Petition No 797 of 2012 BEFORE THE UTTAR PRADESH ...€¦ · Power, Govt. of India (hereinafter...
Transcript of Petition No 797 of 2012 BEFORE THE UTTAR PRADESH ...€¦ · Power, Govt. of India (hereinafter...
Page 1 of 46
Petition No 797 of 2012
BEFORE
THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION
LUCKNOW
Date of Order : 2nd April, 2013
PRESENT:
1. Hon’ble Shri Shree Ram, Member
2. Hon’ble Smt. Meenakshi Singh, Member
IN THE MATTER OF:
Adoption of transmission tariff under Section 63 of the
Electricity Act, 2003 with respect to intra-state transmission
system, to be established by South East U.P. Power
Transmission Company Limited.
AND
IN THE MATTER OF
Petitioner South East U.P. Power Transmission Company Limited
Shalimar Titanium, 601-602, 6th floor, Plot no TC/G-1/1,
Vibhuti Khand, Gomti Nagar, Lucknow - 226010.
Respondents 1. Managing Director, UPPTCL, Lucknow
2. Managing Director, PVVNL, Meerut
3. Managing Director, DVVNL, Agra
4. Managing Director, PuVVNL, Varanasi
5. Managing Director, MVVNL, Lucknow
Page 2 of 46
The following were present:
1. Sri P.K. Sharma, Chief Engineer, UPPTCL
2. Sri D.C. Chaudhry, Superintendent Engineer, UPPTCL
3. Sri A. N. Gupta, Executive Engineer, UPPTCL
4. Sri Alfonso, Director, SEUPPTCL
5. Sri S.K. Bhattacharya, Director, Business Development, SEUPPTCL
6. Sri Ravinder Singh, CGM, SEUPPTCL
7. Sri R.L. Singh, GM, SEUPPTCL
8. Sri A.K. Ganesan, Advocate, SEUPPTCL
9. Sri S.S. Mehta, Consultant, SEUPPTCL
Order
(Date of Hearing 20.11.2012)
1) The Petitioner, M/s South East UP Power Transmission Company Limited
(SEUPPTCL) has filed this petition on 06-03-12 under section 63 of Electricity
Act,2003 (the Act) and in accordance with Para 12.4 of ‘Tariff Based
Competitive Bidding Guidelines for Transmission Service’, issued by Ministry of
Power, Govt. of India (hereinafter referred to as “GOI”), for adoption of
transmission tariff with respect to the development of following intra-state
transmission system titled “765KV S/C Mainpuri-Bara line with 765KV/400KV
AIS at Mainpuri and associated Schemes/Works” on ‘Build, Own, Operate &
Maintain and Transfer’ ((hereinafter referred to as “BOOT”)) basis.
Elements of Transmission System titled “765KV S/C Mainpuri-Bara line with
765KV/400KV AIS at Mainpuri and associated Schemes/Works”
S.No. Name of the Transmission Element / Project
(I) Transmission lines
1 765kV SC Mainpuri - Unnao with Quad Bersimis (175Kms)
2 400kV DC (Quad Moose) Mainpuri (765kV) - Aligarh (120kms)
3 LILO of both circuits of 400kV DC Orai - Mainpuri (PG) at Mainpuri (765kV) with Twin Moose (30Kms)
Page 3 of 46
4 765kV 2x SC Mainpuri - Bara with Quad Bersimis (2x350kms)
5 LILO of 400kV Panki - Obra at 400kV Rewa Road with Twin Moose (12 kms)
6 400kV DC (Quad Moose) Rewa Road -Karchhana (30kms)
7 400kV DC (Quad Moose) Rewa Road -Meja (25kms)
8 400kV DC (Quad Moose) Bara - Meja (25kms)
9 400kV DC (Quad Moose) Bara -Karchhana (30kms)
10 400kV DC (Quad Moose) Tanda - Gonda (100kms)
11 400kV DC (Quad Moose) Gonda -Shahjahanpur (230kms)
12 LILO of 400kV Sarojininagar - Kursi Road (PG) at 400kV Sultanpur Rd, Lucknow with Twin Moose (20kms)
13 LILO of 400kV Obra - Sultanpur at 400kV Aurai with Twin Moose (15kms)
(II) Substations
1 2x1000MVA (765/400kV) AIS at Mainpuri
2 2x315MVA (400/220kV) GIS at Rewa Road
3 2x315MVA (400/220kV), 2x100MVA (220/132kV) AIS at Gonda
4 2x500MVA( 400/220kV), 2x160MVA, (220/132kV) GIS at Sultanpur
Road, Lucknow
5 2x315MVA ( 400/220kV), 2x160MVA(220/132kV) AIS at Aurai
(III) Bus Switching-Arrangement
1 Mainpuri : One & half breaker with double main bus scheme for 765 &
400kV side
2 Rewa Road : Double Main Bus scheme for 400kV and 220kV side
3 Gonda : One & half breaker with double main bus scheme for 400kV, Double main and transfer scheme for 220kV & single main and transfer bus scheme for 132kV side
4 Sultanpur Road, Lucknow : Double Main Bus scheme for 400kV , 220kV & 132kV side
5 Aurai : One & half breaker with double main bus scheme for 400kV, Double main and transfer scheme for 220kV & single main and transfer bus scheme for 132kV side
2) The Petitioner has also enclosed the copies of following documents with the
petition:-
Page 4 of 46
(a) Letter of Intent (LOI) dated 05-07-11, issued by UPPTCL to M/s Isolux
Corsan CONCESIONES S.A. (hereinafter referred to as “Isolux” or
“Successful Bidder”) to establish the transmission system for “765KV S/C
Mainpuri-Bara line with 765KV/400KV AIS at Mainpuri and associated
Schemes/Works” (hereinafter referred to as “Project” or “Transmission
System” or “Package-1”) specified under Tender Specification no ESD-765/4
(Package-1) and all its amendments thereof till the bid deadline.
(b) The Transmission Service Agreement (TSA) signed on 20-01-12 by
SEUPPTCL and the Long Term Transmission Customers (hereinafter
referred to as the “LTTCs”) of the Transmission System namely –
Paschimanchal Vidyut Vitran Nigam Ltd (PVVNL), Dakshinanchal Vidyut
Vitran Nigam Ltd (DVVNL), Purvanchal Vidyut Vitran Nigam Ltd (PuVVNL)
and Madhyanchal Vidyut Vitran Nigam Ltd (MVVNL).
3) The Petitioner has also submitted that:-
a) The Energy Task Force (herein after referred to as “ETF”) constituted by the
Government of Uttar Pradesh (herein after referred to as “GoUP”) has
authorized U.P. Power Transmission Corporation Ltd (hereinafter referred to
as “UPPTCL”) to act as the Bid Process Coordinator (hereinafter referred to
as “BPC”) to carry out the bidding process for selection of the Successful
Bidder as Transmission Service Provider (hereinafter referred to as “TSP”)
for construction, operation and maintenance of the transmission lines in the
Project on BOOT basis through tariff based competitive bidding process
under the guidelines of section 63 of the Act.
b) South East UP Power Transmission Company Ltd. (hereinafter referred to as
the “SEUPPTCL or “Petitioner”) was incorporated on 11th September, 2009
under the Companies Act, 1956 by the BPC/UPPTCL as it is wholly owned
subsidiary to act as Special Purpose Vehicle (SPV) to initiate the activities of
the Project and to subsequently to act as TSP after being acquired by the
Successful Bidder.
Page 5 of 46
c) Subsequent to the process of competitive bidding conducted by BPC, M/s
Isolux Corsan Concesiones S.A. has been evaluated as the successful
bidder and in this regard a Letter of Intent (LOI) has been issued by the BPC
on 05-07-11. Thereafter the Transmission Service Agreement has been
signed on 20-01-12 between the Petitioner and the LTTCs of the
Transmission System.
4) While initiating the bidding process, UPPTCL had submitted that the selection of
the developer would be as per ‘Tariff based Competitive Bidding Guidelines for
Transmission Service’ and ‘Guidelines for Encouraging Competition in
Development of Transmission Projects’ (hereinafter referred to as the
“Guidelines”), issued by Ministry of Power. After completion of the bidding
process and subsequent to the signing of SPA and TSA, UPPTCL submitted
that the bidding documents (RFQ & RFP) were made as per the Standard Bid
Documents of Ministry of Power, GOI, after incorporating the provisions
contained in the Commission’s orders and certified that the bid process & bid
evaluation has been carried out in conformity with tariff based competitive
bidding guidelines for transmission service of GOI.
5) The Commission heard the above petition on 26-04-12 and directed UPPTCL
and SEUPPTCL vide its order dated 18-05-12, to submit certain documents to
the Commission, including the Certification by the Bid Evaluation Committee
(hereinafter referred to as “BEC”) required under Para 12.4 of the Guidelines,
within three weeks from the date of the order and decided to fix the next date of
hearing in the matter after filing of complete documents by both the parties.
6) UPPTCL submitted the copies of the following documents to the Commission
vide its letter dated 07-06-12:-
a) UP Govt. OM no 491 dated 07-09-09 authorizing the Energy Task Force
of GoUP to act as Empowered Committee.
Page 6 of 46
b) UP Govt. OM no 492 dated 07-09-09 for nomination of UPPTCL to act as
the Bid Process Coordinator (BPC) to process the bids for selection of
developer to establish the Transmission System under PPP.
c) UP Govt. OM no 493 dated 07-09-09 for formation of Bid Evaluation
Committee (BEC), comprising of Industrial Development Commissioner
(as Chairman of BEC), Principal Secretary (Law), Principal Secretary
(Finance), Principal Secretary (Planning), Secretary (Energy), Chairman
UPPTCL, MD UPPTCL (as Convener of BEC), Member Central Electricity
Authority, Director (Finance) UPPTCL and Executive Director
(Transmission) UPPTCL.
d) OM No 557 dated 30-10-09 authorizing Chairman UPPTCL for formation
of bid opening committee comprising of Executive Director
(Transmission), Chief General Manager (Finance), Chief Engineer
(765kv), Superintending Engineer (765kv) to open RFQ & RFP bids.
e) Intimation to the Commission by the Executive Director UPPTCL for
initiation of bidding process through letter dated 02-09-09.
f) Publication of the combined RFQ & RFP notice in ‘The Economic times’
(New Delhi, Mumbai and Bangalore), Times of India (New Delhi,
Mumbai), Hindustan times (New Delhi), Business Standard (New Delhi
and Mumbai) and Financial Express (New Delhi and Mumbai) through
letter dated 10-08-09 of UPPTCL.
g) Intimation of the combined RFQ & RFP notice to the Embassy of
Australia, Canada, China, France, Germany, Italy, Japan, New Zealand,
Russian Federation, Spain, South Africa, Switzerland, UAE, UK & USA
through letter dated 12-08-09 of UPPTCL.
h) Letter dated 29-06-11 of CMD UPPTCL to MDs of the distribution
companies (MVVNL, PVVNL, DVVNL & PuVVNL) for nomination to sign
TSA on behalf of LTTCs.
i) Authorization of the distribution companies to sign TSA.
j) Minutes of meeting of Bid Evaluation Committee (BEC) held on 23-02-10
and 30-03-11.
Page 7 of 46
k) Minutes of meeting of Energy Task Force (ETF) held on 24-02-10,
28-02-11 and 30-03-11 under Chairmanship of Chief Secretary, GoUP.
l) Letter no 452 dated 26-05-11 of Secretary, GoUP to CMD UPPTCL
conveying the decision of the Govt. to award the transmission works
under Package-1 to Isolux Corsan at levelized tariff of Rs 870 Cr.
7) The brief contents of the following documents submitted by UPPTCL is as
hereunder:-
a) Minutes of meeting of Bid Evaluation Committee held on 23-02-10
The meeting was held under the Chairmanship of IDC, GoUP against
transmission projects under PPP in specification no ESD/765/4. BEC
agreed to the consultant’s report dated 18-02-10 and recommended ETF for
approving Isolux and Cobra as the qualified bidders for the RFP stage while
disqualifying L&T Transco and Sterlite at RFQ stage itself in accordance
with the legal view of Additional Advocate General of GoUP.
b) Minutes of meeting of Energy Task Force held on 24-02-10
ETF agreed with recommendations of Bid Evaluation Committee and
accorded its consent to issue RFP to Isolux Corsan Concesiones S.A. and
Cobra Instalactiones Servicios S.A.
c) Minutes of meeting of Energy Task Force held on 28-02-10
ETF approved minimum benchmark price for Package-1 as Rs 833.76Cr.
ETF also decided that if the price bid lies within 10% above the minimum
benchmark price then BEC to negotiate with the L1 bidder otherwise if the
price bid lies beyond 10% above the minimum benchmark price then Swiss
Challenge Method is to be adopted.
d) Minutes of meeting of Bid Evaluation Committee held on 30-03-11
The meeting was held under the Chairmanship of IDC, GoUP regarding
PPP transmission projects (Package-1) in specification no ESD/765/4. BEC
recommended to award Package-1 to Isolux Corsan at the levelized tariff of
Page 8 of 46
Rs 870Cr per annum and placed its recommendations before ETF for
further decision in the matter. The minutes also says that the consultant had
presented RFP bid evaluation report before BEC, according to which the
quoted levelized tariff of Isolux Corsan for Package-1 was Rs 910.182Cr
which was the lowest and therefore Isolux was the lowest bidder in
Package-1 followed by Cobra. The consultant further pointed out that L1
levelized tariff was within 10% of the benchmark levelized tariff so in view of
decision taken by ETF, there was no need to invoke Swiss Challenge
Method, and BEC might negotiate with L1-bidder. In view of the
recommendations of the consultant, BEC negotiated with L1 bidder which
agreed to reduce the levelized tariff to Rs 870Cr per annum which was still
4.35% higher than the benchmark levelized tariff approved by ETF. The
minutes further says that in view of large quantum of lines involving right of
way problems and expenses, the Bid Evaluation Committee accepted the
price above 4.35% over the benchmark price and placed its
recommendations before ETF.
e) Minutes of meeting of Energy Task Force held on 30-03-11
ETF while agreeing with the recommendations of BEC, accorded its consent
to award Package-1 to Isolux Corsan at levelized tariff of Rs 870Cr and
directed to accord the approval of the Cabinet also before executing any
agreement with the bidder.
8) SEUPPTCL submitted the copies of the following documents to the
Commission vide its letters dated 30-04-12 and 07-06-12:-
a) Certification of Incorporation, Memorandum of Association, Article of
Association and Certificate of Commencement of Business of
SEUPPTCL.
b) Board resolution of SEUPPTCL for authorization to sign Transmission
Service Agreement (TSA).
c) Board resolution of Mainpuri Power Transmission Private Limited for
authorization to sign Share Purchase Agreement (SPA).
Page 9 of 46
d) Board resolution of SEUPPTCL for amendment to Articles of Association
of SEUPPTCL.
e) Amended Articles of Association of SEUPPTCL.
f) Explanatory Statement of SEUPPTCL pursuant to section 173(2) of the
Companies Act, 1956.
g) Notice dated 22-03-12 issued by Registrar of Companies (RoC), Kanpur
to SEUPPTCL.
h) Reply of SEUPPTCL dated 01-06-12 to the Registrar of Companies.
i) Electronic copies of Form-32, 18, 23, 22B filed by SEUPPTCL in RoC.
9) Subsequent to the submission of a conformity certificate of Sri Nevneet Sehgal,
CMD UPPTCL in Feb’12, another conformity certificate dated 17-07-12 of Sri
Anil Kumar Gupta, Principal Secretary, GoUP, has been submitted to the
Commission. However, the Commission directed UPPTCL, vide letter dated 27-
07-12, to submit the Certification of Bid Evaluation Committee at the earliest.as
per requirement of guideline.
MD UPPTCL, vide letter dated 30-07-12, intimated the Commission that BEC
was formed by Empowered Committee with a specific purpose for evaluation of
bids and after the completion of process of evaluation, BEC is not in existence.
He further added that RFQ & RFP evaluation reports as cleared by BEC, ETF &
UP Govt. along with all related minutes of meeting have already been submitted
to the Commission and therefore the certification by Principal Secretary
(Energy) should suffice the requirement envisaged under para-12 of Guidelines.
In light of this, MD UPPTCL requested the Commission to accept the certificate
already submitted by Principal Secretary (Energy) Govt of U P.
10) The Commission observed that in spite of its clear directions to UPPTCL vide
order dated 18-05-12 and subsequent letters dated 27-07-12 & 08-08-12, the
certification by the Bid Evaluation Committee has not been submitted. The
Commission also observed that apart from the non-submission of the
Certification by BEC, there are some more issues which need to be addressed.
Page 10 of 46
In light of these facts, the Commission decided to review all the pending issues
through a hearing and accordingly issued a notice dated 01-11-12 to all the
concerned parties (SEUPPTCL, UPPTCL, PVVNL, DVVNL, PuVVNL and
MVVNL) for hearing in the matter on 20-11-12.
11) Sri Avdhesh Kumar Verma, Chairman Rajya Vidyut Upbhokta Parishad and the
member of State Advisory Committee submitted a representation on 19-11-12
and sought the Commission’s permission to attend the hearing on 20-11-12.
Sri Verma also raised the following points:-
i. After the finalization of the tender and against the provisions of TSA/RFQ,
the State Energy department / UP Power Transmission Corporation Limited
has constituted a committee to change the conductor to AAAC in place of
ACSR Moose & Bersimis, which is not in line with clause 9.6.4 of the
bidding guidelines and the provisions of Central Vigilance Commission. In
view of this, any consideration for tariff adoption is against the bidding
guidelines.
ii. There is a provision in clause 12.4 of Tariff based Competitive Guidelines of
GOI that the final TSA along with the certification by the Bid Evaluation
Committee shall be forwarded to the appropriate Commission for adoption
of tariffs in terms of section 63 of the Act. It confirms that unless the
Commission looks into the certification by Bid Evaluation Committee, it is
not possible to conclude that the bidding process was transparent.
iii. The Commission will adopt the tariff under section 63 of Electricity Act 2003
after ensuring that the bidding guidelines of GOI have been followed. The
present process itself says that it is not transparent therefore the
Commission needs to pay its attention on above points.
Similarly an intervener application on behalf of Sri Rama Shankar Awasthi
has been filed on 20-11-12 at 3:30pm. Since the application of Sri Awasthi was
received after the hearing even then the Commission has taken it on the
record. The contents of this application are reproduced below:
Page 11 of 46
a. The present Intervener Application is being filed in the present
proceedings being petition No. 797/2012.
b. That it may be stated that as per clause no.12 (a) electricity act 2003 no
person shall transmit electricity unless he is authorized to do so by a
license issued under section 14 or is exempt under sec.13.
c. That as per information received by the applicant till today Commission
has not granted transmission license to South East U.P. Power
Transmission Company Limited and nor exempted for transmission
license on the recommendation of the appropriate govt. in accordance
with the national policy formulated under section 5 in public interest,
direct, by notification that subject to such conditions and restrictions.
d. That as per clause no 9.6.4 of tariff based competitive bidding guidelines
for transmission services approved by Ministry of Power, GOI, and TSA
proposed to be entered with the selected bidder. The TSA proposed in
the RFP stage may be amended based on the inputs received from
bidders during the pre bid conference and it will be made available to all
RFP bidders. No further amendments shall be carried out in the TSA.
As per my knowledge based upon daily news paper that above
company is pursuing to State Govt. and UPPTCL FOR change of ACSR
Moose and Bersimis conductor to AAAC Conductor. So it is a clear cut
violation of TSA guideline.
e. That as per clause no 12.4. of tariff based competitive bidding guidelines
for transmission services approved by Ministry of Power, GOI, The final
TSA along with the certification by the Bid Evaluation Committee shall
be forwarded to the Appropriate Commission for adoption of tariffs in
terms of Section 63 of the Act.
f. As per my knowledge Bid Evaluation Committee are not forwarded
Certificate to commission.
g. That as per clause no. 61 read with 181 UPERC framed Terms and
condition for Transmission Tariff Regulation 2006.
Page 12 of 46
h. That clause no 1.2.1. says that These regulations shall apply, for the
purposes of ARR filing and tariff determination, to all the transmission
licensees including deemed Transmission Licensees within the State of
Uttar Pradesh.
i. That clause no. 2.1.1. says that The Transmission Licensee shall file the
Aggregate Revenue Requirement (ARR) petitions complete in all respect
along with requisite fee as prescribed in the Commission’s Fee and Fine
Regulations on or before 30th November of each year containing the
details of the estimated expenditure and the expected revenue that it may
recover in the ensuing financial year at the prevailing tariff. Information
as per formats specified in Annexure A to these regulations shall form
part of the ARR filings.
j. That as per clause no. 2.3.2 of Transmission Tariff Regulations 2006
says that after receipt of required information, the UPERC may take
appropriate orders regarding admittance of petition, initiation of
proceedings and determination of ARR / Tariff in accordance with the
provisions of its Conduct of Business Regulations. The licensee shall,
within 7 days of the issuance of the admittance order by the Commission,
publish the salient points of the ARR/Tariff petition in such abridged
format and manner, as approved by the Commission, in at least two
national daily newspapers (one English and one Hindi) circulated in its
area of operation for public objections/suggestions/comments.
k. That as per provision of electricity act 2003 and transmission tariff
regulation 2006 petition of transmission charges can file only
transmission licensee and in this case when commission are not grant
transmission license to south east U.P. Power Transmission company
limited then how commission can accept transmission charges petition of
South East U.P. Power Transmission company limited.
l. That UPERC might have appreciated that transmission licensee was
obliged to publish ARR data in News Paper for public objections/
suggestions as per provisions of clause no.2.3.2 of Transmission Tariff
Regulations 2006.
Page 13 of 46
m. That the action of the Transmission Licensees is against the provisions of
the Electricity act 2003 and transmission tariff regulations 2006 as well as
the ratio laid down by the Court/Tribunal in this regard.
n. That the action of the Transmission Licensees is against the provisions of
the Electricity act 2003 and transmission tariff regulations 2006 as well as
the ratio laid down by the Court/Tribunal in this regard.
o. That the issues involved in the aforesaid proceedings is of public
importance. The State exchequer has to suffer huge loss due to the non
compliance of the mandatory provisions of law.
p. That in view of the aforesaid facts and circumstances, it is expedient in
the interest of justice that this Hon’ble Commission may graciously be
pleased to allow the aforesaid application and permit the applicant to
have say in the aforesaid matter and further the applicant may be
permitted to file detailed and comprehensive objection in the aforesaid
matter.
The Commission also observed that Sri Dhruv Kumar, Advocate and Sri
Sarthak of Prastav Dainik also signed the attendance sheet of the hearing but
as they did not represent either UPPTCL or SEUPPTCL, therefore the
Commission did not permit them to attend the hearing.
12. During the hearing, the Commission observed that none from the four
distribution companies – PVVNL, DVVNL, MVVNL and PuVVNL
participated. The Commission expressed its concern on their absence
especially in the light of the fact that the Transmission System, under the
present context, is being developed for the distribution companies only, who
are its Long Term Transmission Customers (LTTCs). It is the distribution
companies who jointly signed the Transmission Service Agreement (TSA)
with SEUPPTCL and from whom the costs would be recovered during the
entire term of 35 years of TSA.
Page 14 of 46
13. The Commission also expressed its displeasure as the Director, UPPTCL
did not participate in the hearing. The Commission inquired from the present
members of UPPTCL whether they are conversant with the issues of the
petition and after obtaining an affirmative reply from them, the Commission
initiated the proceedings.
14. During the hearing the Commission took up the following issues:-
a) Certification by Bid Evaluation Committee
The Commission reiterated its earlier stand for submission of Certification by
Bid Evaluation Committee after quoting the provisions of section-63 of the
Act and para-12.4 of the Guidelines. The tariff adoption U/s 63 of the Act
refers to the bidding process in accordance with the guidelines issued by the
Central Government and Para-12.4 of ‘Tariff based Competitive-bidding
Guidelines for Transmission Service’ of GOI requires final TSA along with
the Certification by Bid Evaluation Committee to be forwarded to the
Commission for adoption of tariffs. In light of above and its earlier order
dated 18-05-12, the Commission inquired why the required Certification of
BEC has not been submitted so far by UPPTCL.
Sri Chaudhry of UPPTCL replied that two certificates, in this regard, have
been submitted to the Commission; one issued by CMD UPPTCL in Feb’12
and another issued by Secretary (Energy) GoUP in July’12. He further added
that the State Govt. has formed the Bid Evaluation Committee, convened all
its meetings and conveyed all its decisions. UPPTCL has no role in all these
processes. UPPTCL neither formed BEC nor convened its meetings. He
submitted that Secretary (Energy) in his certificate dated 17-07-12 has
certified that the bid process & bid evaluation took place as per the
Guidelines of GOI. Sri Chowdhary further submitted that since the Bid
Evaluation Committee is not in existence after the evaluation of bids and all
the relevant documents - BEC minutes, ETF minutes etc have already been
Page 15 of 46
submitted to the Commission, therefore the certificate issued by Secretary
(Energy) may be accepted by the Commission.
The Commission emphasized the need of the Certification by Bid Evaluation
Committee only and inquired categorically why UPPTCL, in its capacity of
BPC, could not obtain the same? UPPTCL was unable to put forth any valid
reason for the same. On the instruction of the Commission, Sri Gupta of
UPPTCL read the provision of section 63 of the Act, the relevant clause of
the guidelines of GOI. He also read the O.M. No 493 dated 07-09-09 of
GoUP, issued by Secretary (Energy) for formation of Bid Evaluation
Committee, as hereunder:-
Section 63 of the Act for Determination of tariff by bidding process
“Notwithstanding anything contained in section 62, the Appropriate
Commission shall adopt the tariff if such tariff has been determined
through transparent process of bidding in accordance with the guidelines
issued by the Central Government.”
Para 12.4 of Tariff based Competitive-bidding Guidelines for Transmission
Service of GOI
“The final TSA along with the certification by the Bid Evaluation
Committee shall be forwarded to the Appropriate Commission for
adoption of tariffs in terms of Section 63 of the Act.”
l fpo] mRr j i zns”k “kkl u ] Å t kZ ¼fut h fu os”k½ i z d ks’B } kj k t kj h d k; kZ y; K ki l a[ ; k
4 93 fnu kad 07 &09 &0 9
* * X ; kj goha iapo’ khZ ; ; kst u k esa i kj s’ k.k Ld a/ k d h ifj ; kst u kvksa d k fØ ; kU o; u i h0 i h0 i h0 fof/ k } kj k d j ku s gsr q fod kl dr kZ d s p; u gsr q vkekaf=r fu fon k iz i =ksa ¼vkj 0 ,Q0 D;w0 o vkj 0 ,Q0 i h0 ½ ds vkWad yu l fefr d k xBu fu Eu or fd ; k t kr k gS %&
1 - voLFkkiu k , oa vkS | ksfxd f od kl vk; q Dr ] m0 iz 0 “kklu ¼v/ ; { k½ 2 - i z eq [ k l fpo] U ; k; ] m0 i z0 “kkl u ¼l n L; ½ 3 - i z eq [ k l fpo] foRr ] m0 iz0 “kkl u vFkok mu d s i z fr fu f/ k ¼l n L; ½ 4 - i z eq [ k l fpo] fu ; kst u ] m0i z 0 “kkl u ¼l n L; ½
Page 16 of 46
5 - l fpo] Å t kZ ] m0 i z0 “kkl u ¼l n L; ½ 6 - v/ ; { k] m0 i z0 i koj V ªkWal fe”ku d kj i ksj s”ku fy0 ¼l n L; ½ 7 - i z cU / k fun s”kd ] m0 i z0 i koj V ªkWal fe”ku d kj i ksj s”ku fy0 ¼l n L; @la; kst d ½ 8 - l n L; ] dsU n z h; fo|q r iz kf/ kd j .k vFkok mu ds i z fr fu f/ k ¼l n L; ½ 9 - fu ns”kd ] foRr m0 i z0 i koj d kj i ksj s”ku fy0 ¼l n L; ½ 1 0- vf/ k”kkl h fu n s”kd ¼i kj s’ k.k½] m0 i z 0 i koj V ªkWal fe”ku dkj i ksj s”ku fy0
¼l n L; @l gla; kst d ½ * *
The Commission clarified UPPTCL that as per the guidelines of GOI,
as read above the Certification by Bid Evaluation Committee is required. The
Commission is of the view that although it was the responsibility of the
members of the Bid Evaluation Committee to certify the transparency in the
bid evaluation process (RFQ & RFP), but this does not bar UPPTCL from its
responsibility as the Bid Process Coordinator which had to necessarily obtain
the required certification from the Bid Evaluation Committee. The
Commission expressed its displeasure in the manner UPPTCL played its
role of Bid Process Coordinator and could not obtain the certification of BEC
especially in the light of the fact that the requirement of said certification has
been effective since Oct’08 whereas the bidding process of package-1 got
completed three years thereafter. The Commission considered it as a very
serious lapse on the part of UPPTCL.
In view of above, the Commission directs UPPTCL to submit the Certification
by Bid Evaluation Committee, within two weeks from the date of this order. It
is also clarified that if the required certification is not submitted within the
said time period UPPTCL shall be held responsible for delay in adoption of
Tariff.
b) Use of Conductor in the Project
The Commission has addressed this issue in the same petition earlier also
vide its order dated 18-05-12 when a letter was submitted by SEUPPTCL,
one day before the first hearing in this petition, stating that SEUPPTCL is
planning to use All Aluminium Alloy Conductor (AAAC) conductor in the
Page 17 of 46
implementation of the Project. The Commission took up this issue in the
hearing on 26-04-12 and accordingly conveyed its decision vide para-6 of
the order dated 18-05-12 that it did not agree to any amendment of the
specifications of the project after the completion of the bidding process.
Subsequently, in reference to another letter dated 29-05-12 of SEUPPTCL,
the Commission issued a letter dated 11-06-12 and denied any amendment
of para-6 of its order dated 18-05-12. It is relevant to mention here that the
Commission had rejected the similar request of Western UP Power
Transmission Company Limited (WUPPTCL) vide its order dated 19-03-12 in
petition 782/2012, who are the successful bidder for the development of
package-2 and whose petition for the adoption of transmission charges
under section 63 of the Act is pending before the Commission. In its petition
WUPPTCL had requested for approval of certain deviations including an
option for use of Bersimis-equivalent AAAC and Moose-equivalent AAAC for
765kv and 400kv lines respectively instead of using only ACSR Bersimis &
ACSR Moose conductors mentioned in the bid documents and accordingly
sought amendments in relevant clauses of RFP & TSA documents. UPPTCL
had strongly objected their request to use Bersimis & Moose equivalent
AAAC in place of ACSR conductor because the benchmark price of the
project cost was worked out at the bidding stage with the use of ACSR
conductors. AAAC even if found technically better, has the financial
implications, affecting the overall price structure of the project and it cannot
be allowed at post bid stage.
The relevant portions of the Commission’s orders dated 18-05-12, 19-03-12
and letter dated 11-06-12 are being reproduced as hereunder:-
Order dated 18-05-12 in petition no 797/2012
“(6) In reference to the letter submitted by SEUPPTCL on 25-04-12,
stating that it shall use ‘All Aluminum Alloy Conductor’ (AAAC) for the
establishment of the project, instead of the conductor specified in the
bidding documents, the Commission held that at this stage when the
bidding process has been completed and the Letter of Intent (LOI) has
Page 18 of 46
been issued by the BPC to the successful bidder, the Share Purchase
Agreement (SPA) has been signed by the concerned parties and the
Transmission Service Agreement (TSA) has been executed between
SEUPPTCL & the Long Term Transmission Customers (LTTCs) it cannot
agree to any amendment of specifications of the project.
In view of above, the Commission does not take cognizance of the said
letter dated 24-04-12 of SEUPPTCL.”
Letter dated 11-06-12 addressed to SEUPPTCL
“Please refer to the clause 1.3 of RFQ and 1.5(a) & 2.14.2.4 of RFP
documents. The survey report provided to you by the Bid Process
Coordinator (UPPTCL) at RFQ stage explicitly mentions that ACSR
conductors are to be used. Besides, after issuance of LOI, amendment in
the specifications is not permissible, as mentioned in the Commission’s
order dated 18-05-2012. As such I am directed to inform you that
modification of para-6 of the said Commission’s order is not required.”
Order dated 19-03-12 in petition no 782/2012 of WUPPTCL
“5(c) Use of other equivalent type of transmission line conductors The petitioner is of the view that Indian utilities have been specifying and
using ‘Bersimis equivalent’ and ‘Moose equivalent’ All Aluminium Alloy
Conductor (AAAC) instead of ACSR due to the benefit of lower losses,
lower weight and lower sag and therefore requested that an option may be
given for use of ACSR/AAAC Bersimis/Bersismis-equivalent and
Moose/Moose-equivalent conductors for 765kv and 400kv lines
respectively, instead of using only Bersimis and Moose conductors,
mentioned in bid documents and accordingly relevant clauses of RFP &
TSA may be amended.”
“6)
……..
UPPTCL strongly objected the petitioner’s request to use Bersimis &
Moose Equivalent AAAC conductor in addition to ACSR conductor, as the
benchmarking of project cost had been carried out at bidding stage with
the use of ACSR conductor as per CERC guidelines. They further
reiterated that any such deviation, at this stage, is not possible as the
equivalent AAAC conductor requires technical suitable study, which even
if found technically better, has the financial implications also and hence
may affect the overall price structure of the project.
……..”
Page 19 of 46
“8) Having heard the deliberations of both the petitioner (WUPPTCL) and
the Bid Process Coordinator (UPPTCL) with due consideration to their
written submissions, the Commission finds that all the issues raised by the
petitioner require amendments in RFP & TSA documents, on the basis of
which, the BPC processed the entire competitive bidding. The
Commission affirmed that as of now it is not going into the merit of the
transparency of the competitive bidding process and asserted that the
same is being taken up separately while considering the petition for
adoption of tariff of package-2. Having said that, the Commission is of the
firm view that in light of the fact that the bidding process has been
completed by the BPC, the Letter of Intent (LOI) has been issued to the
successful bidder, the Share Purchase Agreement (SPA) has been signed
by the concerned parties and the Transmission Service Agreement (TSA)
has been executed between the petitioner and the Long Term
Transmission Customers (LTTCs), the Commission, at this stage, cannot
accord approval to further amend the RFP & TSA documents, on the basis
of which the entire bidding process took place.
9) In view of above, the Commission does not deem it fit to approve now
the amendments sought in this petition.”
Subsequent to its order dated 18-05-12 and letter dated 11-06-12 in this
petition, the Commission observed that several letters, pertaining to use of
the conductor in the Project, were submitted by UPPTCL and SEUPPTCL to
the Commission to resolve the issue of conductor. It made the Commission
understand that the issue is still not settled among the parties, causing
undue delay in the progress of the Project. As the transmission system under
this Project is linked with the evacuation of power of upcoming thermal
power projects (Bara, Karchana, Meja etc) and any delay in its execution
may hamper the evacuation of power from these thermal projects, causing
the consumers of the state to suffer ultimately, therefore the Commission
decided to intervene in the matter. Accordingly, the letters which have been
addressed by the UPPTCL and SEUPPTCL to the Commission to address
the issue of Conductor are being taken on record and have been made the
part of the Petition. SEUPPTCL sent letter No. 109 dated 18.7.2012, letter
dated 12.7.2012. UPPTCL wrote to the Commission letter No. 952 dated
Page 20 of 46
30.07.2012, letter No. 930 dated 25.07.2012 to settle the issue of Conductor.
There are other letters also on the issue between both the parties regarding
this issue. The letters from UPPTCL to SEUPPTCL are No. 952 dated
30.07.2012, No. 1007 dated 28.08.2012, No. 989 dated 14.08.2012. The
letters from SEUPPTCL to UPPTCL are dated 31.08.2012, dated 1.08.2012,
letter No. 108 dated 18.07.2012 on the issue.
Full text of the two letters one of SEUPPTCL dated 18.07.2012 and one of UPPTCL dated
25.07.2012 is reproduced here:
SOUTH EAST U.P. POWER TRANSMISSION COMPANY LIMITED
Shalimar Titanium, 601-602, 6th
Floor, Plot No. TC/G-1/1,
Vibhuti Khand, Gomti Nagar,
Lucknow – 226010, Uttar Pradesh
SEUPPTCL/UPERC/2012-13/109 18-7-2012
The Secretary,
U.P.Electricity Regulatory Commission,
Kisan Mandi Bhawan,
Vibhuti Khand,
Gomti Nagar,
LUCKNOW – 226010
Dear Sir,
Sub: Tender specification ESD 765/4(Package 1) : Establishment of Transmission System
For 765kV S/C Mainpuri – Bara Line with 765/400kV A.I.S. at Mainpuri and Associated
Schemes/Works.
Reg: Use of All Aluminum Alloy Conductor
We refer to our letter SEUPPTCL/UPERC/2012-13/dated 12.7.2012 addressed to you, and
would like to re-iterate the following:
1. Isolux Corsan Concessiones S.A. (hereinafter referred to as ICC) was selected as the
successful bidder for the development, operation and maintenance of the Transmission
System for 765 kV S/C Mainpuri – Bara Line with 765 kV/400 kV AIS at Mainpuri
and Associated Schemes/work. The bids were invited by the Uttar Pradesh Power
Transmission Corporation Limited (UPPTCL) in the year 2010. The bids invited under
Section 63 of the Electricity Act, 2003 based on the competitive bidding documents
notified by the Government of India.
2. The bidding documents issued by UPPTCL consisted of the Request for Qualification
(RFQ), Request for Proposal (RFP) and also the draft of the Transmission Services
Page 21 of 46
Agreement to be entered into by UPPTCL with the successful bidder. The bidding
documents detailed out the terms and conditions of the bidding process and the rights
and obligations to be vested on the successful selected bidder. The terms and
conditions also included the scope of work required to be undertaken by the successful
bidder. The Scope of work provided for in the RFQ is as under:
Sl. No. Transmission System for 765kV S/C Mainpuri-Bara Line with 765mV/400 AIS at
Mainpuri and Associated Schemes/Work
1. Transmission Lines:
1. 765kV Sc Mainpuri – Unnao with Quad Bersimis
(191 ms)
SOUTH EAST U.P. POWER TRANSMISSION COMPANY LIMITED
Shalimar Titanium, 601-602, 6th
Floor, Plot No. TC/G-1/1,
Vibhuti Khand, Gomti Nagar,
Lucknow – 226010, Uttar Pradesh
2. 400 kV DC Quad Moose Mainpuri – Aligarh (120 Kms.)
3. 400 kV DC Twin Moose Mainpuri (765 kV)- Mainpuri (PG) (30 kms)
4. LILO of 400 kV Agra – Agra (PG) at 765 kV Mainpuri
With Twin Moose (90 kms)
5. 765 kV 2xSC Mainpuri – Bara with Quad Bersimis (2x351 kms)
6. LILO of 400 kV Panki – Obra at 400 kV Rewa Road with Twin Moose (12 kms)
7. 400 kV DC (Quad Moose) Rewa Road-Karchhana (20 kms)
8. 400 kV DC (Quad Moose) Rewa Road – Meja (25 kms)
9. 400 kV DC (Quad) Bara-Meja (20 kms)
10. 400 kV DC (Quad Moose) Bara-Karchhana (20 kms)
11. 400 kV D/C (Twin Moose) Tanda-Gonda (100 kms)
12. 400 kV D/C (Twin Moose) Gonda- Shahjahanpur (230 kms)
13. LILO of 400 kV Sarojininagar –Kursi Road (PG) at 400 kV Sultanpur Rd.,
Lucknow with Twin Moose (20 kms.)
14. LILO of 400 kV Obra-Sultanpur at 400 kV Aurai with Twin Moose (15 kms)
II. Sub-Stations:
1. 2X1000MVA, 765/400 KV AIS Mainpuri
2. 3x315QMVA, 400/220kV GIS at Rewa Road
3. 2X315MVA, 400/220kV, 2X100MVA, 220/132Kv AIS
At Gonda AIS
4. 2X500MVA, 400/220Kv, 2X160MVA, 220/132kV AIS at Sultanpur Road,
Lucknow AIS
5. 2X200MVA, 400/132kV AIS at Aurai
III. Switching-stations:
1. Mainpuri: One & half breaker scheme for 765&400kV sides and two main
and transfer scheme for 220kV side
2. Rewa Road: One & half breaker scheme for 400 kV side and two main and
transfer scheme for 220 kV side
Page 22 of 46
3. Gonda: One & half breaker scheme for 400 kV and two main and transfer
scheme for 220kV & single main and transfer bus scheme for 132kV side
4. Sultanpur Road, Lucknow: One & half breaker scheme for 400 kV and two
main and transfer scheme for 220kV & single main and transfer bus scheme
for 132 kV side
5. Aurai: One & half breaker scheme for 400 kV & single main and transfer bus
scheme for 132 kV side
2. The bidding documents required the successful bidder to establish the transmission
system to optimum capacity and based on best utility practices. The bidding documents
did not provide for the nature of the equipments or materials to be used, but left the
same to be decided by the successful bidder. The RFP, inter-alia, provided as under :
“1.3 The TSP shall ensure that design, construction and testing of all equipment,
facilities, components and systems of the Project shall be in accordance with Indian
Standards and Codes issued by Bureau of Indian Standards and only in case they are
not available under certain conditions the other equivalent internationally recognized
Standards and codes shall be followed, with prior approval of CEA.”
3. ICC was adjudged the successful Bidder and was issued a letter of Intent by UPPTCL
on 5th
July, 2011. Subsequently, after completing required formailities, ICC took over
the SPV South-East U.P.Power Transmission Company Limited from UPPTCL.
4.
5. Upon being issued the letter of Intent, ICC began the process of detailed survey of the
line route and all other technical details including the equipment to be procured for the
transmission system. ICC had drawn up the broad technical parameters that would be
the guide line for the engineering/design activities for the transmission system to be
constructed by Isolux. As a part of the bidding exercise, the UPPTCL had only
provided a limited and non-binding survey report for certain lines with the specific
disclaimer that it was for the bidders to conduct their own surveys and not depend in
any manner on the information provided in the bidding process.
6. In the technical parameters finalized by the ICC, the conductor to be used was the All
Aluminium Alloy Conductors (AAAC) type of conductor, based on which the various
technical studies were undertaken by ICC. The AAAC type of conductor was preferred
by ICC over the other prevalent type of conductor, namely the ACSR type of
conductors even though AAAC conductors were more expensive as compared to the
ACSR conductors, on account of the various advantages of the AAC conductors
including the following :
A. Power Losses: Power losses, attracted by Steel, are less in AAAC, which consists
of Aluminium Alloy only, due to absence of magnetic loss. This is grater in ACSR,
the same being attracted by the steel core.
B. Thermal Stability: In ACSR which consists of pure Aluminium occurs at
termperatures exceeding 85 deg C, whereas AAAC, which consists of Aluminium
Alloy only, is stable even at 100 deg C.
Page 23 of 46
C. Surface harness: In AAC, Surface Harness is nearly 80 BHN as compared to 35
BHN for pure Aluminium. Surface damage during handling is reduced
considerably for AAC, leading to lesser Corona and Radio Interference in EHV and
UHV Transmission Lines using AAAC.
D. Corrosion Resistance Capability: AAAC has a high corrosion resistance capability
since it consists of Aluminium Alloy only, and unlike ACSR, there is no steel core
which is an aggravating factor for inviting corrosion.
E. Ultimate Tensile Strength: UTS of AAAC is 30% higher than that of ACSR.
F. Use of AAAC: this is now used worldwide and is preferred over ACSR by most
Utilities for the various advantages noted herein. In India, CEA has also
recommended to all Utilities to use AAAC in place of ACSR.
7. The Central Electricity Authority had also by its circular dated 20.08.2008 had also
recommended the AAAC conductors over the ACSR conductors in view of the various
technical advantages. A copy of the circular of the Central Electricity Authority is
attached hereto and marked as Annexure A.
8. However, the UPPTCL by its communication dated 30.08.2011 stated that the bid
conditions allegedly provided for ACSR conductors as opposed to AAAC conductors
and called up ICC to provide the technical details of ACSR conductors. A copy of the
communication dated 30.08.2011 of UPPTCL is attached hereto and marked as
Annexure B.
9. In reply to the above, ICC vide its letter dated 14.09.2011 provided the various
advantages of AAAC conductors and stating that in view of the various advantages it is
more appropriate to use AAAC conductors for the transmission project. A copy of the
communication dated 14.09.2011 of ICC is attached hereto and marked as Annexure C.
10. However, UPPTCL has been taking the position that the bid allegedly only provided for
the use of ACSR type of conductors and has not been accepting the justifications
provided for by ICC including that there was no stipulation in the bidding conditions
regarding the use of any particular type of conductors. Copies of the correspondence
exchanged between the parties is attached hereto and marked collectively as Annexure
D.
11. ICC has time and again specifically referred to the various advantages of the AAAC
type of conductors and has also confirmed that despite its higher cost, ICC shall not be
claiming any additional charges for the use of the AAAC type of conductors. The only
contention of UPPTCL is that in the survey report which was provided to the bidders at
one place the term ACSR conductor is used while providing for the Sag tension
calculation and therefore the ACSR conductors is to be treated as a part of the bidding
conditions and ICC is seeking a divation from the same which is not permissible.
Page 24 of 46
12. It is submitted that there was no such condition in the bidding documents and on the
other hand the bidding documents specifically provided that the bidder shall choose the
technical parameters and equipment consistent with the codes and standards of the
Bureau of Indian Standards and other acceptable codes with the prior approval of the
Central Electricity Authority. With regard to the survey report, the bidding documents
itself specifically provide for a disclaimer for the contents of the survey report and it is
for the bidders to ensure proper surveys are conducted. In the circumstances, by no
stretch of imagination can it be contended that the use of the ACSR conductor was a
mandatory condition of the bid. It is also submitted that the said contention of
UPPTCL is absurd in as much as AAAC is technically much superior to ACSR
conductors and it is more recommended to use than the ACSR conductors.
13. It is submitted that there is no justification or rationale in the contention taken by
UPPTCL that the bid documents mandates the use of only ACSR type of conductors
and that the use o AAAC conductors contrary to the bid. There is no such stipulation in
the bid conditions or any provision in the bidding documents which mandates the
parties to procure and use any particular type of equipments. The Survey Report being
relied only UPPCL is firstly only indicative and further there is a specific disclaimer in
the bidding documents for the bidders not to rely on the reports and information being
made available and to conduct their own investigations and surveys.
14. ICC has proposed the use of the most suitable and advanced technology presently
available and feasible to be implemented, namely the AAAC type of conductors, which
is also recommended by the Central Elecri9city Authority and also satisfies the
standards of the Bureau of Indian Standards, which is the only condition as mentioned
in the bidding documents. ICC has also specifically confirmed that the use of AAC
type of conductors is as per the bidding documents and that ICC will not claim or
otherwise be entitled to any higher tariff on account of the use of AAC type of
conductors rather than the ACSR type of conductors. In any event, there is no
prohibition in the bidding documents from use of the AAC type of conductors or there
can be any objection or reservation from the use of a better technology by the
successful bidder at the same quoted price.
15. However, in view of the objections being taken by the UPPTCL and their insistence
that ICC is required to use only the ACSR type of conductors, it has become necessary
for ICC to represent before the Hon’ble Commission and seek directions from the
Hon’ble Commission on the use of the AAAC conductors by ICC in the transmission
system is question.
16. In the facts and circumstances mentioned above, it is respectfully prayed that the
Hon’ble Commission be pleased to :
a. Clarify and declare that the bidding documents does not provide for any mandatory
condition for use of ACSR type of conductors or that the use of AAAC type of
conductors or prohibited under the bidding documents.
b. Hold that the objection of UPPTCL regarding the use of AAAC type of conductors
is incorrect and untenable.
Page 25 of 46
c. Pass such other order(s) as the Hon’ble Commission deem just in the facts of the
present case.
Thanking you,
Yours faithfully,
For South East U.P. Power Transmission Company Limited
Alfonso Perez Bustamante Queipo de LIano
Authorized Signatory
U.P. Power Transmission Corporation Ltd.
Shakti Bhawan
14-Ashok Marg
Lucknow
No.930/ESD-765kV/PPP/4/Isolux/vol-2 Dated:25-07-2012
Subject: Use of All Aluminium alloy conductor: for consideration of 765kV
& 400 Transmission lines under PPP package-1
Secretary,
U P Electricity Regulatory Commission,
Kisan Mandi Bhawan, Vibhuti Khand,
Gomti Nagar,
Lucknow.
Dear Sir,
This is in reference to M/s SEUPPTCL letter no.
SEUPPTCL/UPERC/2012-13/109 dated 18.07.2012 addressed to Hon’ble
Commission and a copy endorsed to MD, UPPTCL. In this regard point
wise submissions are as below:
1. No Comments.
2. 2. It may be seen from the scope of work detailed by M/s
SEUPPTCL (as also available in schedule 2 of TSA) that type of
conductor has been clearly mentioned as Quad BERSIMIS for 765kV
line and as Quad/Twin Moose for 400kV transmission lines to be
constructed under PPP package-1. Hon’ble Commission may further
Page 26 of 46
note that BERSIMIS and MOOSE are standard “Code Names” for
ACSR conductors as given in Canadian Standard and British Standard
215 Part-2 respectively (copies of relevant pages are enclosed
herewith as Annexure-1 for ready reference). It is also relevant to
mention here that no other International or National standard
defines/follows these code names. Accordingly, wherever under the
scope of work, the conductors have been mentioned as BERSIMIS
and MOOSE the same are to be understood to mean ACSR
BERSIMIS or ACSR MOOSE conductors only. Further, neither the
RFP documents nor the TSA allow use of equivalent conductors as
has also been observed by the Commission in its orders dated
18.05.2012 and 11.06.2012.
The word “AAAC MOOSE” and AAAC BERSIMIS” is a creation of M/s
SEUPPTCL as “AAAC MOOSE” and AAAC BERSIMIS” are not
defined in any International or National standards. Accordingly, letter
no.ICI/UPPTCL (BOOT)/2011-12/3228 dated 19.07.2011 (copy
enclosed) for adoption of conductors with parameters of AAAC
MOOSE Equivalent and AAAC BERSIMIS Equivalent is in deviation to
RFP documents and the order of Hon’ble Commission.
3. With regard to submission made by M/s SEUPPTCL that bidding
document did not provide for nature of equipment or material to be
used, it is to clarify that as per the order of the Commission
benchmarking of cost of the project was done considering ACSR
MOOSE and ACSR BERSIMIS conductors only and accordingly
conductors have been mentioned as MOOSE and BERSIMIS in RFP
documents and Schedule-2 of TSA which defines the “Scope of Work”.
In line with above, 765 kV Line Survey Report also indicates the
conductor as ACSR BERSIMIS conductor which was integral part of
the RFQ/RFP documents. In this context it is relevant to mention that
the Hon’ble Commission has also treated the request of bidder to use
AAAC conductors to be in deviation to the RFP documents in its orders
dated 18.5.2012 & 11.06.2012.
Page 27 of 46
It is also to bring to the knowledge of the Commission that the firm has
misinformed that the conductor selected by them are having main
parameters as per IS 398 part-4. The 1573.71 kg/km weight and
0.598 ohms/km resistance of AAAC conductors corresponds to a
conductor strand diameter of 3.45 mm instead of 3.55mm mentioned
by them (Refer page 3 of IS 398 part-4). Similarly the parameters of
AAAC conductor having 61 strands and 3.89mm diameter, has not
been defined in the above IS. It indicates that they have selected
parameters of AAAC conductors arbitrarily and have designed the
towers on the basis of these arbitrarily selected parameters. An
adequate tower designing is also not possible without defining correct
parameters of conductors.
With regard to para 1.3 of the RFP quoted by M/s SEUPPTCL it is to
submit that it is for the details which are not covered under the scope
of work. However, for the system and/or parameters that are clearly
defined under the bidding documents and scope of work the developer
does not have the flexibility to change them. For example, if it has
been provided under the scope of work that a substation is to be
constructed with one and half breaker scheme, it cannot be modified to
double main and transfer scheme etc. Accordingly, wherever MOOSE
and BERSIMIS conductors have been mentioned in the bidding
documents and the TSA, the construction details of conductors and
their mechanical & electrical parameters stand specified as per their
respective standards.
4. No comments.
5. The contention of the bidder that UPPTCL had only provided limited
and non-binding survey report is incorrect. The basic understanding
since the conception of the project was that the transmission lines
under the PPP packages would be constructed using ACSR
conductors and accordingly benchmarking of cost was done as
explained in Pt-3 above. In the bidding documents and the TSA, the
Page 28 of 46
conductors have been mentioned as MOOSE and BERSIMIS because
these are standard code names of ACSR conductors only as explained
under Pt.2 above.
6. With regard to superiority of AAAC conductors over ACSR conductor
as made out by M/s SEUPPTCL, following is brought to the knowledge
of the Commission:
a. Power losses: It is to inform that the DC resistance at 20 degree C of
proposed AAAC MOOSE equivalent conductor and AAAC BERSIMIS
equivalent conductor (as per SEUPPTCL letter dated 19.07.2011) are
0.0598 ohm/km & 0.0472 ohms/km respectively. However the DC
resistance at 20 degree C of ACSR MOOSE & BERSIMIS conductors
is 0.055520 ohms/km & 0.04242 ohms/km respectively. As such
AAAC equivalent conductor selected by M/s SEUPPTCL have 7.7%
and 11% higher resistance in comparison to MOOSE & BERSIMIS
conductors respectively. Thus, the transmission losses with AAAC
MOOSE equivalent and AAAC BERSIMIS equivalent would be 7.7%
and 11% more with respect ACSR MOOSE and ACSR BERSIMIS
conductors. The impact of skin effect of ACSR conductors and AAAC
conductors is almost same for determining the AC resistance. (Refer
IEC 61597). Hence, it may not affect in the calculations of “difference
in line losses” due to AC resistance of BERSIMIS & MOOSE
Conductors and AAAC conductors on percentage basis.
However, the temperature coefficient of Resistance is 0.0040 and
0.0036 of ACSR and AAAC conductors respectively. With the increase
in temperature (above 20 degree C) the losses will be reduced in
AAAC conductors with respect to ACSR conductors and the difference
will be less than 1% in the operating temperature range. This cannot
offset the effect of higher DC/AC resistance in AAAC conductor.
Further, due to higher strength to weight ratio of AAAC conductors,
longer spans of transmission line are feasible, reducing the number of
towers in transmission lines. As a result, which SEUPPTCL will save
Page 29 of 46
on their capital cost, LTTC will have additional commercial burden due
to higher transmission losses.
b. Thermal Stability: It has been mentioned by M/s SEUPPTCL that
lines with all Aluminium Alloy would be stable even at 100 degree c. It
is to submit that lines constructed with quad conductors are fully
loaded with respect to their surge impedance loading and conductor
never reach to their thermostability limit and accordingly there is no
possibility of these lines reaching a temperature beyond 75 degree.
Hence higher thermal stability limit of AAAC conductors cannot be
taken advantage off in 765kV & 400kV lines.
c. Surface harness: No Comments.
d. Corrosion Resistance Capability: The MOOSE & BERSIMIS
conductors are having galvanized steel core, which is corrosion free.
Further, lines with ACSR MOOSE and BERSIMIS conductors have
withstood the test of time and are performing satisfactorily in the whole
world.
e. Ultimate Tensile strength: The equivalent AAAC MOOSE conductor
selected by M/s SEUPPTCL is having UTS of 158.66kN against
161.20kN of ACSR MOOSE conductors. Hence the statement of
SEUPPTCL does not hold good.
f. Use of AAAC: As no 765 kV lines has been constructed using AAAC
conductor by PGCIL or any other state transmission utility including
UPPTCL, their performance under Indian conditions is no time tested.
7. With regard to submission by M/s SEUPPTCL that CEA has
recommended use of AAAC conductors it is to submit that in spite of
such recommendation by CEA from last 4 years, PGCIL has not
constructed any 765kV line using AAAC conductors. As per
information gathered from field units in UP Power sector, AAAC
conductors get permanently elongated when fully loaded thus reducing
the clearance at many places.
Page 30 of 46
CEA in their letter no. SETD/421-A/2008/617-678 dated 20.08.2008
(copy enclosed) has mentioned that AAAC conductor has some
advantage over ACSR conductor such as lower power loss, higher
current rating, lesser weight, lower sag, lighter tower design, corrosion
resistance longer life. Accordingly AAAC conductor parameters are
required to be selected in such a way that better strength & lower line
losses are achieved. M/s SEUPPTCL have proposed the use of AAAC
conductors which are having more losses as mentioned above. The
equivalent conductors have been selected arbitrarily without any
equivalence of all the electrical properties and do not match with
conductor parameters specified in IS 398 part-4.
8. No Comments.
9. May please refer to submission made on pt.2, 3,5,6,7 above.
10. May please refer to submission made on pt. 2, 3, 5 above.
11. It is in-correct on the part of M/s SEUPPTCL to state that they are
incurring higher cost transmission lines with AAAC conductors.
In this context it is to submit that the developer is intentionally trying to
mislead the Commission by saying that they will have to incur higher
cost for construction of lines using AAAC conductors.
Due to lower weight of AAAC conductors and better weight to strength
ratio M/s SEUPPTCL would have huge savings in the overall line
construction cost, as the same would help SEUPPTCL in having longer
span between towers and allow use of towers with lesser weight and
light foundations. Further, such a change, if allowed, to M/s
SEUPPTCL would be dispute prone, as Commission has earlier
disallowed M/s WUPPTCL use of AAAC conductors, considering it to
deviation from the RFP documents. M/s WUPPTCL has already
proceeded with the design towers with ACSR conductors mentioned in
the scope of work.
Page 31 of 46
12. Disclaimer in the line survey report is a general disclaimer to safeguard
the interest of both parties because of any inadvertent error. However,
the same cannot be interpreted to mean that developer has the
flexibility to change the conductor type base on which benchmarking of
cost of the project was done. Further, from the point of LTTC’s AAAC
conductor selected by the firm are not superior, as lines with AAAC
conductors will have higher losses as explained under Pt. 6(A) above.
Accordingly, the developer shall not be allowed to change the original
contents of RFP documents such as type of conductor which has been
clearly mentioned in 765kV line survey report as ACSR BERSIMIS
conductor and also with each line under schedule-2 “Project
description and scope of work”. As per provision of RFP & TSA,
choice of conductor is not left on Developer.
Further, the company did not point out to any errors of survey report or
to their intension of using equivalent AAAC conductors in place of
MOOSE & BERSIMIS conductors till the award of PPP Package-1 on
05.07.2011. Even SPA and TSA have been signed by them with
ACSR conductor in transmission lines.
The role of the company as developer is restricted to the
scope of work without putting LTTC’s to any commercial disadvantage.
M/s SEUPPTCL can create better system than envisaged in RFP or
TSA but not the inferior system having more transmission losses.
13. Same as at pt. 6, 11 & 12.
14. The contention of M/s SEUPPTCL that AAAC conductor is most
suitable and advance technology presently available is disputed due to
various reasons given in above paras. Further, it is relevant to mention
that IS for AAAC conductor was formulated in the year 1953 even than
this conductor has not found use on extra high voltage lines at 765kV
Page 32 of 46
& 400kV so far in India as already stated under pt.3 above, the use of
AAAC conductors is not as per bidding documents. M/s SEUPPTCL is
insisting on use of AAAC conductors because the same would result in
huge savings for them. The same is however not acceptable as it is in
deviation to RFP documents and would result in additional financial
burden on LTTC’s du to higher losses in the transmission lines.
15. No comments.
In this context it is also relevant to mention that M/s Isolux vide their
letter no. ICI/UPPTCL (BOOT)/2011-12/3228 dated 19.07.2011 after
issuance of LOI on 05.07.2011 for the first time informed UPPTCL
regarding its intension to use AAAC conductors and requested for
approval of parameters for AAAC MOOSE & BERSIMIS equivalent
conductors. UPPTCL, however vide its letter no. 1938 dated
30.08.2011 advised them to use ACSR MOOSE &BERSIMIS
conductors for constructions of 400/765kV transmission line as per
RFP documents and to submit the technical parameters of ACSR
MOOSE & BERSIMIS conductors for approval.
Thereafter M/s SEUPPTCL repeatedly requested for approval of
parameter for AAAC conductor vide its letter dt. 22.09.2011,
23.11.2011 & 29.12.2012. However, each time UPPTCL (letter no.
2242 dated 11.11.2011, 2316 dated 08.12.2011 & dated 03.01.2012)
advised them to use ACSR MOOSE & BERSIMIS conductors only for
construction of transmission lines in accordance with RFP documents
(copy of letters enclose).
Subsequently, M/s SEUPPTCL requested the Hon’ble Commission
vide letter dated 24.04.2012 to approve the use of AAAC conductors
for construction of transmission lines. The Ho’ble Commission denied
the same vide its order dated 18.05.2012 and 11.06.2012 considering
Page 33 of 46
it to be deviation from RFP documents. In view of above orders of the
Hon’ble Commission, UPPTCL again requested M/s SEUPPTCL to
confirm the use ACSR conductors vide its letter dated 25.06.2012
&28.06.2012. In response to these letters, M/s SEUPPTCL vide letter
no. SEUPPTCL/UPPTCL/2012-13/96 dated 02.07.2012 informed that
they are proceeding with design of towers with AAAC conductor. From
the above it is clear that despite repeated denial to allow use of AAAC
conductors by the UPPTCL and the Hon’ble Commission, SEUPPTCL
unilaterally decided to proceed with the design of towers for AAAC
conductors.
The Commission may also note that M/s WUPPTCL had also filed
petition before the Hon’ble Commission for allowing use AAAC
conductors for construction of transmission lines. However, in
accordance with the order of the Hon’ble Commission dated
19.03.2012, they have now decided to use ACSR MOOSE &
BERSIMIS conductors only for construction of 400kV & 765kV
transmission lines.
Due to above unilateral action of SEUPPTCL, UPPTCL issued a notice
to M/s SEUPPTCL on dated 09.07.2012 to confirm use of ACSR
MOOSE & BERSIMIS conductors for construction of 400 & 765kV
transmission lines. Hon’ble Commission is requested to settle the
issue at an early date as the decision of Commission for use of ACSR
conductor for construction of transmission lines is not being complied
by M/s SEUPPTCL.
Sd./- A.K. Singh
Director (Operation)
These two letters are very comprehensive in their subject of discussion.
The contents and issue raised in the other letters have been incorporated
Page 34 of 46
and discussed /replied comprehensively by both the parties in the above
reproduced two letters. SEUPPTCL vide its letter dated 18.07.2012 is
justifying the use of AAAC and UPPTCL vide its letter dated 25.07.2012 is
denying for use in the construction of transmission lines.
The Commission expressed its displeasure as the directions of the
Commission contained in its order dated 18-05-12 and subsequent letter
dated 11-06-12, regarding the use of conductor in Package-1, were not
complied. Therefore the Commission asked both the parties to explain the
issue in view of the provisions of bidding documents.
Sri Chaudhry of UPPTCL submitted that the bid documents and TSA specify
the use of Moose & Bersimis conductors for the construction of 400kv &
765kv lines respectively which stand for ACSR conductors only. On the other
hand, SEUPPTCL has been seeking permission to use AAAC conductors
which has been turned down by UPPTCL and subsequently by the
Commission as well vide its order dated 18-05-12 and letter dated 11-06-12.
When the Commission asked about the conditions on which the bids have
been finalized, Sri Chaudhry replied that the bids were finalized on Moose &
Bersimis conductors. Under the ‘scope of work’ in the bidding documents &
TSA, every transmission line is specified either with Moose or Bersimis
conductor, therefore use of Moose or Bersimis conductor is already under
the scope of work of the developer and we need to interpret whether Moose
& Bersimis are ACSR conductors or it can be the equivalent conductors like
AAAC, AL49, AL59 also. He further explained that Moose and Bersimis
conductors are defined only in British Standards (BS 215, Part-2) and
Canadian Standards respectively and not defined in any Indian Standards.
The bidding documents (RFQ, RFP) and the TSA mention about Moose &
Bersimis conductors and that stand for ACSR conductors only as indicated in
the survey report as well. AAAC, proposed by SEUPPTCL, is the conductor,
“Equivalent” to ACSR Moose or Bersimis conductors but the “Equivalent”
conductors are not mentioned in the bidding documents.
Page 35 of 46
SEUPPTCL explained that the bidding documents clearly state that the
developer should develop the system as per Indian Standards and if Indian
Standards are not available then system shall be developed as per
International Standards subject to the approval of Central Electricity Authority
(CEA). In the present context, the developer is pursuing to use AAAC as per
Indian Standards without asking for any deviation from the bidding
documents, so the issue arises is whether the use of AAAC can be permitted
in terms of the bid documents or not. SEUPPTCL further submitted that
Moose & Bersimis are the generic names only and are not specified in any
Indian or International Standards.
UPPTCL admitted that it is stated in the bidding documents that Indian
Standards are to be followed by the developer, but it applies when no
definite specification is assigned to any equipment or component under the
scope of work. It cannot be applied where some specific mention has been
made to the item in the scope of work in the bidding documents (RFQ/RFP)
and TSA. Sri Chaudhry further submitted that when it is said that if line is to
be constructed and no specific conductor is mentioned then we need to
interpret ‘which conductor’ shall be used. But when we say Moose or
Bersimis conductor then we do not require any further interpretation because
they are only ACSR conductor. Although, conductors with dimensions similar
to Moose conductors are mentioned in Indian Standard (IS) but IS does not
assign the name ‘Moose’ or ‘Bersimis’ to any conductor. Sri Chaudhry
categorically said that since ‘Moose’ and ‘Bersimis’ conductors are explicitly
mentioned in the bidding documents so it is implied that the developer has to
use ACSR conductors only as per British and Canadian Standards.
SEUPPTCL interrupted the discussion and submitted that with the consent of
the Commission a Committee has been constituted by the Government to
resolve the issue of the conductor and requested the Commission to leave
the discussion as of now till the issue gets finalized by the committee,
however, other matters like tariff adoption and grant of license may be taken
up without linking them to the conductor issue.
Page 36 of 46
The Commission denied their request and asked what is mentioned in the
bid document. The provisions of clause 1.5 of RFP have been read before
the Commission as hereunder:-
“1.5 The BPC has initiated development of the Project and shall be
responsible for the tasks in this regard as specified hereunder:
a) Provide to the Bidders a Survey Report for the 765kV line which has
already been provided at the RFQ stage. The Survey Report will contain
information regarding the transmission line, i.e. voltage level, line
configuration (i.e., S/C or D/C), indicative route alignment, conductor type,
conductor configuration and type of terrain likely to be encountered.
However, Survey for all other lines will be the responsibility of the
Bidders.”
The definition of ‘Survey Report’ as per RFP document was also read as
below:-
“Survey Report” shall mean the report containing initial information
regarding the Project and other details provided as per the provisions of
Clause 1.5 (a) of RFP”.
In view of above, UPPTCL again submitted that the survey report which is
the part of the bidding documents mentions about ACSR conductors only
whereas AAAC is not mentioned in any part of the bidding documents.
SEUPPTCL resisting the argument put forth by UPPTCL and relied its claim
on the disclaimer mentioned just below this clause in RFP which says “that
neither the BPC, its authorized representative, any of the Long Term
Transmission Customer(s), nor their Directors, Employees or
Advisors/Consultants make any representation or warranty, express or
implied, or accept any responsibility or liability, whatsoever, in respect of any
statements or omissions made in the Survey Report, or the accuracy,
completeness or reliability of information contained therein, and shall incur
no liability under any law, statute, rules or regulations as to the accuracy,
reliability or completeness of such Survey Report, even if any loss or
damage is caused to the Bidders by any act or omission on their part.”.
UPPTCL countered that it is a general disclaimer to safeguard the interest of
Page 37 of 46
both the parties because of any inadvertent error. It cannot be interpreted to
mean that the developer has the flexibility to change the type of conduct0r.
Moreover, benchmarking cost of the project was based on ACSR conductor
and any change in the conductor specification will change the financial
scenario of the project.
SEUPPTCL submitted that the type of conductor used in the project does
not affect the total tariff as the quoted tariff under the competitive bidding
does not depend upon the interpretation of bid document and therefore the
issue of conductor should not be linked with adoption of tariff under section
63 of the Act.
Having heard the arguments of both the parties and in the light of the
various facts brought to the notice of the commission by UPPTCL &
SEUPPTCL, the Commission is of the opinion that it is not appropriate at this
stage to determine the technical implications of using AAAC or ACSR
conductors and hence decided to restrict its observation to see which
conductor/conductors is/are permitted in accordance with the bidding
documents, irrespective of being superior or inferior technically.
The Commission observed that during the hearing both the parties agree
on this fact that under the scope of work in the bidding document & TSA, the
word ‘Moose’ or ‘Bersimis’ is specifically associated with each transmission
line. Both the parties also agree that the Moose & Bersimis conductors have
not been specified in the Indian Standards. The argument of UPPTCL that as
per British & Canadian Standards, Moose & Bersimis conductors are ACSR
conductors only has also not been opposed by SEUPPTCL. The
Commission looked into the papers, submitted by UPPTCL during the
hearing, regarding British & Canadian Standards. Regarding the plea of
SEUPPTCL that clause 1.3 of RFP restricts the developer to follow Indian
Standards & Codes only, the Commission went through the bidding
documents and is of the view that as per bidding documents Indian standard
Page 38 of 46
is to be followed in execution of project but if some specific mention has
been made to a certain item in the project then only prescribed specification
shall be used whether it exists in Indian standard or not. Since the conductor
type to be used in the transmission line has been associated with Bersimis or
moose under the scope of work in the bid document, therefore, the
Commission decides that only Bersimis or moose conductor (which stands
for ACSR conductor) shall be used in the construction of line. One more
important reason in support of above decision is this that benchmark price of
the project was worked out by the UPPTCL on BERSIMIS and MOOSE
conductors only.
The Commission was unable to understand SEUPPTCL’s view that on the
consent of the Commission, some committee has been set up to examine
the conductor issue. The Commission clarifies its stand that it never
recommended anybody to re-examine the conductor issue. SEUPPTCL is
probably referring to letter dated 20.7.2012 & 27.7.2012 of the Commission.
These letters state that the technical issues related with the execution of the
project may be examined by the UPPTCL. To draw the inference that it
relates to examine the issue of conductor in construction of line is not
correct. In this regard the Commission reaffirms its view that after the
completion of the bidding process any change related with the specification
of the project can neither be re-examined nor amended. Moreover, any post
bid change in the specification part affecting the financial part of the project
will amount to rebid.
In view of above deliberations, the Commission finds no substantial
reason to deviate from its decision in its interim order dated 18.5.2012 and
subsequent letter dated 11.06.12 in the same petition regarding the use of
conductor and therefore, Commission directs SEUPPTCL to use BERSIMIS
and MOOSE Conductors only for construction of transmission lines under
the project and submit its acceptance in this regard to UPPTCL within two
weeks from the date of this order under an intimation to the Commission.
Page 39 of 46
c) Clause 19.2.3 of TSA
Clause 19.2.3 refers to the technical criteria to be fulfilled by the new owner /
consortium in case of any change in the ownership of SEUPPTCL. As per
the directions of the Commission vide its order dated 15-09-10, the technical
criteria was to be decided mutually by UPPTCL and the successful bidder
during pre-award discussions. Accordingly the clause 19.2.3 of TSA has
been finalized as hereunder:-
Clause 19.2.3 TSA
“ …………
In case of any change in ownership, the new owner/consortium must fulfill
the minimum technical requirement as specified below:
A) In case of change in ownership until COD+2 years, the new owner /
consortium shall have at least the same technical requirements than
the bidders were required to have at the RFQ stage to be qualified.
B) After COD+5 years the new owner / consortium shall demonstrate
capacity to operate Transmission Lines & substations achieving the
stipulated standards of performance either himself or through a
contractor who have atleast 10 years experience of maintaining 765kv
substations and 400kv lines. In case of persistent failure to deliver the
stipulated performance the LTTC will have a right to terminate the TSA
after giving one month notice.”
The Commission pointed out that there is a gap of three years between
COD+2 & COD+5. The Commission referred to the review petition 690/2010
filed by UPPTCL under clause 19.2.3 of TSA, UPPTCL added the provision
of the technical criteria to be fulfilled by the new owner / consortium in case
of any change in the ownership of SEUPPTCL under clause 19.2.3 of T S A.
The Commission further pointed out that the clause 19.2.1 of TSA says
that “the aggregate equity share holding of the selected bidder in the issued
and paid up equity share capital of SEUPPTCL shall not be less than (a)
51% upto a period of 2 years after COD of the Project; and (b) 26% for a
period of 3 years thereafter”. In view of above clause of TSA, if the
aggregate equity share holding of the selected bidder in the issued and paid
Page 40 of 46
up equity share capital of SEUPPTCL shall not be less than 26% up to a
period of 5 years after COD of the project then the selected bidder shall be
the part of SEUPPTCL up to the five years after COD of the Project.
Therefore any exit of the selected bidder from SEUPPTCL will come up only
after (COD+5) years and hence the technical criteria to be fulfilled by the
new owner / consortium in case of any change in the ownership of
SEUPPTCL may arise only after (COD+5) years. In light of above facts, the
Commission asked UPPTCL to clarify the issue.
Sri Chaudhry from UPPTCL explained that in accordance with the
provisions of clause 19.2.1, the selected bidder has to retain 51% shares of
the company till (COD+2) years and 26% for a period of 3 years thereafter.
Further clause 19.2.3 says that if there is a change in ownership before COD
itself and till (COD+2), all the technical & financial conditions, defined in the
RFQ document, have to be fulfilled by the new owner. If the ownership
changes after (COD+5) then the new owner may not have the same
qualifications as defined in RFQ. It can be interpreted like this. The different
technical requirements of the new owner are mentioned for (a) up to
(COD+2) years and (b) after (COD+5) years. It means the ownership cannot
be changed between (COD+2) and (COD+5) years.
SEUPPTCL explained that the TSA has been signed was approved by the
Commission vide its order dated 15.9.2010 and when there is no dispute
between the concerned parties - UPPTCL & SEUPPTCL over this clause,
why this issue is being taken up by the Commission again. SEUPPTCL
requested that if at all there is some ambiguity, it should be dealt in a
separate proceeding with a notice to the parties.
The Commission clarified that it is an issue which was to be decided by
UPPTCL and the selected bidder during pre-award discussions. The issue
got finalized during pre-award and accordingly TSA has been amended and
signed by all the parties. The issue came up to the knowledge of the
Page 41 of 46
Commission after the signing of TSA documents and then only the
Commission observed some inconsistency in the clause. SEUPPTCL
reiterated its stand that when both the parties agree to it, issue need not
required to be raised again.
The Commission was not convinced with the arguments of SEUPPTCL
and decided that it cannot leave any ambiguity in the documents. As this
clause was finalized by the BPC, therefore the Commission directs UPPTCL
to file its reply under an affidavit within two weeks from the date of this order.
If UPPTCL observes any ambiguity in the clause, they should also submit
their proposal for the amendment of the clause along with the filing of their
reply.
d) Schedule-10 of TSA
As per TSA document, the entire bid (both financial and non-financial
bids) of the Selected Bidder is required to be attached under Schedule-10 of
TSA.
It has been observed that only the originally quoted transmission
charges were attached by BPC under TSA schedule-10, whereas the LOI
dated 05-07-11 indicated that some negotiation with the L1 bidder (Isolux
Corsan) also took place during the bidding process and thereafter the bidder
submitted the revised transmission charges of 35 years corresponding to the
levelized tariff of Rs 870Cr/year. The revised transmission charges quoted
by the L1 Bidder on the basis of which LOI has been issued by BPC, has not
been made the part of TSA schedule-10. Therefore there is an inconsistency
between TSA schedule-10 and TSA schedule-6. In view of such
inconsistency, the Commission is of the opinion that the revised transmission
charges should have also been made the part of TSA schedule-10 (financial
bid). UPPTCL agreed to make the revised transmission charges as part of
TSA Schedule-10.
Page 42 of 46
The Commission directed UPPTCL to make the revised transmission
charges of the Selected Bidder along with all the relevant correspondences
in this regard, as part of TSA Schedule-10 and get the amended part of TSA
signed by all the concerned parties within two weeks from the date of this
order, with a copy to the Commission.
The Commission also inquired how the non-financial bid had been
evaluated as most of the documents attached with TSA Schedule-10 under
non-financial bid are in foreign language. Both the parties, UPPTCL &
SEUPPTCL confirmed that the English version of all such documents has
also been made the part of the TSA Schedule-10.
e) Signing of Share Purchase Agreement (SPA)
In accordance with the contents of approved SPA documents, “SPA” is
an agreement amongst UPPCL, SEUPPTCL and the Successful Bidder for
the purchase of 100% shareholding of SEUPPTCL, for the Acquisition Price,
by the Successful Bidder. Further, as per LOI dated 05-07-12 issued by
UPPTCL, the Successful Bidder in the Project was M/s Isolux Corsan
CONCESIONES SA. Therefore, the Commission is of the view that SPA was
required to be signed only by the three parties - UPPCL, SEUPPTCL and
M/s Isolux Corsan CONCESIONES SA., whereas it has been observed that
SPA was signed by the fourth party - Mainpuri Power Transmission Pvt. Ltd
also. The Commission also observed that SEUPPTCL in its letter dated 01-
06-12 addressed to Registrar of Companies stated that Mainpuri Power
Transmission Private Limited has acquired 100% equity stake of SEUPPTCL
from UPPTCL in accordance with SPA dated 16-12-11.
In view of above, the Commission asked who acquired SEUPPTCL and
inquired about the role of Mainpuri Power Transmission to sign SPA. Both
UPPTCL and SEUPPTCL were unable to reply satisfactorily.
Page 43 of 46
The Commission considered it as a deviation from the approved SPA
document and directed UPPTCL & SEUPPTCL to file their replies under an
affidavit within two weeks from the date of this order.
The Commission also directed SEUPPTCL to submit the latest share holding
pattern and the Board of Directors of SEUPPTCL, Isolux Corsan
CONCESIONES SA and Mainpuri Power Transmission Pvt. Ltd along with
the Board resolution of Isolux Corsan CONCESIONES SA for authorization
to sign Share Purchase Agreement (SPA), as already directed vide its order
dated 18-05-12. All these documents will be submitted under an affidavit
within two weeks from the date of this order.
f) Delay in bidding process
(I) As per the Guidelines of GOI, the total time to complete the bidding
process, starting from publication of RFQ to signing of agreements, is
only 240 days; whereas UPPTCL took more than 875 days to complete
the bidding process. The Commission inquired the reasons of this delay.
UPPTCL replied that it was due to the delay in getting the approval of
various documents and procedures required at different levels of
decision making bodies.
(II) As per bidding documents, the SPA & TSA were required to be signed
within 15 days of issue of LOI. Since LOI was issued on 05-07-11 and
SPA & TSA were signed on 16-12-11 & 20-01-12 respectively, the
Commission inquired about the delay in signing of SPA (after a period of
five months) and TSA (after a period of 6 months). UPPTCL replied that
it was due to the time taken by the Successful Bidder (Isolux Corsan
Concesiones), in completing the requisite formalities.
(III) UPPTCL allowed submission of RFQ bids up to 12-11-09 and RFP bids
up to 20-11-10, which was not in accordance with the directions of the
Commission. The Commission vide its orders dated 15-10-09 &
20-10-09 directed UPPTCL to issue modified RFQ to the bidders within
Page 44 of 46
seven days of the order and next seven days for filing the responses.
Similarly the Commission, vide its orders dated 02-07-10 directed
UPPTCL to issue modified RFP documents within seven days of the
order and next 30 days for submission of RFP bids. Since the modified
RFP & RFP Project Documents had already been issued to the bidders,
the Commission directed UPPTCL vide its order dated 15-09-10 in the
review petition 690/2010 filed by UPPTCL, to make the necessary
modifications in the documents according to the decisions and directions
of the Commission through an amendment within seven days of the
order and issue the amendment to both the bidders within three days
thereafter. In view of above, the Commission inquired why the
submission of RFQ and RFP bids did not take place as per the orders of
the Commission.
UPPTCL replied that submission of RFQ bids was extended on the
requests of the bidders to enable more participants to submit the bids
and submission of RFP bids was extended from time to time and finally
to 20-11-10 on the bidder’s request.
In light of the above replies of UPPTCL and to the fact that the selection
process to establish intra state transmission system through competitive
bidding route under the guidelines of GOI in section 63 of the Act has been
taken up for the first time in the state of Uttar Pradesh, the Commission
decides to consider the above deviations of its orders and the delays at
various stages of bidding and directs both the parties to file their replies
under an affidavit within two weeks from the date of this order. However, the
Commission observed that all the concerned entities involved directly or
indirectly in the bidding process, should have taken it in a more serious
manner.
Page 45 of 46
g) General Clarifications (I) The Commission sought clarifications from UPPTCL about the
negotiation with the L1 bidder and placement of LOI on negotiated price,
when there was no such provision in the RFP bid document. UPPTCL
could not reply satisfactorily. The Commission directed UPPTCL to file
its reply under an affidavit within two weeks from the date of this order.
(II) In view of clause 3.4.1.5 of RFP read with para-11(c) of the
Commission’s order dated 02-07-10 and para-7 of the Commission’s
order dated 15-09-10, the Commission sought clarifications from
UPPTCL about non-adoption of Swiss Challenge Method (SCM) even
when the originally quoted levelized tariff was above the benchmark cost
of the Project. UPPTCL could not reply satisfactorily. The Commission
directed UPPTCL to file its reply under an affidavit within two weeks from
the date of this order.
(III) The Commission asked SEUPPTCL to explain the electronic copies of
Forms 32, 18, 23 and 22B, submitted vide its letter dated 07-06-12.
SEUPPTCL explained each of these documents to the satisfaction of the
Commission.
h) Submission of more documents
The Commission directed UPPTCL to submit the following documents
within two weeks from the date of this order:-
(I) An affidavit for publishing RFQ & RFP notices on the website of
UPPTCL and the Govt. along with the copies of newspaper cuttings for
publication of NIT with publication date, required under para-9.2 of
guidelines.
(II) An affidavit for opening the RFQ & RFP bids in public and in the
presence of representatives of bidders along with the copy of the
attendance sheet, having details & signatures of persons, present during
Page 46 of 46
the opening of the RFQ & RFP bids, required under para-9.9 of
guidelines.
i) Provisions under Article 3.3.1 of TSA
The Commission inquired from UPPTCL regarding payment of additional
Contract Performance Guarantee of Rs 4.72 Cr per week from SEUPPTCL
to LTTCs in terms of Article 3.3.1 of TSA. UPPTCL replied that letters in this
regard have already been sent to SEUPPTCL but SEUPPTCL requested to
waive such additional CPG under the Article 11 (Force Majeure) of TSA.
The Commission directs both the parties to submit their replies under an
affidavit within two weeks from the date of this order
15. The Commission directs UPPTCL and SEUPPTCL to submit all the necessary
documents and replies, as directed by the Commission in various paras above,
under an affidavit, within two weeks from the date of this order. The Commission
will review the status of the submission of documents after two weeks and
accordingly take a final decision on this petition.
16. The next date of hearing in the matter, if any, shall be fixed after filing of all
documents and clarifications.
(Meenakshi Singh) (Shree Ram)
Member Member
Place: Lucknow
Dated: 2nd April, 2013