Penang Safety 1409

download Penang Safety 1409

of 36

Transcript of Penang Safety 1409

  • 8/13/2019 Penang Safety 1409

    1/36

  • 8/13/2019 Penang Safety 1409

    2/36

    NOTICE

    This Guideline has been prepared for the proper planning andcontrol of hillsite development activities in Penang. It is to be

    used by implementing agencies, developers, engineers,contractors, property owners and the public as a guide in

    planning, developing and maintaining hillsitesand the surrounding areas.

    This Guideline is applied by MPPP and MPSP in consideringand evaluating for approval applications for planning permit

    submitted via the state One-Stop Centre (OSC).

    The States planning policy at the material timeshall take precedence.

  • 8/13/2019 Penang Safety 1409

    3/36

    Penang Island has an area of 285 sq km and

    of which about 40% are lands of Class 3 andClass 4 with slope gradient exceeding 25.A significant portion of them is privatelyowned land and the rest belongs to the stategovernment.

    This Guideline aims to improve safety andthe environment of hillsite developments. TheState Government has appointed the HillsiteDevelopment Advisory Panel Committee,which developed the Guideline after reviewing

    existing guidelines, lessons learnt from slopefailures and landslides as well as studyinggood practices.

    The Guideline will serve as the main referencein considerations of planning approval forhillsite development applications, and to beused by all the relevant agencies.

    Penang Local Governments (MPPP & MPSP)

    are to strengthen their Geotechnical Unit,which processes and approves applicationsfor hillsite developments, followed by strictenforcement.

    A monitoring team will be established toensure compliance in construction andmonitoring performance of slopes. The unitwill initially recruit contract staff with slopeengineering expertise, and eventually has itsown permanent experienced engineering

    staff.

    YAB Tuan Lim Guan Eng

    An advisory panel of experts will be appointed

    to help the Geotechnical Unit. The Panel shallmeet regularly to provide input and trainingto the staff of the unit and that of allstakeholders.

    Due care and diligence of all the staff of thestakeholders are needed to use and implementthe Guideline to mitigate landslides andprevent loss of lives from landslides whilefacilitating sustainable land use for the well-being of Penangites.

    Penalty for non-compliance will be betterstated for ease of enforcement.

    Let us all work together towards a safe andgreen Penang.

    YAB Tuan Lim Guan EngChief Minister of Penang

  • 8/13/2019 Penang Safety 1409

    4/36

    0 - 15 = 52%

    Legend

    > 15 - 25 = 9%

    > 25 - 35 = 19%

    > 35 = 20%

  • 8/13/2019 Penang Safety 1409

    5/36

  • 8/13/2019 Penang Safety 1409

    6/36

    Tuan Haji Zainuddin Ahamad

    Hillsite development has been tightened with guidelinesfrom federal government agencies following the collapseof Block 1 of the Highland Towers in 1993, with the intention

    of improving safety for developments.

    This new set of guidelines for hillsite development has beenspecifically formulated for Penang, and to be used by allstake holders. The Advisory Panel, who developed theguideline, comprised slope engineering experts from Malaysiaand local practising engineers from Penang.

    Top state and federal government officers having experiencedealing with approvals and control of hillsite developmentsalso assisted the Panel.

    The Guideline has gone through rigorous review processesincluding a public forum involving all stakeholders, both inthe public and private sectors.

    Thus, this Guideline for Hillsite Development can now provideclear and consistent application procedures together withtransparent approving mechanisms and controls duringconstruction.

    The plinth areas for Class 3 and Class 4 lands have alsobeen reduced by more than 5% for Class 3 and about 20%for Class 4. This is to enhance the safety of slopes andpreserve more green areas.

    Tuan Haji Zainuddin Ahamad

    DirectorPenang Town & Country Planning Department

  • 8/13/2019 Penang Safety 1409

    7/36

    Table 1 : Slope classification for design purposes 11Table 2 : Submission requirements 12Table 3 : Qualifications of Engineers 13Table 4 : Appointment of Geotechnical Engineer and

    Independent Checker 14Table 5 : Construction supervision requirements 14Table 6 : Colour Code for Terrain Mapping 16Table 7 : Criteria for Selecting a Competent Engineer 19

    List of Tables 5List of Figures 5

    List Appendices 5Abbreviations 6Objectives 7Towards A Safe & Green Penang 8Major Considerations 9Classification of Slopes 11Submission Requirements 15Appointment of Competent Engineers 18Maintenance Inspection 20The Way Forward 22Appendices 23Acknowledgement 32

    Fig. 1 : Terrain Map of Penang Island 2Fig. 2 : Terrain Map of Seberang Perai 3FIg. 3 : Buffer Zone 10

    Fig. 4 : Development on Slope 10Fig. 5 : Hillsite Development Plan Submission Flow Chart 16Fig. 6 : Typical Inspection Procedure 21

    Appendix 1. Proposed Format for Geotechnical Report 24Appendix 2. Independent Checker Report format 28Appendix 3. Criteria for a relevant experienced engineer 29

    Appendix 4. Checklist for Maintenance Manual 31

  • 8/13/2019 Penang Safety 1409

    8/36

    For easier understanding, the following are acronyms used in the Guideline:

    BEM Board of Engineers, Malaysia

    CKC Cawangan Kejuruteraan Cerun (Hillsite Engineering Division)

    GE Geotechnical Engineer

    JAS Jabatan Alam Sekitar (Department of Environment)

    JKR Jabatan Kerja Raya (Public Works Department)

    JMG Jabatan Mineral dan Geosains (Minerals and Geoscience Department)

    JPBD Jabatan Perancang Bandar dan Desa (Town and Country Planning Department)

    JPS Jabatan Pengairan dan Saliran (Department of Irrigation and Drainage)

    MASMA Manual Saliran Mesra Alam (Environmental Friendly Urban Drainage Manual)

    MPPP Majlis Perbandaran Pulau Pinang (Penang Island Municipal Council)

    MPSP Majlis Perbandaran Seberang Perai (Seberang Perai Municipal Council)

    OSC One Stop Centre

    PBT Pihak Berkuasa Tempatan (Local Authority)

    PSP Principal Submitting Person (Planner, Architect or Engineer)

    SP Submitting Person

    (Engineer Civil & Structural and/or Mechanical & Electrical)

    UBBL Uniform Building By-laws

  • 8/13/2019 Penang Safety 1409

    9/36

    The Penang Safety Guideline For Hillsite Development 2012is to streamline both

    the existing federal and state guidelines for all hillsite developments with the aim to

    improve slope safety and enhance the environment.

    This Guideline will no doubt mitigate the risk of landslides when used and implemented

    diligently by all the stakeholders.

    The Hillsite Development Advisory Panel Committee, appointed by the Penang Government,

    has reviewed the existing guidelines and lessons learnt from slope failures and landslides

    as well as current good and safe practices.

    The Guideline, among others:

    Has made clearer classification of slopes for ease of implementation at planning stage.

    Has stated the duties and responsibilities of Engineers and Independent Checkers

    during design and construction stages.

    Requires Independent Checkers to visit project sites during constructions and report

    any non-compliance directly to the local authority for prompt enforcement.

    Has defined better the qualification and experience of key personnel (geotechnicalengineer and independent checkers) to ensure quality of works for hillsite developments

    during the design and construction stages.

    Has made it mandatory for developers to engage qualified engineers and independent

    checkers - having the required expertise and experience on hillsite developments and

    sufficient capacity to design and supervise the constructions.

    Requires contractors to comply with the design drawings and specifications for the

    slope works.

    Has reduced the requirement for plinth area (maximum allowable hard surface footprint)

    for buildings on Class 3 and Class 4 hillside lands, with the intention of preserving

    more natural green areas.

    Requires engineered slopes including earth retaining systems to incorporate green

    features to enhance Penangs natural environment.

  • 8/13/2019 Penang Safety 1409

    10/36

    The Guideline addresses and upgrades existing safety measures and outlines better projectimplementation procedures and effective enforcement. It strives to inculcate good slopedesign, construction and maintenance culture. With its proper implementation, theGuideline will inspire confidence in the safety of hillsite developments in Penang.

    The advisory panel which drew up the Guideline will continue to assist the authorities

    to effectively implement and enforce it. This is to ensure that developers, engineers,contractors and property owners in hillsite areas comply with good engineering practicesrelating to the stability of hill slopes.

    Still lingering in the Malaysian publics consciousness are the many hill land failures whichcaused tragedies over the past 20 years.

    The major causes of slope failures can be summarized as follows:

    1. Design inadequate ground investigation, lack of understanding of engineeringanalysis and design.

    2. Construction lack of quality assurance and quality control by contractors and lackof proper site supervision by engineers.

    3. Maintenance lack of slope maintenance culture is prevalent in both the public andprivate sectors.

    4. Communication lack of communication amongst various parties involved inconstruction.

    The resulting loss of lives, destruction to public and private properties as well as theensuing legal tangles that may be still ongoing have triggered various reactions; therehad been conferences, seminars, dialogues, more stringent rules and regulations andbetter practices for hillsite development.

    The Guideline makes a concerted attempt to incorporate all the lessons learnt.

  • 8/13/2019 Penang Safety 1409

    11/36

    Numerous guidelines for hillsite developments from various agencies have been produced

    after the collapse of Block 1 of Highland Towers in 1993. This Guideline aims to simplify

    existing procedures and to improve the safety of hillsite developments.

    To further improve the safety of slopes and earth retaining systems, this Guideline has

    some major considerations that include:

    1. Slope classification for planning approval has been simplified for clarity and consistency.

    2. Design requirements of slope have been strengthened through clearer definitions.

    3. The required qualifications of engineers including geotechnical engineers needed fordifferent terrain classification of slopes are established.

    4. The requirement and need for independent checkers is now better defined and the

    input is extended beyond design to include inspection during construction.

    5. Maintenance of slope needs proper input by the Engineers which includes the need

    to produce maintenance manuals so that owners know their responsibilities and what

    entails in the maintenance of slopes.

    6. The maximum allowable hard surface footprint has been intentionally reduced by

    more than 5% for Class 3A & 3B and about 20% for Class 4A & 4B slopes. This will

    improve safety and enhance the preservation of the green environment.

  • 8/13/2019 Penang Safety 1409

    12/36

  • 8/13/2019 Penang Safety 1409

    13/36

    52%

    9%Class 1

    Class 2

    Class 3 (A & B)

    Class 4 (A & B)

    19%

    20%

    Slopes are classified according to slope gradient and type.

    The slope gradient, in degrees, is measured from the horizontal plane. Sufficient surveypoints shall be obtained to produce accurate contour lines at 5m intervals. More surveypoints shall be obtained at localized areas such as existing slip, man-made slopes/structures,etc. The extent of survey shall include an area beyond the land boundary not less than20 metres.

    The type of slopes is divided into natural or man-made slope. Man-made slope is furtherdivided into cut or fill slope. Higher risk is associated with fill slope.

    Table 1 shows the Slope Classification for Design Purposes. The table also shows theassociated risk and the maximum allowable hard surface footprint. The maximum allowablehard surface footprints for Class 3A, 3B, 4A and 4B are reduced in this guideline as

    compared to the previous guidelines. This is to preserve the green area and to allow easymaintenance and strengthening of slopes.

    The maximum allowable hard surface in Table 1 below is applicable to all allowabledevelopments. Nonetheless, the states planning policy at the material time shall takeprecedence.

    35%

    35%

    30%

    30%

    ASSOCIATED RISK

    CLASS SLOPEGRADIENTNATURAL

    SLOPE

    MAN-MADE SLOPE1

    CUT FILL

    Notes:1 For man-made slope within a proposed development area, which is formed previously prior to the current application for development.2 Hard Surface is an impervious surface as defined in MASMA.

    MAXIMUMALLOWABLE

    HARDSURFACE2

    FOOTPRINT

    1

    2

    3A

    3B

    4A

    4B

    0 - 15

    > 15 - 25

    > 25 - 35

    > 25 - 35

    > 35

    > 35

    Low

    Low

    Medium

    Not Applicable

    High

    Not Applicable

    Low

    Low

    Medium

    Not Applicable

    High

    Not Applicable

    Low

    Low

    Not Applicable

    High

    Not Applicable

    Very High

    Refer to

    current policy

    Table 1: Slope Classification for Design Purposes

    Penang Islands Hill Land Distribution

  • 8/13/2019 Penang Safety 1409

    14/36

    Table 2 shows the submission requirements for all the classes of slopes by submission

    engineers. The qualifications of the submission engineers are stated in Table 3. Table 4

    states the responsible party for the appointment of Geotechnical Design Engineer and

    Independent Checkers.

    Please take note of the following:

    i) The Civil Engineer and Geotechnical Engineer for a particular project can be the same

    or different engineer.

    ii) The Geotechnical Engineer and Independent Checker for a particular project must be

    different engineers. They must also not be from the same firm.

    Table 2: Submission Requirements

    SUBMISSION REQUIREMENTSCLASS

    1 (Low Risk)

    2 (Low Risk)

    3A (Medium Risk),

    3B, 4A (High Risk)

    4B (Very High Risk)

    Slope Stabilization Analysis by Civil Engineer

    Geotechnical Report by Geotechnical Engineer

    Geotechnical Report by Geotechnical Engineer

    and

    Geotechnical Review Report by Independent Checker

  • 8/13/2019 Penang Safety 1409

    15/36

    Table 3: Qualifications of Engineers3

    SUBMISSION

    ENGINEER

    QUALIFICATIONS

    Civil Engineer

    Geotechnical

    Engineer3

    Independent

    Checker3

    1. Meets relevant Local Authoritys requirements.

    2. Registered Professional Engineers with Board of Engineers, Malaysia (BEM).

    1. Meets relevant Local Authoritys requirements.

    2. Registered Professional Engineers with BEM with minimum three years practical

    geotechnical experience and one year gained in Malaysia.

    1. Meets relevant Local Authoritys requirements.

    2. Registered Professional Engineers with BEM with:

    At least 10 years relevant practical experience in the design or construction of

    buildings and, during the period 7 years immediately preceding the current

    appointment, has been engaged in geotechnical design after registration as a

    professional engineer with at least one year of such practical experience gained

    in Malaysia.

    At least 3 years relevant practical experience in slope engineering with at least

    one year of such practical experience gained in Malaysia.

    OR

    Registered Accredited Checkers (Geotechnical) with BEM

    Note:3 Qualifications of Geotechnical Engineer and Independent Checker shall be clearly specified to ensure only competent geotechnical

    engineers with relevant experience undertakes the design and checking works.

    Classification of Slopes

  • 8/13/2019 Penang Safety 1409

    16/36

    Table 4: Appointment of Geotechnical Engineer and Independent Checker

    APPOINTMENTCLASS

    1 (Low Risk)

    2 (Low Risk)

    3A (Medium Risk),

    3B, 4A (High Risk)

    4B (Very High Risk)

    Geotechnical Engineer is not required.

    Appointment of Geotechnical Engineer by Developer.

    Appointment of Geotechnical Engineer and Independent Checker by Developer.

    Appointment of Geotechnical Engineer and Independent Checker by Developer and

    concurred by Local Authority.

    During construction, proper and adequate supervision are important. Table 5 states theconstruction supervision requirement.

    Table 5: Construction supervision requirements

    SUPERVISION REQUIREMENTSCLASS

    1 & 2 (Low Risk)

    3A (Medium Risk),

    3B, 4A (High Risk)

    4B (Very High Risk)

    No changes to existing requirements as stipulated in UBBL Sections 5 and 7.

    Additional audit via site visits shall be carried out by Independent Checker.

    Minimum frequency of site visits shall be once a month.

    Additional audit via site visits shall be carried out by Independent Checker.

    Minimum frequency of site visits shall be once every fortnightly.

    Instrumentation monitoring shall be carried out to monitor conditions of slopes.

  • 8/13/2019 Penang Safety 1409

    17/36

    Pre-Submission Consultation

    Submitting Person (SP) be it the Planner, Architect, Engineer, Geotechnical Engineer

    or Surveyor shall engage in pre-submission consultation with the relevant departmentsprior to submission of Layout Plan and Geotechnical Report for all hillsite developmentprojects.

    The submitting person shall compile or make available some basic documents and/orinformation for discussion during the pre-submission consultation with the relevantauthorities. For example land classification, land suitability, preliminary proposed Layout

    Plan, Land Survey Plan and Terrain Mapping.

    Preparation of final Layout Plan & Geotechnical Report

    The SP shall ensure that there will be no more changes made to the Layout Plan and shallorder the Final Geotechnical Report to be prepared for concurrent submission to OSC.

    Changes made during the delivery process may result in re-submission of Layout Plan andGeotechnical Report for approval.

    The table below shows the colours to use in preparing terrain map.

    Table 6:Colour Code for Terrain Mapping

    ColourRed

    Decimal RGB CodesSlope

    Classification

    EquivalentAutoCAD

    Colour Index #Green Blue

    71

    51

    41

    11

    20

    1Notes:Decimal RGB codes for the 256 Colors in equivqalent with AutoCAD Color Index (numbers 0-255).Equivalent AutoCAD colour Index is provided for comparison and reference purposes only.

    212

    255

    255

    255

    255

    255

    255

    255

    234

    170

    63

    0

    170

    170

    170

    170

    0

    0

    Class 1

    Class 2

    Class 3A

    Class 3B

    Class 4A

    Class 4B

    Light Green

    Beige

    Brown

    Orange

    Light Red

    Red

  • 8/13/2019 Penang Safety 1409

    18/36

    Fig. 5: Hillsite Development Plan Submission Flow Chart:(Concurrent Submission of Planning Permission (Layout Plan) and Geotechnical Report)

    Applicant (PSP/SP/GE)

    Pre-submission Consultation

    OSC

    OSC

    Technical Departments

    Check and Commenton Submitted Plan

    JKR P. Pinang

    Risky Land DevelopmentCommittee SecretariatDistribution of reports to

    Technical Departments

    Applicant (PSP/SP)

    Compliance of Requirements

    including requirements from GE

    PBT (Planning Dept.)Confirmation of Plan

    Recommendation of Plansfor approval

    OSC

    Issuance of Final Approval

    Technical Departments

    Check/Comment on Submitted Plan

    [Chairman, MPPP, MPSP, JMG, JAS,JPS, JPBD, CKC/JKR]

    21 days

    2 days

    2 days

    40 days

    1 day

    14 days

    37 days

    14 days

    Total Time = 108 days

    Compilation and forwarding

    of comments/requirements from

    technical departments

    to Applicant

    Applicant (PSP/SP/GE)

    Compliance of Requirements

    Presentation to Risky LandDevelopment Committee

    40 days

    JKR P. PinangRisky Land DevelopmentCommittee Secretariat

    Approval of Geotechnical Report

    7 days

    Total Time = 70 days

    Geotechnical Report LayoutPlan

    Synchronization of Layout Plan

    to Geotechnical requirements

    Synchronization of Layout Plan

    to Geotechnical requirements

  • 8/13/2019 Penang Safety 1409

    19/36

    Notes to the Submission Flow Chart

    1. Pre-Submission ConsultationSubmitting Person, be it Planner, Architect, Consulting Engineer, Geotechnical Engineer andSurveyor shall engage in pre-submission consultation with the relevant Departments prior tosubmission of layout plan and geotechnical report for all project located in hillsite.

    For hillsite project, submitting person shall compile or make available some basic documentsand/or information for discussion during the pre-submission consultation with the relevantauthorities. (e.g. Land Classification, Land Suitability, Preliminary Proposed Layout plan, LandSurvey plan, Terrain Mapping and etc.)

    2. Preparation of final Layout Plan and Geotechnical Report for SubmissionSubmitting person to ensure that there shall be no more changes made to the layout planand order the Final Geotechnical Report to be prepared for concurrent submission to OSC.

    Changes made during the delivery process may result in re-submission of layout plan andGeotechnical Report for approval.

    3. Submission to OSCUpon receipt of Layout Plan and 8 copies of Geotechnical Report, OSC will forward the planand Geotechnical Report to the relevant Departments.Time frame : 2 days

    4. Submission of Geotechnical Report to JKRUpon receipt of Geotechnical Report from OSC, JKR (Risky Land Development CommitteeSecretariat) will then distribute it to the relevant Departments for Comments/Clearance.Time frame : 2 days

    5. Comments and Requirements from All Technical DepartmentsComments, requirements and /or recommendations from various technical departments shallbe submitted to JKR (Risky Land Development Committee Secretariat) within 21 days andshall be forwarded immediately to the SP/Geotechnical Engineer for immediate compliance.Time frame : 21 days.

    6. Compliance of Requirements by Geotechnical EngineerUpon receipt of comments, requirements and or recommendations from various technicaldepartments, Geotechincal Engineer shall notify the Architect/Planner of any changes, whichmay affect the layout or building design. Upon compliance of all requirements imposed byauthorities, and synchronization of the drawing and design with Architect/Planner, Geotechnical

    Engineer shall re-submit report to JKR.

    Geotechnical briefing and presentation to the Risky Land Development Committee by theGeotechnical Engineer shall be accomplished within 40 days.Time frame : 40 days.

    7. Approval of Geotechnical ReportGeotechnical Report shall be approved after satisfactory deliberation in the Risky LandDevelopment Committee meeting. Copy of approval will be forwarded to OSC to synchronizewith the approval process of layout plan.Time frame : 7 days

    Note : Durations quoted are in calendar days.

  • 8/13/2019 Penang Safety 1409

    20/36

    The method of selecting engineers by ability shall be as follows:

    a) Technical Competenceb) Managerial Ability

    c) Availability of Resources

    d) Professional Independence & Integrity

    e) Fairness of Fee

    f) Quality Assurance System

    These are very important criteria to be

    considered in selecting a competent engineer(see appendix 3 for detailed explanation & examples).

    The other considerations are the engineers personal attributes such as having good

    commitment towards project, communication skills and engineering judgement, and

    these should be well augmented with his experience in the industry.

  • 8/13/2019 Penang Safety 1409

    21/36

    Table 7: Criteria for Selecting a Competent Engineer

    Technical Competence(Max. 30pts)

    - Competency, experience and qualifications of key personnel

    - Knowledge management system

    - Methodology of technical approach to be utilized

    - List of similar projects

    - Comments from previous clients

    Managerial Ability and Availability of Resources(Max. 30pts)

    - Adequate experienced staff for the project

    - Similar experience in handling the scale of project

    - Record of project achievements and success of previous projects

    - Engineers technical manual, check-lists or procedures to ensure quality output

    - Evidence of value-engineering

    Professional Independence and Integrity(Max. 5pts)

    - Reputation of the engineer

    - List of clients

    Fairness of Fee(Max. 25pts)

    - Value-for-money service in relation to the detailed scope of work

    Quality Assurance System(Max. 10pts)

    - Examine documentation of a project particularly on the:

    Check & review Traceability ex. meeting notes, etc

    - ISO9001:2000 certified is encouraged

    Total Score

    CRITERIA

    Selection Procedure

    The Selection procedure shall have thefollowing key components:

    1) Terms of reference2) Pre-qualification3) Short-listing4) Request for technical and fees proposals5) Assessment of proposals

    SCORE

  • 8/13/2019 Penang Safety 1409

    22/36

    The maintenance of slopes and earth retaining walls should generally follow the guidelines

    given in the Public Works Departments publication Guidelines on Slope Maintenance

    in Malaysia, JKR 21503-0001-06, Slope Engineering Branch, Public Works Department

    Malaysia, August 2006.

    Those responsible for the slope design shall prepare recommendations for regular

    inspections and maintenance that are essential to be followed. Regular inspections and

    maintenance are essential for the continued stability of well-designed and well-constructed

    slopes.

    Routine maintenance inspection, engineer inspection for maintenance, regular checks

    of buried water carrying services and regular monitoring of special measures are fourmajor categories of maintenance inspection.

  • 8/13/2019 Penang Safety 1409

    23/36

    Fig. 6: Typical Inspection Procedure

    The typical inspection procedure is set out as above.

    Maintenance manual

    A maintenance manual shall be prepared by the Engineer, and the maintenance programme

    includes monitoring of the installed instruments if they are specifically needed in the

    design.

    The proposed actions shall clearly be specified at various threshold readings or profiles

    of the monitoring results.

    All stake holders are to accord maintenance effort to slopes and retaining structures with

    respect to their consequences. It must be noted that safe and efficient access is important

    for maintenance works.

    Refer to Appendix 4 for a Checklist for Maintenance Manual.

    Records of blockage, cracks, slips and chainage

    Verify records by Maintenance/Inspection Team

    Carry out technical assessment on existing

    conditions and stability of slopes

    *Frequency may be reduced to once every two

    months for slopes with less than two berms height

    Carry out remedial works

    (if necessary)

    Inspection Once Every 5 Years

    by Geotechnical Engineer

    Inspection Once Every Year

    by Competent Personnel

    Monthly Inspection

    by Maintenance/Inspection Team

    Routine

    Maintenance Inspections

    If defects are found

    Verify records

    If minor

    defects

    If major slip or

    recurring cracks

    Immediate inspection by

    Competent Personnel

    Non-routine

    Immediate inspection byGeotechnical Engineer

    Carry out

    repair works

  • 8/13/2019 Penang Safety 1409

    24/36

    This Guideline needs the commitment of all the stakeholders to improve safety of hillsitedevelopment and enhance the environment. To succeed, it demands:

    (i) Developers must engage competent engineers and contractors with capability andcapacity.

    (ii) Engineers must exercise due skill and care when performing their duties in planning,analysis, design and supervision, and must complement these duties with a regimentof quality checking and review. Their service must include the preparation ofmaintenance manuals and the duty of adequate post-construction inspections.

    (iii) Contractors must have trained personnel and proper and adequate plant andequipment to meet the design and specification requirements of the Works. Theimportance of implementing temporary works for safety, site control and erosionprotection must be instilled in the workers and implemented at the construction site.

    (iv) Approving authorities must have experienced engineers in their geotechnical unitsto facilitate and enforce compliance with the Guideline.

    When hard surfaces such as earth retaining systems and reinforced slopes have to beconstructed to enhance or achieve safety, all stakeholders must be committed to thegreen initiative to incorporate planting provisions on these facilities to achieve a friendlier

    environment.

  • 8/13/2019 Penang Safety 1409

    25/36

  • 8/13/2019 Penang Safety 1409

    26/36

    PROPOSED FORMAT FOR GEOTECHNICAL REPORT

    EXECUTIVE SUMMARY

    BODY OF REPORT

    1. Project Information

    1.1 Project Title1.2 Name and contact details of developer1.3 Name and contact details of architect1.4 Name and contact details of C & S Engineer1.5 Name and contact details of submitting geotechnical engineer1.6 Curriculum vitae of submitting geotechnical engineer1.7 Approving authorities1.8 PM No.

    2. Scope of Geotechnical Report

    2.1 General scope2.2 Limitations

    3. Background of Development

    3.1 Location and land size3.2 Information on proposed development3.3 Information on surrounding developments

    4. Area Geology and Terrain Classification

    4.1 Regional geology4.2 General site geology and general structural geology highlighting the presence

    of observable discontinuities e.g. rockslopes, cliffs, etc. Need Requirements forgeologist input (if necessary).

    4.3 Terrain classification (terrain map) - terrain classification map to be plotted and

    prepared based on the approved colour codes.4.4 Terrain geological component4.5 Construction suitability map

  • 8/13/2019 Penang Safety 1409

    27/36

    5. Site Investigation

    5.1 Topographical survey5.1.1 Topographical survey plans5.1.2 Aerial photographs

    5.2 Site reconnaissance and desk study5.2.1 Site photographs5.2.2 General observations and description of the site (nature of terrain, surface

    boulders, etc)5.2.3 Observable evidence of potential slope instability, water marks or slip

    scars

    5.3 Sub-surface soil investigation

    5.3.1 Types of investigation (boreholes, mackintosh probes, etc)5.3.2 Weather conditions before and during the soil investigation5.3.3 Subsoil profiles derived from soil investigation to be plotted and

    superimposed over the cross sections. Cross-sections should beperpendicular to ground contours and cross-sections need not be in astraight line.

    5.3.4 Field testing and results5.3.5 Laboratory testing and results5.3.6 Groundwater table level measurements and records5.3.7 Selected soil parameters for design total and effective strength

    parameters

    5.4 Geophysical survey (if applicable)5.4.1 Need requirements for geophysical survey5.4.2 Type and method of geophysical survey5.4.3 Results of geophysical survey

    6. Geotechnical Design

    6.1 Geotechnical design considerations6.1.1 Geotechnical issues associated with the project

    6.1.2 Design concepts and considerations

  • 8/13/2019 Penang Safety 1409

    28/36

    6. Geotechnical Design (contd)

    6.2 Slopes

    6.2.1 Proposed cut slope6.2.2 Proposed fill slope6.2.3 Proposed rock cut slope6.2.4 Natural slope profiles6.2.5 Determination of worst probable groundwater table levels and /or

    presence of perched groundwater table conditions6.2.6 Slope stability analyses (total or effective stress conditions, types/methods

    of analysis and computer programs used)6.2.7 Stability analyzes and considerations of natural and man-made slopes

    in neighbouring developments, which may affect the stability of thecurrent project and vice versa

    6.2.8 Recommended slope stabilization/strengthening measures6.2.9 Recommended testing on the adequacy, safety and performance of

    slope stabilization works

    6.3 Earth Retaining Structures6.3.1 Types of earth retaining structures for the project6.3.2 Overturning stability, sliding stability and bearing capacity checks6.3.3 Global stability checks

    6.4 Foundation Design

    6.4.1 General considerations6.4.2 Preliminary foundation design information/calculations6.4.3 Effect of slopes on foundations and vice versa6.4.4 Recommendations

    6.5 Filled Platforms and Embankments6.5.1 Settlement analyses6.5.2 Stability analyses

    6.6 Rockfall Analysis (if applicable)6.6.1 Methods of analysis

    6.6.2 Recommended measures to prevent and/or control rockfall and/orrecommended land buffer requirements

    6.7 Earthwork Quantities6.7.1 Estimated cut quantity6.7.2 Estimated fill quantity6.7.3 Estimated rock excavation quantity

    6.8 Surface and Sub-surface Water Problems (if applicable)6.8.1 Presence and/or evidence of surface/sub-surface water conditions

    affecting the stability of slopes, retaining structures or foundations6.8.2 Recommended rectification and/or controlling measures

  • 8/13/2019 Penang Safety 1409

    29/36

    6. Geotechnical Design (contd)

    6.9 Temporary and permanent slope protection and surface drainage provisions

    6.10 Instrumentation and Monitoring6.10.1 Need requirements for instrumentation and monitoring6.10.2 Type, location and quantity of instrumentation6.10.3 Recommended instrumentation monitoring programme

    7. Earthworks Construction

    7.1 Temporary works7.2 Construction control and safety provisions7.3 Construction method statement

    7.4 Erosion and sediment control plan7.5 Controlled rock blasting requirements (if applicable)

    8. Post-construction Slope and Site Maintenance

    8.1 Maintenance of slopes and related facilities8.2 Frequency of slope maintenance inspections8.3 Responsibility for slope maintenance8.4 Slope maintenance manual

    9. Conclusions And Recommendations

    10. Engineers Declaration

    11. References

    12. Attachments

    12.1 Planning Layout (Extracted Copy)12.2 Survey Plan and Terrain Map12.3 Slope Stability Analysis Results

    12.4 Preliminary Design Calculations12.5 Erosion Sediment Control Plan12.6 Soil Investigation Reports12.7 Slope Maintenance Manual12.8 Independent Checker's Report

  • 8/13/2019 Penang Safety 1409

    30/36

    INDEPENDENT CHECKER REPORT FORMAT

    CURRICULUM VITAE OF INDEPENDENT CHECKER

    EXECUTIVE SUMMARY

    BODY OF REPORT

    1. Introduction

    2. Limitations

    3. Development description and location

    4. Area geology and terrain classification

    5. Site investigation

    5.1 Description of site5.2 Sub-surface soil investigation

    5.2.1 Subsoil profile5.2.2 Field test results5.2.3 Laboratory test results5.2.4 Underground water table

    5.3 Design soil parameters5.4 Geophysical survey

    6. Geotechnical design

    6.1 Geotechnical design consideration6.2 Slopes

    6.2.1 Proposed cut slope6.2.2 Proposed fill slope6.2.3 Proposed rock slope6.2.4 Natural slope profile6.2.5 Slope stability analysis6.2.6 Slope stabilization measures6.2.7 Type of test for slope stabilization measures

    6.3 Retaining structures

    6.4 Foundation design considerations6.5 Slope protection and surface drainage provisions6.6 Instrumentation

    7. Construction

    8. Maintenance

    9. Conclusion and Recommendations

    10. Independent Checkers declaration

    REFERENCE

    ATTACHMENT

  • 8/13/2019 Penang Safety 1409

    31/36

    CRITERIA FOR A RELEVANT EXPERIENCED ENGINEER

    1. Technical Competence

    a) Engineer should provide technical approach and methods for the project (e.g.types of foundation system, what are the pros & cons, cost effectiveness, long-term maintenance and serviceability).

    b) Obtain a list of similar projects carried out by the firm. (e.g. projects of similartechnical nature and subsoil condition, constructed and handed over)

    c) The competency, experiences and qualifications of personnel including peerrecognition. (e.g. technical papers published in seminar, conferences, etc.),

    d) Check whether Engineer carry out knowledge management including Researchand Development (R&D) to improve their services. (e.g. evidence of in-houseengineering manuals, check-lists etc.). This is to ensure Clients get value designswhich are safe, cost effective and construction friendly.

    e) Discuss with owners/clients of previous projects that involved the Engineer.

    2. Managerial abilitya) Ensure Engineer have adequate manpower resources and maintain schedules.

    (e.g. size of company and resources committed to be mobilized for the project)

    b) Ensure Engineer have similar experience in handling the scaleof project.

    c) Examine Engineers record of project achievement and success on previous projects(e.g. awards won, peer recognition, etc.). However, it is important to checkwhether the personnel involved in the previous successful projects are still withthe companyand will be involved in the project to be awarded.

    d) Examine Engineers manual, check-lists or procedures of engineering that hefollows in order to perform his services (e.g. to submit the list of design manual,check-lists etc. for review by Client).

    3. Availability of ResourcesEnsure Engineer has sufficient staff available to carry out the works & to obtain thelist of staff to be involved in the project.

    4. Professional Independence & IntegrityEnsure the Engineer is registered with BEM. Also consult industry players on thereputation of the Engineer (e.g. on his reputation, integrity, competency, etc.)

  • 8/13/2019 Penang Safety 1409

    32/36

    5. Fairness of FeeEngineers need to be adequately paid to ensure that they are able to give a highquality service with proper attention to detail, alternative designs, material and method

    of construction.

    a) Therefore, the Engineer shall be employed based on Value for Money ratherthan Lowest Price. This is because the engineers fees only contribute a verysmall percentage to the project cost. If ineffective or non-economical designs wereproduced by the engineer and used, the cost of remedial and unnecessary wastageof materials and workmanship will be SIGNIFICANTLY more than the fees paid.In addition, ineffective design may also cause DELAY in the project.

    b) Alternatively if bidding process is still necessary to ensure competitiveness isobserved, only Pre-Qualified Engineers shall be invited to participate.

    6. Quality Assurance SystemQuality of the project is often the most important measure of the services received.Without quality assurance system, the product and design may have high risk of notachieving its intended purpose.

    a) It is encouraged that the Engineering Firm is ISO9001:2000 certified (e.g. eitherby SIRIM Berhad or other accrediting bodies).

    b) The Engineer shall have proper procedures (written in black and white) andfollowed by the Engineers and staff to ensure all designs are checked. This shall

    include having the necessary forms to record checking (examineevidence ofchecking and recording). The Client shall request the Engineer to submit theirprocedures and forms for verification.

    c) The Engineer shall have proper filing and re-tractable procedures in place. (e.g.project filing and identification and traceability, which allows documents to betraced and submitted within a short period (e.g. less than 1 day).

    d) All design (calculations, specifications, drawings, etc.) shall be properly checkedand reviewedby different person of relevant experiences within the company.The process shall have proper forms for evidence and record purposes.

    e) The client has the right to engage another consulting firm with specialist to carryout independent review if needed.

  • 8/13/2019 Penang Safety 1409

    33/36

    CHECKLIST FOR MAINTENANCE MANUAL

    Man-made ItemSurface drainage channels,catchpits and sand traps

    Weepholes and drainagepipes

    Impermeable surface cover(e.g. gunite and shotcrete)

    Vegetated surface cover

    Rock slopes and boulders

    Facing

    Slope furnitureinstrumentations:inclinometers, settlementmarkers, tilt meters etc.installed on slopes andretaining structures.

    Check ForDebris, undesirable vegetation and otherobstructions.

    Cracks.

    Missing or deteriorated joint fillers and sealant.

    Obstructions (e.g. weeds and debris) inweepholes at pipe ends.

    Undesirable vegetation growth.

    Cracks or spalling.

    Erosion.

    Surface cover that has separated fromunderlying soil.

    Missing or deteriorated joint fillers and sealant.

    Dead, decaying or unstable trees.

    Erosion

    Dead vegetation surface

    Overgrown vegetation.

    Dead, decaying or unstable trees.

    Cracked or spalled concrete surface andsupport.

    Loose rock debris.

    Undesirable vegetation.

    Deteriorated mortar joints on masonry face.

    Cracked or spalled concrete surface andreplace missing or deteriorated joint fillersand sealant.

    Rust.

    Reading (within acceptable range).

    Movement on slope or retaining structure.

  • 8/13/2019 Penang Safety 1409

    34/36

    There have been many who contributed their expertise, time and effort to produce the Penang GuidelineFor Hillsite Development 2012, including:

    The Guideline Advisory Panel Committee

    ChairmanIr Dr Gue See Sew

    Deputy ChairmanIr Lim Kok Khong

    Panel MembersIr Dr Goh Teik Cheong

    Ir Dr Wong Fook KeongIr Ng Sin Chie

    Ir Ting Chek Choon

    Guideline Secretariat (Penang Island Municipal Council)

    Ir Addnan Mohd RazaliMohd Mokhtar Hj Mohd MuradMohd Shukor Rejab

    Amer HamzahMohamed Noor Mohamed Yunus

    Mohamed Zaini Ayub

    GOVERNMENT ENTITIES

    Public Works DepartmentIr Naelah Mat Kasa

    Town and Country Planning Department

    Neoh Siew YinMinerals and Geoscience Department

    Wan Salmi Wan Harun

    Department of Irrigation and DrainageMohamad Faisal Mohamed Salahudin

    Mohd Hasrulhisham Abdullah

    Penang Island Municipal CouncilChe Noraini Abdullah

    Mohd Nizam SaadS Bavani

    Siti Nor Zalina MehatAmi Azlimi AhmadFazillah Sabuddin

    Danny Koay Hock HsiangMusyarina Idrus

    Norsuriana SulimanSiti Dayana Mohd Khairi

    Seberang Perai Municipal CouncilMohd Saedon Ahmad

    Land and District OfficeIsmail Yahaya

    Reza Shamsuddin

    Perbadanan Bekalan Air Pulau Pinang

    Tan Lam Huat

    All those attending the forum for a public presentation of the Guideline

  • 8/13/2019 Penang Safety 1409

    35/36

  • 8/13/2019 Penang Safety 1409

    36/36