Perdue Farms: A Case Study in Upgrading
Jack KutchenInformation Technology Supply Chain ManagerPurdue Farms Inc.
© SAP AG 2004, Navigating Successful Upgrades / 2
Topics
Definition & Scope
Project organization
Training
Testing
Readiness Assessment
Timeline
Cutover
Results
© SAP AG 2004, Navigating Successful Upgrades / 3
Project Definition & Scope
To upgrade the SAP Enterprise System from the current 4.0B release to 4.6C (The latest version of IS-OIL). The upgrade is required to maintain ongoing support and provide a platform for future initiatives such as Procurement, Financials and Plant Maintenance.
The project is a Technical upgrade only. Current functionality will remain and no new functionality will be added.
Only SAP is being upgraded, other systems such as CFS will remain intact with no change.
© SAP AG 2004, Navigating Successful Upgrades / 4
Project Organization
Project Manager
Jack Kutchen
Linda Benson• Gus Lebois• Dan DiGrazio• Tom Mann• Larry Brown•Dean Lisenby•Kevin Cherry
Executive SponsorEileen BurzaBusiness SponsorSteve EvansBusiness LeadGus Lebois / Dan DiGrazioIT ManagerLinda BensonProject ManagerJack Kutchen
Steering CommitteeEileen Burza Larry WinslowDon Taylor
Steve EvansRex Thompson Kerry Doughty
George Rawlston
Lou Rascona• Mike Hyland• Steve Thomas•Jack Tatem•June Weeks•Mike Lindsey
Pete Skilton
Operating Committee
Functional Lead
Edna Hearn
Development Lead
George Crowdes
InfrastructureLead
Kevin Cherry
Testing Lead
Kelly TimmonsGretchen Kessner
Training Lead
Barbara KuczmaGretchen Kessner
Business Leads: John Savage, Jeff Titus, Jim Kaylor, Marilou Gordy
© SAP AG 2004, Navigating Successful Upgrades / 5
Project Organization
Development LeadGeorge Crowdes
Functional Lead
Edna Hearn
InfrastructureLead
Kevin Cherry
TestingLead
Kelly TimmonsGretchen Kessner
TrainingLead
Barbara KuczmaGretchen Kessner
DevelopmentDave SchreyKristie DunnSean HowardBob Duryea
EDIChristine Jones
Dane Miller
InterfacesMichelle Faulkner
Allison Foltz
MFG SystemsDavid WynneMike LindseyTorry Brown
FunctionalKelly TimmonsJennifer Morton
Al Strickroth
SecurityHillary WrightGretchen Foley
Bob Miller
TechRuss Brooks
Doug CrossanTim Moore
Lynda Schepler
GUIRandy Todd
TelecomEd Lubniewski
SchedulingDenise GlandJim Beattie
Business Team
Jim KaylorJohn Savage
Marilou GordyJeff Titus
Michelle PaschalJoyce Jordon
Laura ColonnaTerri RuarkTerry Feret
Jean CrowderSue Olischar
Christina HurleyBernadette Kniedler
Jimmy CraftGary Foxwell
Stephanie MartinKaren Merideth
Greg GriesHal Runner
Bruce MeilhammerKay Bruch
Theresa WrightDan Maupin
Gerry FarrellyVicki MartinaRob Nichols
PlantTeam
Bennie GrayGary FoxwellKevin GreeneJoel KnouseRon BolingDave HigbyAlishia King
John SimmonsRon CosmeVera ShaverTorry Brown
Larry TippmanJeff StallsJoe Smith
Debbie TowersSteve Maas
Steve PasswaterDionne Church
Bill BowersKevin Hill
PlantTeam
Anita DavisTeresa SibertEvers TurnerRon Barton
Barry PendleyJerry Moore
David HutchinsonRenetta Coleman
Ricky WatsonTom ReddenAlvin Bracey
Regina HardisonGloria Gatling
Tashia HallLynn ColeJason Neal
Dean EnglishJack TraderCliff GrimesLisa Hauser
© SAP AG 2004, Navigating Successful Upgrades / 6
Training
50 plant trainers identified, trained and provided training materials.
Plant trainers trained all SAP plant associates.
Corporate trainers trained all SAP corporate associates.
Project team members personally certified all key positions such as order taking, inventory and shipping (320).
© SAP AG 2004, Navigating Successful Upgrades / 7
Testing
Business developed 600 unit tests scripts (etc. take an order)
Business develop 200 cycle tests scripts (etc. take an order, tie into load, drop to plant, PGI & ship, and bill the customer, & apply credit memo)
I/T initially ran unit tests & cycle tests
Business ran unit tests & cycle tests
I/T ran exception tests, cutover tests etc.
I/T practiced technical upgrade 12 times.
Critical functions heavily tested.
Objective: Non Event to the customer!!!!!!!!!!!!
© SAP AG 2004, Navigating Successful Upgrades / 8
Readiness Assessment
Checklist of remaining activities regarding testing, training, preparation and overall readiness.
Color coded to allow quick review of status.
Distributed to steering committee, Operating Committee, complex managers, plant managers and plant leads over the past 6 weeks.
Team makes recommendation to Operating Committee.
Operating Committee makes recommendation to Steering Committee.
© SAP AG 2004, Navigating Successful Upgrades / 9
TimelineJan Feb Mar April May June July Aug. Sept NovOct Dec
Prelim Assessment Definition Development User Test
AccomplishmentsSandbox Upgrade 1AnalysisProcesses
Go Live
Sandbox Dev QA ProdLandscape Sandbox 2
AccomplishmentsSandbox Upgrade 2AnalysisTest ResourcesTest RequirementsTest Cases - UnitTest GUIDiscoveryGUI Rollout PlanningPre - Training PlanningDev UpgradeCER Approved
Planned•Support
PlannedProduction Upgrade
Production FreezeAccomplishments
Apply ChangesTraining Validation Write Test Cases / CycleGUI RolloutI/T Unit TestsUpgrade PracticeCutover PlanningTraining PlanningQA UpgradePrep Readiness Assess Training Server
In ProgressReadiness AssessmentI/T – Exception TestsEPSS DocumentationUpgrade Practice
AccomplishmentsBusiness – Unit TestsTrain the TrainerI/T Cycle TestsUpgrade practice (3)New Upgrade ServerInterface TestsCutover Plan – RefineStress TestOnsite CertificationCutover AssessmentGo-live AssessmentNew Production ServerTrainingBusiness – Cycle Tests
© SAP AG 2004, Navigating Successful Upgrades / 10
Timeline
Preliminary Assessment Phase
Sandbox Upgrade 1
Plan
Jan Feb Mar
© SAP AG 2004, Navigating Successful Upgrades / 11
Timeline
Definition Phase
Sandbox Upgrade 2
Test Resources
Test Requirements
Test Cases – Unit
Test GUI
Discovery
Mar Apr May Jun
© SAP AG 2004, Navigating Successful Upgrades / 12
Timeline
Definition Phase
GUI Rollout Planning
Pre – Training Planning
Dev Upgrade
CER Approved
Mar Apr May Jun
© SAP AG 2004, Navigating Successful Upgrades / 13
Timeline
Development Phase
Apply Changes
Training Validation
Write Test Cases / Cycle
GUI Rollout
I/T Unit Tests
Upgrade Practice
Cutover Planning
Jul Aug Sep
© SAP AG 2004, Navigating Successful Upgrades / 14
Timeline
Development Phase
Training Planning
QA Upgrade
Prepare Readiness Assessment
Training Server
Jul Aug Sep
© SAP AG 2004, Navigating Successful Upgrades / 15
Timeline
User Test Phase
Business – Unit Tests
Train the Trainer
I/T Cycle Tests
Upgrade practice (3)
New Upgrade Server
Interface Tests
Cutover Plan - Refine
Sep Oct Nov
© SAP AG 2004, Navigating Successful Upgrades / 16
Timeline
User Test Phase
Business Cycle Tests
Training
Onsite Certification
Cutover Assessment
Go-live Assessment
New Production Server
Stress Test
Sep Oct Nov
© SAP AG 2004, Navigating Successful Upgrades / 17
Timeline
User Test Phase
Readiness Assessment
I/T Exception Tests
EPSS Documentation
Upgrade Practice
Sep Oct Nov
© SAP AG 2004, Navigating Successful Upgrades / 18
Cutover
SAP Blackout for 40 hours to allow conversion to new version.
Cutover begins on Saturday at 6am and is returned to the business on Sunday at 10pm.
Shipping activities at plants during blackout period will be using CFS generated manifests. (Est. 50 – 75 shipments)
Business will conduct dry run as last step in cutover to verify system is functioning
© SAP AG 2004, Navigating Successful Upgrades / 19
Consulting Strategy
SAP Project Management consultant onsite for 1 week of project planning. Provided ongoing QA 1-2 days per month.
SAP Technical support brought in as needed. Many issues resolved offsite and onsite averaged 1-2 days per month. (Jason Fox)
SAP expertise onsite for Cutover and Go live. Released early in week.
© SAP AG 2004, Navigating Successful Upgrades / 20
Results
Implementation was a Non-Event to the business. Orders, inventory, shipping activities occurred as planned.
Minor issues were quickly resolved.
Project ahead of schedule and under budget.
Maintained a 4.0 environment to troubleshoot issues called in.
Lunch recognition given to team 2 weeks later.
Team members given Chainman’s Excellence Award for outstanding effort.
© SAP AG 2004, Navigating Successful Upgrades / 21
Critical Success Factors
1. Build a plan, work the plan.
2. Sponsorship at the highest levels.
3. Gain business commitment early (resources).
4. Production Freeze
5. Use the “Best” technical consultants (SAP).
6. Certify training using team members.
7. Business developed test cases & testing.
8. Readiness Assessment to monitor “Health”
9. Practice, practice, practice the upgrade
10. Test, test and test