Permastore Construction Guide
Transcript of Permastore Construction Guide
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 1/101
Doc Ref: P132 Rev 9 1/5/10 Page 1 of 102
CONSTRUCTION GUIDEfor
TANKS AND SILOS
These are guidance notes that cover the mechanics of the various tasks detailed. They onlyrefer to issues directly connected with the execution of the works. Only authorisedpersons/contractors adequately supervised, correctly equipped and trained in all aspects ofthe risks involved and the equipment to be used should be employed to carry out this work.They must also be familiar with the safety data sheets of all products used.
It is the responsibility of the person/contractor undertaking these works to consider eachparticular installation, its environment and the specific risks involved.
Whilst every care has been taken to ensure the accuracy of this guide through 1 May 2010,Permastore shall have no liability for any loss or damage (direct, indirect, special orconsequential) arising out of or in connection with this guide. This guide is subject tosupplementation or change at any time without notice at Permastore's sole discretion. Thisguide does not constitute a representation or warranty of any kind in favour of the customer,and the customer's sole warranty is that which is provided in its sales contract with thedistributor. This guide does not amend or change such sales contract in any way.
Permastore Limited
Eye, Suffolk,
IP23 7HS,
England
Tel : +44 (0) 1379 870723Fax : +44 (0) 1379 870530
E-mail : [email protected]
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 2/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 2 of 97
LIST OF CONTENTS
PART SECTION TITLE PAGE
FOREWORD 3-6
One 1 General System Description 7-8One 2 Tools and Equipment 9-11
One 3 Planning 12-14
One 4 General Construction Information 15-19
One 5 Sheet Identification 20-21
One 6 Standard Sealants, Cleaners and Primers 22-23
One 7 Applications Requiring the use of Silicone Sealants 24-25
One 8 Tank Fixing Details 26-28
One 9 Structure Dimensions 29-30
Two 1 Foundation Design and Sealing Options 31-34
Two 2 Clamping and Levelling Systems 35-36
Three 1 Assembly of Tanks From the Base Up 37-39
Four 1 Assembly of Tanks Using Jacks 40-45
Four 2 Assembly of Tanks Using Jacks and Starter Ring 46-47
Four 3 Assembly of Double Skin Tank Sheets 48-50
Five 1 Annular Tanks 51-52
Five 2 Backfilled Tanks 53-56
Six 1 Roof Construction Introduction 57-58
Six 2 Trough Deck Roof Construction 59-60
Six 3 20° Stainless Steel Roof Construction 61-63
Six 4 External Tapered Beam Roof Construction 64-65
Six 5 External Parallel Beam Roof Construction 66-68
Six 6 GRP Roof Construction 69-70
Six 7 Pressure Testing of Roofs 71-72
Seven 1 Glass-Fused-to-Steel Floors 73-75
Eight 1 Cones 76-79
Nine 1 Ancillaries 80-89
Ten 1 Checklist 90-91
Ten 2 Low Voltage Testing 92-93
Eleven 1 Troubleshooting 94-97
Appendix A Pictures from Tools List in Part One Section 2 A1-A4
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 3/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 3 of 102
FOREWORD
This Construction Guide is provided by Permastore Limited for its Distributors/Contractors.Distributors/Contractors are advised to study this guide thoroughly and ensure that their buildingcrews are properly trained to use the information provided. Distributors/Contractors are
contractually responsible to their customers for the quality construction of the as built structure.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 4/101
Permastore Construction Guide Foreword
Doc Ref: P132 Rev 9 1/5/10 Page 4 of 102
This Construction Guide is intended as a quickreference manual for experienced crews trained by
Permastore. It is not intended as a do-it-yourselfmanual by end users, as it does not included step-by-step instructions for assembly, installation orcommissioning.
The Guide is correct at the time of going to press. Inthe event of any doubt concerning any technical point, please contact the Sales Office at Permastore.
Health and Safety Requirements
All work described in this guide must be carried outin accordance with all relevant local health and safetyregulations. In the United Kingdom the Health andSafety at Work Act 1974 applies. The requirementsfor training and instruction of work crews are covered by Section 2 of this Act. Regulation 3 of the
Management of Health and Safety at WorkRegulations 1992 requires a risk assessment to becarried out at all sites prior to commencement ofwork.
Irrespective of legal requirements, always observe thefollowing health and safety rules:-
1. The Safe Handling of Chemical Products
The chemical products (sealants, primers,cleaners, etc) needed for the construction ofPERMASTORE
® tanks and silos must be
handled only by experienced personnel, whoshould be adequately supervised by theiremployer to ensure that all work is carried out ina safe and correct manner. Always observe thefollowing points:-
a) Read the manufacturer's instructions on thecontainer or accompanying safety datasheet before starting to use the product.
b) Chemical products must never be allowedto come into contact with eyes or skin.
Always wear appropriate protectiveclothing and eye protectors. Use a barrier
cream on your hands and generally observegood industrial hygiene practices. Removesplashes with an industrial hand cleanser,never use cleaners or solvents to removesplashes from skin. Persons vary in theirsensitivity to different chemicals. Some persons react to trace chemicals fromsplashes on outer clothing; ensure thatclothing is properly laundered. In the eventof irritation, burns or other symptoms, refer
to safety data sheets and seek medicalassistance.
c) Do not swallow chemicals and do not usethem in areas where food is consumed. If
any chemicals are ingested, refer to safetydata sheets and seek medical assistanceimmediately. Make sure that chemical products are kept and used out of the reach
of children and animals.
d) Do not smoke in areas where chemical products are used, as many of them areflammable.
e) Do not inhale chemical vapours or dust.Use a suitable mask and ensure that theworkplace is adequately ventilated.Vapours from solvent-based products mayhave a cumulative effect over time; theyalso tend to build up in enclosed spaces. Inthe event of any symptoms, leave the workarea immediately and move into fresh air.If the symptoms persist refer to safety data
sheets and seek medical assistance.
f) Ensure that there are adequate facilities forwashing and cleansing the skin and that
appropriate cleansers and barrier creams areavailable.
g) Store chemicals in sealed containers in well
ventilated areas and out of the reach ofchildren. Do not transfer chemicals from
one container into another unless suchaction is called for by the process.
h) Clean up all spillages immediately.
i) Except for transport in closed packages orsealed containers, chemical products should
be handled only by authorised personnel.
j) Ensure that the correct equipment isavailable for handling the chemical
products provided.
k) If any person handling the chemical products on the site shows symptoms which
may be caused by exposure to the products,remove the person from the site, refer tosafety data sheets and seek medical advice.
2. Fire and Explosion Risk
Some of the products used on site are flammable.Vapours given off by some products, whenmixed with air, may be explosive. Therefore:-
a) Never use naked flames in the work area.
b) Do not smoke in the work area.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 5/101
Permastore Construction Guide Foreword
Doc Ref: P132 Rev 9 1/5/10 Page 5 of 102
c) Avoid the use of spark-producingequipment (electric switchgear, grinders,
etc) in the work area.
d) Never use water as an extinguishant. UseCO² extinguishers or dry powderextinguishers.
e) Ensure good ventilation in the work areaand keep chemical product containerssealed when not in use.
f) Store all flammable materials in accordance
with the relevant safety regulations.
3. Handling Hints
Chemical products used on site may have alimited shelf life, which is dependent on storagetemperature. Do not order these products
prematurely, to avoid deterioration. They should be stored in areas which are cool, dry, wellventilated and secure. Refer to themanufacturer's instructions or accompanyingsafety data sheet.
Sealants: Can burn if subjected to intense heator direct flames. To extinguish burning sealant,use CO²/foam or dry powder extinguisher.
Remove splashes of sealant on skin immediatelywith an industrial hand cleanser. Sealants
normally present no inhalation problems givengood ventilation. Scrape up spilled sealant ordrips from excessive application, then wash thearea affected with a strong industrial detergent inhot water.
Primers and Cleaners: Contain solvents andare flammable. Use them only in well ventilatedareas.
Do not smoke when using them and keep awayfrom all naked flames, intense heat or sparkingequipment. To extinguish a fire use CO²/foam or
dry powder extinguisher or, in an emergency,dry sand or earth.
Remove splashes on the skin with an industrialhand cleanser. Dry the skin with disposable
paper towels, not with a cloth towel.
Solvent vapours, even under conditions of lowrates of evaporation, can quickly build up in
enclosed areas lacking adequate ventilation.Wear a suitable air mask. If you feel drowsy,nauseous or if you experience breathing
difficulties, move into fresh air.
Never dispose of surplus sealants or cleaners intothe drains; ensure their safe removal in
accordance with regulations for the safe disposalof industrial waste. If primer or cleaner arespilled, soak up the spillage with dry sand, scoopthe sand into strong polythene bags and dispose
of them in accordance with regulations for thesafe disposal of industrial waste.
4. Site Safety
All relevant site safety regulations must beobserved. In general, these would include thefollowing requirements:-
a) Wear appropriate safety clothing, includinghelmets, masks, goggles, ear protectors,coveralls, gloves and safety boots.
b) For work above ground level, use approvedsafety harness.
c) Secure all ladders at the top. In some casesit may also need to be restrained by anassistant. If a ladder is not secured and notin use, it must be laid down.
d) Scaffolding must be erected in the approvedmanner and secured during use. When notin use, scaffolding must be left secure andwith all means of access removed.
e) All hand held electric tools and equipmentshould be of 110v type.
f) All plant and electric equipment must beinspected at regular intervals and faultsmust be repaired before further use.
g) Every installation crew must be providedwith a first-aid kit as standard equipment.
h) Personnel working on sewage treatment
plants must be protected against leptospiral jaundice. Infection is usually via broken
skin or cuts, which must therefore be properly protected. All personnel must beissued with and must always carry a special
card containing details of their occupation,the name of their doctor and precautions to
be taken against leptospiral jaundice. Thiscard must be produced when a visit is madeto a doctor or hospital and those inattendance must be made aware of theholder's occupation.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 6/101
Permastore Construction Guide Foreword
Doc Ref: P132 Rev 9 1/5/10 Page 6 of 102
i) Special precautions, such as the provisionof forced ventilation and lifting harness,
must be taken to safeguard personnelworking within a structure which has beenclassified as a 'confined space'.
5. Site Practice
To ensure that all work is carried out to therequired standard of quality, observe thefollowing rules:-
a) Tank kits are shrink-wrapped prior to
shipment; they should not be accepted fordelivery to the site more than 4-6 weeks before commencement of installation.
b) Store kits off the ground and clear of anysurface water. Avoid storing kits in busy
areas where they may suffer damage.c) Whenever possible, transport the sheets to the
tank site on their original packing skids. Usecare when lifting sheets off the stack.
d) Keep the storage time of sealants to a
minimum, as they have a limited shelf life,especially at high ambient temperatures.
6. Safety Awareness Signage
All Safety Awareness signage provided withinthe tank construction kit must be installed at lowlevel in close proximity to entry/accessequipment (eg Access Hatch, Ladder, Staircase,Walkway etc) ensuring that those who need toenter or access the structure for inspection ormaintenance purposes are made aware of any potential dangers.
About This Guide
Where necessary, comments on three levels have been
added to the instructions:-
NOTE: Denotes information of a general or technicalnature which may be found helpful.
CAUTION: Draws attention to actions which maycause damage to equipment or materials.
WARNING: Highlights risks of accidents or injuryto personnel.
The instructions and notes are intended primarily as a
guide for the proper construction of Permastore tanksand silos. The cautions and warnings, as well as the
general safety and health rules above, are provided in
the interests of safety. Any person in control of aconstruction project or responsible for site safety in
any other capacity must comply fully with all nationaland local safety laws and regulations; any such person
not fully conversant with these requirements mustcontact his local Health and Safety Advisory Board
for assistance. While every care has been taken toensure the accuracy of this guide up to the date of publication, Permastore shall have no liability for anyloss or damage (direct, indirect, special or
consequential) arising out of or in connection withthis guide. This guide is subject to additions,deletions or changes at any time without prior noticeat the sole discretion of Permastore.
This guide does not constitute a representation ofwarranty of any kind in favour of the customer. Thecustomer's sole warranty is that which is provided inthe customer's sales contract with the distributor ofPermastore products. This guide does not amend,
change or supersede such sales contract in any way.
Registered Trade Names and Copyright
The following trade names, PERMASTORE®,
FUSION®, ISOFUSION® V700, HV ISOFUSION®,TRIFUSION
®, ECOFUSION
®, TRIFUSION
® PLUS
and Fusion Tanks & Silos are the property ofPermastore Limited.
Permastore Limited reserves all copyright in thisguide. Neither the complete guide nor any part of it
may be used without prior permission for any purposeother than the purpose for which it is issued byPermastore.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 7/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 7 of 97
PART ONE – Section 1
General System Description
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 8/101
Permastore Construction Guide General System Description
Doc Ref: P132 Rev 9 1/5/10 Page 8 of 97
The Permastore product is a bolted modular systemfor the construction of tanks, silos and similar steel
structures of essentially regular cylindrical form ofdiameters from 3.41m to 85.38m (11ft-280ft) andheights from 1.4m to 29.4m (5ft-96ft) dependent uponthe diameter. Capacities range from 13m
3 to over
36,000m3
(2,860gals –
7,920,000 gals).
The system comprises essentially high-grade steelsheets, silo bolts, roof beams and panels, stiffeningand fixing members, as well as a wide range ofancillaries (manholes, flanges, launders, ladders, platforms, etc). The steel sheets, which are roll-curved to the radius appropriate for any givenapplication, are punched with one or several rows ofholes, through which they are bolted together on site.
The sheets are coated on both sides by a specialGlass-Fused-to-Steel vitreous enamelling process for
which the trade names ECOFUSION ,ISOFUSION
® V700, HV ISOFUSION
®,
TRIFUSION® and TRIFUSION
® PLUS are used.
This FUSION® family of vitreous enamel provides
cost effective storage solutions in applications fromthe storage of agricultural sludges to very demandingmunicipal/industrial effluents.
The coating is sprayed and fused onto the specially prepared sheets at the Permastore plant. Sheets aretested to confirm continuity of the Glass-Fused-to-Steel vitreous enamel coating. For protection duringtransport and storage the edges are coated with an anticorrosive system.
The overlap between sheets (both horizontal andvertical) must be coated with sufficient sealant forenough to be squeezed out when the bolts aretightened to allow it to be smoothed into a fillet whichcovers the edge of the sheet and extends severalmillimetres onto the exposed side of the sheet.Similarly, bolts and holes must have sufficient sealantto protect the bore and the shank, and to squeeze outto form a seal around the bolt head and nut. A bead of
sealant must also be used to seal the nut when plasticnut covers are utilised.
The proper application of sealant is absolutelyessential for making the tank leakproof. Strictsupervision of the sealing operation can save you a lotof trouble after completion and testing, when anyleaks will have to be made good.
Another point calling for special attention is the proper expansion of vertical sheet joints. Althoughtanks are nominally straight-sided, each ring
(horizontal course of sheets) is slightly taperedinward, so that the outer face of one ring can fitagainst the inner face of the ring below it. The slighttaper is achieved by the appropriate location of the
holes. Since each hole must be slightly larger than the bolt to facilitate assembly, all bolts must be in shear
between sheets when they are tightened. Hence theimportance of ensuring the correct straight shanklength is used. See Part One: Section 7.
Where tanks are provided with Glass-Fused-to-Steelvitreous enamel floors strict supervision is called forduring construction of the floor and any further work.The floor should be temporarily protected fromdamage which may be caused by footwear andcareless handling of tools.
Following completion of construction the structureshould be swab tested to confirm the continuity of theinternal Glass-Fused-to-Steel vitreous enamel coating.See Part Ten: Section 2 of this guide. Theapplication of this test must be witnessed by thecustomers site representative following which the 'OnSite Wet Swab Testing Results Chart' (Doc Ref:02.04.02 Appendix 7) and the 'Certificate of
Completion' (Doc Ref: 02.04.02 Appendix 4) must beauthorised by the Sub-contractor and the customer'srepresentative.
All tanks, silos and similar storage and processvessels are subject to containment and environmentalstresses. Each unit is carefully designed to givereliable performance. You must therefore ensure thatthe methods of construction as detailed in this guide
are carefully followed.
In case of doubt, don't guess; ask your employer forclarification.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 9/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 9 of 97
PART ONE – Section 2
Tools and Equipment
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 10/101
Permastore Construction Guide Tools and Equipment
Doc Ref: P132 Rev 9 1/5/10 Page 10 of 97
SMALL TOOLS AND EQUIPMENT FOR
ERECTION AND TESTING
The following schedule of small tools is ourrecommendation for a single construction crew:-
1. Levelling instrument accurate to within 1.5mm
(1
/16 inch) – (recommend Dumpy or laser level). – See Appendix A Picture No: 1.
2. Large tape measure capable of measuring radiusof tank.
3. Ratchet spanner.
4. 19mm (¾ inch) A/F impact sockets x 4 (heavy
duty).
5. Tapered podgers to align holes in sheet, 3mm(1/8 inch) tapered up to 14mm (9/16 inch)(recommend Britool pry bars No 219 x 4). SeeAppendix A Picture No: 2.
6. Cold chisel.
7. Spanner set (open end and ring).
8. Screwdriver set.
9. Putty knife x 8.
10. Hacksaw and blades.
11. 1m (3ft) spirit level. See Appendix A Picture No: 3.
12. Lifting hooks for carrying shell sheets. See
Appendix A Picture No: 4.
13. Sheet plate carrier.
14. Centre punch.
15. Crowbar 3ft long.
16. Hammer – ball peign.
17. Torque wrench to cover range from 14Nm(10ft-lb) to 70Nm (50ft-lb). See Appendix A
Picture No: 5.18. Plastic bucket x 6.
19. Marker pens and chalk.
20. Mole grips. See Appendix A Picture No: 6.
21. Tin snips.
22. Pliers.
23. Scissors.
24. Broom.
25. Shovels x 2.
26. Plastic floats x 2. See Appendix A Picture No:
7.
27. Bolt croppers.
28. Small tape measure – 5m (15ft).
29. Polyester slings for moving skids and liftingsheets.
30. 12.5mm (½ inch) bridge reamer. SeeAppendix A Picture No: 8.
31. 300mm (12 inch) adjustable spanner.
32. Stilsons. See Appendix A Picture No: 9.
33. 220mm (9 inch) cutting discs x 4.
34. Safety glasses. See Appendix A Picture No: 12.
35. Ear protectors. See Appendix A Picture No 10.
36. Safety helmets. See Appendix A Picture No 11.
37. Safety harness. See Appendix A Picture No 13.
38. Gloves – good supply. See Appendix A Picture No 14.
39. Wheelbarrow x 2.
40. Large special socket ½ inch drive for anchor
bolts.
41. Cleaning cloths.
42. Selection of drill bits 3mm (⅛ inch) to 13mm
(½ inch).
43. Wet sponge continuity detector – Elcometer
model 269. See Appendix A Picture No 16.
44. Aluminium mobile scaffold tower.
45. Sealant trowels x 2.
46. One set of Allen keys.
47. String line
48. Lock-up tool chest to be kept on site.
49. 2 x 10mm (⅜ inch) shackles.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 11/101
Permastore Construction Guide Tools and Equipment
Doc Ref: P132 Rev 9 1/5/10 Page 11 of 97
ELECTRICAL EQUIPMENT (ALL 110 VOLTS)
1. Impact gun ½ inch drive – Bosch, Makita,Dewalt or similar. See Appendix A Picture No: 15
2. Extension lead – length suitable for site.
3. Power drill. See Appendix A Picture No: 17.
4. 220mm (9 inch) disc grinder.
5. Electrical hoist for lifting sheets.
6. Jig-saw – recommend Bosch variable speed (ifholes are to be cut in tank plates) with a selectionof blades to suit above, Bosch type T118B. SeeAppendix A Picture No: 18.
7. Mobile generator if mains power is not availablefor 110v electric tools. See Appendix A Picture
No: 21.
8. HILTI Hammer Drill plus drill bits to installanchor bolts.
9. Single phase 110v Transformer.
LARGE EQUIPMENT FOR SPECIFIC
APPLICATIONS
1. Concrete vibrator for rebate concrete. SeeAppendix A Pictures No: 19 & 20.
2. Small crane, or similar, for the installation of
sheets for tanks 2 rings high and above and for positioning pallets of sheets strategically aroundthe tank when construction jacks are the preferred solution.
3. Crane to lift roof beams and centre support rings.
4. Construction Jacks are recommended for theconstruction of tanks/silos with roofs and/or
2 rings high and above. (Contact Permastore forfurther advice on suitability and usage).
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 12/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5 /10 Page 12 of 97
PART ONE Section 3
Planning
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 13/101
Permastore Construction Guide Planning
Doc Ref: P132 Rev 9 1/5 /10 Page 13 of 97
PLANNING
1. The distributor/contractor should commission a
soil load-bearing test by a qualified soil test
engineer. Copies of the certificate should be
given to:-
a) The construction team/crew leader.
b) The customer.
The original certificate should be retained in the
distributor/contractor project file.
2. When planning the site layout the customer's
future plans should be taken into account as this
could affect the positioning.
3. A site plan must be drawn, agreed and signed by
the customer to safeguard against any possible
changes being requested after the installationcommences.
4. The distributor/contractor should ensure the
availability of the tools and equipment list in
Section 2 of this guide.
5. The distributor/contractor should appoint a
suitably qualified construction team and also
ensure that all plant and materials required will
be on site when required.
6. One suitably trained person from the
construction team should be made crew leader.The crew leader should be responsible at all
times for the safe working practices of the crew
operation, as well as ensuring safe site
conditions, correct sequence of work and co-
ordination in general.
a) The crew leader should:-
i) liaise with the distributor/contractor to
ensure the arrival of plant and
materials;
ii) liaise with the customer to discuss thesite plan and safe site working with
respect to other sub-contractors and
normal site operations;
iii) set a good example to the other
members of the crew.
b) The crew leader must also be capable of
reading site plans and drawings, and be
conversant with all aspects of erection
work.
ON ARRIVAL AT SITE
1. The Crew Leader Should:-
a) Make contact with the customer and jointly
inspect the site location to ensure that there
are no obvious safety hazards (eg overhead
power cables etc) and that clear access isavailable for delivery vehicles and
construction equipment.
b) Study the site plan and soil load-bearing
certificate.
c) Ensure that the distributor/contractor has
ordered necessary materials. Remember
that materials are not always available at
short notice.
d) Mark out the site and obtain the customer's
signature on the site plan. Do not
commence operations without this signature
unless you already have a signed copy.
e) Place and fix a centre post, if installing
foundation/bases.
f) Check with the distributor/contractor about
soil disposal and who is responsible for it.
g) Supervise the digging of the foundation
footings, placement of levelling stakes and
reinforcing.
2. The Remaining Crew Members Should:-
a) Make a thorough check of the parts box and
sheet pallets against the packing list
provided and report any shortages
immediately to the crew leader. The
distributor/contractor should immediately
report any shortages so as to prevent delays
at a later stage of the construction.
b) Do sub-assembly work on ladders and
platform. 3. During Construction
Supervision checks should be made:-
a) After excavation work is complete and
before pouring concrete, should there be
any indication of the presence of organic
matter such as rotting vegetation or other
foreign objects, work should cease and
expert advice sought.
b) To check the approved drawings footings
and base dimensions, anchor bolt, structure
bolt positions and any other relevant
measurements.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 14/101
Permastore Construction Guide Planning
Doc Ref: P132 Rev 9 1/5 /10 Page 14 of 97
c) Where construction of the tank is on a
previously prepared concrete foundation by
others, the centre point and orientation
datum's must be marked by the customer or
his representative.
d) After the base ring is complete and beforepouring concrete, the base ring should
conform with the specified levels,
concentricity (fit top angle temporarily) and
be clamped securely.
e) Following or during construction the
internal Glass-Fused-to-Steel coating
should be checked in the presence of the
customer's representative to ensure
continuity. Part Ten : Section 2 of this
guide refers.
4. After Structure Completion
The structure must be inspected by the
distributor/contractor or his delegated competent
representative in accordance with the
specifications detailed herein. Refer to the
Permastore Inspection and Maintenance Manual
Document Reference P110, as well as
Part Eleven of this guide.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 15/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 15 of 97
PART ONE – Section 4
General Construction Information
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 16/101
Permastore Construction Guide General Construction Information
Doc Ref: P132 Rev 9 1/5/10 Page 16 of 97
GENERAL CONSTRUCTION INFORMATION
1. Sheet surfaces must be clean and dry whensealant is being applied. See Note 2 under'Standard Sealants and Primers Part 1 Section 6.
Sealant must always be spread to cover the total
area of the overlap to ensure correct sealing.
2. CAUTION: Glass-Fused-to-Steel sheets will bend to a natural tolerance but special careshould be taken when handling.
3. CAUTION: Take care that objects are notdropped onto any Glass-Fused-to-Steel sheets.
4. Tanks are assembled using 12.5mm (½ inch) bolts within 14mm (
9/16 inch) holes. It is
important that all vertical joints are fullyexpanded during construction to preventmovement under full hydraulic load, failure to dothis can cause leaks and deformed verticalseams.
5. For tank sheets above 10mm thick, fullyexpanded vertical joints using a tank sheet
hydraulic joint expander assembly. A sheet jointexpander kit is available from Permastore.
6. When building tanks from the base up it is easierto assemble rings of sheets working clockwise.
7. CAUTION
Bolts should be tightened to a torque of 65Nm(46ft-lb) except through tapered inserts, whichshould be tightened to a torque of 32Nm(23ft-lb).
Failure to conform to this standard may causedamage to the panels.
8.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 17/101
Permastore Construction Guide General Construction Information
Doc Ref: P132 Rev 9 1/5/10 Page 17 of 97
It is essential that the correct length bolts areused in the correct place during construction.
Always check fixings charts for the bolt sizes to be used.
9. Before inserting the structure bolts, ensure
sealant has been applied into and around each bolt hole as a safeguard against leaks.
10. It is essential to fillet all sheet edges, vertical andhorizontal, both inside and outside the structure.
11. At all points where an angle overlaps a vertical joint, tapered inserts must be used.
12. All ancillary items bolted to Glass-Fused-to-Steel sheets such as angles and brackets must be
fully coated with sealant on contact surfaces to prevent leakage.
13. All levels must always be maintained at + or – 1.5mm (
1/16
inch).
Wherever possible levels should be checkedfrom within the structure.
14. The circularity on all structures must be to thefollowing standards:-
Diameter Circularity
Up to 13.7m (45ft) ± 6mm (¼ inch)
From 14.5m to 26.5m(48ft to 87ft)
± 12.5mm (½ inch)
27.3m (90ft) and
above± 25mm (1 inch)
Refer to Part One – Section 8 for structurediameters.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 18/101
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 19/101
Permastore Construction Guide General Construction Information
Doc Ref: P132 Rev 9 1/5/10 Page 19 of 97
17. CAUTION: If Glass-Fused-to-Steel panelsrequire cutting on site the operation must always
be carried out using a jig-saw type cutter (referto Part Eleven – Section 1).
18. CAUTION: Do not attempt to cut Permastoresheets with gas cutting equipment or use on other parts in the locality of Glass-Fused-to-Steel,where sparks may contact and adhere to the
surface.
19. CAUTION: Do not attempt to cut Permastoresheets with a mechanical grinder or use on other
parts in the locality of Glass-Fused-to-Steelwhere sparks may contact and adhere to thesurface.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 20/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 20 of 97
PART ONE – Section 5
Sheet Identification
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 21/101
Permastore Construction Guide Sheet Identification
Doc Ref: P132 Rev 9 1/5/10 Page 21 of 97
SHEET IDENTIFICATION
The sheet identification system (ID holes) is visibleexternally after construction and the ID piercing provides a clear indication of sheet thickness, steelgrade and sheet taper.
MATERIAL IDENTIFICATION
Four different hole shapes indicate the grade of steel:-
MATERIAL THICKNESS IDENTIFICATION
To indicate the sheet thickness the standard horizontal bolt holes are used as datum points.
"Whole numbers" ie 2mm, 3mm, 4mm etc are positioned 40mm to the right of the datum point andthe "half numbers" ie 2.5mm, 3.5mm etc are positioned 40mm to the left of the next datum point.For examples refer to the drawing.
MATERIAL IDENTIFICATION EXAMPLES
TAPER IDENTIFICATION
In order to ensure trouble free sheet to sheet assembly,Series 1400 sheets are produced with a slight taper toaccommodate the horizontal overlap. Dependent onthe sheet thickness and tank diameter one of the
following options will be provided. The absence ofany notch would signify a straight sheet with no taper.
Notch 1 = Taper Reference 14t Notch 1 & 2 = Taper Reference 38t
Notch 1, 2 & 3 = Taper Reference 62t Notch 1, 2, 3 & 4 = Taper Reference 86t
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 22/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 22 of 97
PART ONE – Section 6
Standard Sealants, Cleaners and Primers
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 23/101
Permastore Construction Guide Sealants and Primers
Doc Ref: P132 Rev 9 1/5/10 Page 23 of 97
STANDARD SEALANTS, CLEANERS AND
PRIMERS
The following list of sealants and ancillary productsrepresents those most commonly used for the standardrange of applications.
Sealant Colour
The standard utilisation policy for the construction ofall dark coloured tanks, including standard blue andgreen tanks, is to use Sikaflex TS Plus Black sealant.
For all light shades of colour including white, grey
and desert tan tanks Sikaflex TS Plus Grey sealantwill be utilised.
Sikaflex TS Plus
Used for sheet joints, painted and galvanised surfacesin direct contact with Glass-Fused-to-Steel panels,
perimeter base fillet type seals and minor internalrepairs. Due to its high performance specification TS
plus is also used for more specialist applicationsrequiring chemical and temperature resistance.
Sikasil Pool
Silicone sealant used in conjunction with Sikaflex TSPlus for the internal primary seal for onerous and/orhigh temperature applications.
Sikaflex 221
Only to be used in applications where fast cure is an
essential requirement. (Remedial, maintenance etc).
Sikaswell S2
Hydrophilic base seal.
Sikalastomer 710
Perimeter bond breaker used in conjunction withSikaflex TS Plus for tanks above 33.2m diameter and11.2m in height.
Sika Primer 3N
Concrete primer for perimeter base seals.
Sika Primer 210T
Galvanised surfaces on roof top stiffener and floorfoundation angles.
Sika Cleaner 205
General cleaner for Glass-Fused-to-Steel surfaces and pre-treatment for silicone sealant overpointing.
Permastore Repair Kit Corroless EP
Minor repairs to panel surfaces and sheet edges.
NOTE 1: Sealant and Primers may vary inaccordance with the process design criteria of thestructure.
NOTE 2: It is recommended practice for Glass-Fused-to-Steel surfaces to be clean and dry prior to
the application of the sealant. Glass-Fused-to-Steel panels are wrapped after manufacture to ensure thatthey are clean and dry at the time of construction.When it is necessary to clean the surface use Sika
Cleaner 205 or alternatively, pure xylene,methylethylketone (MEK) or isopropylalcohol (IPA).Do not use any solvents or cleaners that might leave aresidue or contain turpentine, white spirits, phenols,organic acids, surfactants or silicones. If in doubtcheck with Permastore prior to use.
Always follow the manufacturer's advice on Healthand Safety and guidelines for application and curingtimes.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 24/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 24 of 97
PART ONE – Section 7
Applications Requiring the use of SiliconeSealants
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 25/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 25 of 97
CONSTRUCTION WITH SILICONE
SEALANTS
1. For applications where the operational
temperatures exceed 50 ₀C or the process
conditions are particularly onerous silicone
sealant is used.
2. The tank is constructed using Sikaflex TS
Plus with the external tank sheet edges over
pointed with Sikaflex TS Plus. Sheet
surfaces must be clean and dry when the
Sikaflex TS Plus construction sealant is
being applied. See note 2 under ‘Standard
Sealants and Primers Part 1 Section 6’.
3. The Sikaflex TS Plus sealant is applied over
the bolt holes as normal but controlled
around the internally exposed sheet edges to
minimise excess sealant being extruded into
the contact area of the tank.
4. Use the extruded Sikaflex TS Plus sealant
around the internal sheet edges to form a
small protective fillet.
5. It is essential to fillet all internal sheets
edges, vertical and horizontal correctly. For
the inside of the tank structure the Sikaflex
TS Plus is over pointed with silicone sealant.For the outside of the tank structure external
pointing is completed using Sikaflex TS Plus
sealant only.
6. Following a minimum period of 24 hours
check that the Sikflex TS Plus internal
sealant is touch dry.
7.
Prior to applying the internal silicone sealantas detailed above the existing Sikaflex TS
Plus sealant fillet must be cleaned with
cleaner 205.
8. Over point the internal sheet edge sealant
with silicone sealant as detailed above.
9. This method of sealant construction will also
be used for Glass-Fused-to-Steel Floors.
10. For foundation perimeter sealing the Sikflex
TS Plus fillet should also be over pointedwith silicone sealant.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 26/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 26 of 97
PART ONE – Section 8
Tank Fixing Details
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 27/101
Doc Ref: P132 Rev 9 1/5/10 Page 27 of 97
To be used in conjunction with the Fixings Chart on Page 26 of this Guide.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 28/101
Permastore Construction Guide Tank Fixing Details
oc Ref: P132 Rev 9 1/5/10 Page 28 of 97
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 29/101
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 30/101
Permastore Construction Guide Structure Dimensions
Doc Ref: P132 Rev 9 1/5/10 Page 30 of 97
INTERNAL DIMENSION OF STRUCTURES
Nominal Radius Nominal Radius
Model
Diameter
Reference
Sheets
Per
Ring
MetresFeet and
Inches
Model
Diameter
Reference
Sheets
Per
Ring
MetresFeet and
Inches
11 4 1.708 5' 7¼" 146 52 22.200 72' 10"14 5 2.135 7' 148 53 22.627 74' 2⅞"
17 6 2.562 8' 4⅞" 151 54 23.054 75' 7⅝"
20 7 2.988 9' 9¾" 154 55 23.481 77' ½"
22 8 3.415 11' 2½" 157 56 23.908 78' 5¼"
25 9 3.842 12' 7¼" 160 57 24.335 79' 10⅛"
28 10 4.269 14' ⅛" 162 58 24.762 81' 2⅞"
31 11 4.696 15' 4⅞" 165 59 25.189 82' 7⅝"
34 12 5.123 16' 9¾" 168 60 25.616 84' ½"
36 13 5.550 18' 2½" 171 61 26.042 85' 5¼"
39 14 5.977 19' 7⅜" 174 62 26.470 86' 10⅛"
42 15 6.404 21' ⅛" 176 63 26.896 88' 3"
45 16 6.831 22' 4⅞" 179 64 27.323 89' 7¾"48 17 7.258 23' 9¾" 182 65 27.750 91' ½"
50 18 7.685 25' 2½" 185 66 28.177 92' 5⅜"
53 19 8.112 26' 7⅜" 188 67 28.604 93' 10⅛"
56 20 8.359 28' ⅛" 190 68 29.031 95' 3"
59 21 8.965 29' 5" 193 69 29.458 96' 7¾"
62 22 9.392 30' 9¾" 196 70 29.885 98' ⅝"
64 23 9.819 32' 2⅝" 199 71 30.311 99' 5⅜"
67 24 10.246 33' 7⅜" 202 72 30.738 100' 10¼"
70 25 10.673 35' ¼" 204 73 31.166 102' 3"
73 26 11.100 36' 5" 207 74 31.593 103' 7¾"
76 27 11.527 37' 9⅞" 210 75 32.020 105' ⅝"
78 28 11.954 39' 2⅝" 213 76 32.447 106' 5⅜"
81 29 12.380 40' 7⅜" 216 77 32.873 107' 10¼"
84 30 12.808 42' ¼" 219 78 33.300 109' 3"
87 31 13.235 43' 5" 221 79 33.727 110' 7⅞"
90 32 13.662 44' 9⅞" 224 80 34.154 112' ⅝"
92 33 14.089 46' 2⅝" 227 81 34.581 113' 5½"
95 34 14.516 47' 7½" 230 82 35.008 113' 10¼"
98 35 14.942 49' ¼" 233 83 35.436 116' 3¼"
101 36 15.369 50' 5⅛" 236 84 35.863 117' 8"
104 37 15.796 51' 9⅞" 239 85 36.290 119' ¾"
106 38 16.223 53' 2¾" 242 86 36.717 120' 5⅝"
109 39 16.650 54' 7½" 245 87 37.144 121' 10½"112 40 17.077 56' ⅜" 248 88 37.571 123' 3¼"
115 41 17.504 57' 5⅛" 251 89 37.998 124' 8"
118 42 17.931 58' 10" 254 90 38.425 126' ⅞"
120 43 18.358 60' 2¾" 257 91 38.851 127' 5¾
123 44 18.785 61' 7½ 260 92 39.278 128' 10½"
126 45 19.211 63' ⅜" 262 93 39.705 130' 3¼"
129 46 19.638 64' 5⅛" 265 94 40.132 131' 8"
132 47 20.065 65' 10" 268 95 40.559 133' ⅞"
134 48 20.492 67' 2¾" 271 96 40.986 134' 5¾"
137 49 20.919 68' 7⅝" 274 97 41.413 135' 10½"
140 50 21.346 70' ⅞" 277 98 41.840 137' 3¼"
143 51 21.773 71' 5¼" 280 99 42.267 138' 8⅛"
For tank diameters larger than those charted above please contact Permastore for further advice.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 31/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 31 of 97
PART TWO – Section 1
Foundation Design andSealing Options
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 32/101
Permastore Construction Guide Foundation Design and Sealing Options
Doc Ref: P132 Rev 9 1/5/10 Page 32 of 97
FOUNDATION DESIGN AND SEALING
OPTIONS
1. Ring Beam and Infill Design
Generally considered to be the least complexdesign and favoured where the installation team
has responsibility for the base and tankconstruction.
The ring beam can be installed prior to arrival ofthe tank kit on site and the foundation bolts positioned whilst the concrete is still wet, if
required.
The base slab (infill) is generally pouredfollowing construction of the starter or base ring.
Alternatively it is poured following completionof the tank shell if the structure is being built
using construction jacks.
TANKS UP TO AND INCLUDING 8 RINGS HIGH
TANKS ABOVE 8 RINGS HIGH.
Rebate Base Design
Utilised mainly where the base design and
construction is by a third party, it facilitates a proven concept to achieve effective hydrostaticcontainment where two separate contractingagents have responsibility for a common
workface.
2. Flat Base Design
Generally as (2) overleaf, but requires a veryhigh standard of base concrete construction toachieve an acceptable level and flatness.
It is essential that these levels of workmanshipare attained to enable the tank to be successfullyconstructed and sealed.
This concept has a limited range of use and is
only recommended for experienced installationteams.
TANKS UP TO AND INCLUDING 8 RINGS HIGH
TANKS ABOVE 8 RINGS HIGH
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 33/101
Permastore Construction Guide Foundation Design and Sealing Options
Doc Ref: P132 Rev 9 1/5/10 Page 33 of 97
LIMITED TO TANKS WITHIN THE RANGE
3.4M (11FT) – 16.2M (53FT) DIAMETER AND
1 RING - 6 RINGS HIGH
4. Agricultural Slurry Tank Base Design
Identical to Ring Beam and Infill design with theexception that case-in anchor bolts are alwayssupplied.
TANKS UP TO AND INCLUDING 6 RINGS
HIGH
BASE PERIMETER SEAL OPTIONS
1. Perimeter Fillet Seal
a) Pour concrete to the level specified on thedrawing or level with existing foundations.Ensure that the concrete completely fills the
gap between the ring beam or floor slab andthe base angle.
NOTE: It is recommended that a concretevibrator is used to ensure that the concretefully flows beneath and around the base
angle.
b) When the concrete has cured sweep cleanthe perimeter of the foundations inside the
tank to remove any surface debris.
c) Clean the Glass-Fused-to-Steel surface
immediately above the concrete level insidethe tank to ensure good adhesion for thesealant fillet. See Note 2 under 'StandardSealants and Primers' Part 1 Section 6.
d) Apply primer to the concrete base only
extending approximately 50-60mm(2 inches) inwards from the tank wall.
e) Review the instructions for use of the
perimeter sealant being used and then applythe sealant.
f) Allow to cure as manufacturer's instruction.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 34/101
Permastore Construction Guide Foundation Design and Sealing Options
Doc Ref: P132 Rev 9 1/5/10 Page 34 of 97
2. Perimeter Fillet Seal with Bond Breaker
for tanks above 33.2m diameter and 11.2m
in height.
a) Pour concrete to the level specified on thedrawing or level with existing foundations.Ensure that the concrete completely fills thegap between the ring beam or floor slab andthe base angle.
NOTE: It is recommended that a concretevibrator is used to ensure that the concretefully flows beneath and around the baseangle.
b) When the concrete has cured sweep clean the perimeter of the foundations inside the tank toremove any surface debris.
c) Clean the Glass-Fused-to-Steel surfaceimmediately above the concrete level insidethe tank to ensure good adhesion for thesealant fillet. See Note 2 under 'StandardSealants and Primers' Part 1 Section 6.
d) Apply primer to the concrete base onlyextending approximately 50-60mm (2 inches)inwards from the tank wall.
e) Apply the perimeter bond breaker as detailedand ensure it is touch dry and then apply the perimeter seal fillet.
f) Allow to cure as manufacturer’s instructions.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 35/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 35 of 97
PART TWO – Section 2
Tank to Base Clamping andLevelling Systems
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 36/101
Permastore Construction Guide Clamp and Levelling Systems
Doc Ref: P132 Rev 9 1/5/10 Page 36 of 97
ANCHOR BOLT AND CLAMP
1. Brush clean the top surface of the ring wall.Mark out the tank radius on the concrete surface.
2. Place shims inside each anchor bolt at the correct
radius from the centre point of the tank.
Check the levels of the shims to within 1.5mm(1/16 inch).
3. There must be a minimum gap of 25mm (1 inch)
between the foundation angles and foundationconcrete.
4. It is essential that anchor clamps are clampeddirectly onto a shim pack.
LEVELLING SYSTEM
1. Using a Dumpy level (or similar) check that allthe levelling plates are installed to within 1.5mm(1/16 inch), whilst always maintaining a minimumof 25mm (1 inch) gap between the foundationconcrete and the underside of the base angles.Tighten the levelling plates.
NOTE: Always maintain an even adjustmentof the levelling plates.
2. From the tank centre stake mark out thefoundation angle radius on to the levelling plates.Place the foundation angles round the tankcircumference, on top of the levelling plates,ensuring that when sheets are fitted, verticalseam joints are adjacent to a levelling system,with another levelling system situated mid sheetand all are equally spaced.
3. Fit the hold down clamps onto the outer anchor bolt and foundation angle and loosely tighten,
whilst checking that the correct radius ismaintained.
THROUGH ANGLE FIXING (EMBEDDED AND
FLAT BASE TANKS)
1. For Through Angle fixing the base angle will besupplied pre-punched to identify the location ofthe anchor bolts. Position of bolt holes to beused is shown on construction drawings.
2. For applications where the tank is constructedfrom the base ring upwards (stack building) the
foundation bolts are installed followingcompletion of the base ring. For applications
where the tanks are constructed using jacks thefoundation bolts are installed following
completion of the final ring of sheets (base ring).
3. It is essential that shim packs are located in close proximity to the foundation bolts and PVCisolation washers are fitted.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 37/101
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 38/101
Permastore Construction Guide Assembly Methods
Doc Ref: P132 Rev 9 1/5 /10 Page 38 of 97
ASSEMBLY OF TANKS AND SILOS FROM
THE BASE RING UPWARDS
The Base Ring of Sheets
1. Refer to bolt charts for correct bolt placement
and assembly.
2. Apply sealant to the inside face of the foundation
angles and proceed to fit the foundation sheets
ensuring that angles are fitted with an equal
overlap from each vertical joint and tapered
inserts are fitted at the vertical joint positions of
the foundation angles. See Note 2 under
'Standard Sealants and Primers' Part 1 Section 6.
3. Working in a clockwise direction around the
circumference, apply sealant to the inside face of
the vertical overlapping sheet seam ensuring all
bolt holes are covered.
4. Leaving out 2 bolts from each vertical seam (the
top bolt and the bolt positioned 5 up from thebottom), install all remaining bolts checking that
sealant has been applied over each bolt hole
before inserting the bolts.
SPECIAL NOTE: It is essential that top
angles are fitted temporarily to maintain the
tank shape. Bolt the angles to the top of the
ring of sheets, without sealant, using 6 bolts
equally spaced and tightened to
25Nm (18ft-lb).
5. Before tightening the bolts in the vertical seamensure that it is fully expanded using the 2 bolt
holes previously left for this operation (see Note
4 above).
6. For tank sheets above 10mm thick, fully expand
vertical joints using a tank sheet hydraulic joint
expander assembly. A sheet joint expander kit is
available from Permastore.
7. Fit all remaining base sheets.
SPECIAL NOTE: If the levels or the
concentricity are not maintained, problems
will occur when building higher rings,
especially the final stiffener angles.
Diameter Circularity
Up to 13.7m (45ft) ± 6mm (¼ inch)
From 14.5m to 26.5m
(48ft to 87ft) ± 12.5mm (½ inch)
27.5m (90ft) and
above ± 25mm (1 inch)
8. After the vertical joints are fully expanded top
and bottom fit the two bolts left out for this
operation and tighten to correct torque.
NOTE: Check the concentricity of the structure
at this point.
9. Tighten all bolts to 65Nm (46ft-lb) torque with
the exception of bolts through tapered inserts,
which should be tightened to 32Nm (23ft-lb)
only.
10. Remove the temporarily fitted top stiffener
angles.
11. Using a pointing trowel, fillet off the vertical
seam sealant as shown below.
12. We recommend the installation of an expanding
peripheral waterstop as shown on the project
base drawing.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 39/101
Permastore Construction Guide Assembly Methods
Doc Ref: P132 Rev 9 1/5 /10 Page 39 of 97
INTERMEDIATE RINGS
1. Refer to bolt charts for correct bolt placement
and assembly.
2. Build the second ring of sheets using suitable
lifting equipment.
3. Mark all structure holes for the wind stiffener
clip angles with chalk before assembling the ring
of sheets. As the sheets are constructed fit the
clip angles at the same time as the structure bolts
are installed.
FOUR CORNER JOINT VIEWED FROM
EXTERIOR OF TANK
SPECIAL NOTE: It is essential that top
angles are fitted temporarily to maintain the
tank shape. Bolt the angles to the top of the
ring of sheets, without sealant, using 6 bolts
equally spaced and tighten to 25Nm (18ft-lb).
4. Fully expand vertical joints and check
concentricity.
5. For tank sheets above 10mm thick, fully expand
vertical joints using a tank sheet hydraulic joint
expander assembly. A sheet joint expander kit is
available from Permastore.
6. Tighten from the centre of each sheet to either
corner on the horizontal seams; tighten the
vertical seam from the corner joint to the top
ensuring that the seam is expanded.
NOTE: If possible, do not start a new ring of
sheets late in the day if only a small number of
sheets will be completed. Where it is not
possible to complete a full ring of sheets by the
end of the day, secure each end of the unfinished
ring with ropes to prevent any possible overnightwind damage.
7. Before tightening a partially completed ring,
ensure the end sheets are truly vertical, as these
sheets tend to lean.
8. Apply sealant fillets to cover sheet edges on
vertical and horizontal joints inside and outside
the tank.
9. Remove the temporarily fitted top stiffener
angle.
10. All bolt heads are to have a sealant squeeze out
and the 4 corner joints should be completely
covered with sealant.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 40/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 40 of 97
PART FOUR Section 1
Assembly of Tanks and SilosUsing Construction Jacks
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 41/101
Permastore Construction Guide Assembly Methods
Doc Ref: P132 Rev 9 1 /5 /10 Page 41 of 97
ASSEMBLY OF TANKS AND SILOS USING
CONSTRUCTION JACKS
Important Information
a) Permastore construction jacks are designed to
build only Permastore structures.
b) The construction jacks must only be operated by
trained and competent personnel.
c) The jacks must not be used when wind speeds
exceed 25mph (40km/hr). If the wind speed
approaches this figure the structure should be
lowered and anchored down to the base. Special
care is needed when gusting winds can exceed
this figure.
d) The structure should be lowered and anchored
each evening in case of overnight winds.
NOTE: For c) & d) above, ensure that
anchors are removed prior to jacking.
e) An electrically driven 'Master Jack' drives the
jack units via PTO drive shafts.
f) Standard operation is for one jack per vertical
seam of the structure with one master jack. For
certain applications slave gearboxes are available
to reduce the requirement for standard
construction jacks (see page 45). Extra jacks
may be used and extra master drive jacks
required for special structures.
It is recommended that jacks be used on both
seams adjacent to platforms and similar heavy
ancillaries.
g) Before setting up the jacks it is essential to
ensure that they stand on a firm, level
foundation. The jack bases must be level to
prevent overloading of individual jacks and to
ensure that the structural load is evenly
distributed across all of the jacks.
h) The jacks must be positioned vertically, fixed to
the concrete base using the foundation bolts
provided or clamped to the bottom sheet/angle
and supported by centre and side stays. Centre
and side/top stays must be utilised on every
installation. Special length top stays are
provided for use with Slave Gearboxes.
i) The jack spacer plate must be used between the
carriage and structure sheet.
j) Ensure that electricity supply cables cannot be
accidentally damaged or cut, cover over ifnecessary. The use of armoured cable is
recommended.
k) Jacks are generally used to construct tanks and
silos which are 3 rings high and above. They are
also regularly used to construct structures with
roofs or starter rings. (Contact Permastore for
further advice on suitability and usage).
l) Permastore construction jacks are regularlymaintained and load tested. Copies of test
certificates are available to confirm suitably.
CONSTRUCTION JACK MAINTENANCE
Before Commencement of Work
1. With jacks vertical, check gearbox oil is up to
level plug. (Use EP90 or equivalent).
2. Check splines on gearbox and PTO shafts for
wear or damage and ensure that locking pins are
free and oiled. Grease splines on both and
ensure PTO shaft guards are fitted correctly.
3. Examine motor couplings and drive shaft splines
for wear and check motor/gearbox alignment.
4. Check all turnbuckle threads are free and oiled
and stays are in good condition.
5. Examine jack carriage assembly for damage or
wear and oil jack drive screw.
Daily Checks
1. Check jack lifting carriage assemblies fordamage and security.
2. Check jack retaining clamp for tightness.
3. Examine jack support stays and pins and check
jacks for being upright with masons level.
4. Make sure that jack lifting bolts and nuts are
always in good condition. Any replacement
bolts must be to the correct grade and shank
length. (Minimum Grade 8.8).
Weekly Checks
1. Jack gearbox oil levels.
2. Grease rollers on rear of jack carriage plate.
3. Grease PTO shaft universal joints.
4. Oil jack drive screws.
NOTE: Ensure that all jacking equipment is kept
clean and in a serviceable condition during the
construction period.
After construction is complete, fully examine all partsfor wear and lubricate before packing away.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 42/101
Permastore Construction Guide Assembly Methods
Doc Ref: P132 Rev 9 1 /5 /10 Page 42 of 97
TYPES OF CONSTRUCTION JACK
Within our stock of construction jacks that are
available for hire we have two distinctly different
models.
1. High Level Gearbox
The high-level gearbox jacks have the gearbox
and transmission shafts located at the top of the
jack body and have a swivel mounted base plate
for conical foundations. The high level jacks are
tested for a safe working load of six tonnes
(13,200 lbs).
2. Low Level Gearbox
The low-level gearbox jacks have the gearbox
and transmission shafts located at the bottom of
the jack body and the drive motor is an
independent unit which is floor mounted
between two jacks. The low-level jacks are
tested for a safe working load of four tonnes
8,800 lbs).
3. Slave Gearboxes
One advantage associated with the low-level
jacks is the opportunity to utilise 'slave
gearboxes' for a specified range of applications.
Slave gearboxes are low cost units that allow
safeconstruction utilising a reduced number of jack legs.
The advantage being more cost effective use of
the jack legs by reducing the amount required to
construct a specified vessel and facilitating
increased use of a limited number of high cost
assets.
Special length top stays are provided for use with
slave gearboxes to ensure positive location of the
assembled equipment. Centre stays and top stays
MUST be utilised on EVERY installation.
A recommended usage chart for slave gearboxes
and low-level jacks is included for reference (see
page 45).
SETTING UP FOR JACK CONSTRUCTION
1. Set up base angle, level and check concentricity.
2. Place jacks inside structure on base.
3. Assemble top row of sheets onto base angle.
Apply sealant to vertical seams only; locate onto
base angle with four bolts per sheet. Expand
sheets and tighten vertical bolts to 65Nm (46ft-
lb).
4. Re-check concentricity and clamp down base
angles.
5. Place jacks at every vertical seam as standard
layout ensuring that they are the correct distance
from the tank wall. For Low Level Jacks the
dimension from inside tank wall to the front face
of the Jack Column should be 140mm and for
High Level Jacks 56mm.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 43/101
Permastore Construction Guide Assembly Methods
Doc Ref: P132 Rev 9 1 /5 /10 Page 43 of 97
6. Use level to check jack base plates. Pack up
with shims if necessary as the jacks must be on
level base datum to prevent stress during lifting
and possible gearbox damage due to over-run.
Level carriage plates and bolt to sheet using
spacer plates. Make sure that carriage plates are
at their lowest position without fouling the jackstops.
7. Fit support struts, check that jacks are vertical
and clamp down with foundation bolts through
the base plates or use clamps.
8. Install the motor mounting assembly to the
master jack and connect the drive shaft and cover
guard.
CARRIAGE PLATE ASSEMBLY
9. Fit PTO shaft guards over the universal joint
connections.
10. Check oil levels and lubricate screw thread.
INSTALLED HIGH LEVEL JACK ASSEMBLY
OPERATION OF JACKS
1. Jack bolts must be of the correct size and
strength.
2. Ensure that the jacks are in the low position
before connecting to the sheets and a spacer is
located between the carriage and the sheet.
3. In all cases a jack bolt must be fitted to every
accessible hole in the carriage plate. A minimum
of three jack bolts must always be utilised.
4. Loosely tighten the jack bolts and raise the
structure until weight is being taken on the jacks.
Ensure that the jack bolts are located in the
bottom of the carriage plate slots and tighten to
65Nm (46ft-lb) torque.
5. Raise the top ring of sheets to the correct height
for installation of the next row of sheets or roof.
CAUTION: Isolate drive motor and remove
drive shaft before commencement of work.
WARNING: When raising the jacks they must
not be run up to the end stops. The carriage plate
must not travel beyond the safe working area.
This will result in damage to the unit and if
persistently abused this could result in failure of
the equipment.
6. Apply sealant and hang the second row of sheets
in an anti-clockwise direction. Leave out the
bolts at the position the jacks will locate on thenext lift.
7. Complete a full ring of sheets and fully expand
the vertical seams before tightening.
8. Fit wind stiffener assemblies where applicable as
full rings are completed.
9. Loosely pull in any gaps in sheet faces, tighten
from centre to both corners on the horizontal
seam and tighten the vertical seam from the
corner down to the bottom ensuring that the joint
is fully expanded.
10. When the ring of sheets is complete lower the
structure onto supports until the weight is taken
off the jacks. Remove the jack bolts and spacer
bars and lower the jacks to locate on the next
sheet. Check that the carriage plates jam whilst
lowering.
WARNING: When lowering the jacks they must
not be run up to the end stops. The carriage plate
must not travel beyond the safe working area.
This will result in damage to the unit and if
persistently abused this could result in failure of
the equipment
11. Repeat the procedure until the structure is
complete.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 44/101
Permastore Construction Guide Assembly Methods
Doc Ref: P132 Rev 9 1 /5 /10 Page 44 of 97
JACK SYSTEM USAGE CHART(For guidance only)
Series 1400 Low Level System
Each jack leg has a safe working load (SWL) of 4000 kg (8,800 lbs). For small diameter standard tanks use a jack leg on every vertical seam. For other standard structures up to and including 5 rings high use a combination
of jack legs and slave gearboxes as recommended within the usage chart. Slave gearboxes are suitable only for
structure diameters included within the chart.
For tank diameters outside the scope of this chart including tanks with roofs and any tank in excess of 6 rings high
you must refer to Permastore for advice and confirmation of jack usage.
Sheets Per Ring
(SPR)
Model Diameter
(ft)
Jack Legs
(No
of units)
Slave Gearbox
(No
of units)
6 17 6 0
7 20 7 08 22 8 0
9 25 9 0
10 28 10 0
11 31 11 0
12 34 9 3
13 36 9 4
14 39 10 4
15 42 10 5
16 45 10 6
17 48 10 718 50 10 8
19 53 10 9
20 56 11 9
21 59 11 10
22 62 12 10
23 64 12 11
24 67 13 11
25 70 13 12
26 73 14 12
27 76 14 13 28 78 15 13
29 81 15 14
30 84 16 14
31 87 16 15
32 90 17 15
33 92 17 16
34 95 18 16
35 98 18 17
36 101 19 17
37 104 19 18
Table Continued on Page 46
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 45/101
Permastore Construction Guide Assembly Methods
Doc Ref: P132 Rev 9 1 /5 /10 Page 45 of 97
Table Continued from Page 45
Sheets Per Ring
(SPR)
Model Diameter
(ft)
Jack Legs
(No
of units)
Slave Gearbox
(No
of units)
38 106 20 18
39 109 20 19
40 112 21 19
41 115 21 20
42 118 22 20
43 120 22 21
44 123 23 21
45 126 23 22
46 129 24 22
47 132 24 23
48 134 25 23 49 137 25 24
50 140 26 24
51 143 26 25
52 146 27 25
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 46/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 46 of 97
PART FOUR Section 2
Assembly of Tanks and Silos UsingConstruction Jacks and a Starter Ring
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 47/101
Permastore Construction Guide Assembly Methods
Doc Ref: P132 Rev 9 1 /5 /10 Page 47 of 97
SETTING UP FOR TANK/SILO
CONSTRUCTION USING JACKS AND A
STARTER RING
Standard base structures may incorporate a starter ring
located onto the base angle. Starter rings are
generally used where a tank/silo may be extended atsome future date. They are also used to progress
installation of the base foundation and can be supplied
in advance of the main tank kit.
Starter Ring
1. Locate jack support plate (Part No. 512805) at
starter ring vertical seam. Space out with
washers to allow for thickness of base sheet.
2. Set up construction jacks as standard procedure.
3. Secure jacks by drilling and rawl bolting through
jack base plate into concrete or use clamps.
4. Fit structure support brackets (Part No. 523355)
to starter ring.
5. Hang top row of sheets onto jack carriage plates
using sealant, fit all bolts, expand seams top andbottom, check circularity and tighten to torque
65Nm (46ft-lb).
6. Continue installation as described in
Part Four - Section 1.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 48/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 48 of 97
PART FOUR Section 3
Assembly ofDouble Skin Tank Sheets
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 49/101
Permastore Construction Guide Assembly Methods
Doc Ref: P132 Rev 9 1 /5 /10 Page 49 of 97
ASSEMBLY OF DOUBLE SKIN TANK SHEETS
1. A Permastore Site Supervisor is recommended
for the installation of double skin sheets, unless
the Distributor has prior supervised experience.
2. Refer to Construction Guide PART THREE
Section 1 for general tank construction guidance.
3. Refer to bolt charts for correct bolt placement
and assembly.
4. Ensure double skin sheet assembly rig is
provided and ready prior to construction.
5. Lift the inner double skin sheet onto the
assembly rig ensuring the sheet is positioned as
shown below.
6. Apply sealant to the vertical and horizontal bolt
seams and to the outer surface of the inner sheet.
7. Lift the double skin outer sheet onto the inner
sheet ensuring the holes are aligned as shown in
the view below. Bolt the inner and outer sheettogether using the 8-off bolt holes in the centre
of the sheet.
8. Lift the assembled sheets into position for the
tank shell construction and apply sealant to the
vertical and horizontal bolt seams of the outer
double skin sheet.
VIEW OF ASSEMBLED INNER AND OUTER DOUBLE SKIN SHEETS ON ASSEMBLY RIG
Outer double skin tank sheetInner double skin tank sheet
Assembly rig
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 50/101
Permastore Construction Guide Assembly Methods
Doc Ref: P132 Rev 9 1 /5 /10 Page 50 of 97
9. Fully expand vertical joints using the double skin
tank sheet hydraulic joint expander assembly. A
sheet joint expander kit is available from
Permastore.
10. The vertical joint and corner assembly
arrangements for double skin and quad row
vertical series 1400 sheet joint interchanges are
shown below as viewed from the exterior of the
structure.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 51/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 51 of 97
PART FIVE Section 1
Annular Tank Construction
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 52/101
Permastore Construction Guide Annular Tank Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 52 of 97
ANNULAR TANKS
Annular tank systems are generally used for
continuous process applications. They provide a cost-
effective solution where floor space is at a premium.
The basic concept is two circular tanks of equal
height, one inside the other.1. When constructing an annular tank system, first
mark out on the foundation both the inner and
outer tank internal diameters. Also mark a line
from the centre which crosses the internal and
external marked diameters for each of the baffle
walls.
NOTE: Before commencing construction work
check all the relevant drawings for layout
configurations of tanks, especially if they
incorporate launders, baffle walls or revolving
bridges. It is important to ensure the correctorientation and fitment of all constituent parts.
2. Construct the inner tank in accordance with the
instructions specified in Part Three or Part Four
of this guide. Ensure the baffle wall fixing holes
are in line with the marked positions. Fit
external stiffener angles as specified on the
arrangement drawing and all exposed fixings on
the exterior of the inner tank must be protected
using the plastic nut caps provided.
3. Construct the outer tank around the inner tanktaking care to ensure that the baffle wall fixing
positions are in alignment and the datum levels
are consistent with the inner tank.
PLAN VIEW OF TYPICAL ANNULAR SYSTEM
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 53/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 53 of 97
PART FIVE Section 2
Backfilled Tank Construction
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 54/101
Permastore Construction Guide Backfilled Tank Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 54 of 97
BACKFILLED TANKS
Backfilled tanks are designed to be constructed either
wholly or partially below ground level.
IMPORTANT NOTICE: All work must be
undertaken by competent building crews familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it is
the responsibility of the building crew undertaking
these works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work, to
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
1. Check all relevant drawings for layoutconfigurations. It is important to ensure the
correct orientation and fitment of all constituent
parts.
2. The tank should be constructed in accordance
with the instructions specified in Part Three or
Part Four of this guide.
3. During construction it is essential that all the
stif fener bands are positioned as shown on the
general arrangement drawing and all exposed
fixings on the exterior of the tank must beprotected using the plastic nut caps provided.
4. Before the backfill material is laid the tank must
be successfully hydrostatically tested to ensure
complete expansion and as a check on all joints.
The water level must be maintained during
backfilling to prevent possible load damage.
5. The backfill should be placed in layers 300mm
(12 inches) deep. Each layer must be fully
circumferential. Take care if excavated earth is
being re-used to backfill the tank, this may
contain larger stones or boulders which maydamage the tank. Sand or pea gravel are the
preferred backfill materials but if you are using
local earth then hardboard sheets should be used
to prevent damage.
6. If the backfill material is to be compacted the
density of the compacted material should not be
greater than the surrounding conditions. Ensure
that machinery used for compaction does not
damage the tank walls.
7. Unless the tank is specifically designed to suchloads all heavy vehicles or equipment should not
be allowed close to the tank wall. An angle
drawn at 45° from the tank wall/base level gives
the intersection. Where it is essential that heavy
traffic passes close to the tank or parks close to
the tank for process purposes, the tank should be
backfilled locally with concrete.
8. Where tanks are designed to be backfilled with afully drained material a positive drainage system
should be provided.
RECEPTION PITS
Important Notice
All work must be undertaken by competent
building crews familiar with the relevant
regulations with particular regard to Health and
Safety. Furthermore, it is the responsibility of the
building crew undertaking these works to consider
each particular installation, its environment andthe specific risks therein prior to commencement
of work, to determine the protective equipment
required by personnel and to plan the safe system
of work that should be adopted in order for the
task to be carried out safely.
1. Reception pits are available in a range of sizes
up to a maximum 20ft diameter, usually 1½ rings
deep. They are mainly utilised in agricultural
applications as gravity fed collection tanks.
2. For excavation dimensions refer to the approved
reception pit drawings (supplied separately).
EXCAVATE THE PIT AREA
1. Mark out the perimeter.
2. Determine the total depth and diameter of the pit
excavation required and proceed with the
excavation, allowing an additional 600mm
(24 inches) on the diameter. Should there be any
risk of soil collapse the excavation area may
have to be increased accordingly.
DANGER: Under no circumstances shouldanyone get into the excavation at this stage.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 55/101
Permastore Construction Guide Backfilled Tank Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 55 of 97
ASSEMBLE THE PIT
1. The pit should be assembled, above ground, on a
suitable level and firm foundation, ie on an area
of concrete adjacent to the excavated site.
2. Apply sealant to one vertical and one horizontal
seam only, ensuring the bolt holes are covered.
3. Start by bolting just the top full ring of sheets
together using the standard overlap right over
left.
4. Fit the top stiffener angles to the ring of sheets
using tapered inserts at sheet overlap points.
5. Fit anchor rods at regular spacing as shown on
the approved pit drawing.
Temporarily fit the foundation angles to the pit
without sealant. Use 4 equally spaced bolts perangle and tighten to 32Nm (23ft-lb).
6. Tighten all sheet bolts to 65Nm (46ft-lb).
7. The assembled top ring can now be lifted using
suitable lifting equipment fixed at four equally
spaced points around the pit top. While the pit is
suspended, remove the foundation angles and fit
the lower ring of sheets. Fit the foundation
angles with sealant, using tapered inserts at the
sheet overlap points.
8. Tighten all bolts to the correct torque.
9. Fillet all sheet edges both inside the pit and
outside.
10. The assembled pit can now be lowered into the
excavation and should be suspended clear of the
base whilst a crew member goes inside.
11. From inside the pit the crew member should
place concrete blocks in position under the
foundation angle ensuring they are on a level and
firm footing.
12. Check that the pipe opening is set to the centre
line of the main tank and lower the pit onto the
concrete blocks.
13. Check levels and shim until the pit is level to +
or 1.5mm (1 / 16 inch) with the shims provided
and the top of the pit is to the required finished
height (allowance for pit top or grid to be
included).
14. Place the reinforcing mesh in the base area,
ensuring correct concrete cover by supporting
the mesh with chairs/stools and then pour the
concrete into the pit centre. Ensure that the
concrete flows out underneath the foundation
angles by using a concrete vibrator. Ensure that
levels inside and outside the pit are correct by
referring to the approved pit drawing.
15. Compacted granular fill may be used in the pit
excavation to within 100mm (4 inches) of the
foundation angles, unless the distance betweenthe edge of the reception pit and the main tank is
less than 2.5m (8ft 3in), when it is then advisable
to backfill with concrete that half of the pit
excavation which is nearest to the main tank.
Determine the amount of compacted granular fill
required, taking into account that all inlet pipes
and anchor rods around the top of the pit are to
be encased in mass concrete. Refer to approved
pit drawings.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 56/101
Permastore Construction Guide Backfilled Tank Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 56 of 97
16. When the concrete has cured sufficiently, after a
minimum of 3 days, apply a surface primer to the
concrete base only, as shown, wait for it to
become tack free, then seal inside the pit with a
fillet of sealant between the concrete and Glass-
Fused-to-Steel sheet.
WARNING: Serious damage will result to the
Glass-Fused-to-Steel if a flame torch is used to
dry out base concrete to install the sealant seal.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 57/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 57 of 97
PART SIX Section 1
Roof Construction
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 58/101
Permastore Construction Guide Roof Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 58 of 97
INTRODUCTION
IMPORTANT NOTICE: All work must be
undertaken by competent building crew familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it is
the responsibility of the building crew undertakingthese works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work. To
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
As a general rule all roofs should be constructed at
ground level.
Dependent upon the type of roof being installed, site
and environmental conditions and otherproject-specific factors, roofs can be constructed at
varying stages of the installation process.
In some extreme cases alternative methods of roof
construction may affect the roof design.
It is therefore extremely important to evaluate this
subject at the earliest opportunity and plan
accordingly.
The construction methods described within this
section may not apply to all installations.
For advice on alternative methods of construction
please contact Permastore.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 59/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 59 of 97
PART SIX Section 2
Trough Deck Roof Construction
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 60/101
Permastore Construction Guide Roof Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 60 of 97
TROUGH DECK ROOF CONSTRUCTION
IMPORTANT NOTICE: All work must be
undertaken by competent building crew familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it is
the responsibility of the building crew undertakingthese works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work. To
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
NOTE: Roofs up to and including 8.53m (28ft)
diameter are constructed at low level before the tank
is jacked to full height. Roofs above 8.53m (28ft)
diameter are generally built following completion of
the tank.
1. Study drawing for layout of support brackets,
beam configuration, upright supports etc.
2. Pre-assemble beams if required.
3. Fix support brackets to top angle at positions
indicated on drawing.
4. Fit primary beams and uprights (where required)
ensuring correct location to provide a shallow
fall across the roof.
5. Fit secondary beams and tie rods if required.
6. Anchor vertical supports to base.
7. Position centre row of cladding across tank.
Pilot drill and fix with the self-tapping screws
provided.
8. Fit rest of cladding working from centre row
outwards. Refer to drawing for special panellayouts and overlaps. If access is required onto
any area of the roof that has already been clad
then spreader/crawler boards must be utilised
and safety rails fitted along any exposed edges.
Alternatively safety netting can be suspended
underneath the roof.
9. Trim off around edge of top stiffener angle using
a suitable portable nibbler or hand saw.
10. Seal between top stiffener angle and cladding
with aerosol canned foam (where required).
11. Fit perimeter flashing around the tank using the
self -tapping screws provided.
12. Check all coated parts for damage and repair if
necessary.
TROUGH DECK ROOF SHOWING BEAM END AND GRP FLASHING
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 61/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 61 of 97
PART SIX Section 3
20° Stainless Steel Roof Construction
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 62/101
Permastore Construction Guide Roof Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 62 of 97
20° STAINLESS STEEL ROOF
CONSTRUCTION
IMPORTANT NOTICE: All work must be
undertaken by competent building crew familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it isthe responsibility of the building crew undertaking
these works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work. To
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
1. 20° Roofs are constructed at ground level.
2. Assemble top ring of sheets as detailed with Part
Four Section 1.
3. Set roof cap centre support at the height specific
on the adjacent sketch, dependent on the roof
diameter.
4. Variations to tank height can also be calculated
using the combination of sheet heights identified.
5. Where special height sheets form part of the
supply these will be specified on the project
drawings.
6. Fit the centre roof cap onto the roof cap centresupport column.
7. For roof diameters 6.83m (22ft) and above the
panels are manufactured in two pieces and
panels should be pre-assembled prior to
construction.
8. The first panel fitted must overlap the sheet
vertical joint by at least one clear hole pitch.
9. Successive roof panels must be constructed in a
clockwise direction ensuring fitment of the
internal radial stiffener angles as each new panel
is installed.
10. Do not tighten the panels to the roof cap until the
whole assembly is complete.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 63/101
Permastore Construction Guide Roof Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 63 of 97
SPECIAL NOTES
1. Fit tapered inserts on top of roof panel overlap
points before fixing to underside of roof cap.
Also at the roof panel to tank overlap points and
where the tank shell vertical joints overlap.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 64/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 64 of 97
PART SIX Section 4
External Tapered Beam Roof Construction
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 65/101
Permastore Construction Guide Roof Construction
Doc Ref: P132 Rev 9 1/5/10 Page 65 of 97
EXTERNAL TAPERED BEAM GLASS-FUSED-
TO-STEEL ROOF CONSTRUCTION
IMPORTANT NOTICE: All work must be
undertaken by competent building crew familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it isthe responsibility of the building crew undertaking
these works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work. To
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
1. Tapered Beam roofs are constructed at ground
level.
2. Assemble top ring of sheets including the topangle, as detailed in Part Four Section 1.
3. Set up suitable load bearing scaffold in the center
of the tank at the correct height to support the
roof during building.
4. Refer to assembly drawings for positions of
inserts, sealer plates, bolt lengths etc. Roof top
stiffener angle galvanised parts to be primed
with Sika Primer 210T along joint face and
allowed to dry before applying sealant.
EXTERNAL BEAM ROOF
5. To assist when hanging very large panels a hole
is punched for attachment of a special lifting
bracket. After fitting the panel apply sealant
around the hole, insert a store bolt and tighten to
65Nm (46ft-lb).
6. When assembling Glass-Fused-to-Steel roof
panels the bolt torque setting should be 65Nm
(46ft-lb) generally and 32Nm (23ft-lb) where
tapered inserts are fitted. 7. Check that centre support ring is level and set to
the correct height above the top stiffener angles.
8. Check roof layout for access upstand/flange
positions and walkways and proceed to install
the first four roof beams, placing them at 90°
intervals.
9. Assemble the next four beams in the centre of
the four beams already installed. Proceed to
assemble the rest of the beams using the same
technique.
10. When all beams are in position the roof panels
can be installed.
11. Proceed to fit outer roof panels in an
anticlockwise direction by slackening and
supporting the beams and inserting the panels
between the beam and the top angle, ensure that
the rubber inserts are correctly placed. It is
advisable to assemble at least three panels before
tightening and always leave two loose panels
between the one being installed and the one
being tightened.
12. Following completion of the outer ring of panels
commence installation of the inner roof panels,
again in a clockwise direction.
13. Apply sealant to upper surface of roof panel,
along all bolt seams except at the top (shortest)
edge. With suitable lifting equipment proceed to
lift roof panels into position and fix to under side
of beams installing all bolts in opposite sides of
adjacent beams and lower edge seam.
14. Complete the full ring of panels torque up bolts
in panel previously installed and apply sealant
fillet along the edges of this panel.
15. Proceed to assemble the roof using these
techniques on subsequent rings.
16. Apply sealant and fit roof cap plates together
with roof cap stiffener.
17. The centre annulus support scaffold must not be
removed until all roof panels are fitted.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 66/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 66 of 97
PART SIX Section 5
External Parallel Beam Roof Construction
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 67/101
Permastore Construction Guide Roof Construction
Doc Ref: P132 Rev 9 1/5/10 Page 67 of 97
EXTERNAL PARALLEL BEAM GLASS-
FUSED-TO-STEEL ROOF CONSTRUCTION
IMPORTANT NOTICE: All work must be
undertaken by competent building crew familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it isthe responsibility of the building crew undertaking
these works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work. To
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
1. Paralled Beam roofs are constructed at ground
level.
2. Assemble top ring of tank sheets including thetop angle as detailed within Part
Four - Section 1.
3. Set up suitable load bearing scaffold in the center
of the tank at the correct height to support the
roof during building.
4. Refer to assembly drawings for positions of
inserts, sealer plates, bolt lengths etc. Roof top
stiffener angle galvanised parts to be primed
with Sika Primer 210T along joint face and
allowed to dry before applying sealant.
PARALLEL BEAM ROOF
5. To assist when hanging very large panels a hole
is punched for attachment of a lifting bracket.
After fitting the panel apply sealant around the
hole, insert a store bolt and tighten to 65Nm
(46ft-lb).
6.
When assembling Glass-Fused-to-Steel roofpanels the bolt torque setting should be 65Nm
(46ft-lb) generally and 32Nm (23ft-lb) where
tapered inserts are fitted.
7. Check that centre support ring is level and set to
the correct height above the top stiffener angle.
8. Check roof layout for start datum and install
starter roof panels. Ensure that rubber inserts are
correctly positioned.
9. Install first four roof beams, placing them at 90°
intervals. Refer to sketches on the followingpage for details of beam end attachment.
10. Install next four beams central to the four beams
already installed. Proceed to install the rest of
the beams following the same procedure until all
beams are in position.
11. Following completion of the outer ring of panels
commence installation of the inner roof panels,
again in a clockwise direction.
12. Apply sealant to upper surface of roof panel, ie
along the bolt seams except at the top (shortest)edge. With suitable lifting equipment proceed to
lift roof panel into position and fix to underside
of beams installing all bolts in opposite sides of
adjacent beams and lower edges seam.
13. Complete the full ring of panels working in a
clockwise direction, torque up bolts in panel
previously installed and apply a sealant fillet
along the edges of this panel.
14. Proceed to assemble the roof using these
techniques on subsequent rings.
15. Apply sealant and fit roof cap plates together
with roof cap stiffener.
16. The centre annulus support scaffold must not be
removed until all roof panels are fitted.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 68/101
Permastore Construction Guide Roof Construction
Doc Ref: P132 Rev 9 1/5/10 Page 68 of 97
PARALLEL BEAM END ATTACHMENT DETAILS
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 69/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 69 of 97
PART SIX Section 6
Glass Reinforced Plastic (GRP)Roof Construction
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 70/101
Permastore Construction Guide Roof Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 70 of 97
GRP ROOF CONSTRUCTION
IMPORTANT NOTICE: All work must be
undertaken by competent building crew familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it is
the responsibility of the building crew undertakingthese works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work. To
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
1. GRP roofs are constructed at ground level.
2. The design and shape of GRP roofs vary
considerably and for this reason the following
instructions are very generalised.
3. Set up suitable load bearing scaffold in the centre
of the tank at the correct height to support the
roof during building.
4. Using a mobile crane, place first roof panel
positioning the panel onto roof support angles
and centre support scaffold.
5. Join remaining roof panels together installing
sealer strip or sealant in between joints and bolt
together using the stainless steel setscrews,
washers and nuts provided. Tighten inaccordance with the manufacturers instructions.
6. After installing all the roof panels drill out holes
in outer roof support flange to align with holes
already in outer roof support angles. Lift up roof
sheets from roof support angles using a pinch bar
or similar, clean out drill swarf, apply sealant in
between roof support angles and roof flange.
Install store bolts provided and tighten to 30Nm
(20ft-lb).
7. Place roof cap into position, drill through roofcap and roof panels with a suitable size drill to
accommodate the fixings provided. Remove
roof cap, clean drill swarf apply sealant, install
fixings provided and tighten in accordance with
the manufacturers instructions.
8. Do not remove centre roof support scaffold until
all bolts are in position and tightened around the
perimeter of roof and roof cap is correctly
installed.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 71/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 71 of 97
PART SIX Section 7
Pressure Testing ofRoofs
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 72/101
Permastore Construction Guide Roof Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 72 of 97
PRESSURE TESTING OF ROOFS
IMPORTANT NOTICE: All work must be
undertaken by competent building crew familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it is
the responsibility of the building crew undertakingthese works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work. To
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
1. Where the project specification dictates a
pressurised roof these are designed to withstand
internal pressures and vacuums. Following
construction and hydrostatic testing it is
important to test the roof to ensure that it is
effectively sealed and meets the specified
test/specification conditions.
2. Equipment needed:-
a) Electric blower capable of pressure
required.
b) Electric extension cables to reach the top of
the structure.
c) Manometer ('U' tube water gauge).
d) Pipe connection kit.
e) Appropriate personal safety equipment.
f) Knapsack sprayer.
3. Seal all tank outlet pipe flanges and access
hatches.
4. Fill tank with water to operational level.
5. Install blower connection kit and pressurise roof
to test pressure.
ROOF PRESSURE TEST KIT
6. Use a water and detergent mixture to test all roof
seams and flange connections.
7. Pressure must be maintained during the period of
test, generally one hour maximum.
8. Mark any leaks that need to be repaired.
9. Release pressure from structure and repair any
leaks. If leaks were repaired, re-pressurise and
check they are sealed.
NOTE: It is advised that tests are carried out on
a calm and cloudy day. Variations in
temperature due to sun, rain or wind can greatly
affect internal pressure. These changes will
cause pressures to fluctuate and will need to be
compensated for during the test.
Extreme fluctuations may cause a serious
over/under pressurisation of roof resulting in
damage if venting is not adequate.
10. Ensure the roof is vented before draining internal
water to prevent implosion.
11. When pressure testing to specific test/contractual
conditions it is advisable to ensure the customer's
representative witnesses the test.
CAUTION: WHEN FILLING AND/OR
DRAINING A TANK IN PREPARATION FOROR FOLLOWING ROOF PRESSURE TESTING
IT IS IMPORTANT TO ENSURE THAT ROOF
INSPECTION HATCHES, VENTS, APERTURES
ETC ARE LEFT OPEN TO PREVENT AN
OVER-PRESSURE OR VACUUM SITUATION
OCCURING WHICH MAY RESULT IN
PERMANENT DAMAGE TO THE TANK
STRUCTURE.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 73/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 73 of 97
PART SEVEN Section 1
Construction of
Glass-Fused-to-Steel Floors
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 74/101
Permastore Construction Guide Glass-Fused-to-Steel Floor Construction
Doc Ref: P132 Rev 9 1/5/10 Page 74 of 97
GLASS-FUSED-TO-STEEL FLOOR
CONSTRUCTION
1. Prior to proceeding with the installation ensure
you have read and understood the layout
drawings for the type and size of floor to be
assembled. 2. From the centre point of the prepared foundation
mark a circle equivalent to the nominal tank
diameter plus 150mm (6 inches).
3. Mark out the 0°-180° and the 90°-270° centre
lines ensuring they are clearly identifiable
outside of the circle.
4. Lay base angles to confirm location of shim
packs and install shim packs to the CORRECT
radius and level.
5. Install the bitumen sand (asphalt/tank base)
within the tank circle as detailed on the layout
drawing and level with the shim packs.
6. Care must be taken to ensure the asphalt surface
is level. A slight rise to the centre is desirable.
7. Lay polythene sheet and cover asphalt before
installing floor.
8. Special care must be taken to protect the floor
panels during construction of the floor and tank.
9. Before each sheet is laid, insert the bolts inreadiness for fitting the adjoining sheets, secure
the bolts with the 'push on' fixing (Part Number
208059091).
10. Apply sealant ensuring a liberal covering around
the protruding bolts.
11. For Glass-Fused-to-Steel floors up to and
including 21.347m (70ft) diameter the perimeter
holes for fixing the floor to the foundation angles
are pre-drilled.
This is feasible due to the circular accuracy of
smaller diameter tanks.
12. For Glass-Fused-to-Steel floors above 22.2m
(73ft) diameter and above the perimeter holes
need to be drilled on site.
13. Lay the first panels (row 'D') and ensure that thefirst row of floor sheets is in a straight line
before tightening; very important on large tanks.
FLOOR LAYOUT
14. Lay subsequent panels in sequential order as
specified on construction drawing.
15. Fit tapered inserts at the sheet overlap areas
between the floor sheets and the base angles.
16. Fit full rows of sheets before tightening bolts
using the standard torque settings to assist with
alignment.
17. Fillet all sheet edges.
18. As there is no expansion pressure on a flat
surface it is not necessary to use a joint expanderduring construction.
19. For floors up to and including 21.347m (70ft)
diameter that are pre-drilled lay the perimeter
panels first and work inward.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 75/101
Permastore Construction Guide Glass-Fused-to-Steel Floor Construction
Doc Ref: P132 Rev 9 1/5/10 Page 75 of 97
20. Providing the procedures have been carefully
followed there should not be any cause for
leakage, however, it is advisable for the crew
leader to carefully inspect all areas of the sealing
joints and fillets. This may be your last chance
to ensure a seal.
21. Dependent on the method of construction for the
tank cylinder, protective nut caps should be fitted
now if not using jacks. Where jacks are being
used to construct the tank the nut caps should not
be fitted until after the tank is constructed and all
jack equipment removed.
22. Floor fixings should be treated with Sika Primer
210T and coated with sealant prior to fitting nut
caps.
23. Install the foundation angles and where they join
fit the joint sealer angles (Part Number 559299)as shown. Floor foundation angles joint faces to
be primed with Sika Primer 210T and allowed to
dry before applying sealant. Construct the first
ring of tank cylinder sheets in the conventional
manner.
24. Tapered inserts should also be fitted at the
vertical sheet joints.
25. Expand the vertical sheet joints before tightening
the bolts to 65Nm (46ft-lb).
FLOOR PLATE BASE ANGLE CONNECTION
26. Continue building the tank structure referring to
the relevant section of this guide.
27. When the structure is complete drill and fit the
foundation bolts and PVC isolation washers and
install the internal perimeter sealant fillet.
SECTION THROUGH FOUNDATION BOLT
28. Fillet the outside of the structure with concrete if
specified/required.
29. Fit plastic nut caps to the floor area if not already
installed.
30. The finished floor assembly MUST be wet swab
tested at this stage (Part Ten Section 2) and any
repair work undertaken. For details of suitable
repair procedures refer to Part Twelve Section 1
of this guide.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 76/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 76 of 97
PART EIGHT Section 1
Cone Tank Construction
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 77/101
Permastore Construction Guide Cone Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 77 of 97
CONE TANK CONSTRUCTION
IMPORTANT NOTICE: All work must be
undertaken by competent building crews familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore it is the
responsibility of the building crew undertakingthese works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work, to
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
Introduction
1. Cones and structures are designed to conform
with the product being stored and customer
requirements. The connection and designtechniques will remain similar.
2. Except for skirt mounted structures a crane will
be required to lift the structure and cone onto the
supporting steelwork.
3. Construction layout and techniques are the same
as standard tank design, ie joint overlap and bolt
torque.
4. A tapered insert is used at angle and sheet
transition overlap areas.
5. Cone structures are designed to be supported by
Glass-Fused-to-Steel sheets (skirt mounted) or
sectional steel (steel-frame mounted). The actual
design being determined during the enquiry stage
when the operational and storage details are
clear.
6. Skirt mounted cone structures can, in most cases,
be assembled using the conventional installation
equipment traditionally used to construct
Permastore tank and silos.
7. Steel frame mounted cone structures generally
require specialist lifting equipment to ensure a
quality and safe construction.
SKIRT MOUNTED STRUCTURES
1. Build tank structure as standard procedures
ensuring that for the final lift before the hip- joint
the jacks are taken down to their lowest position.
This will ensure the extra height required to
install the hip-joint. Lift jacks to their highest
position and check that clearance is sufficient to
assemble hip- joint and first row of skirt sheets.
2. Check all relevant drawings and assemble hip-
joint leaving out section at jack positions and
ensure that correct length bolts are used, do not
fit those where stiffener ring is to be connected.
Leave bolt finger tight.
3. Hang first row of sheets leaving out any bolts
where stiffener ring is to be fitted.
4. Lower structure onto support and disconnect jack
bolts.
5. Lower jacks and connect for next lift, raise
structure sufficiently to allow completion of hip
joint and fitting first row of cone sheets. After
tightening cone sheets assemble and fit external
stiffener. Raise structure again to hang second
row of skirt sheets.
6. Continue to build structure adding cone sheet
rings and internal stiffener brackets as required.
Fit internal stiffener on completion of skirt
sheets.
7. Fit cone outlet adapter to final row of cone
sheets before they are tightened.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 78/101
Permastore Construction Guide Cone Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 78 of 97
8. Typical view showing the layout and assembly
of cone structure.
STEEL FRAME MOUNTED CONE
STRUCTURES
1. These structures are supported below the cone
hip-joints directly onto a steel superstructure and
will require a crane on site, time will be
dependent on method of build.
2. In most cases the top row of cone sheets would
be assembled on a firm, level area of ground.
Attach the cone support ring and cylinder base
angle.
3. Check that the ring of sheets are level, expand
the vertical seams and tighten. Do not tighten
the bolts from the cone support ring to base
angle at this stage.
4. Lift cone ring with crane using either internal
bracing or a spreader frame to prevent distortionof the ring. Further rows of cone sheets can be
added at this stage depending on the size of
crane employed.
5. Lift the cone onto the platform and bolt down.
Tighten all bolts in base angle and channel.
6. Choose a firm level piece of ground and build
the main structure using construction jacks.
Ensure that the jacks are securely anchored
down. Fit a suitable lifting bracket to each
vertical seam on the top row of sheets.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 79/101
Permastore Construction Guide Cone Construction
Doc Ref: P132 Rev 9 1 /5 /10 Page 79 of 97
7. Using a spreader bar lift structure onto top of
cone and couple up. Ensure that a good sealant
fillet is applied inside to fully cover the hip- joint
area.
ALTERNATIVE METHODS OF CONE
CONSTRUCTION
1. The structure can be built by using the crane
instead of construction jacks. Build the top row
of sheets and roof on a suitable level piece of
ground. Fit lifting brackets and install other
rings of sheets while suspended.
2. Lift pre-assembled structure and couple to cone
at ground level before installing onto steel
platform.
3. After fitting the cone onto the platform, scaffold
can be placed internally and externally around
the top of the cone and steelwork and the main
structure built directly on top of the cone using
construction jacks. This system will require load
bearing scaffolding and special brackets
manufactured to support the jacks.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 80/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1/5/10 Page 80 of 97
PART NINE Section 1
Construction of Ancillary Products
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 81/101
Permastore Construction Guide Ancillary Products
Doc Ref: P132 Rev 9 1/5/10 Page 81 of 97
GENERAL GUIDANCE NOTES
The ancillary products contained within this part of
the Construction Guide have all been designed by
Permastore or have been technically assessed for
suitability with our standard product.
Although Permastore offer a comprehensive range ofancillary products there are situations where
customers manufacture their own ancillary products
or where unique process requirements dictate the use
of special equipment, fixtures and fittings.
It is extremely important to ensure the technical
suitability of any ancillary equipment that is not
supplied by Permastore and is to be mounted or fixed
to one of our structures. The un-necessary
introduction of dis-similar metals for example can
induce an electrolytic cell within the as constructed
tank.
Permastore cannot accept any responsibility for
problems associated with the attachment/fitment of
ancillary equipment by others unless those products
have been approved for use, in writing, by our
Engineering Department.
IF IN DOUBT, ASK.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 82/101
Permastore Construction Guide Ancillary Products
Doc Ref: P132 Rev 9 1/5/10 Page 82 of 97
PROTECTIVE NUT COVERS
1. Plastic nut covers are supplied as standard with
Glass-Fused-to-Steel floors, backfilled tanks and
inner annular tanks. They are provided to
protect the exposed fixings only where there is a
risk of contents or environmental corrosion.
They can also be purchased separately for
aesthetic purposes if required.
2. Check the relevant drawings for the position ofthe protective nut covers (eg backfilled tanks
have nut caps fitted in the area of backfill only,
unless otherwise specified).
3. Once the nut has been tightened to the final
torque, ensure that there is plenty of sealant
squeeze-out around the nut and washer, then
push the protective nut cover onto the nut and
washer. Use either a rubber or wooden mallet to
install tight caps.
4. If the sealant around the nut and washer has
cured, scrape off the cured sealant and apply a
bead of sealant to the inside of the protective nut
cove and push onto the nut and washer assembly.
FLANGE CONNECTORS
1. Flange connectors are available in a range of
options, the standard supply is detailed below:-
2. Refer to the assembly drawings for the correct
orientation/position.
3. When installing flange connectors, apply sealantaround the sheet aperture where the connector is
in contact with the Glass-Fused-to-Steel plate.
Position the connector and backing flange and fit
the fixing bolts. Tighten fixings to 50Nm (36ft-
lb).
4. Fillet the internal edges of the connector
assembly ensuring that the bore is not restricted
by sealant.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 83/101
Permastore Construction Guide Ancillary Products
Doc Ref: P132 Rev 9 1/5/10 Page 83 of 97
VENTS AND ROOF HATCHES
1. Pre-assemble vent or hatch if required.
2. Apply sealant around roof aperture where the
vent or hatch is in contact with the Glass-Fused-
to-Steel sheet. Fit and tighten fixing bolts to
50Nm (36ft-lb).
3. Glass reinforced plastic or aluminium fittings
should only be tightened to 30Nm (20ft-lb).
4. Steel fitments should be tightened to 50Nm
(36ft-lbs).
5. Fillet all internal and external edges with sealant.
TANK WALL ACCESS MANWAYS
1. Tank wall access manways are supplied as a
complete assembly including a pre-cut aperture
sheet and are designed to complement the
particular application required. The standardmanway is 800mm diameter with a hinged cover
to facilitate safe and easy access.
2. Dependent upon the specification supplied it
may be necessary to use a mobile lifting rig to
position the manway frame.
3. Apply sealant around the sheet aperture inside
and outside the tank, ensuring sufficient
coverage to effectively seal the flange plates.
4. Position the backing plate inside the tank and
insert a small quantity of fixings.
5. Position the external frame and fit nuts and
washers to the locating fixings.
6. Insert the remaining fixings and tighten to the
standard torque setting.
7. Fillet the internal and external edges of the frame
assembly ensuring effective edge protection.
8. Position and fix the access door ensuring ease ofoperation and effective closure.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 84/101
Permastore Construction Guide Ancillary Products
Doc Ref: P132 Rev 9 1/5/10 Page 84 of 97
LADDERS AND PLATFORMS
1. Ladders and platforms are supplied in various
configurations according to the height, diameter,
market standards and client specification. It is
therefore very important to refer to the assembly
drawing prior to construction to ensure thecorrect layout details.
2. Pre-assemble the ladder platform sections and
mark the position on the tank of the ladder and
platform support brackets.
3. Ensure the tank bolts have been omitted during
tank construction.
4. Apply sealant to the tank wall and support
brackets before installing the fixings.
5. The ladder sections and platform assembly can
then be fitted to the support brackets at low level
as the tank is being built.
6. Base ladders should be fitted to confirm
suitability but removed before leaving site and
handed to the client for safe storage.
Base ladders should only be fitted to
accommodate controlled access.
7. Install the platform base onto the relevant
support brackets and then complete the assembly
by fitting the upright support and handrails.
8. Several variations of the standard ladder and
platform options are shown for reference only on
the following pages.
SECTIONAL VIEW OF INNER AND OUTER
LADDER ASSEMBLY.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 85/101
Permastore Construction Guide Ancillary Products
Doc Ref: P132 Rev 9 1/5/10 Page 85 of 97
INDUSTRIAL LADDER AND PLATFORM OPTIONS
OPEN TOP TANK LADDER
ASSEMBLY
OPEN TOP TANK LADDER ASSEMBLY
WITH OPTIONAL 1M SQUARE
VIEWING PLATFROM
OPEN TOP TANK LADDER ASSEMBLY
WITH OPTIONAL 2M x 1M VIEWING
PLATFORM
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 86/101
Permastore Construction Guide Ancillary Products
Doc Ref: P132 Rev 9 1/5/10 Page 86 of 97
AGRICULTURAL LADDER AND PLATFORM OPTIONS
OPEN TOPPED AGRICULTURAL TANK LADDER ASSEMBLY WITH OPTIONAL 2M x 1M (6ft x
3ft) PLATFORM WITH CENTRE FLOOR HATCH
5 RING TANK 4 RING TANK 3 RING TANK
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 87/101
Permastore Construction Guide Ancillary Products
Doc Ref: P132 Rev 9 1/5/10 Page 87 of 97
CIRCUMFERENTIAL LAUNDERS
1. Launders are used to remove clarified or settled
liquids from the top of process tanks.
2. Within our standard range of ancillaries there are
two distinctive systems available.
'Z' TYPE LAUNDER SYSTEM
3. 'Z' type launders are mounted directly onto the
tank wall with a separate scumboard assembly.
4. Ref er to all relevant drawings before
commencement of work to ensure correct
assembly layout. Launder systems should be
fitted at ground level.
5. Position first launder section at correct height
and central to the outlet flange. Some launders
may incorporate a special dropped outlet. Locate
this section first.
6. Where a GRP 'Z' type launder is being installed
drill holes 14mm (½ inch) diameter through the
launder trough section using the holes in the
Permastore sheet as a template.
7. Apply sealant to mating face of launder trough
and Permastore sheet, fit launder in place andbolt in position.
8. Proceed to fit launder trough around tank in an
anti-clockwise direction ensuring that each
section is bolted together with sealant and
fixings.
9. The last section of launder trough may need
trimming (GRP only) on the plain section end to
ensure correct joint with outlet section.
10. Fit weir plates in position at the correct level
ensuring the sealer strip is effectively placed to
avoid seepage.
'U' TYPE LAUNDER SYSTEM
11. 'U' type launders are mounted on brackets with
an internal scum board.
12. Refer to all relevant drawings before
commencement of work to ensure the correct
assembly layout. Launder systems should be
fitted at ground level.
13. Install mounting brackets as detailed around the
perimeter of the tank.
14. Position the first launder section central to the
outlet flange. Some launders may incorporate a
special drop box. Locate this section first.
15. Proceed to mount launder trough on the support
brackets around the tank in an anti-clockwise
direction, ensuring that each section is bolted
together with sealant and fixings supplied.
16. Fix launder trough to mounting brackets usingpre-punched holes, ensuring good sealant
application around fixings.
17. Fit weir plates in position at the correct level
ensuring the sealer strip is effectively positioned
to avoid seepage.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 88/101
Permastore Construction Guide Ancillary Products
Doc Ref: P132 Rev 9 1/5/10 Page 88 of 97
BAFFLES AND BAFFLE WALLS
1. Internal baffle assemblies are utilised to provide
a homogenous mixture of contents in process
tanks.
2. Directly dependent on the height of the tank the
baffle assembly may be designed as a single
price structure or a modular concept.
3. Refer to all relevant drawings before
commencement of work to ensure correct
assembly layout. Baffle assemblies and baffle
walls should be installed at ground level.
4. Apply sealant to the contact surfaces and fit
vertical support angle frames to the tank wall.
5. Fit Glass-Fused-to-Steel baffle plates to the
angle frame.
BAFFLE WALL
1. Baffle walls are utilised to separate different
sections or processes within a tank.
2. Apply sealant to contact faces and fit vertical
support angles to inner and outer tank.
3. Fit baffle wall to support angles.
4. Fit top angle to baffle wall using splice plates to
join to inner tank.
5. After fitting floor angles drill out concrete and fit
expanding anchor bolts.
6. After completion of baffle walls install concrete
haunch over floor angles if specified.
7. Apply sealant to contact faces and fit weir weld
assembly to inner tank.
8. Fit splice plates to weir weld assembly to join to
top stiffener angles.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 89/101
Permastore Construction Guide Ancillary Products
Doc Ref: P132 Rev 9 1/5/10 Page 89 of 97
AGRICULTURAL VALVE KIT (SLUICEGATE)
1. Refer to approved valve assembly drawings.
2. When installing the valves and trunking or
pipework, ensure any PVC joints are glued
correctly.
3. Support the pipe or trunking and valves in the
trench, to allow a minimum of 150mm (6 inches)
concrete cover over the pipework.
4. Valves must be installed with flow direction
arrow facing the reception pit to ensure that the
valve plate is under flow pressure against the
seal.
5. Wrap the entire length of PVC pipework in
polythene sheeting.
6. Care should be taken when pouring the concreteto ensure the pipework or trunking is not
disturbed or damaged.
7. Concrete clearance must be maintained at the top
of the valve to allow for top plate removal.
8. Fitting the outlet into the reception pit may
require the cutting of the Glass-Fused-to-Steel
sheet (Refer to Part Eleven Section 1).
SACRIFICIAL ANODE CATHODIC
PROTECTION SYSTEM
1. There are some applications where the process
requirements or commercial factors dictate that
routine inspection and maintenance is
impractical. Where such conditions existPermastore recommends that a suitable cathodic
protection system is installed, monitored and
maintained. Cathodic protection systems can
provide a low cost, long term solution to protect
your investment.
2. For further information please refer to Document
Ref: P145 'Guidance Notes for the Application
and Use of Sacrificial Anode Cathodic
Protection Systems'.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 90/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 90 of 97
PART TEN Section 1
Checklist Following Construction
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 91/101
Permastore Construction Guide Checklist
Doc Ref: P132 Rev 9 1 /5 /10 Page 91 of 97
CHECKLIST AFTER CONSTRUCTION
1. Ensure sufficient sealant has been applied
correctly.
a) To provide full cover to all areas of sheet
overlap;
b) To provide a squeeze out of sealant around
bolt heads, nuts and washers.
2. Have bolts been fitted to all holes used for joint
expansion or jack location?
3. Have all sheet edges been pointed correctly to
give full protection both internally and
externally?
4. Have all ancillaries attached to Glass-Fused-to-
Steel coated sheets been fully coated with sealant
on contact surfaces before being bolted?
5. Have tapered inserts been used in appropriate
areas at top and bottom angles?
6. Are the levels and concentricity in accordance
with recommendations?
7. Are all the bolts within the specified torque
limits?
8. Has the peripheral base seal been applied
correctly and checked for adhesion?
9. Are all ancillary items securely fastened?
10. Has the full structure been examined carefully
and swab tested internally to identify any
installation damage and have the damaged areas
been repaired? The application of this test must
be witnessed by the customers site representative
following which the 'On Site Wet Swab Testing
Results Chart' (Doc Ref: 02.04.02 Appendix 7)
and the 'Certificate of Completion' (Doc Ref:
02.04.02 Appendix 4) must be authorised by the
sub-contractor and the customers representative.
For full instructions on repair procedures refer tothe Permastore Inspection and Maintenance
Manual Document Reference P110.
11. Check serial plate has been fitted.
12. Check that the Safety Awareness signs provided
within the tank construction kit are installed as
instructed (refer to Item 6, of 'Forward' Section
of this guide)
13. Ensure the structure has been left in a safe and
secure condition for following operations/testing.
For example:
a) Base ladders removed and stored safely by
the client.
b) Access doors fitted/closed correctly
c) Pressure test blanking plates removed.
d) No debris/fixings left in the tank that coulddamage process equipment.
e) Any other obvious or client specified
activities.
13. Ensure all packing and waste materials have
been cleared up, disposed of properly and the
site is left tidy. All COSHH substances and
contact packaging must be disposed of in a safe
manner commensurate with the manufacturers
data sheet.
14. Inspect the structure with the customer'srepresentative and assuming everything is in
order request his authorisation of a Construction
Completion Certificate.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 92/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 92 of 97
PART TEN Section 2
Low Voltage Continuity Testing on Site
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 93/101
Permastore Construction Guide Testing on Site
Doc Ref: P132 Rev 9 1 /5 /10 Page 93 of 97
LOW VOLTAGE CONTINUITY (WET SWAB)
TESTING ON SITE
All structures should be wet swab tested on the
internal surface following construction.
We recommend that for tall structures being built with jacks, that a check on the continuity of the internal
Glass-Fused-to-Steel coating is conducted on a ring
by ring basis during construction.
This will identify any minor repairs that may be
necessary following construction and will reassure the
end user that the product has a defect free
containment surface.
It is important to advise the customer's site
representative prior to testing, giving sufficient time
for the test to be witnessed and approved following
completion.
The internal surface of the structure should be clean
and free of surface contaminants. Testing is carried
our using an Elcometer Model 269 Wet Swab Unit set
at 9 volts. The test sponge shall be wet but not
saturated with water containing a small amount of
detergent to reduce surface tension.
In the unlikely event that a discontinuity is found the
following repair procedure should be adopted.
The identified area will be inspected for any signs of
corrosion. Should corrosion be evident the area must
be treated locally with Corroguard, abraded and then
allowed to dry for a minimum of 6 hours and then
overcoated with a 2mm ( inch) thick layer of sealant
overlapping the discontinuity area by 20mm (¾ inch)
all round.
The area of repair will again be subjected to low volt
test proving satisfactory repair.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 94/101
Permastore Construction Guide
Doc Ref: P132 Rev 9 1 /5 /10 Page 94 of 97
PART ELEVEN Section 1
Troubleshooting
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 95/101
Permastore Construction Guide Troubleshooting
Doc Ref: P132 Rev 9 1 /5 /10 Page 95 of 97
TROUBLESHOOTING
Introduction
This section has been compiled to assist the
construction team to resolve minor assembly issues
and undertake replacement or modification work.
One of the features of a Glass-Fused-to-Steel bolted
construction tank is the ability to modify the structure
on site to accommodate new or changed process
conditions. It is also possible to extend some
structures in height using either a top or bottom
extension but in all cases reference should be made to
Permastore to ensure suitability of proposed change.
IMPORTANT NOTICE: All work must be
undertaken by competent building crew familiar
with the relevant regulations with particular
regard to Health and Safety. Furthermore, it is
the responsibility of the building crew undertakingthese works to consider each particular
installation, its environment and the specific risks
therein prior to commencement of work. To
determine the protective equipment required by
personnel and to plan the safe system of work that
should be adopted in order for the task to be
carried out safely.
LEAKAGE REPAIRS
WARNING: If the structure has been in use there
may be potential hazards from toxic gases or
substances.
Please refer to the Health and Safety information
included within the Foreword of this guide.
In the unlikely event that leaks are in evidence on the
structure it may only be possible to effect a reseal
from the inside. The structure must then be drained
completely and the affected area thoroughly dried
before commencement of repair.
NOTE: Should the leak appear on the outside at a
bolt, the source of the leak is not necessarily at the
bolt head but may start through the sheet overlap.
Should the leak appear on the outside at a sheet
overlap the source of the leak is not necessarily at the
same point of the sheet overlap but may start from the
bolt head.
1. Bolt or Seam Leaks
a) To repair, mark the point of the leak
precisely on the outside of the tank before
draining the tank.
b) After draining the tank remove completely
all structure bolts and internal sealant filletwithin 150mm (6 inches) of the leak. Insert
fresh sealant into the bolt holes (from the
inside of the structure) and cover the bolt
head area of the sheet liberally with sealant.
c) Re-insert the bolts and tighten to the
prescribed torque. Replace the internal
sealant fillet and repoint.
d) Should the leak be serious, ie more than adribble, it may be necessary to part the
sheets with a small hard wooden wedge and
insert sealant to the complete overlap area
with a pallet knife.
2. Corner Joint Leaks
a) Remove existing sealant around the corner
joint extending beyond the nearest bolt in
all four directions.
b) Remove the corner bolt completely and
slacken the four bolts immediatelysurrounding the corner bolt.
c) Wedge open the joint internally with a hard
wooden wedge and inject sealant into the
open joint.
d) Repeat point (c) externally.
e) Replace the corner bolt, nut and washer.
f) Tighten the corner and four surrounding
bolts to the specified torque.
g) Re-point the corner joint and surrounding
seams with new sealant.
3. Perimeter Seal Leaks
If the leak is from the base area, again remember
that the point of the leak showing externally is
not necessarily the source and may start from
any point of the perimeter seal up to 3m (10ft)
from the leak. The source may also be from an
area of the floor because of porous concrete. For
perimeter seal leaks:-
a) Check the adhesion to the tank wall and
concrete foundation.
b) Suspect areas should be cut away 500mm
(18 inches) either side of the affected area
and the concrete cleaned and dried.
c) Apply concrete primer as specified for each
type of perimeter seal.
d) Apply new sealant to the area cut away.
NOTE: For all sealant repairs allow a minimum
of 10 days to cure before refilling the tank. For
temperatures below 15°C an extended cure
period will be required.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 96/101
Permastore Construction Guide Troubleshooting
Doc Ref: P132 Rev 9 1 /5 /10 Page 96 of 97
REMOVAL OF FLAT SPOTS ON THE
CORNER JOINTS OF A STRUCTURE
1. Remove all bolts surrounding the four corner
joints, clean, apply new sealant in the joints and
loosely install new bolts.
2. Secure a wooden support inside the tank with aM10 ( inch) diameter eye bolt through bolt
hole in sheer joint and pull out flat spot to the
correct shape of the tank. This is best done using
a chain block or similar anchored to a suitable
pulling point. After pulling out flat spots tighten
bolts to the correct torque. Remove chain block,
replace eye bolt and apply sealant fillets to blend
in with the existing fillets.
REMOVING AND REPLACING A GLASS-
FUSED-TO-STEEL SHEET
WARNING: If the structure has been in use there
may be potential hazards from toxic gases or
substances.
Please refer to the Health and Safety information
included within the Foreword of this guide.
1. Set up scaffold to a working height on the
outside and inside of tank adjacent to where
sheet is to be removed.
To remove the sheet, carefully take out all the
sheet fixing bolts from the sheet overlaps. Itmay be necessary to remove the bolts on
adjoining sheets at the four sheet overlap joint
for the distance of about 300mm (12 inches).
Using wooden wedges gently prise the sheet
joints apart. Using suitable lifting equipment
remove tank sheet. Thoroughly clean sealant
from the sheet overlap joints.
2. To fit replacement tank sheet, sealant must be
applied to all the overlap faces and with wooden
wedges prise a gap between the adjoining sheets
as with removal. When the replacement sheet islowered into position with suitable lifting
equipment, ensure sealant is applied between the
prised open joints and applied to the replacement
bolts before fitting.
When all bolts are fitted tighten to the standard
torque and apply sealant fillets over sheet edges
to blend in with the existing fillets.
DRILLING AND CUTTING HOLES IN GLASS-
FUSED-TO-STEEL SHEETS
WARNING: Do not use disc grinders or flame-
cutting equipment to cut holes in Glass-Fused-to-Steel
sheets. Always use electric drill and jig-saw.
Always use eye protection when cutting or drillingsheets.
If the structure has been in use there may be potential
hazards from toxic gases or substances.
Please refer to the Health and Safety information
included within the Foreword of this guide.
DRILLING HOLES
Mark the position of the hole to be drilled and dot
punch the centre. Start with a small pilot drill and
gradually increase the drill size to the required size tothe required hole diameter.
CUTTING OPENINGS
1. Apply masking tape over the areas of the
openings to be cut. Mark out the opening and
dot punch the inside edge. Drill out to 10mm
(13 / 32 inch) and using a jig-saw cut around the
marking opening. Recommend Bosch blades
type T118B.
2. After cutting or drilling remove all traces of
swarf and burred edges.
3. Ensure that all edges have been covered with
sealant on completion of work.
PERMASTORE REPAIR KIT
INSTRUCTIONS FOR USE
1. Corroless EP is a two part glass reinforced rust
stabilising primer.
2. Surface Preparation
Steel should be clean and free from any looseGlass-Fused-to-Steel coating, oil, grease or rust.
Abrade the surface and surrounding 25mm (1
inch) of sound Glass-Fused-to-Steel with
medium grit emery cloth.
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 97/101
Permastore Construction Guide Troubleshooting
Doc Ref: P132 Rev 9 1 /5 /10 Page 97 of 97
3. Mixing and Application
Mix the two components at a 1:1 ratio and apply
without delay using a small, clean brush. Ensure
that the material overlaps onto the abraded
Glass-Fused-to-Steel. Do not over brush.
Externally applied repairs should be over paintedthe next day with locally sourced enamel paint to
match the Glass-Fused-to-Steel.
Internal repairs should be covered the following
day with the build sealant. Ensure the sealant
completely covers the repair material and
extends a minimum 20mm (¾ inch) beyond the
repair site.
4. Properties
Mix ratio 1:1 (by volume)
Working life 45 mins (at 18°C)
Drying time Touch 6 hours
Hard 16 hours
Over coating Min 16 hours
Max 3 days
Application temp Min 2°C
Max 30°C
5. Handling Precautions
Precautions normally taken when handling
chemicals should be observed. The material
must not come into contact with foodstuffs or
food utensils. The use of protective clothing,
goggles, barrier cream and rubber gloves arerequired. Adequate ventilation of the work area
is recommended. Leaflets are available on the
handling of these materials and we strongly
advise they are read prior to using the products.
6. Data Sheets
Material Safety and data sheets for all sealants,
primers and cleaners used to build Permastore
structures are generally provided with the project
documentation but are also available on request.
Whilst every care has been taken to ensure accuracy throughout this guide Permastore shall have noliability for any loss or damage, (direct or indirect or consequential) arising out of or in connectionwith this guide.
This guide is subject to supplementation or change at any time without notice at Permastore's solediscretion.
© Copyright 2009 Permastore Limited
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 98/101
APPENDIX A
Doc Ref: P132 Rev 9 1/ 5 /10 Page A1
1
2
3
4
6
5
7
8
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 99/101
APPENDIX A
Doc Ref: P132 Rev 9 1/ 5 /10 Page A2
9
10
12
11
13
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 100/101
APPENDIX A
Doc Ref: P132 Rev 9 1/ 5/ 10 Page A3
14
15
16
18
17
8/9/2019 Permastore Construction Guide
http://slidepdf.com/reader/full/permastore-construction-guide 101/101
APPENDIX A
19
20