    Financing PFI projects in the creditcrisis and the Treasurys response

    RepoRT by THeCoMpTRolleR andaudiToR GeneRal

    HC 287

    SeSSion 20102011

    27 july 2010

  • 8/4/2019 Pfi Credit Crisis

    2/37

    The National Audit Ofce scrutinises public spending on behal o

    Parliament. The Comptroller and Auditor General, Amyas Morse, is an

    Ofcer o the House o Commons. He is the head o the National Audit

    Ofce which employs some 900 sta. He and the National Audit Ofce

    are totally independent o Government. He certifes the accounts o all

    Government departments and a wide range o other public sector bodies;

    and he has statutory authority to report to Parliament on the economy,

    efciency and eectiveness with which departments and other bodies

    have used their resources. Our work leads to savings and other efciency

    gains worth many millions o pounds: 890 million in 2009-10.

    Our vision is to help the nation spend wisely.

    We apply the unique perspective o public audit

    to help Parliament and government drive lasting

    improvement in public services.

  • 8/4/2019 Pfi Credit Crisis

    3/37

    Ordered by the House o Commons

    to be printed on 26 July 2010

    Rrt th Cmtrr atr Gr

    HC 287 Session 20102011

    27 July 2010

    London: The Stationery Oce

    14.75

    This report has been

    prepared under Section 6

    o the National Audit Act

    1983 or presentation to

    the House o Commons

    in accordance with

    Section 9 o the Act.

    Amyas Morse

    Comptroller and

    Auditor General

    National Audit Oce

    22 July 2010

    HM Trsr

    Financing PFI projects in the creditcrisis and the Treasurys response

  • 8/4/2019 Pfi Credit Crisis

    4/37

    This report examines the eects o the

    credit crisis on privately nanced government

    inrastructure projects, the Treasurys response

    and the challenges ahead.

    National Audit Ofce 2010

    The text o this document may be reproduced ree o charge in

    any ormat or medium providing that it is reproduced accurately

    and not in a misleading context.

    The material must be acknowledged as National Audit Ofce

    copyright and the document title specifed. Where third party

    material has been identifed, permission rom the respective

    copyright holder must be sought.

    Printed in the UK or the Stationery Ofce Limited

    on behal o the Controller o Her Majestys Stationery Ofce

    2378668 07/10 STG

  • 8/4/2019 Pfi Credit Crisis

    5/37

    Contents

    Summary 4

    Part One

    The Treasurys response

    to the eect o the credit

    crisis on privately nanced

    inrastructure projects 14

    Part Two

    The eect o the new

    nancing terms on contracts

    let since the credit crisis 20

    Part Three

    The inrastructure challenges

    in the current economic

    environment 26

    Appendix One

    Methodology 29

    Appendix Two

    PFI Benchmarking 31

    Appendix Three

    Case Studies 32

    Glossary 34

    The National Audit Oce study team

    consisted o:

    Mark Halliday, David Molony,

    Colin Ratclie, Jonathan Tang and

    Richard Wade, under the direction

    o David Finlay

    This report can be ound on the

    National Audit Oce website at

    www.nao.org.uk/inrastructure-

    nancing-2010

    Photographs courtesy o

    xxxxxxxxxxxxxxxxxxxxxxxx

    For urther inormation about the

    National Audit Oce please contact:

    National Audit Oce

    Press Oce

    157-197 Buckingham Palace Road

    Victoria

    London

    SW1W 9SP

    Tel: 020 7798 7400

    Email: [email protected]

    Website: www.nao.org.uk

    Twitter: @NAOorguk

  • 8/4/2019 Pfi Credit Crisis

    6/37

    4 Smmr Financing PFI projects in the credit crisis and the Treasurys response

    Summary

    Introduction

    Economic and social inrastructure orms the backbone o economic activity1

    in the United Kingdom, and enables the delivery o public services across thecountry. The term inrastructure encompasses social and economic sectors such as

    communications, education, energy, health, transport, waste and water.

    In the ve years to April 2010 approximately 30 billion per year was invested in2

    UK inrastructure. Future investment is orecast in the range o 40-50 billion per annum

    until 2030. Investment is nanced in a range o ways:

    Finance can be provided by private companies, but with some orm o explicit

    public regulation or implicit public support. Examples include the water and energy

    sectors, which are largely privately owned and nanced.

    Finance can be provided by public resources only, or or large one-o projects

    such as the Olympics, with a mixture o public and private resources.

    Finance can also be provided under the Private Finance Initiative (PFI) or other

    orms o Public Private Partnership (PPP). Sectors o economic and social

    inrastructure provided in this way include, or example, new hospitals and

    some roads.

    PFI projects are long-term contractual arrangements between public authorities3

    and private sector companies with project nancing raised by private companies.

    Project nance means that the nancing is provided or a sole project, through a special

    company set up or the purpose. Departments generally conclude that the contract

    oers value or money when the benets associated with the transer o project risk

    outweigh any additional PFI nancing cost.

    PFI projects typically use around 90 per cent debt nance and 10 per cent equity4

    nance. The debt portion o this nancing can be provided by bank loans and/or bonds.

    The banks and bond holders receive interest on their loans related to risks. Interest

    charged on a bank loan is usually a combination o two parts, the reerence rate (usually

    the interbank rate) and the loan margin (Fgr 1). The interbank rate refects general

    market risks, while the loan margin refects project specic risks. Variable rate bank loans

    are swapped to xed rates to provide stable monthly payments over the project lie.

  • 8/4/2019 Pfi Credit Crisis

    7/37

    Financing PFI projects in the credit crisis and the Treasurys response Smmr 5

    Bond nance is where a loan is split up into many identical bonds which saving5

    institutions can trade in public markets known as capital markets. Credit Rating

    Agencies analyse individual project and nance structure risks and publish a rating as

    a guide to investors. Beore the credit crisis, the purchase o credit insurance could

    improve the rating o the bond, thus making the risks acceptable to non-specialised

    lenders such as pension unds.

    In late 2007, market condence in the providers o this credit insurance collapsed,6

    leaving PFI projects in the United Kingdom without access to capital markets.

    The bank loan market, however, continued to unction. Banks can make loans7

    while they have sucient reserve capital (see Glossary) to allocate against them. To keep

    making new loans banks must ree up reserve capital by selling existing loans, in whole

    or in part, to other banks or raise new capital. This process is known as syndication.

    The collapse o Lehman Brothers in September 2008 led to a halt in loan syndication,continuing throughout 2009. This limited the ability o banks to make new PFI loans.

    The equity nance is provided by a projects contractors and nancial institutions.8

    It typically comprises a mixture o shares and shareholder loans. Equity nance is known

    as risk capital because, generally, the equity will be lost rst i the project company

    ails. The shareholder loans are higher risk as their repayment in a ailure is junior to the

    external debt, known as senior debt, which is repaid rst.

    Figure 1

    This shows how a variable rate loan is converted to a fixed rate and the

    composition of loan interest costs

    NOTES

    1 LIBOR means the London Inter Bank Offered Rate (see Glossary) which is similar to base rate, but usually higher to

    reflect risk of bank failure.

    2 A swap fee is payable to convert a variable rate loan to a fixed rate loan. Short-term rates can often exceed long-term

    rates during the life of a project.

    Source: National Audit Office

    Reflects

    Project Risks

    Reflects

    Market Risks

    Cushion for changes

    in Market Risks

    Swap Fee

    Margin

    Index Rate

    (LIBOR) Variable

    Swapped Rate

    (LIBOR)

    Fixed Long Term

    Margin

  • 8/4/2019 Pfi Credit Crisis

    8/37

    6 Smmr Financing PFI projects in the credit crisis and the Treasurys response

    Sc

    This report examines the eects o the credit crisis on privately nanced9

    government inrastructure projects and the Treasurys response. Although unable

    to control conditions in the nancial markets, the Treasury sets guidance on how

    departments assess value or money and approves signicant projects. It thereore

    was responsible or coordinating the Governments response to the nancial crisis and

    mitigating its impact on inrastructure procurement. In particular, the report sets out:

    how the Treasury responded to the impact o the credit crisis on the availability

    and terms o nance or PFI contracts;

    the impact o the credit crisis on the cost o nance or PFI contracts; and

    the challenges ahead.

    The report does not consider the value or money o individual projects, nor does it

    address the remit o Inrastructure UK, the new body established to coordinate the

    Governments approach to the inrastructure challenge. The report does, however, make

    recommendations on issues that Inrastructure UK should address.

    Figure 2

    Average international project finance loan margins compared to PFI

    Margin (%)Credit Crisis

    Year

    No of PFI deals

    NOTES

    1 The margins are averages based on monthly data.

    2 Numbers in bold are the number of PFI projects financed in that year.

    Source: National Audit Office and project finance chart based on data from the Infrastructure Project Finance Benchmarking Report 1995-2009 further

    description at http://infrastructureeconomics.org/2010/02/09/project-finance-benchmarking-report/

    0.0

    0.5

    1.0

    1.5

    2.0

    2.5

    3.0

    3.5

    1998 1999 2000 2001 2002 20031995

    1 15 24 46 54 68 52 54 51 61 50 57 57 31 35

    1996 1997 2004 2005 2006 2007 2008 2009

    All PFI

  • 8/4/2019 Pfi Credit Crisis

    9/37

    Financing PFI projects in the credit crisis and the Treasurys response Smmr 7

    K fgs

    The Treasurys response to lower availability o nance

    The Treasurys role in establishing the PFI market contributed to reductions10

    in the risk margin o private debt nance between 1999 and 2007. Over this period,

    the establishment o the PFI market and the availability o bank nance lowered nancing

    costs as bank competition increased. Departments took advantage by letting around

    300 contracts with relatively low nancing charges. The part o the interest cost relating

    to project risk, the PFI loan margin, averaged around one per cent, or less. These rates

    were lower than intern ational project loan margins which averaged 1.7 per cent rom

    1994 to 2008 (Fgr 2).

    As the credit crisis took hold in autumn 2008, debt nance became11

    increasingly unavailable. As a result o market conditions, largely outside the

    Treasurys control, rst bond nance, and then bank nance, became severely restricted.

    But as the UK economy entered recession, the Government had a signicant pipeline o

    inrastructure projects, with an investment value exceeding 13 billion (Fgr 3).

    Figure 3

    The investment value of UK infrastructure projects notified in the Official Journal of the European

    Union as at March 2009

    billion

    NOTES

    1 Building Schools for the Future (BSF) is a secondary schools investment programme.

    2 Local Improvement Finance Trusts (LIFT) finance primary medical care projects.

    Source: HM Treasury

    Capital value of pipeline by sector

    0.0

    0.5

    1.0

    1.5

    2.0

    2.5

    3.0

    3.5

    4.0

    4.5

    Housing Health Street

    lighting

    Emergency

    Services

    Libraries Education

    (other)

    Waste Educat ion

    (BSF)

    Transport Leisure Prisons NHS

    LIFT

    Joint-service

    centres

    Courts

  • 8/4/2019 Pfi Credit Crisis

    10/37

    8 Smmr Financing PFI projects in the credit crisis and the Treasurys response

    The Treasury was concerned about the macroeconomic impact o the12withdrawal o debt nance. With debt nance increasingly unavailable, individual

    contracts became harder to nalise. The Treasury eared that, as a result o this potential

    slowdown in new PFI contracts, the opportunity to stimulate the economy through

    new inrastructure would be lost. In addition, important benets, or example, improved

    school acilities and dealing with road congestion, depended on the completion o

    planned PFI projects.

    The Treasury thereore sought to maintain a fow o signed PFI contracts.13

    The overarching Government policy in late 2008 was that the pipeline o PFI deals

    should reach nancial close promptly, to stimulate national and local economies, and

    create jobs. The Treasury ollowed this policy whilst continuing to apply standard PFIvalue or money tests.

    Bank lending was so restricted in late 2008 that, despite Treasury14

    encouragement, no sizeable contracts could be let. In September 2008, the

    Treasury asked the European Investment Bank to step up its lending to inrastructure

    projects which the Bank did. The Treasury, however, did not set PFI lending targets or

    UK banks when they received government support during that winter. The Treasury

    initiated internal discussions about such targets but did not pursue them because the

    banks concerned were a sub-set o the PFI lending market and because PFI lending

    was only a small part o the issues acing the Treasury in relation to its banking support.

    In early 2009, there continued to be insucient bank debt or larger projects becausebanks did not resume lending as expected.

    The Treasury helped to reactivate the lending market or inrastructure15

    projects by setting up its own nance unit. In March 2009, the Government rapidly

    set up The Inrastructure Finance Unit to address the scarcity o debt nance. The

    units role was to be available to provide government loans to inrastructure projects, on

    commercial terms, so shortalls in the amount o available bank nance could be met.

    In April 2009, The Inrastructure Finance Unit helped to nalise a large waste16

    treatment and power generation project. The unit provided a 120 million loan to

    complete a 582 million nancing package or a waste treatment and power generation

    project in Greater Manchester. The Treasurys participation in this loan, on the same

    terms as commercial banks, is intended to be temporary and reversible.

    The Treasurys willingness to lend improved market condence and17

    subsequently around 35 government inrastructure projects have been agreed

    without any urther public lending. The Inrastructure Finance Unit has not made any

    urther loans. But since its establishment, around 35 projects have been agreed. There

    is thereore some evidence that the unit improved market condence. In addition, the

    availability o government loans provided some competitive tension to the banks in a

    market which, since 2008, had lacked competition on loan nancing terms.

  • 8/4/2019 Pfi Credit Crisis

    11/37

    Financing PFI projects in the credit crisis and the Treasurys response Smmr 9

    Th cst fc

    We ound that as a result o the credit crisis, the total interest cost o bank18

    nance increased by one-th to one-third. In the 35 projects agreed ater the

    establishment o The Inrastructure Finance Unit, we ound that the part o the cost

    relating to loan margins on PFI deals, which had been 1 per cent or less, widened

    signicantly to around 2.5 per cent on average (Fgr 4). Some, or example, the

    complex Greater Manchester Waste project, will rise to more than 3 per cent in stages

    over the project lie. The increased loan margins resulted in substantial increases to the

    cost o nance (Figure 4).

    These increases occurred despite the all in short-term borrowing rates and19

    little change in the intrinsic risk prole o projects. The all in the underlying short-

    term bank lending rate (the base rate) to 0.5 per cent only had a slight impact on PFI

    deals. This is because the private sector xes the interest cost on their long-term PFI

    borrowings. This xed interest rate, currently around 4 per cent, refects the risk o uture

    changes in interest rates and is a market actor that is not specic to PFI.

    In line with policy on acting to stimulate the economy, the Treasury gave20

    priority to closing deals at the prevailing market rates, even i this meant paying

    more and banks carrying less risk. In addition to charging higher margins, the

    banks have sought to de-risk their lending to projects ollowing the credit crisis. They

    renegotiated their lending terms with preerred bidders, through: lowering the proportion

    o debt in projects; increasing cover ratios (see Glossary); requiring the private sector

    to inject risk capital earlier; and placing more onerous conditions on when the private

    investors can withdraw cash rom the project.

    Figure 4

    Comparison o interest costs on PFI projects

    Str ds lrg ds

    pr crss pst crss pr crss pst crss

    K csts Sm rcts(2007)

    Sch sm(2009)

    FSTa(Mrch 2008)

    GMW(ar 2009)

    M25(M 2009)

    Level o project risk Various Low High/medium High Medium

    Interest rate margin (%) 0.79 2.51 1-1.15 3.25-4.50 2.5-3.5

    Total interest cost (%) 5.9 6.9 5.9-6.1 7.7-8.91 6.9-7.9

    Increase post crisis

    (minimum) (%)

    +18 +31 +17

    noTeS

    1 The indicative level o project risk shown above illustrates the act that the projects are not directly comparable. The change in interest margin

    percentages partly reflects this.

    2 The Future Strategic Tanker Aircrat (FSTA) project raised unding o 2.5 billion. Greater Manchester Waste (GMW) borrowed 582 million.

    3 The increase post crisis will rise with stepped increases in the interest rate margin i refnancing (see Glossary) does not take place.

    Source: KPMG and National Audit Office

  • 8/4/2019 Pfi Credit Crisis

    12/37

    10 Smmr Financing PFI projects in the credit crisis and the Treasurys response

    Our analysis shows that the higher nancing costs increased the annual21charge o typical PFI projects by 6 to 7 per cent (Appendix Two). Riskier PFI

    projects experienced a larger increase. For example, we estimate that the increase in

    the nancing charges o the Greater Manchester Waste project added 12 per cent to

    its annual contract price (Figure 11 on page 25). To address this, in October 2008 the

    Treasury increased the public sector share o any uture reductions in debt costs rom

    50 per cent to 70 per cent.

    We estimate that between 500 million and 1 billion o higher cost has been22

    locked in, partly oset by the increased public sector share o renancing gains.

    The higher end o this range refects the dierence between current PFI bank rates and

    low rates prior to the credit crisis. Although departments can now press investors torenance, any renancing requires careul judgement and will depend on uture market

    conditions. We doubt whether more than hal o the current higher nancing costs might

    be recovered.

    Higher nancing costs eroded the value or money advantage that23

    departments attribute to PFI. Departments initially seek assurance on the value

    or money o PFI procurement by comparing alternative ways o providing the same

    results. Although we have oten expressed concern about these calculations, the

    typical estimate o the PFI cost advantage lay in the range o 5 to 10 per cent (and

    some cases we have audited showed smaller savings). We estimate that nancing rate

    changes increased the annual contract charge by around 6 to 7 per cent. This ndingsuggests an increased risk to value or money resulting rom the credit crisis. Given the

    Governments policy objectives or stimulating the economy, we accept, however, that

    delays rom resubmission o individual business cases might have put the policy at risk.

    Although the Treasury and departments took steps to assess the impact24

    on the value or money o projects, there were limitations to their assessment.

    Despite the higher nancing costs the Treasury and departments considered that all

    35 contracts let in 2009 continued to represent value or money. The Treasury relied

    on the normal review processes or PFI projects and a review by Partnerships UK o

    the expected eect o higher bank risk margins on a sample o projects. There were,

    however, limitations to this approach, as:

    although the Partnerships UK review, commissioned by the Treasury, was useul

    analysis, it did not cover all projects let or all aspects o nancing costs. In addition,

    the Treasury monitored actual nancing terms, but did not have a ull analysis o the

    impact o the higher rates on the cost o projects that closed in 2009;

    some schools projects did not ully reassess their business cases, using out o date

    guidance which had said an updated quantitative analysis was only necessary i

    costs increased by 25 per cent; and

    the value or money assessments or the M25 and Greater Manchester Waste

    projects continued to rely on assumptions, rom earlier business cases,that high savings in uture whole lie costs would not be available under

    conventional procurement.

  • 8/4/2019 Pfi Credit Crisis

    13/37

    Financing PFI projects in the credit crisis and the Treasurys response Smmr 11

    Challenges

    The Treasury, through Inrastructure UK, aces a number o challenges to25

    identiy the best unding models or projects now being developed. The Treasury

    has ormed Inrastructure UK to oversee inrastructure investment in the UK, including

    aspects o Government capital spending. It will ace important challenges regarding the

    prioritisation o projects and procurement methods given the large decit in the public

    nances and the increased cost o using private nance.

    There are alternative nancing options to PFI.26 Projects such as the Olympics

    and Crossrail have relied on, or will be using, a greater input o public money. There were

    other nancing options, and although these would not have been likely to achieve the

    Governments policy objectives in 2009, they could be relevant in uture:

    The French government guarantees 80 per cent o the debt, once a project

    is operating successully, to reduce the use o bank risk capital and thereore

    nancing costs. The disadvantage is that this approach is not a temporary or

    reversible intervention and retains some operating project risk or the public sector.

    The not-or-prot European Investment Bank (EIB) is generally able to make unding

    available on more avourable terms (such as margins and ees) than commercial

    banks. Some European countries have used public loans in a similar manner.

    Ccs v r m

    We have assessed how the Treasury managed the risks to value or money,27

    rather than examining individual projects. Departments ability to nance the existing

    programme was in doubt until the Treasury set up The Inrastructure Finance Unit and

    reactivated the lending market. Our value or money conclusion relates to projects

    actually nanced in 2009. However, we accompany that conclusion with a warning on

    value or money or subsequent projects.

    On projects nanced in 2009:28 It is our opinion that in the circumstances the extra

    nance costs o projects nanced during 2009 were value or money. We take this view

    because the overarching policy priority to provide economic stimulus severely limited thescope or the Treasury to do more than they did to protect public value while ensuring

    that the programme o PFI projects was moved orward. In reaching this view we

    considered the act that the nancing margin being paid had widened signicantly, and

    that banks renegotiated lending terms which resulted in an increased cost o risk or the

    public sector. We regard this as having been oset to some extent, and as ar as was

    reasonably achievable in all the circumstances, by the increased renancing gain share

    terms obtained by the Treasury.

  • 8/4/2019 Pfi Credit Crisis

    14/37

    12 Smmr Financing PFI projects in the credit crisis and the Treasurys response

    We also considered whether the PFI deals could have been required to29submit individual revised business cases, which might have led to some o the least

    advantageous projects being postponed or discontinued with the eect o improving

    overall value or money. We concluded that this requirement would have imposed urther

    delay that might have put the policy objectives at risk, and would not thereore be a

    reasonable yardstick to assess the protection o value or money in the programme.

    However, having concluded thus positively on projects nanced at the height o the

    crisis, we would expect more exacting criteria to be applied subsequently.

    On projects which have yet to be ully developed:30 There should be no

    presumption, based on earlier business case analysis, that continuing the use o private

    nance at current rates will be value or money. We now expect a thorough projectby project review o the orward programme to apply more exacting and narrower

    criteria than applied to projects nanced at the height o the crisis. PFI is less likely to

    be value or money unless there are substantial and credible savings to oset higher

    nancing costs. The Treasurys ormation o Inrastructure UK gives a platorm or wider

    consideration o risks, other unding options and alternative procurement models.

    Rcmmts

    To the Treasury

    Market disruption, causing a lower availability o nance, has interrupted

    the Governments inrastructure programme.The Treasury should analyse

    the lessons rom the past two years. It should use these lessons to prepare a

    contingency plan or how departments should handle uture market disruption

    aecting procurement plans.

    There is limited evidence that projects undamentally re-evaluated their

    business cases in light o the credit crisis. Where there are material changes,

    such as project costs increasing by 15 per cent, the Treasury should require that

    the department re-evaluate the project. This re-evaluation should assess all the

    benets, and potential loss o benets, o continuing the project in its current orm,

    compared to other available options, including other orms o procurement.

    Increased reliance on a single type o nance, with reduced competition,c

    promotes ineciency. The Treasury should continue to consider how a greater

    mix o nance sources, with less emphasis on the use o commercial bank loans,

    can be used to nance inrastructure projects.

  • 8/4/2019 Pfi Credit Crisis

    15/37

    Financing PFI projects in the credit crisis and the Treasurys response Smmr 13

    To the Treasury and departments

    Allowing individual projects to negotiate renancing will lead to variable and

    overall sub-optimal outcomes. The Treasury should adopt a portolio approach

    to renancing, with input rom the relevant departmental team, so that individual

    authorities do not exercise any right to a renancing on a piecemeal basis. During

    the operating phase o a number o projects, taking a portolio approach will

    enhance the public sector bargaining position, reduce transaction costs and

    increase potential gains. The Treasury should also consider whether the returns to

    equity investors are aligned with the changed risk allocation in deals that has arisen

    ollowing the credit crisis.

    The increase in nance costs, including some reduction in risk borne by

    banks, makes PFI less likely to be a value or money solution. In line with

    Treasury guidance, departments should not presume that a wholly privately

    nanced project oers a solution likely to secure good value or money. During

    procurement, and in drating notices or the Ocial Journal o the European Union,

    departments should assess a range o nancing options, including all public

    nance or part public and part private nance.

    The public sector gave greater priority to securing agreed contracts than

    to negotiating better outcomes. In such situations, departments should

    nevertheless make greater use o sensitivity analysis to inorm decision-making

    over negotiation on possible small changes in nancing rates and on each request

    to take on additional project risk.

  • 8/4/2019 Pfi Credit Crisis

    16/37

    14 prt o Financing PFI projects in the credit crisis and the Treasurys response

    Part One

    The Treasurys response to the eect o the creditcrisis on privately nanced inrastructure projects

    During 2008, the market capacity or providing bank nance decreased, pricing1.1

    increased and other terms tightened. Fgr 5 shows the main changes aecting the

    nancing market and the eect on inrastructure projects.

    Th Trsrs t rss t th mct pFi ctrcts

    The Treasurys initial response was to evaluate the extent o the impact o nancial1.2

    market disruption on PFI projects. From June 2008, it analysed increasing evidence that

    the disruption to the credit markets was aecting unding or the PFI market, in terms

    o both the pricing and availability o project debt. In particular, it concluded that market

    changes had increased project costs, leading to delays, and putting the overarching

    policy o stimulating the economy at risk. In addition, i cheaper nance were to become

    available in the uture, the private sector would then gain more benet rom renancing

    (see Glossary). Departments were, thereore, already being advised to seek a right to

    bring about a renancing and obtain an increased share o any gains. In October 2008,

    this was made a ormal amendment to standard contract terms.

    Banks put up their ees and interest charges to borrowers generally, including1.3

    PFI borrowers, but most were unwilling to provide long-term loans in greater amounts

    than about 25 million per project. As a result many PFI borrowers had to take time to

    assemble a club o ve or six banks to do a large deal. Such a deal would previously

    have involved only one negotiating bank and later syndication on pre-agreed terms at

    the risk o that lead bank.

    All-in interest charges and other lending terms worsened or PFI deals during 2008,1.4

    and most notably during 2009. Complex deals, like the M25 project and the Greater

    Manchester Waste project struggled to orm bank clubs or the substantial amounts

    they needed.

  • 8/4/2019 Pfi Credit Crisis

    17/37

    Financing PFI projects in the credit crisis and the Treasurys response prt o 15

    Figure 5

    Key events and Treasury response

    pr/dt K vts Trsr

    rss

    ect rstrctr rcts

    December 2007 Last bond issue: Northern

    Ireland Road II project raises

    146 million

    Projects, such as the Ministry o Deences Future

    Strategic Tanker Aircrat project, change rom bond

    to bank inance

    March 2008 Future Strategic Tanker

    Aircrat inancing raises

    2,200 million

    Bank group ormed with eight arranging banks and

    15 participants. Interest cost about 6 per cent, up to

    1.15 per cent above the then bank cost o unds

    September 2008 Lehman collapse Some banks withdraw, others charge more than

    1.5 per cent above cost o unds (some as high as

    2.2 per cent) compared with 1 per cent previously.

    This makes it diicult to procure debt inance to

    complete contracts. Major projects such as the

    Greater Manchester Waste project and the M25

    are delayed

    October 2008 Government provides banks

    with inancial support

    Treasury notes unding

    gaps or large or more

    complex projects

    Projects compete with corporate borrowers or

    scarce bank capacity. Finance cost increases are

    partially oset by alling underlying interest rates.

    Government support to the banking sector does not

    trigger a rapid resumption in lending

    November 2008 Treasury proposes a range o

    possible solutions, including

    greater EIB involvement

    Increased Authority capital contributions

    Authority loans on commercial bank terms

    Working Group on medium-term solutions

    January 2009 Treasury proposes direct

    lending accepted

    30 January 2009

    Advice leaves open any decision on the lending

    body, although Department or Transport may act

    as lender on the M25

    March 2009 Ministerial Statement on The

    Inrastructure Finance Unit

    Treasury lends 120 million to the Greater

    Manchester Waste project which, in April 2009, is

    the irst contract to be let ollowing the credit crisis.

    Treasury places letter with lending criteria on websitein May. The market realises that it is now possible to

    complete PFI deals in the current market conditions.

    The M25 contract is let in May 2009 without the

    need or a departmental loan

    August 2009 Treasury Application Note

    provides new guidance

    or taking orward private

    inance projects

    No signiicant change is made in the way that projects

    are assessed ater the Outline Business Case. The

    intent is to avoid excessive reliance on uncertain

    inancing proposals early in procurements, the low o

    new deals is now becoming more established

    Source: National Audit Office

  • 8/4/2019 Pfi Credit Crisis

    18/37

    16 prt o Financing PFI projects in the credit crisis and the Treasurys response

    The Treasury approached the European Investment Bank in September 2008, to1.5step up its lending activity to help ease the situation. The Treasury, however, did not

    set PFI lending targets or UK banks when they received government support during

    that winter. The Treasury initiated internal discussions about such targets but did not

    pursue them because the banks concerned were a sub-set o the PFI lending market

    and because PFI lending was only a small part o the issues acing the Treasury in

    relation to its banking support. Banks did not resume lending as expected and, between

    October 2008 and March 2009, only our smaller PFI projects were nanced, including

    two school projects.

    Th mct v r m ssssmts

    The Treasury-chaired Project Review Group was responsible or the scrutiny o1.6

    business cases or major PFI contracts. Partnerships or Schools undertakes the same

    role or schools contracts. Both require projects to rework the economic assumptions

    behind the choice o procurement route, made at the Outline Business Case stage, i

    there has been market ailure or a major change. Current guidance does not contain

    an actual number to dene what constitutes a major change, relying instead on overall

    judgement. Some projects such as schools, however, took guidance rom August 2004

    exempliying major change as an increased cost, in real terms, o 25 per cent.

    In our audits, previous business cases oten indicated that PFI projects were1.7

    expected to deliver savings in the range o 5 to 10 per cent. We have also reported in thepast that there were faws in these comparisons between the PFI price and conventional

    procurement.1 An increase in the cost o nance thereore represented an increased

    risk to value or money, and could have led to reappraisals o the value or money o

    individual projects. A review o a sample o Outline Business Cases by Partnerships UK

    estimated, however, that all cases remained value or money at higher bank risk margins

    o 3 per cent.

    Given the Governments policy objectives or stimulating the economy, we accept1.8

    that delays rom resubmission o individual business cases might have put the policy at

    risk. We also generally accept the case or absorbing higher nancing costs or projects

    at an advanced stage in 2009, but would still have expected some supplementaryanalysis o the impact at the project level. In particular, where projects had yet to be ully

    developed, we would have expected departments to have presented wider value or

    money assessments to the Treasury on the benets and disadvantages o proceeding

    with their PFI projects.2 Where applicable, this should have included the eect o the

    public sector taking on greater project risks, where the banks made this a condition o

    their nancing, balanced against lost service benets rom delaying the projects. Such

    analysis would have improved the Treasurys understanding o the trade-os involved in

    accepting higher nancing costs, as well as inorming uture decisions on the use o PFI.

    1 See, or example, Private Finance Projects, A Paper or the Lords Economic Aairs Committee, October 2009,

    paragraph 4.9, pages 46-47.

    2 An example o this orm o analysis is in Appendix Five o this report and can be ound at www.nao.org.uk/

    inrastructure-fnancing-2010.

  • 8/4/2019 Pfi Credit Crisis

    19/37

    Financing PFI projects in the credit crisis and the Treasurys response prt o 17

    Delayed projects were vulnerable to the credit crisis. The M25 case study, or1.9example, shows a cost increase o over 600 million on a contract which had originally

    been due to close in February 2008 (Appendix Three).

    One school case, however, illustrates how innovation mitigated the disruptive eect1.10

    that the credit crisis had on certain projects reaching contract closure. In this project, to

    build a new school in the London Borough o Newham, the bank supporting the winning

    bidder withdrew a month beore the planned nancial close. Partnerships or Schools

    proposed a solution based on the Local Education Partnership contracting a Design &

    Build contract, without committed private nance.3 On an exception basis, the Treasury

    allowed the London Borough o Newham to conclude this school project on condition

    that interim grant unding would be replaced by private nance within six months, whichwas achieved.

    The establishment o The Inrastructure Finance Unit

    Following the worsening o the credit crisis in autumn 2008, it became clear that1.11

    sucient debt nance, whether bank loans or bonds, was no longer available to privately

    nance larger government inrastructure projects. The Treasury wished to close the

    contracts in the pipeline to re-establish the market or government inrastructure projects

    as part o the broader scal stimulus package. The Treasury thereore considered

    options and developed a contingency plan to establish a lending unit. This unit obtained

    Government approval at the end o January 2009.

    In March 2009, the Government implemented its plan or the lending unit to ensure1.12

    that some 110 privately nanced inrastructure projects (exceeding 13 billion) would go

    orward, despite diculties in raising debt nance. The unit, known as The Inrastructure

    Finance Unit, was created with the purpose o unding any shortalls in bank nance

    on privately nanced inrastructure projects. The lending terms would be on the same

    commercial terms as the banks.

    Ater ten months o negotiation, with almost all o the available banks, the Greater1.13

    Manchester Waste project had remained unable to raise the last 120 million to

    complete its nancing. In March 2009, the Treasury agreed to make up this shortallthrough a 120 million loan. The Inrastructure Finance Unit subsequently monitored and

    provided support to a number o other projects but no urther loans have been required.

    The Treasury intervention on the Greater Manchester Waste project was timely1.14

    and helped to reactivate the market. The Treasury chose this project because it clearly

    met its lending criteria. Raising enough bank nance had proved dicult because the

    project carried more risk than the average PFI project (see Part Two). The possibility o

    Treasury loans was not needed on the other large complex deal, the M25 project, as

    the Department or Transport had already developed a contingency plan to be ready

    to act as a co-lender to the project. Other projects were smaller and did not appear to

    have nancing gaps or could be grant-unded on a temporary basis, as permitted in theexceptional case o the Newham school.

    3 See National Audit Ofce The Building Schools for the Future Programme Renewing the secondary school estate,

    February 2009 or an explanation o the Local Education Partnership role.

  • 8/4/2019 Pfi Credit Crisis

    20/37

    18 prt o Financing PFI projects in the credit crisis and the Treasurys response

    Although helpul in moving projects in the pipeline towards contract closure,1.15Treasury lending created increased risks or the public sector parties. Public sector

    lending also caused some concerns or the private sector about inormation sharing

    (Fgr 6).

    During the onset o the credit crisis rom autumn 2008 through to summer 2009,1.16

    the Treasury amended renancing provisions and continued to apply existing guidance

    to departments on how they were to consider value or money issues on PFI contracts.

    Rather than issue additional guidance, the Treasury ocused on getting procurements

    moving again and later on the ormation o its lending unit. A guidance note on eligibility

    or Treasury loans was issued in May 2009, and an Application Note on PPP projects in

    current market conditions was issued in August 2009. The latter did not make materialchanges to the tests that should determine value or money in the nancing conditions

    that had arisen ollowing the credit crisis because the Treasury believed its value or

    money guidance remained sound.

    Figure 6

    The main risks and concerns related to Treasury lending

    I the project ailed then the Treasury might lose part or all o the money it had lent. As the economy

    was in recession there was a higher risk o project ailure due to service deliverers running into

    inancial diiculties than beore the credit crisis. This risk was mitigated by hiring sta with appropriate

    proessional experience.

    There was the potential or conlicts o interest within government over decision-making i a project ran

    into diiculties. The procuring department would be seek ing to protect service delivery, and i the project

    had to be terminated it would expect the banks to share in any losses that would arise. The Treasury, as

    lender, would be motivated in the opposite direction to ensure that it recovered as much as possible o

    the money it had lent. This risk was mitigated by a governance structure including a credit committee and

    a steering group with some independent members.

    The commercial banks lending to the project would be concerned that the Treasury, as lender, might

    receive inormation about the departments intentions or the project which had not been communicated

    to the banks. The Inrastructure Finance Unit is, however, treated in the same way as any commercial

    lender in terms o access to inormation.

    Source: National Audit Office

  • 8/4/2019 Pfi Credit Crisis

    21/37

    Financing PFI projects in the credit crisis and the Treasurys response prt o 19

    othr ts r mtg rct csts

    There were other nancing options, and although these would not have been likely1.17

    to achieve the Governments policy objectives in 2009, they could be relevant in uture.

    The French government guarantees 80 per cent o the debt, once a project is

    operating successully. Although this can reduce nancing costs by several million

    pounds, it increases public sector exposure to operating risks. Large projects in

    France have struggled to reach conclusion on this basis since 2008, and none

    closed in 2009.

    The not-or-prot European Investment Bank (EIB) is generally able to make unding

    available on more avourable terms (such as margins and ees) than commercial

    banks. Some European countries have publicly owned banks playing a similar

    role. Lending at similar rates was not pursued because the Treasury considered

    government lending should be temporary and reversible. In a uture renancing, it

    would be dicult to sell such loans to other parties to recover the original unding.

  • 8/4/2019 Pfi Credit Crisis

    22/37

    20 Part Two Financing PFI projects in the credit crisis and the Treasurys response Financing PFI projects in the credit crisis and the Treasurys response Part Two 21

    During 2008, the market capacity or providing bank nance decreased, pricing2.1

    increased and other terms tightened. Figure 7 shows the main changes in the nancing

    market and their eect o n the timing o the inrastructure projects we reviewed.

    Helped by the Treasurys establishment o its lending unit, condence improved,2.2

    market activity resumed and 35 delayed projects closed between March and

    December 2009 (Figure 8 overlea).

    Where private nance has been used since the credit crisis, however, the cost was2.3

    always more expensive than beore, generally by around one per cent. The act that the

    base rate is currently at an all time low has not ully oset the higher loan margins that

    banks are charging. This is because the cost o a xed interest loan, as with government

    borrowing over 20-30 years, refects uture interest rate expectations. These rates are lower

    than two years ago but the reduction has not been sucient to oset the signicantly wider

    loan margins now charged by the banks (Figure 9 overlea).

    Part Two

    The eect o the new nancing terms on

    contracts let since the credit crisis

    1 Jun

    2009

    1 May

    2009

    1 Apr

    2009

    1 Mar

    2009

    1 Feb

    2009

    1 Dec

    2008

    1 Nov

    2008

    1 Oct

    2008

    1 Sept

    2008

    1 Aug

    2008

    1 Jul

    2008

    1 Jun

    2008

    1 May

    2008

    1 Jan

    2009

    8 Apr 2009

    Financial close

    December 2008

    Department for Transports

    willing-to-lend letter

    20 May 2009

    Financial close

    16 Sept 2008

    Lehman Brothers

    filed for bankruptcy

    27 Mar 2008

    FSTA project reached

    financial close

    8 Oct 2008

    Banking support

    measures announced

    by the Treasury

    19 Jan 2009

    Further support

    measures announced

    5 Mar 2009

    Bank of England started

    Quantitative Easing

    3 Mar 2009

    Treasury

    announced

    lending unit

    3 Apr 2009

    EIB increased capital by

    67bn (or 40%) to expand

    lending during crisis

    16 Jan 2009

    Contract signed for design and build

    aspects with a Laing ORourke consortium

    23 Jun 2009

    Financial close

    13 Nov 2008

    BP4L consortium

    selected as

    preferred partner

    7 Jul 2009

    Financial close

    8 May 2008

    Connect Plus selected

    as preferred bidder

    Figure 7

    Timeline of key events affecting case examples after notice in Official Journal of the European Union (OJEU)

    PFI project/capital value

    Source: National Audit Office

    Barnsley

    schools 111m

    Newham

    schools 69m

    M25 1,073m

    Greater Manchester

    Waste 795m

    1 Apr

    2008

    1 Mar

    2008

    1 Feb

    2008

    1 Jan

    2007

    1 Jan

    2006

    1 Jan

    2005

    1 Jan

    2008

    22 Feb 2005

    OJEU issue

    1 Oct 2005

    Pre-qualification/bidder invitation

    to submit outline solution

    29 Jan 2007

    Viridon/Laing selected

    as preferred bidder

    Change in

    timeline scale

    Major events

    during credit crisis

    Continuous delays in achieving financial close

    23 Mar 2005

    OJEU issue

    13 Oct 2006

    Flow, Connect Plus, Amey/Laing,

    ORourke/Ferrovial shortlisted

    19 Dec 2007

    Downgraded credit ratings of a

    number of credit insurers

    13 Sept 2007

    Run on deposits

    in Northern Rock

    Further downgrades by credit

    rating agencies on credit

    insurers during first half of 2008

    26 May 2006

    OJEU issue

    7 Aug 2006

    Invitation to tender

    11 Apr 2008

    Preferred

    bidder selected

    16 Mar 2007

    OJEU issue

    17 May 2007

    Bidder

    longlist

    selected

    23 Jan 2008

    Number of

    bidders

    reduced to two

    21 Jun 2007

    Bidder

    shortlist

    selected

  • 8/4/2019 Pfi Credit Crisis

    23/37

    22 prt Tw Financing PFI projects in the credit crisis and the Treasurys response

    The increased nancing costs since the credit crisis have come ater a period in2.4

    which around 300 PFI contracts were let at relatively low nancing rates when compared

    to other types o project nancing, as shown earlier (Figure 2 on page 6). The low rates

    refected the successul establishment o the PFI market and availability o bank lendingwhich encouraged competition in the nancing terms.

    Th mct hghr t fc csts c sctr

    srvc mts

    The increased cost o nance has generally been passed through by the private2.5

    sector service provider to the public authority in the orm o an increased monthly

    payment, known as the unitary charge. In Appendix Two, Figure 15 sets out the impact

    in real terms, compared to projects that were nanced in 2007, and suggests that, on

    an all-in basis, the extra cost increased by around 5.6 per cent to 7.4 per cent. The

    nancing costs o schools projects, which are airly typical, moved up sharply at the starto 2009 (Fgr 10).

    Figure 9

    Increase in loan margins applied by the banks

    2007 2009 j 2010

    Borrowing rate (%) 5.1 4.46 4.18

    Schools margin (%) 0.6 2.55 2.23

    annual interest cost or a typical 20 million 1.1m 1.4m 1.3m

    school project

    Waste project margin (%) 1.2 Above 3

    annual interest cost or a typical 190 million 10.8m 14m

    waste project

    noTe

    1 Project values shown above relate to the amount o senior debt and the annual interest cost reduces as loan

    repayments are made.

    Source: National Audit Office analysis

    Figure 8

    PFI deals concluded April to December 2009

    ds Ct V (m)

    Greater Manchester Waste PFI 631

    M25 project (whole lie present cost 3,360 million) 1,073

    20 PFI school projects 1,396

    12 other PFI/PPP deals 1,795

    Total 4,895

    Source: National Audit Office

  • 8/4/2019 Pfi Credit Crisis

    24/37

    Financing PFI projects in the credit crisis and the Treasurys response prt Tw 23

    Figure 10

    Typical changes, after December 2008, in loan margins and total interest

    rates, exemplified by Building Schools for the Future (BSF) projects

    Percentage

    BSF PFI deals bank average margins

    0.00

    0.50

    1.00

    1.50

    2.00

    2.50

    3.00

    Percentage

    14 Dec

    2005

    2 Jul

    2006

    18 Jan

    2007

    6 Aug

    2007

    22 Feb

    2008

    9 Sept

    2008

    28 Mar

    2009

    14 Oct

    2009

    2 May

    2010

    14 Dec

    2005

    2 Jul

    2006

    18 Jan

    2007

    6 Aug

    2007

    22 Feb

    2008

    9 Sept

    2008

    28 Mar

    2009

    14 Oct

    2009

    2 May

    2010

    NOTES

    1 The first chart shows the effect on bank margins. The second chart shows the effect on total interest costs. The charts

    show two main points:

    a There was a dramatic increase in bank margins between July 2008 and June 2009. There has been a very slight

    easing in the margins, moving into 2010.

    b The total increase in interest costs (i.e. bank margins + swap rates) is not as great as the increase in bank margins.

    This is due to the fall in swap rates, by about one per cent, over the same period.

    Source: Partnerships for Schools

    BSF PFI deals total interest rates

    0.00

    1.00

    2.00

    3.00

    4.00

    5.00

    6.00

    7.00

    8.00

    PFI school deal interest rates Bank base rate 25-year gilt rate

  • 8/4/2019 Pfi Credit Crisis

    25/37

    24 prt Tw Financing PFI projects in the credit crisis and the Treasurys response

    The Treasurys approval o the nal nancing terms or contracts, such as the2.6Greater Manchester Waste project and the M25, demonstrates that it gave priority

    to agreeing contracts, and that it believed that it aced a lenders market. In such a

    lenders market, it was not possible to resist price increases, particularly ater the Future

    Strategic Tanker Aircrat (FSTA) nancing in March 2008, as shown in Fgr 11.4

    A similar trend was starting to be visible in other countries. The nearest comparator or

    the M25, a toll road in Germany obtained project nancing in March 2009. That projects

    total interest cost was about 6.5 per cent, including debt margins o over 2 per cent

    during construction (M25 2.5 per cent) and early operating years (over 3 per cent

    ater 10 years M25: 3.0-3.5 per cent).

    On large deals it was dicult, costly and time consuming to arrange bank nance.2.7A very large deal, such as the M25 described in Appendix Three, also resulted in a club

    o 16 banks eventually taking shares o around 25 million to 65 million each.

    Margin increases have not been the sole impact o any reduced competition2.8

    resulting rom club deals. Based on analysis o projects concluded in 2007 and 2009

    (see Appendix Two), banks have also sought to reduce their project risk by lowering the

    proportion o debt in projects and increasing cover ratios (see Glossary). This increases

    the risk to investors, who have passed the corresponding cost to the public sector

    by increasing the unitary charge. The M25 cover ratio originally required cash, at a

    minimum, exceeding 1.23 times the amount needed in each period to service the debt.

    The banks increased this coverage requirement to 1.4 times the amount needed tocover the debt. The nal M25 contract also resulted in some additional risks being borne

    by the Highways Agency. The Agency negotiated concessions in return.

    In all types o lending, banks are seeking shorter periods or the repayment o2.9

    their loans. In the case o PFI, or example, at the time o selecting the Preerred Bidder

    (July 2008), the planned nal repayment o the M25 loans was six months beore the end

    o the concession and it was subsequently increased by three years.

    In the Greater Manchester Waste project, there are progressive step-ups in loan2.10

    margins ater the ninth year (see Appendix Three). The banks chose this structure to

    increase the likelihood o the private borrower and/or the public authority seeking a

    renancing at lower margins. This is preerable to imposing an obligation to renance the

    loans at a specied uture date.

    Ftr rfcg

    Based on a survey we commissioned with market participants, the consensus view2.11

    was that they expected margins in three to ve years time to be in the range o 1.25 per cent

    to 1.75 per cent. As such, we have assumed the new debt margin on the renanced debt to

    be 1.5 per cent. The potential eect on a typical project is set out in Fgr 12.

    4 National Audit Ofce Delivering multi-role tanker aircraft capability, March 2010, reported in paragraph 18 that the

    selection o a PFI solution was made without a sound evaluation o alternative procurement routes to justiy why

    the PFI route oered the best value or money.

  • 8/4/2019 Pfi Credit Crisis

    26/37

    Financing PFI projects in the credit crisis and the Treasurys response prt Tw 25

    Renancings will only occur i market conditions improve and i the private sector2.12can be motivated to renance the projects with revised arrangements that now give

    most o the renancing benet (70 per cent o typical renancings) to the public sector.

    Since October 2008, the public authority has a contract right to request a renancing,

    which is exercisable once in any two year period.5 Until that time is judged to be right,

    the Government is locked into substantially higher nancing costs that we estimate to be

    between 500 million and around 1 billion.

    Taking the illustrated level o renancing gain, at the our year stage, an aggregate2.13

    recovery o 400 million might be obtained across the basket o deals concluded in 2009.

    Although there are some technical actors that could increase the renancing gain, these

    are likely to be oset by the private sectors share o the gain and by transaction costs.

    5 Refnancing gains are shared on a sliding scale basis: Up to 1 million 50 per cent; between 1-3 million 60 per cent

    and greater than 3 million 70 per cent. Both Greater Manchester Waste and the M25 achieved higher shares.

    Figure 11

    Change in notional unitary charge on large, complex projects

    Trm FSTa

    Mrch

    2008

    GMW

    ar

    2009

    M25

    M

    2009

    Level o project risk High/

    medium

    High Medium

    Total interest cost (%) 5.9 - 6.1 7.7 - 8.9 6.9 - 7.9

    Final repayment (months beore end o concession) 24 months 18 months 42 months

    Debt inance proportion (%) 86.2 85.2 84.7

    Unitary charge increase compared to FSTA (%) 12 6

    noTe

    1 Although the projects dier, and each has dierent proportions o operating costs, the unitary charge has been

    re-scaled, or comparison with the typical 190 million base case in Appendix Two.

    Source: KPMG and National Audit Office

    Figure 12

    Potential renancing gains on a project with 190 million senior debt andan estimated locked-in cost o 8.6 million

    Rcg dt ptt G

    (rs tr strt orts) (nt rst v m)

    Three years 3.52

    Four years 3.45

    Five years 3.37

    noTe

    1 The gain is calculated gross (beore sharing) on an original capital investment o 170 million.

    Source: National Audit Office

  • 8/4/2019 Pfi Credit Crisis

    27/37

    26 prt Thr Financing PFI projects in the credit crisis and the Treasurys response

    Part Three

    The inrastructure challenges in the currenteconomic environment

    Th chgs t th Gvrmt

    The Government aces challenges in planning inrastructure investment in3.1

    the current economic environment. Inrastructure UK, the new coordinating body

    established within the Treasury, estimates that the Government needs to continue

    to encourage substantial investment in new inrastructure, possibly 40-50 billion

    per annum until 2030.6 But government departments need to reduce annual spending

    to assist the public nances; and the cost o using private nance has increased

    signicantly compared with beore the credit crisis.

    Th cst sg rvt fc

    Our analysis in Part Two has shown the increase in the cost o using private nance3.2

    compared with beore the credit crisis. This increased cost may not be a temporary

    phenomenon, because one o the primary eects o the credit crisis may have been to

    change the attitudes to corporate and project risk within banks. As a result, there may

    have been a long-term increase in the cost o using private nance.

    In addition, a signicant problem or banks at the peak o the credit crisis was the3.3

    mismatch between long-term loans (their assets) unded by short-term borrowing (their

    liabilities). So although PFI projects are underpinned by revenue rom public unds, the

    combination o long-term loans and remaining risk transer may have permanently increasednance costs and reduced the number o participants willing to lend in this market.

    Th stshmt irstrctr uK

    Inrastructure UK was established ater the 2009 Pre-Budget Report to coordinate3.4

    the long-term inrastructure needs o the UK. Inrastructure UK is a unit inside the Treasury

    incorporating a number o policy, nancing, and delivery bodies to lead work within the

    Treasury to enable greater private sector investment in inrastructure, and improve the

    Governments long-term planning and delivery. In the autumn, the Government will publish

    a national inrastructure plan that will set out priorities or UK inrastructure on a cross-

    sector basis. Inrastructure UK will also carry out an investigation into how to reduce thecost o delivery o civil engineering works or major inrastructure projects.

    6 HM Treasury Strategy or national inrastructure March 2010.

  • 8/4/2019 Pfi Credit Crisis

    28/37

    Financing PFI projects in the credit crisis and the Treasurys response prt Thr 27

    By consulting stakeholders, Inrastructure UK has identied that there is a3.5signicant risk o a gap emerging in the provision o equity capital to large complex

    inrastructure projects, particularly in the energy sector, within the next ew years.

    This issue compounds the challenges posed by the reduction in availability and increase

    in cost o debt nance highlighted in this report. Inrastructure UK has also set out to

    identiy the critical interdependencies that impact on economic inrastructure investment

    needs (Fgr 13) and will publish an action plan, setting out how the risks and

    interdependencies will be managed, by spring 2011.

    As a result o the interaction o these issues, there is a need to re-evaluate3.6

    unding mechanisms across the whole range o public and private inrastructure

    investment. Some unders may be repaid rom public sector payments or services,mostly originating in taxation, and others out o payments by users or consumers

    (see Fgr 14 overlea).

    Inrastructure UK recognises that it needs to nd ways to maximise unding sources,3.7

    and in particular to nd new ways or inrastructure projects to obtain unding rom the

    capital markets. The main obstacle is that institutions, such as pension unds, do not have

    the internal credit approval processes and skills to assess the risk and return or investing

    in project bonds, typically issued with a lower credit rating than BBB.7 Such investors

    will only develop this new line o business i they believe that there is a substantial uture

    pipeline o inrastructure projects that carry relatively low repayment risk.

    7 Investments are graded according to methodologies produced by credit rating agencies such as Standard and

    Poors (Range: AA A to D). Triple B (BBB) is the lowest investment grade rating and indicates a 0.32 per cent

    probability o deault.

    Figure 13

    Economic inrastructure

    Sctr Sgct ssts

    Water Water resources (rivers, reservoirs and dams), drink ing water distr ibution (pipes

    and pumping stations), waste water treatment, sewerage systems, lood and

    coastal deences.

    Waste Landill, recycling acilities, waste collection and processing, hazardous waste

    treatment, energy recovery.

    Transport Roads (strategic and local), heavy rai l, l ight rai l, a irports, ports, metro systems.

    Energy Gas storage, transmission and distribution, electr icit y generation (renewable and

    non-renewable), transmission and distribution.

    Communications Fixed voice and data networks, mobile voice and data networks, satellite

    networks, television and radio broadcast networks and radio spectrum.

    Source: Strategy for National Infrastructure

  • 8/4/2019 Pfi Credit Crisis

    29/37

    28 prt Thr Financing PFI projects in the credit crisis and the Treasurys response

    Renancing and secondary market equity sales

    The risk proles o PFI projects vary considerably during the construction phase3.8

    making it dicult to renance a number o projects on a pooled basis. Once in

    operation, many dierences all away making possible an approach that coordinates

    the right to renance by a number o public authorities. This aligns with the interest o

    lenders in selling loans to ree up reserve capital and then support new projects.

    In March 2010, the House o Lords Select Committee on Economic Aairs,3.9

    in its report Private Finance Projects and off-balance sheet debt8 called or urther

    investigation o any impact on service delivery that may result rom the sale o shares by

    the original private sector investors, known as secondary market sales (See Glossary).

    Treasury guidance currently permits such equity sales without the sharing o resulting

    gains with the public sector. The Treasury has yet to publish research on the contribution

    made by equity investment at various stages in the lie o a public private partnership.

    8 Published 17 March 2010 (HL Paper 63-I and 63-II).

    Figure 14

    Methods o inrastructure unding by sector, with examples

    WtrWstTrsrtTcmserg

    Source: Strategy for National Infrastructure

    pc ct

    User

    unding

    Public

    industry

    commercial

    waste

    operations

    by Local

    Authorities

    Scottish

    water

    Taxpayer

    unding

    Conventional

    capital

    procurement

    most

    roads

    municipal

    waste

    acilities

    lood and

    coastal

    deences

    prvt c

    Taxpayer

    unding

    PPP/PFI M25

    widening

    municipal

    waste

    treatment

    Northern

    Ireland

    water PFIs

    User

    unding

    Economically

    regulated

    private industry

    National

    Grid

    BT

    Openreach

    some

    airports

    England and

    Wales water

    supply and

    sewerage

    Other private

    industry

    electricity

    generation

    cable

    networks

    ports commercial

    waste

    disposal

  • 8/4/2019 Pfi Credit Crisis

    30/37

    Financing PFI projects in the credit crisis and the Treasurys response ax o 29

    Appendix One

    Methodology

    This report examined whether the Government has put in place an economic, ecient

    and eective strategy or nancing public services projects ollowing the banking crisis.The main elements o our eldwork, which took place between November 2009 and

    April 2010, were:

    Mth prs

    Banks survey

    We commissioned KPMG to survey 40 banks and

    inancial institutions, incorporating all the main PFI

    lenders, on an anonymous basis.

    To understand:

    Views o market participants on current PFI

    issues, in particular:

    The appetite or PFI lending.

    Credit terms and conditions.

    Role o The Inrastructure Finance Unit.

    Approaches and lessons learned on major

    recent transactions.

    Future expectations.

    Interviews

    We also held semi-structured interviews with

    other key stakeholders, including HM Treasury,

    Partnerships UK, Department or Environment,

    Food and Rural Aairs (DEFRA), and Partnerships

    or Schools (PFS), and inancial institutions including

    the Bank o Ireland and the European InvestmentBank (EIB).

    To identiy:

    Views o stakeholders.

    Benchmarking and modelling o results

    Using market data provided by KPMG, DEFRA

    and PFS, we analysed the changes in loan terms

    between 2007 and 2009.

    We also commissioned KPMG to analyse the

    aordability impact o change in inancing terms.

    Using a generic PFI inancial model, KPMGs

    sensitivity analysis illustrates how the change in

    each variable has led to changes in unitary charge

    and returns to sponsors.

    To identiy:

    The trends in banks PFI margins and other

    terms beore and during the banking crisis.

    Using sensitivity analysis and the inancial

    model, the relative weight o each driver and

    the extent o any recoverable costs.

  • 8/4/2019 Pfi Credit Crisis

    31/37

    30ax o Financing PFI projects in the credit crisis and the Treasurys response

    Mth prs

    Case studies o changes in scope and bank

    pricing and impact on VFM

    We identiied our case studies which represent

    signiicant developments in the PFI market during

    the credit crisis:

    Greater Manchester Waste the only project in

    which the Treasury made a loan.

    M25 Design Build Finance Operate project.

    Newham School.

    Barnsley School.

    To identiy:

    Comparison o terms at Outline Business Case

    stage and Final Business Case.

    Whether costs and beneits had been checked

    or adjusted.

    The involvement o The Inrastructure Finance

    Unit as a lender.

    The role o the European Investment Bank as

    a lender.

    Documents Review

    We reviewed relevant documents including:

    Documents, emails and minutes relating to

    inancing inrastructure projects held by the

    Treasury in the period leading up to setting up

    The Inrastructure Finance Unit.

    To understand:

    The rationale or setting up The Inrastructure

    Finance Unit.

    Changes in guidance.

    Overseas comparison

    We also reviewed documents rom the

    European PPP Expertise Centre (EPEC)

    on how other countries are undinginrastructure projects.

    EPEC/EIB documents.

    To understand:

    How other countries have responded to

    the crisis.

    Potential savings i the UK were to adopt the

    French guarantee scheme.

    Expert Panel

    We established an expert panel who, together,

    had expert knowledge o the banking and

    inrastructure/project inance sector, to provide

    challenge and assurance or the study.

    The members o the panel were:

    Dr Harry Bush, CB, Board Member and Group

    Director, Civil Aviation Authority

    Jeremy Barker, Director, KPMG

    Corporate Finance

    John Layton, CPA

    Proessor Roger Strange, Proessor o

    International Business at the University

    o Sussex

    To identiy:

    Challenges to study indings.

  • 8/4/2019 Pfi Credit Crisis

    32/37

    Financing PFI projects in the credit crisis and the Treasurys response ax Tw 31

    Appendix Two

    PFI Benchmarking

    As part o the eldwork, and under our direction, KPMG have benchmarked1

    changes in the cost o PFI nance. The table at Fgr 15 below sets out the eects ona base case model o a variety o changes, drawing on data taken rom a broad sample

    o actual projects.

    Figure 15

    Impact on aordability o changes in nancing terms rom 2007 to 2009

    Ctgr assmt

    2007

    assmt

    2009

    a

    utr

    Chrg

    ()

    Chg

    2009

    (%)

    Base Case model (2007) 33,392

    Debt amount as a percentage 89.7% 87.7% 33,790 1.19

    Swap Rate (variable to ixed) 5.1% 4.3% 32,315 -3.23

    Loan margin 0.79% 2.39%-2.59% 36,145 8.24

    Arrangement Fee 1.1% 1.57% 33,530 0.41

    Commitment Fee 0.38% 1% 33,575 0.55

    Interval ater inal repayment 11 months 15 months 33,487 0.28

    Minimum ADSCR/LLCR 1.17x/1.22x 1.19x/1.23x 33,500 0.32

    Swap Credit Spread 0.11% 0.25% 33,662 0.81

    2009 model (rom range o results) 25th Percentile 35,295 5.7

    75th Percentile 35,870 7.4

    noTeS

    (see Glossary or ADSCR and LLCR under Cover ratios)

    1 The unitary charge shown above is based on separately applying the terms & conditions to a typical size deal with

    a capital cost o 170 million and debt o about 190 million and a rate o return to equity o 12.5 per cent.

    2 The sum o the price impacts o each change individually, totalling 8.57 per cent, would be incorrect and greater

    than the price impact rom the base case to the current climate. The reason or a lower result is that increasing the

    unitary charge, to fx a par ticular variable, mitigates the impact o other changes.

    3 I the unitary charge is held constant, the rate o return to equity alls to 6.55 per cent.

    Source: KPMG

  • 8/4/2019 Pfi Credit Crisis

    33/37

    32ax Thr Financing PFI projects in the credit crisis and the Treasurys response

    Appendix Three

    Case Studies

    bchmrkg th M25 dsg b Fc ort prct

    The single Design Build Finance Operate project or the M25 will widen1

    two sections (38 miles). The 30-year cost includes maintaining the Dartord crossings

    and operating 250 miles o existing motorway. This cost increased by 23 per cent rom a

    net present value o 2,756 million beore the banking crisis, to 3,400 million by the time

    the nancing was complete in May 2009.

    We estimate that the largest component o the increase aced by the Highways2

    Agency was an increase, arising rom debt nance costs, o around 15 per cent compared

    to market terms available in 2007. This nding is extrapolated rom our benchmarking

    model or typical cost changes on smaller transactions (see Appendix Two).

    Larger and more complex projects were already acing higher bank costs in3

    March 2008 when the Future Strategic Tanker Aircrat (FSTA) project closed early in

    the credit crisis (see timeline in Figure 7). The M25 nancing terms, when applied to

    the KPMG model, show a cost 6 per cent greater than that derived when applying the

    FSTA nancing terms. This is similar to the lower end o increases experienced since

    October 2008 on other PFI projects.

    We will be reporting separately on the value or money o the M25 project.4

    l mrgs r th Grtr Mchstr Wst rct

    The Greater Manchester Waste Authority is the largest waste authority in England,5

    covering 5 per cent o national waste. The 25 year recycling and waste management

    project includes 36 recycling acilities, across 23 sites, and a waste-red thermal power

    station. The project will reduce local waste diverted to landll by 75 per cent.

    In addition to 184 million rom the European Investment Bank, the banks6

    supporting the project set market pricing or 280 million o lending, leaving a gap o

    120 million. The Inrastructure Finance Unit provided this balance on the same terms as

    the banks.

  • 8/4/2019 Pfi Credit Crisis

    34/37

    Financing PFI projects in the credit crisis and the Treasurys response ax Thr 33

    It is dicult to benchmark this pricing, in order to be satised that lenders did not7behave in an opportunistic manner. Unlike a schools project, primarily providing lower

    risk accommodation, waste projects involve complex industrial processes which rely

    on the nancial and technical ability o companies to perorm inter-related contracts.

    These higher risks result in higher margins and the most similar deal, which had closed

    in 2008, had a provisional margin o 2 per cent that was increased to 2.75 per cent in

    January 2009 at the launch o syndication. Subsequently, at least one bank told Bank o

    Ireland that it could not expect an approval rom its credit committee unless the margin

    was set at more than 3 per cent.

    Greater Manchester Waste closed with margins on the ollowing sliding scale:8

    Construction 3.25%

    Completion to Year 9 3.35%

    Years 9 to 15 3.70%

    Years 15 to 21 3.95%

    Years 21+ 4.50%

    The amount o department credit support accorded to this project, as a result o9

    the banking crisis, was increased rom 109.5 million to 124.5 million. In January 2007,

    the second stage review by Partnerships UK commented It is also apparent romthe bids received, that the Authoritys original cost assumptions were excessively

    conservative, hence the considerable aordability headroom.

    Additional Appendices Four and Five are at www.nao.org.uk/inrastructure-

    nancing-2010.

  • 8/4/2019 Pfi Credit Crisis

    35/37

    34 Gssr Financing PFI projects in the credit crisis and the Treasurys response

    Glossary

    Trm dft

    Cover Ratios Ratios that measure the extent to which current and uture

    liabilities to lenders are covered by available cash fows.

    There is a minimum Annual Debt Service Cover Ratio

    (ADSCR) and a Loan Lie Cover Ratio (LLCR).

    Debt service costs The periodic instalments o loan principal and interest, and

    associated ees, due rom a consortium to its lending banks.

    Floating/variable

    interest rate

    A rate o interest which varies periodically, in accordance

    with a stated market reerence, usually the London

    Interbank Oered Rate (LIBOR).

    Interest/lending margin An additional amount that a bank charges on a commercial

    loan over and above its own cost o providing the loan. The

    margin compensates the risk o not having the loan repaid,

    potentially providing a prot.

    LIBOR London Interbank Oered Rate. The interest rate at which

    banks will lend to each other, which became dicult to

    determine at times during the banking crisis.

    Renancing The process by which the unding terms, put in place at

    the outset o a PFI contract, are later changed, usually

    with the aim o creating benets or renancing gains.

    Renancing may be benecial where project risk has

    reduced, or example, ater the completion o construction.

    Reserve Capital The amount o capital regulators require a bank to hold

    in relation to its lending based on international guidance

    produced by the Basel Committee on Banking Supervision.

    Secondary market The market or buying and selling shares in project

    companies that, usually, have commenced trading.

    Swap An arrangement whereby a loan which has a variable rate

    o interest (which continually changes in relation to market

    rates o interest) is exchanged or a loan which has a xed

    rate o interest.

    Unitary Charge The amount that the public body contracts to pay

    each month or the service being delivered. It will cover

    operations and maintenance, on a whole-lie basis as well

    as the ully nanced construction cost.

  • 8/4/2019 Pfi Credit Crisis

    36/37

    Design and Production by

    NAO Communications

    DP Re: 009310-001

    This report has been printed on Consort

    155 and contains material sourced rom

    responsibly managed and sustainable

    orests certiied in accordance with FSC

    (Forest Stewardship Council).

    The wood pulp is totally recyclable and

    acid-ree. Our printers also have ull ISO

    14001 environmental accreditation

    which ensures that they have eective

    procedures in place to manage waste and

    practices that may aect the environment.

    002825

  • 8/4/2019 Pfi Credit Crisis

    37/37

    Published by TSO (The Stationery Oice) and available rom:

    o

    www.tsoshop.co.uk

    M, Th, Fx & em

    TSO

    PO Box 29, Norwich, NR3 1GN

    Telephone orders/General enquiries: 0870 600 5522

    Order through the Parliamentary Hotline

    Lo-Call 0845 7 023474Fax orders: 0870 600 5533

    Email: [email protected]

    Textphone: 0870 240 3701

    The Parliamentary Bookshop

    12 Bridge Street, Parliament Square,

    London SW1A 2JX

    Telephone orders/General enquiries 020 7219 3890

    Fax orders: 020 7219 3866

    Email: [email protected]

    Internet: http//www.bookshop.parliament.uk

    TSo@bckw thr accrt agts

    Customers can also order publications rom:

    ISBN 978-0-10-296546-9

    14.75