Pertemuan 2 PTM

20
Perhitungan Produktifitas Alat Berat

description

Perpindahan Tanah Mekanik

Transcript of Pertemuan 2 PTM

Page 1: Pertemuan 2 PTM

PerhitunganProduktifitas Alat Berat

Page 2: Pertemuan 2 PTM

Tujuan:

• Mengetahui faktor-faktor yang mempengaruhi produktifitas alat berat

• Mampu menghitung produktifitas alat berat

Page 3: Pertemuan 2 PTM

Metode Perhitungan Produktifitas

Rumus umum:Q = q x N x E = q x (60/Cm) x EDimana: • Q :Hourly production (m3/h, cu.yd/h)• q :Production (m3, cu.yd) per cycle, of loose,

excavated soil (This is determined by the machine capacity)

• N :Number of cycles per hour = 60/Cm• E :Job efficiency

• Cm : Cycle time (in minutes)

Page 4: Pertemuan 2 PTM
Page 5: Pertemuan 2 PTM
Page 6: Pertemuan 2 PTM

Earth Volume Conversion factor (f)

Page 7: Pertemuan 2 PTM

Job Efficiency (E)

When planning a project, the hourly production of machine needed in the project is the standard productivity under ideal conditions multiplied by certain factor. This factor is called job efficiency.Depends on:– Topography– Operator’s Skill– Proper selection and disposition machine

Page 8: Pertemuan 2 PTM

TRAKTOR

• Kendaraan yang dibuat untuk mengubah tenaga mesin menjadi tenaga traksi.

• Fungsi : – Prime Mover (alat penggerak)– Menggerakkan alat yang dipasang (mounted)

• Dua tipe: – Crawler Tractor– Wheel Tractor

Page 9: Pertemuan 2 PTM

Bulldozer(Traktor dengan dozer attachment)

Tractor

Dozer attachment

Page 10: Pertemuan 2 PTM

Produksi per siklus (q)

Untuk pelaksanaan dozing, kapasitas blade secara teoritis dihitung sebagai

berikut:

aqq *1

Dimana:

q1 : kapasitas blade

a : faktor blade

Ketika menghitung produktifitas standar bulldozer maka digunakan kapasitas blade. Kenyataan di lapangan, produktifitas siklus tergantung pada tipe tanah, sehingga perlu dilakukan penyesuaian terhadap kapasitas blade tersebut

Page 11: Pertemuan 2 PTM

Blade Factor

Dozing Condition Blade Factor

Easy Full Blade of soil can be dozed as completely loosened soil.

Low water content, uncompacted sandy soil, general soil, stock

pile material

1.1 ~ 0.9

Average Soil is loose, but impossible to doze full blade of soil.

Soil with gravel, sand, fine crushed rock

0.9 ~ 0.7

Rather

Difficult

High water content and sticky clay, sand with cobbles, hard dry

clay and natural ground

0.7 ~ 0.6

Difficult Blasted rock, or pieces of rock 0.6 ~ 0.4

Page 12: Pertemuan 2 PTM

Waktu siklus (Cm)

Waktu siklus merupakan waktu yang diperlukan oleh bulldozer untuk

menyelesaikan satu siklus (dozing, reversing and gear shifting), dihitung sbb:

ZR

D

F

DCm

Dimana:

D : haul distance (m)

F : forward speed (m/min atau yd./min) 3 ~ 5 km/jam

R : reverse speed (m/min atau yd./min) 5 ~ 7 km/jam

Z : time required for gear shifting (min) 0.1 menit untuk Direct Drive

Machine dan 0.05 menit untuk TORQFLOW machine

Page 13: Pertemuan 2 PTM

Grade Factor

0.7

0.8

0.9

1

1.1

1.2

1.3

-15 -10 -5 0 5 10 15

Grade (%)

Fac

tor

Page 14: Pertemuan 2 PTM

Kondisi Pelaksanaan

Efisiensi Kerja

Baik 0.83

Rata-rata 0.75

Agak jelek 0.67

Jelek 0.58

Job Efficiency (E)

Page 15: Pertemuan 2 PTM

Ripping

Produksi ripping tergantung pada properti batuan, metoda pelaksanaan dan

kemampuan operator. Estimasi produksi ripping sulit dilakukan.

Ripping dan Dozing

Produksi ripping dan dozing dihitung sbb:

DR

DR

QQ

QQQ

*

Dimana:

Q : produksi ripping dan dozing

QR : produksi ripping

QD : produksi dozing

Page 16: Pertemuan 2 PTM

DOZER SHOVEL AND WHEEL LOADER(LOADING)

Page 17: Pertemuan 2 PTM
Page 18: Pertemuan 2 PTM
Page 19: Pertemuan 2 PTM
Page 20: Pertemuan 2 PTM