Performance Based Navigation(PBN)

Canadian Implementation

Presentation toAir Transport Association of Canada

9 November 2010

Page 2: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

Presentation Overview

• PBN Background– Performance Based Navigation– Why PBN?

• PBN in Canada– Current status– Coordination– Framework– Short, Medium and Long term plans and timelines

Page 3: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

3

Performance-Based Navigation

GNSSPrimary Navigation

FutureVision

Today

Ground-BasedPrimary Navigation

RNAV & RNP

Moving towards• Leveraging aircraft capabilities• Safety, Capacity, Efficiency

Optimize benefits:• Airspace design• CNS technologies• Traffic Flow Management

Page 4: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

Why PBN? - Benefits

• Facilitates more efficient design of airspace and procedures

• Improves safety, access, capacity, predictability, and operational efficiency.

• Minimizes reliance on ground based navigation routing and infrastructure

• Reduces aviation impact on the environment–Less fuel burn and GHG emissions–Less noise pollution

4

Page 5: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

PBN in Canada

5

Page 6: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

PBN in Canada

• May 2010 – PBN Framework document developed. Linked to a Concept of Operations

• Sept 2010 – NAV CANADA received implementation feedback from the ATOCC PBN Coordination Group

• October 2010 – Transport Canada committed to the creation of a CARAC Working Group to review the intent of PBN changes and the requirement for regulatory structure

• October 2010 – NAV CANADA short term implementation strategies provided to the aviation community through the ATOCC / ANSNAC meetings

Page 7: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

ATOCC PBN Coordination Group

• A combined NAV CANADA and customer group plus ADHOC industry experts coordinating activities and milestones – Scope of related issues is expanding– NAV CANADA PBN Coordination Manager : Jeff Cochrane

• Goal is efficient and effective extraction of benefits from latest technology and coordinated implementation of PBN– Cooperative/collaborative approach– Coordinated investment– Examination of ATC and Aircrew procedures– Coordination of testing and implementation of new or revised

procedures– “Now” and future targets

Page 8: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

CustomerCertification and

qualification

Linking the Objectives

8

Regulatoryenablers

ANSPInfrastructure

Page 9: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

PBN Framework - Purpose

• To align NAV CANADA and our customer expectations, priorities and objectives for the implementation of PBN concepts in Canada over the next 10 - 15 years

• To implement where feasible– Coordinated with customer equipage plans

9

Page 10: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

Implementation StrategyShort Term (2010-15)

• Continue with the Windsor/Toronto/Montreal Airspace Review• Implement RNP 10 in Edmonton FIR• Convert remaining CMNPS and RNPC airspace to PBN• Develop prioritized list of airports for PBN and commence terminal

redesigns based on PBN concepts• Address AIS targets of opportunity

• Cyclic reviews

• Continue to implement 3rd party RNP designs

• Develop internal capability for RNP design

• Decommission non-essential ground based nav aids• Educating NAV CANADA and the aviation community on PBN

• Explore viability of a Canadian or US test site for GBAS evaluation

12

Page 11: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

Implementation StrategyMedium Term (2015-20)

• Continue Terminal airspace reviews in accordance with a prioritized list

• Re-assess and re-define the low level airspace structure in concert with the surveillance strategy, to incorporate PBN concepts

• Continue to expand the implementation of GNSS procedures as customer equipage expands

12

Page 12: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

Implementation StrategyLong Term (2020 and beyond)

• Transition to a full PBN capability• 4D RNP operations and a gate to gate flight management environment

• Ground based navigation aid infrastructure is reduced to the lowest possible

• Back up capability based on risk assessment/vulnerability study

• Regulatory change is required

12

Page 13: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

1313

Page 14: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

What is PBN?

• Transition from ground based sensor navigation to area navigation (RNAV)

• Framework for defining navigation performance requirements/ specifications in terms of:

– Accuracy, Integrity, Availability, Continuity, Functionality

• A toolbox of navigation specifications that can be applied to a specific type of airspace to improve and standardize operations

• Includes both RNAV and RNP as types of specifications

14

Page 15: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

RNAV and RNP

• Area Navigation or RNAV– Enables aircraft to navigate point to point by using

onboard navigation equipment and updates from ground based ( DME) , aircraft based (inertial units) or space based ( GNSS satellite) navigation systems.

• Required Navigation Performance or RNP– Same as RNAV except RNP aircraft have onboard

performance monitoring and alerting capability

15

Page 16: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

16

Performance Based Navigation

RNAV SIDs

RNAV Routes

RNAV STARs

RNP Restricted approachesRNAV approaches

Reduced reliance on ground based navigation aidsReduced reliance on ground based navigation aids

Page 17: Performance Based Navigation (PBN) Canadian Implementation Presentation to Air Transport Association of Canada 9 November 2010.

Customer Perspective

• Departure Phase– Standard Instrument Departures for every departure runway that

quickly allows aircraft to join their route to destination

• En-route Phase– Routes that are flexible based on that day’s operating conditions and

upper winds. – If flexible routes are not possible then a network of RNAV and RNP

direct routes is preferred

• Arrival Phase– Standard Arrivals that provide least track miles to the initial approach

fix, preferably with a CDA profile from top of descent

• Approach Phase– A runway aligned with lateral and vertical guidance for every runway

end that terrain allows

17- Reference IATA