PENNDOT PROJECT INFORMATION · PENNDOT PROJECT INFORMATION ... pipe culvert with a reinforced...

9
PENNDOT PROJECT INFORMATION Chapel Drive Culvert Replacement SR 1005, Section B03 North Sewickley Township, Beaver County

Transcript of PENNDOT PROJECT INFORMATION · PENNDOT PROJECT INFORMATION ... pipe culvert with a reinforced...

Page 1: PENNDOT PROJECT INFORMATION · PENNDOT PROJECT INFORMATION ... pipe culvert with a reinforced concrete box culvert. ... Construction anticipated in summer of 2018 Example of a concrete

PENNDOT PROJECT INFORMATION

Chapel Drive

Culvert ReplacementSR 1005, Section B03

North Sewickley Township, Beaver County

Page 2: PENNDOT PROJECT INFORMATION · PENNDOT PROJECT INFORMATION ... pipe culvert with a reinforced concrete box culvert. ... Construction anticipated in summer of 2018 Example of a concrete

PROJECT TEAM

Design Division

Direct questions to:

Cassie Lloyd, P.E. - Project Manager at 412.429.2815 or [email protected]

Mark Young- District Environmental Manager

Tyler Mercer, P.E. - Assistant District Environmental Manager

Press Office

Steve Cowan-District Press Officer

Please complete survey at end of presentation

Page 3: PENNDOT PROJECT INFORMATION · PENNDOT PROJECT INFORMATION ... pipe culvert with a reinforced concrete box culvert. ... Construction anticipated in summer of 2018 Example of a concrete

PURPOSE OF PRESENTATION & PROJECT INTRODUCTION

SR 1005, Section B03 (Chapel Drive) Project

The purpose of this PowerPoint presentation is to introduce the project to the public, gather feedback, and present the detour information.

The purpose of the project is to maintain a safe and reliable crossing of Chapel Drive over a branch of Connoquenessing Creek in North Sewickley Township, Beaver County.

Full replacement of the existing corrugated metal pipe culvert with a reinforced concrete box culvert.

Page 5: PENNDOT PROJECT INFORMATION · PENNDOT PROJECT INFORMATION ... pipe culvert with a reinforced concrete box culvert. ... Construction anticipated in summer of 2018 Example of a concrete

PROPOSED PROJECT IMPROVEMENTS

Culvert replacement

Current culvert is a metal pipe culvert constructed in 1950

Replacement will be a reinforced concrete box culvert

Project will be built under a full detour

Detour will be in place approximately 6 weeks

Guiderail will be updated across the structure and on both approach roadways

Minor Right-of-Way involvement, including mostly Temporary Construction Easements

Construction anticipated in summer of 2018 Example of a concrete box culvert

Page 6: PENNDOT PROJECT INFORMATION · PENNDOT PROJECT INFORMATION ... pipe culvert with a reinforced concrete box culvert. ... Construction anticipated in summer of 2018 Example of a concrete

NATIONAL ENVIRONMENTAL POLICY ACT (NEPA)Public outreach begins with the NEPA (National Environmental Policy Act) process.

NEPA requires agencies to integrate environmental values into their decision-making processes by considering the environmental impacts of their proposed actions and reasonable alternatives to those actions.

As a part of NEPA, the Section 106 Process seeks to accommodate historic preservation concerns by identifying historic properties potentially affected by the project, assess the effects and seek ways to avoid, minimize, or mitigate any adverse effects on historic properties.

NEPA also includes public involvement activities and gathering feedback from the public

Image courtesy of MDOT