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW, 1 x 5 MW in Phase II)} in
Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 35
(b) Power Requirement and Source
The total power requirement for proposed project will be 9 MW, which will be
sourced from own proposed 40 MW cogeneration power plant.
(c) Steam Requirement
Steam requirement is 155.32 TPH, which will be sourced from proposed boilers
(100TPH X 1 no, 60TPH X 1 no, and 40TPH X 1 no).
TABLE – 7 (A)
STEAM REQUIREMENT FOR GRAIN BASED DISTILLERY (250 KLPD & 125 KLPD)
S. No. Purpose Steam Requirement (TPH)
250 KLPD Mode
Steam Requirement (TPH)
125 KLPD Mode
1. Cooking & Liquefaction 8.0 4.0
2. Multi-pressure Distillation 32.60 16.30
3. Evaporation (Integrated) 3.2 1.6
4. DWGS Drier (DDGS) 36.0 18.0
5. Boiler De-aeration & HP
Heater 5.2
3.1
Total 85 43
TABLE – 7 (B)
STEAM REQUIREMENT FOR MOLASSES BASED DISTILLERY
S. No. Purpose Steam Requirement (TPH)
1. Vessels Sterilisation 1.30
2. Multi-pressure Distillation 16.66
3. Evaporation (Integrated) 7.80
4. Boiler De-aeration 1.56
Total 27.32
Boiler Details
(100TPH X 1 no, 60TPH X 1 No) Boilers and 40TPH X 1 No Boiler cum Incinerator with ESP as APCE
will be sufficient to meet the requirements. Others details regarding this are mentioned in the
table given below:
TABLE – 8 (A)
BOILER DETAILS
S. No. Details
1. Type of Fuel Coal , Rice Husk , Pet Coke , Bio Mass,
Natural Gas etc
2. Capacity of Boiler (100TPH X 1 no, 60TPHX 1 No)
3. Stack Height 63 MTS
4. Pollution Control Equipment Measures ESP
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain and
125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW, 1 x 5 MW in Phase II)} in
Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 36
TABLE – 8 (B)
BOILER Cum INCINERATOR DETAILS
S. No. Details
1. Type of Fuel Slop From Molasses Evaporator with
supporting fuel of Rice husk/ Coal
2. Capacity of Boiler 40 TPH
3. Stack Height As per CPCB Guidelines
4. Pollution Control
Equipment Measures ESP
Details regarding the D.G. Sets
3 D.G. sets of 1000 KVA will be installed for the power backup. Details regarding the D.G. Sets are
mentioned in the table given below:
TABLE – 9
DETAILS REGARDING THE D.G.SETS
S. No. Details
1. Type of Fuel HSD
2. Capacity 3 X 1000 KVA
3. Stack Height (above roof level) As per CPCB/SPCB norms
4. Pollution Control Equipment Measures Adequate stack height/ Acoustic
(x) Quantity of waste to be generated (liquid and solid) and scheme for their
management/disposal
o The proposed project is based on “ZERO EFFLUENT DISCHARGE”.
Molasses Based Operation:-
o Efforts will be made to conserve as much water as possible by recycling and reuse.
o Spent wash generated during Molasses operation, would be concentrated in Multi-
effect evaporator and then used as fuel in boiler.
o Record of wastewater returned back to process for utilization in
Fermentation/cooling tower and to gardening will be kept.
o Process condensate from MEE will be treated and recycled back in the process.
Grain Based Operation:-
o The proposed project will be based on “ZERO EFFLUENT DISCHARGE”.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain and
125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW, 1 x 5 MW in Phase II)} in
Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 37
o Grain Slops (Spent Wash) will be taken through Centrifuge Decanters for separation
of Suspended Solids separated as Wet Cake.
o Thin Slops from the Decanter Centrifuge will be partly recycled back to process (30-
35%) and partly taken to Thins Slops Evaporation Plant for concentration of
remaining solids to form a Syrup. This Syrup is mixed with the Wet Cake coming out
of Decanter Centrifuge and forms part of Cattle Feed. (Also known as Distillers Wet
Grain Solubles - Collectively known as DWGS).
o DWGS is taken to a dryer operating on steam and is dried to make it DDGS –
Distillers Dried Grain Solubles.
o The process condensate is cooled and collected into a neutralization tank with
sufficient residence time. After Neutralization, this process condensate will be
recycled into process and is used for green belt development within the complex.
o Solid waste from the Grain based operations generally comprises of Fibres and
proteins in the form of DDGS, which will be ideally used as Cattle Feed.
o Ash from the Boiler will be sold to Brick manufacturers.
o Yeast sludge will be sent to the Sludge Drying Beds or may be added to the Wet
Cake.
o Used oil & grease generated from plant machinery / Gear boxes & D.G. Set will be
partly used in oiling & greasing as lubrication of external parts of machinery &
partly will be sold to the CPCB authorized recycler.
4.0 SITE ANALYSIS
(i) Connectivity
The project site is well connected to National Highway NH-64 (~0.5 km in South
direction). The nearest railway station is Sangat Mandi Railway Station (~ 3 km in
NW direction), nearest city is Nathinda (17.5 km in NNE direction) and nearest
airport is Sri Guru Ram Dass Jee International Airport, Amritsar (~ 180 km in North
direction).
The site is suitably located with respect to availability of raw material, water, road
network, skilled/semi skilled/unskilled and professional manpower etc. All
communication facilities such as telephone, telefax & internet are available in the
vicinity of the project site.
(ii) Land from Land use and Land ownership Total land requirement for the proposed
project is 8.8 Ha (22.0 Acre) and has been completely acquired by Om Sons
Marketing Private Limited.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain and
125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW, 1 x 5 MW in Phase II)} in
Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 38
(iii) Topography
Topography of the core zone for the project is almost flat.
(iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies
(including area under CRZ)), shortest distances from the periphery of the project
to periphery of the forests, national park, wild life sanctuary, eco sensitive areas,
water bodies (distance from the HFL of the river), CRZ. In case of notified
industrial area, a copy of the Gazette notification should be given
TABLE – 10
Environmental Settings of the Area
S.
NO. PARTICULARS
DETAILS
(with approximate aerial distance & direction from project
site)
1. Nearest Village Sangat Kalan (1.5 km in NW direction)
2. Nearest Town/City Bathinda City (Approx. 17.5 km in NNE direction)
3. Nearest National Highway /
State Highway
NH-64 (Approx. 0.5 km in South direction)
4. Nearest Railway station Sangat Mandi Railway Station (3.0 km in NW direction)
5. Nearest Airport Sri Guru Ram Dass Jee International Airport, Amritsar (~ 180 km
in North direction)
6. National Parks, Wild Life
Sanctuaries, Biosphere
Reserves, Tiger/ Elephant
Reserves, Wildlife Corridors
etc. within 10 km radius
No National Parks, Wild Life Sanctuaries, Biosphere Reserves,
Tiger/ Elephant Reserves, Wildlife Corridors etc. lies within 10
km radius of the project site.
7. Reserved Forests (RF) /
Protected Forests (PF) etc.
within 10 Km. radius
No Reserved Forests (RF) / Protected Forests (PF) etc. lies
within 10 Km. radius of the project site.
8. River / Water Body (within 10
km radius)
� Lower Lassara Nallah (0.7 km in SE direction)
� Canal (1.0 km in SSW direction)
� Sirhind Canal (5 km in SE direction)
(v) Existing Infrastructure
Proposed installation will be done within the existing 120 KLPD Grain based Distillery.
(vi) Soil classification
The district has two types of soils, the arid brown soils and siezoram soils. The arid brown
soils are calcareous in nature; these soils are imperfectly to moderately drain. Salinity and
alkalinity are the principal problems of this soil. In siezoram soils the accumulation of
calcium carbonate is in amorphous or concretionary form (kankar). Presence of high
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain and
125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW, 1 x 5 MW in Phase II)} in
Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 39
amount of calcium carbonate and poor fertility is the main problem of this soil. The arid
brown soils are found in mostly eastern parts of the district and siezoram soils are found
in the western part of the district.
(vii) Climatic data from secondary sources
The climate of the district can be classified as tropical desert, arid and hot. The area
receives about 389 mm annual normal rainfalls which is unevenly distributed over the
area in 23 days, out of which about 79% occurs during south west monsoon. Rain fall in
the district decreases from north east to south west. The district lies in the South-
western region of the State and in far away from the Shivalik ranges in the North of the
state. It is the nearest to the Thar Desert of Rajasthan and also far away from the Major
rivers lines that run through the state. Therefore, climatically, the district has a very hot in
summer and frequently scorching heat is in full swing. The climate of Bathinda district can
be classified as tropical steppee, semi arid and hot which is mainly dry except in rainy
months and characterised by intensely hot summer and cold winter. During three months
of monsoon season from July to September, the moist air of oceanic origin penetrates
into the district and causes high humidity, cloudiness and good monsoon rainfall. The
period from October to November constitutes post monsoon season. The cold weather
season prevails from December to February followed by the hot weather season or Pre-
monsoon season which ends upto the last week of June.
Rain fall: The normal annual rainfall of Bhatinda District is 408 mm in 20 days which is
unevenly distributed over the district. The southwest monsoon sets in last week of June
and withdrawn towards end of September and contributes about 82% of annual rainfall.
July and August are the rainiest months. Rest 18% of the annual rainfall occurs during non
of the year in the form of thunder storm and western disturbances. Rainfall in the district
increases from southwest to northeast.
Rainfall
Normal Annual Rainfall: 408 mm
Normal monsoon Rainfall: 335 mm
Normal Rain days: 20
Temperature
Mean Maximum: 420C (May & June)
Mean Minimum: 3.90C (January)
(viii) Social Infrastructure available
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain and
125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW, 1 x 5 MW in Phase II)} in
Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 40
There are primary schools, dispensaries, small hospitals, places of worship in nearby area
of the project site.
5.0 PLANNING BRIEF
(i) Planning Concept (type of industries, facilities, transportation etc.)/ Town and
country Planning/ Development authority classification.
The project is installation of Ethanol/RS Industrial/ENA/SDS Plant within existing
distillery. Facilities required for the proposed project will be provided as per
requirement. Transportation of raw material and final product will be done via
existing road network and cement concrete road will be developed within the
proposed project area.
(ii) Population Projection
Temporary influx of people will be there as the managerial and supervisory staff
will generally be outsider. A projection may be made by a governmental
organization, or by those unaffiliated with a government.
(iii) Land use planning
Total Plant area is 8.8 Ha (22.0 acres). Proposed installation project will be set up in
the existing plant premises. No additional land will be required. About 33 % of the
total plant area is being/will be covered under green belt & plantation in order to
reduce dust & noise pollution levels & to increase aesthetic beauty of the area. The
same will be maintained.
(iv) Assessment of infrastructure demand (Physical & Social)
The Company will assess the demand of infrastructure (Physical & Social) in nearby
area of the proposed site and will be developed in under corporate social
responsibilities programs.
(v) Amenities/Facilities
The Company will develop the Amenities/Facilities in nearby area of the proposed
project site as per requirement of local people of the nearby area under corporate
social responsibilities programs.
6.0 PROPOSED INFRASTRUCTURE
(i) Industrial Area (Processing Area)
Total Plant area is 8.8 Ha (22.0 acres). Proposed installation project will be set up in
the existing plant premises.
(ii) Residential area (Non Processing area)
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain and
125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW, 1 x 5 MW in Phase II)} in
Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 41
Residential colony is not proposed for the project. The local labor will be preferred
to provide employment opportunities.
(iii) Green Belt
Out of the total project area ~33 % is being/will be developed under greenbelt area
& plantation in order to reduce noise pollution levels & to increase aesthetic beauty
of the area.
(iv) Social Infrastructure
Proposed project will result in growth of the surrounding areas by increased direct
and indirect employment opportunities in the region including ancillary development
and supporting infrastructure.
(v) Connectivity
The proposed project is well connected with Rail and Road.
(vi) Drinking Water
10 m3/day of water will be required for drinking & domestic purpose in the
proposed project which will be sourced from Canal Water.
(vii) Sewerage System
The waste water generated from the sanitary blocks will be disposed off in soak pit
via septic tanks.
(viii) Industrial Waste management
The proposed unit would be based on “ZERO EFFLUENT DISCHARGE”.
(ix) Solid Waste Management
� Grain Operation - Solid waste from the Grain based operations generally
comprises of Fibres and proteins in the form of DDGS, which will be ideally used
as Cattle Feed.
� Molasses Operation - Spent wash generated during Molasses operation, would
be concentrated in Multi-effect evaporator and then used as fuel in boiler.
� Ash from the Boiler will be sold to Brick manufacturers.
(x) Power requirement and source
The total power requirement for the proposed project will be 9 MW, which will be
sourced from proposed Co generation power plant of 40 MW & D.G Sets (for
emergency).
7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN
(i) Policy to be adopted (Central/State) in respect of the project affected persons
including home oustees, land oustees and landless labourers.
Proposed installation of Unit II –500 KLPD Ethanol/RS Industrial/ENA/SDS Plant {(250 KLPD Grain Based in Phase I) & (125 KLPD Grain and
125 KLPD Molasses Based in Phase II)} & 40 MW Co-generation Power Plant {(20 MW in Phase I ) & (1 x 15 MW, 1 x 5 MW in Phase II)} in
Existing Distillery Plant
At Village Sangat Kalan, Tehsil Bathinda, District Bathinda, Punjab
Form–I / Appendix–I
Om Sons Marketing Private Limited 42
Proposed installation will be done within the existing plant premises. No additional
land is required for the same. Therefore, there will not be displacement of people
and hence, Rehabilitation & Resettlement is not applicable.
8.0 PROJECT SCHEDULE AND COST ESTIMATES
(i) Likely date of start of construction and likely date of completion (time schedule
for the project to be given).
The project will start only after obtaining Environmental Clearance and all other
required clearance and will complete after two years of commencement.
(ii) Estimated project cost
� Total cost of the Project: Rs. 566 Crores
� Cost for Environment Protection Measues:
� Capital Cost: Rs. 56 Crores
� Recurring Cost/annum: Rs. 10 Crores/annum
9.0 ANALYSIS OF PROPOSAL
(i) Financial and social benefits with special emphasis on the benefit to the local
people including tribal population, if any, in the area.
The project activity and the management will support local administration and provide
other form of assistance for the development of public amenities in the region. Plantation
will be developed in and around the project area. The project will help in improving the
overall status of the area.