Transcript of Petals SAP Point of Sale System M.Tech. Team SE 15 (Saturday) Team 08 28-Aug-2008.
Presentation Overview
Project Team Project Introduction Functional Requirements Schedule & Milestones Management Report
Project Team
No Name Role
1 David Tan Project Owner
2 Rama Project Manager
3 Ajish QA Manager
4 Wu Xue Song System Architect
5 Zang Yan Technical Lead
6 Zhang Xi Programmer 1
7 Bensam Programmer 2
8 Zhao Zu Qiu Programmer 3
Project Manager(PM)
QA Manager(QM)
Technical Lead(TL)
Programmer 1/2/3(SE)
System Architect(SArch)
Presentation Overview
Project Team Project Introduction Functional Requirements Efforts Estimation Schedule & Milestones Technical & Management Strategy Risk Analysis & Mitigation Plan Progress Report
Project Introduction
The Project objective is to provide a Client based Sales system for Retail Sales that will integrate with the SAP Business One Accounting System for OBTech Asia Pacific Pte Ltd, Singapore
The current system is having the multiple problems and the client’s intention is to create a new system to take care of all those issues and provide the basic functionalities
Functional Requirements - Scope
Development of POS system integrated with SAP B1 Accounting System
Automate the synchronization between HQ SAP B1 Database and client side Databases.
Functional Requirements - 2
SAP B1 HQ
Customer Master Data Inventory Master Data Payment Methods Price List Special Prices Shipping Methods Currency Exchange Rate Tax
FTP
STORE MANAGER POS FRONT
Point of Sale Cash Register Payment Suspend / Recall Peripherals
Stock Reconciliation Item Requisition Day Start User Maintenance Generate Reports Item Exchange Sales Return Refund Cash Register Amend Transaction Maintain Store Data
MASTER DATA CREATION
OUTLET
Day End Transaction Posting
Planned Milestones
Analysis Modeling
JAN FEB MAR APR MAY JUN JUL
AUG SEP OCT NOV DEC JAN FEB
Project Kick off
PrototypingReq Identification
ISS Audit 1
Initial Planning
Req Modeling
Design Modeling
Design Modeling
Programming
Integration
TestingUAT
User Document
Prototype Product
Detailed Design
ISS Audit 2
UCRR (Analysis)
UCRR (Req)
Functional Spec
URS
ISS Audit 3
Project & Quality Plan
Src code
Executables
Release candidate
UAT Signoff
Management Report – 2nd Phase
2nd Phase Deliverables
UI Prototype Prototype Study Report Use Case Model Survey Use Case Realization Report (Analysis) High-level Design Specification
Management Report – 2nd Phase
Task Assignment Assign task owners for each task.
Task owner to plan and implement task
Task owner to request for resources and for review meetings
Provide team members with visibility of all tasks using effort estimate table
Management Report – 2nd Phase
Begin detailed design after first iteration of prototyping
Divide team to 2 groups to do work in parallel POS and Store Manager Data transfer service
Involve user early in all key review phases High level design Prototype Change user requirement
Management Report – 2nd Phase
Problems and Solutions
Change request in URSConduct internal meeting on the Change Request and estimate the efforts
Slight delay in ScheduleDelay in schedule by three days and adjusted by planned buffer days