PECC4 POWER ENGINEERING CONSULTING...
Transcript of PECC4 POWER ENGINEERING CONSULTING...
RP82VOL. 20
X ~~~~~SOCIALIST REPUBLIC OF VIET NAM
\ \ } ~~~ELECTRICITY OF VIT NAM
PECC4 POWER ENGINEERING CONSULTING COMPANY 4
.~~~IO O12O. ~~~~~~~PROJECT: 07 -04
DOC SOI - QUANG NGAI 220kV TRANSMISSION LINE
FEASIBILITY STUDY REPORT
RESETTLIEMENT ACTION PlAsN (RAP) |
(FINAL REVISION)
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
SOCIALIST REPUBLIC OF VIET NAM
ELECTRICITY OF VIET NAM
PECC4 POWER ENGINEERING CONSULTING COMPANY 4
SO 900:2000
PROJECT: 07- 04
DOC SOI - QUANG NGAI 220kV TRANSMISSION LINE
FEASIBILITY STUDY REPORT
RESETTLEMENT ACTION PLAN (RAP)(FINAL REVISION)
Head of Department : Nguyen Kim Dong
Head of Project Design: Nguyen Thanh Hai
Khanh Hoa Province, October 2005
FOR AND ON BEHALF OF
POWER ENGINEE LTING COMPANY 4
UYEN HUU TAP
DEPUTY DIRECTOR
Resettlement Action Plan (RAP)
UNITS
Units of Length
m meter
km kilometer
Units of Area
m2 square meter
km2 square kilometer
Units of Mass
kg kilogram
Units of Energy
kWh kilowatt-hour
MWh megawatt-hour
GWh gigawatt-hour
Units of Temperature
°C : degree Celsius or Centigrade
Units of Electricity
W watt
KW kilowatt
MW megawatt
GW gigawatt
A ampere
V volt
kV kilovolt
kVA kilovolt ampere
MVA megavolt ampere
Mvar megavar (mega volt-ampere-reactive)
ohm
Units of Time
s second
min minute
h hour
FS on Doc Soi - Quang Ngai 220kV transmission line 3
Resettlement Action Plan (RAP)
d day
m month
y year
Units of currency:
VND Vietnam Dong
US$/USD US Dollar
FS on Doc Soi - Quang Ngai 220kV transmission line 4
Resettlement Action Plan (RAP)
CONTENTS
SUMMARY 8
1. Policy framework 8
2. Project impacts 9
3. Compensation policy 9
4. Public consultation 10
5. Grievance 10
6. Management organization 10
7. Implemetation schedule 10
8. Cost estimate 11
9. Information deiisemination 11
CHAPTER 1: GENERAL INTRODUCTION 12
1.1 Basis of the report 12
1.2 Objectives and proposals 12
1.3 Validity of RAP implementation 13
1.4 Description of the project 13
1.5 Project impacts on land and assets 14
1.6 Project impacts mitigating measures on land and assets 15
1.7 Total project cost 16
CHAPTER 2: IMPLEMENTATION ORGANIZATION AND LEGAL 17
FRAMEWORK FOR COMPENSATION AND RESETTLEMENT
* 2.1. Institutional arrangements 17
2.2. Organizational responsibility 17
2.3. Staffing organization and responsibilities 21
2.4 Legal framework 22
CHAPTER 3: ENTITLEMENT POLICY 25
3.1 Definition of PAP and limitation to eligibility 25
FS on Doe Soi - Quang Ngai 220kV transmission line 5
Resettlement Action Plan (RAP)
3.2 Resettlement and compensation principles 25
3.3 Eligibility to get compensation entitlements 26
3.4 Entilement policy 27
3.5 Impacted categories 30
CHAPTER 4: SOCIO-ECONOMIC SITUATION OF PROJECT AREA 32
AND THE PROJECT IMPACTS
4.1 The socio-economic condition of project area 32
4.2 Project impacts 34
CHAPTER 5: PULIC PAR TICIPA TION AND CONSULTA TION 36
5.1 Objectives of information campaign and consultation program 36
5.2 Consultation and inform to people 36
5.3 Information dissemination and PAPs'consultation 38
CHAPTER 6: COMPLAINTS AND GRIEVANCE 40
CHAPTER 7: MONITORING AND SUPERVISION 42
7.1 Internal monitoring 42
7.2 Independent monitoring 42
CHAPTER 8: IMPLEMENTATION ORGANIZATION FOR 44
COMPENSA TIONAND RESETTLEMENT PLAN
8.1 Measures for the project implementation 44
8.1.1 Announcement to PAPs 44
8.1.2 Compensation and Resettlement deadlines 44
8.2 RAP implementation process 44
8.3 RAP implementation schedule 46
CHAPTER 9: COSTS AND BUDGET 47
9.1 Budget 47
9.2 Compensation price determination 47
9.2.1 Project 47
9.2.2 Land 48
FS on Doc Soi - Quang Ngai 220kV transmission line 6
Resettlement Action Plan (RAP)
9.2.3 Trees and crops 49
9.3 Compensation cost estimate 49
9.3.1 Compensation cost 49
9.3.2 Cost for RAP establishment 51
9.3.3 Management cost 51
9.3.4 Monitoring cost 52
9.3.5 Reserved cost 52
9.4 Total cost for RAP implementation 52
CHAPTER 10: CONCLUSIONAND PROPOSALS 53
10.1 Conclusion 53
10.2 Proposals 53
APPENDICES 54
Annex 1: Entitlement matrix 55
Annex 2: Inventory of project affected households for Dung Quat 220kV 68
substation
Annex 3: Entitlements of project affected households 67
Annex 4. Socio-economic household data sheet of PAPs 74
Annex 5: Minutes of public consultation 75
FS on Doc Soi - Quang Ngai 220kV transmission line 7
Resettlement Action Plan (RAP)
SUMMARY
Implementing the Vietnamese Communist Party's policy on the national
industrialization and modernization program, EVN decided to use the loan of WB to
invest in the Project "System Efficiency Improvement - Equitization and Renewable
Energy" (3680-VN). One of its component is Doc Soi - Quang Ngai 220kV
transmission line project with total route length of 60,303m through territory of Binh
Son, Son Tinh, Nghia Hanh, Tu Nghia and Mo Duc districts of Quang Ngai province.
Doc Soi - Quang Ngai 220kV transmission line project is constructed in-line
with Doc Soi 220kV outgoing feeder at Doc Soi 220kV substation and Quang Ngai
220/lOkV substation in order to perfect the power grid, increase the transmission
capacity on the line and the reliability, safety and continuity in power supply for
Quang Ngai province and adjacent areas and furthermore, increasing the economical
nature in operation.
In addition, the construction of this project also aims to wait in front for
receiving the electricity power source from Thuong Kon Tum HPP (expected to put
into operation in 2010) for intermediate transport the electricity power of the plant into
the national power grid. This makes contribution to upgrade the electricity power
quality, creating the 220kV grid connection in provinces of Quang Nam, Binh Dinh
and Western Highlands area, increasing the stability of power system, making the
distribution and supporting of the power supply capacity in the system safer and more
flexible.
1. Policy framework
The plan on project compensation and resettlement is established based on Decree
197/2004/ND-CP dated December 3, 2004 of the Government regarding the
compensation, resettlement support when the State takes back the land; Decree
1982004/ND-CP dated November 16, 2004 of the Government regarding the method
to determine the land price and the price framework of land kinds; Decree
181/2004/ND-CP of the Government regarding the implementation of Land Law, etc...
and guideline on RAP establishment of WB (the policy framework of unvoluntary
FS on Doc Soi - Quang Ngai 220kV transmission line 8
Resettlement Action Plan (RAP)
resettlement OD 4.30). According to this policy, PAPs are people, households, entities
with or without juridical personality for their assets on project impacted land and
inventoried before the cut-off-date (May 25th, 2004) are compensated according to the
Government's regulations.
2. Project impacts
- Permanent land acquisition for construction of the tower foundation (total
permanent land acquisition area of the whole project is 29,500m2).
- Causing damage to the industrial trees, crops (paddy, peanut, manioc...) and
other assets in the tower foundation positions and within ROW
Whereas:
+ Land area of paddy and crops (peanut, manioc ...) : 165,300m2 .
+ Number of impacted eucalyptus tree : 65,020 trees
+ Number of impacted cashew tree :1,590 trees
- Temporary land acquisition when the project is constructed
Results of project data collection show that:
+ There are 100 households with 484 persons affected locate on the safe
corridor of line.
+ No household loses over 25% area of agricultural land
+ No affect to cultural relics area, preservation area, pagoda and sensitive areas
+ No ethnic minority household among impacted households.
During public consultation process, impacted households were agreed to select the
compensation procedure on land and assets in cash.
3. Compensation policy
The ending date of survey is May 25th, 2004. The price for making compensation
on land, assets and crops is based on the compensation unit price of Quang Ngai
Provincial People's Committee.
All impacted households are entitled according to the policy framework and
Vietnam Decrees. Up till now, the survey result and damage inventory shows that no
remarkable impacts to people, the community and the public assets. As a result, it is
unnecessary to have economical recovery measures.
FS on Doc Soi - Quang Ngai 220kV transmission line 9
Resettlement Action Plan (RAP)
4. Public consultation
PAPs consultation to get feedback comments will restrict the contradictions and delay
when implementing the project. The resettlement plan will be implemented following
to the reference comments from the authorities and people in order to maximize their
participation in the resettlement plan and implementation as well as socio-economical
benefits. The authorities and people are consulted in line route location, the
resettlement policy, implementation of RAP and grievance mechanism.
5. Grievance
During project implementation, grievances of impacted people will be solved based on
Vietnam law. All grievances will be solved equitably and the grievances procedures
will be guided by related authorities. The griever will pay no cost for this grievance.
CPPMB and the local authority are responsible for monitoring the RAP
implementation process. In addition, an independent consulting agency will be
assigned to supervise independently and appraise the compensation and resettlement
implementation process in accordance with the policy stated in this dossier. This
agency can be selected and awarded the contract by the PMB after the approved
resettlement plan or selected and awarded the contract by WB. The supervising
activities are implemented from the beginning of project implementation stage. This
independent supervising agency will report to PMB or WB about its results of
supervising activities.
6. Management organization
CPPMB is the project coordinating unit and cooperates with other agencies such as the
Provincial People's Committee, Power Company of Quang Ngai province and WB in
implementing detailed works of project, especially the RAP implementation plan.
7. Project implementation schedule
Technical investigation, establishing and submitting the construction drawing forapproval: :04/2005 - 10/2005
Establishing the site claerance documents and asking for compensation land:09/2005 - 12/2005
Establishing and submitting the bidding documents for approval (if any):01/2006 . 03/2006
FS on Doc Soi - Quang Ngai 220kV transmission line 10
Resettlement Action Plan (RAP)
Procurement of materials and equipment :11/2006 * 05/2007
Construction, revision, testing, hand-over : 02/2007 10/2007
Commissioning and putting the project into operation : 12/2007
8. Cost estimate
Total project compensation cost is about VND 10,266,778,900 (or USD 649,796).
Total investment cost of the project is VND 164,032,602,000 (or USD 10,381,810)
9. Information dissemination
The draft RAP will be disclosed in Quang Ngai province and the Information
Development Center of WB (VDC) at 63 Ly Thai To, Ha Noi. CPPMB will send
copies of entitlement statement form to the authority of project district. All feedbacks
from the local authority and people are considered and supplemented into the RAP.
FS on Doc Soi - Quang Ngai 220kV transmission line 11
Resettlement Action Plan (RAP)
CHAPTER 1
GENERAL INTRODUCTION
1.1 THE BASIS OF THE REPORT
RAP report on Doc Soi - Quang Ngai 220kV transmission line is established
based on the followings:
+ Correspondence No. 1095/EVN/KH-HDQT concerning the assignment of
Feasibility Study establishment of projects which are expected to be financed by WB,
in which CPPMB is the Owner on behalf of EVN.
+ The contract signed between CPPMB and PECC4.
1.2 OBJECTIVES
This report is set up with the purpose:
+ The overall objectives of RAP are to determine the compensation and
resettlement program on basis of minimizing affected households and assets. Where
unavoidable, the program will set out provisions to ensure and help affected
households to improve or at least to maintain their pre-project conditions.
+ Helping to choose the right design alternative, minimize the degree of damage
at the implementation of project and ensure the highest socio-economic interests of the
project. During the project establishment, when implementing the survey of
livelihood-economic-social damage of project area, there was the agreement with local
authority concerning the policy on compensation and resettlement for PAPs. The
survey and data collection work mainly focuses on the ROW. Where unavoidable, the
program will set out provisions to ensure and help affected households to improve or
at least to maintain their pre-project conditions.
The objective of the Resettlement Policy is:
All PAP's residing, working, doing business or cultivating land in right-of- way
(ROW) of transmission line (T/L), surrounding areas of tower foundation, the
substation areas, in the service roads under the Project as of the date of the baseline
surveys are entitled to be provided with rehabilitation measures sufficient to assist
FS on Doc Soi - Quang Ngai 220kV transmission line 12
Resettlement Action Plan (RAP)
them to improve. Lack of legal rights to the assets lost will not bar the PAP from
entitlement to such rehabilitation measures.
During RAP preparation, Decrees and Circulars of Vietnamese Government
such as Decree 197/2004/ND-CP, Decree 181/2004/ND-CP, Decree 188/2004/ND-CP,
etc and Decisions about compensation unit price issued by the provincial people's
committees are applied. The entitlement policy in this RAP are suggested as follows:
+ Apply a compensation rate according to the market price or replacement
price: Compensation of land and crops (short-day trees) at market price. Compensation
of houses and trees (perennial trees) at conversion price.
+ All affected properties are legible from the cut-off-date (25/5/2004). The
affected households who have been registered will be compensated.
This RAP will be furnished to GOV and WB for concurrence
1.3 VALIDITY OF RAP IMPLEMENTATION
Resettlement and compensation program for PAPs, policies and provisions on
resettlement and compensation entitlement in RAP will only be applied after approval
of WB and GOV.
To meet RAP's objectives such as minimizing the resettlement and land
acquisition, PAPs will be supplied the information on project, compensation and
resettlement, the compensation costs will be paid at replacement cost or market cost.
Thus, before implementing resettlement and compensation program, the project owner
and local authorities should check and revise the applied compensation costs in this
report. If there is any compensation unit price non-conforning at the time of program
implementation, the local authorities and Resettlement and Compensation Board
(RCB) need to revise them to ensure sufficient compensation payment for PAPs
according to principles stated in RAP.
1.4 DESCRIPTION OF THE PROJECT
1.4.1 Project location
* Location: Doc Soi - Quang Ngai 220kV transmission line project with total
length as per the expected alternative of 60,303m goes through territory of 5
districts namely Mo Duc, Tu Nghia, Nghia Hanh, Son Tinh and Binh Son,
Quang Ngai Province.
FS on Doc Soi - Quang Ngai 220kV transmission line 13
Resettlement Action Plan (RAP)
* Scale of the project
- Total route length : 60,303m
- Voltage level :220kV
- Number of circuit : 02 circuits (only 1st circuit is made in I" phase)
- Width of ROW 21.2m
- Conductor Aluminum steel reinforced conductor, code ACSR-
400/51 with grease layer for anti-erosion.
- Ground-wire : Using composite optical fiber overhead ground-wire
OPGW-68 on line route, for incoming section and outgoing section of 220KV substation
suspended another ground-wire GSW-70, length of each section is about 2km.
-Insulator using glass insulator or equivalent standard with anti-
erosion zinc circle. Electro-mechanical load of suspension string is 7000daN and tension
string is 16000 daN. The creepage distance of suspension disc is 295mm and tension disc
is 340mm.
- Towers steel tower with hot dip galvanizing, linked by bolts,
domestic manufacturing.
- Arms Manufacture arms with towers all-in one block
- Foundation : using two types of foundation: raft foundation for weak
soil and pier foundation (4 piers for each position) for good soil.
1.5 PROJECT IMPACTS ON LAND AND PROPERTIES
a. Permanent impacts:
- Permanent land acquisition for tower foundations, etc... total permanent land
acquisition area of the whole project is 29,500m2 .
b. Temporary impacts:
- Trees, crops (peanut, manioc...) of all types within ROW and construction
temporary road.
- Trees, crops around the tower foundation construction areas.
ROW of the OHL is regulated in Decree 106/2005/ND-CP dated 17/8/2005 of
the Government concerning the detailed regulations and guidelines on implementation
FS on Doc Soi - Quang Ngai 220kV transmission line 14
Resettlement Action Plan (RAP)
of some articles of the Electricity Law pertaining to the safe protection of high voltage
power network.
With the above characteristics, acquired land for the project includes of:
- Permanent acquisition land area : 29,500m2.
- Temporary acquisition land area in ROW : 1,278,424m2.
- In the area of the project Doc Soi - Quang Ngai 220kV line, there are 100
households with 484 persons affected locate on the safe corridor of line.
1.6 PROJECT IMPACTS MITIGATION MEASURES ON LAND AND
PROPERTIES
Selection of rational line route: For the investigation and design of line route
completely avoid passing:
- Market areas, densely populated areas.
- Airport, military areas, petrol warehouse
- Near or parallel with communication system
- Temple, pagoda
- Protection forests, natural preserved areas, historic and cultural heritage, etc...
- In addition, the route line is designed with direction conversion many times,
creating many turning angles with high values, crossing roads many times in
order to avoid affecting to houses and works.
Technical solutions:
Rational design of tower span, foundation structure is designed with different
measures in conformity with the chosen site.
Design a rational work execution alternative, choose time for work execution at
periods of harvest and complete work when next crop is not yet cultivated (land is at
rest). If the cultivated period cannot be avoided then manual construction measures are
used in order to diminish the surface of land acquired for work execution, road for big
trucks are not constructed, organize work according to many shifts at high
productivity, reducing the time of lay-out acquisition.
During the process of stringing conductor, make scaffold and pull conductor
neatly on belt of land about Sm to avoid causing damages of trees and agricultural
crops. Make definitely each item of work, each part of route line to reduce the time of
FS on Doc Soi - Quang Ngai 220kV transmission line 15
Resettlement Action Plan (RAP)
land appropriation. Make full use of the existing roads for transportation of
equipments and for other purposes during the time of work execution, limiting the
construction of new road.
During investigation and work execution process, the workers's camps (if any)
are set up on vacant lot, on communal office area, not on private land or cultivated
land.
The result of these mitigating measures is that affected houses and land on the
line route are the least.
1.7 TOTAL PROJECT COST
Unit: VND
Item Item content Amount (VND)
1 Construction cost 109,990,350,000
2 Equipment cost 3,861,528,000
3 Other cost 35,268,669,000
4 Contingency cost 14,912,055,000
5 Tota investmw cost (1+2+3+4) 164,032,602,000
FS on Doc Soi - Quang Ngai 220kV transmission line 16
Resettlement Actio n Plan (RAP)
CHAPTER 2
IMPLEMENTATION ORGANIZATION AND LEGAL FRAMEWORK FOR
COMPENSATION AND RESETTLEMENT
Project Management Board and Local Authority of all levels will be responsible
for implementing RAP. It should be on schedule, suitable with approved schedule for
the project. The coordination between the project owner and local authorities will be
made closely in order to ensure entitlements for PAPs and to avoid the interruption or
delay of RAP implementation.
2.1 INSTITUTIONAL ARRANGEMENTS
The following institutions/agencies will be involved in implementing RAP:
- Electricity of Viet Nam (EVN)
- Quang Ngai Provincial People's Committee
- Project Management Board - Central Power Projects Management Board
- Consultant Company - Power Engineering Consulting Company No.4.
- Department of Finance and Goods Price of Quang Ngai Province
- Land Clearance Board of Quang Ngai province
- People's Committees of affected districts: Binh Son, Son Tinh, Tu Nghia,
Nghia Hanh and Mo Duc, Quang Ngai province.
- Land offices of the above project districts.
- Land clearance Committees of the above districts
- People's Committees of project affected communes
- Project affected persons
2.2 FUNCTIONS, TASKS FORCE AND RESPONSIBILITY
*: Electricity of Viet Nam (EVN)
EVN is the owner of the project and is responsible for managing and organizing
of investment policy, investigation, design, construction as well as supervision for
RAP implementation. EVN controls the project preparation and implementation via
professional agencies, approving decisions concerning resettlement work submitted by
PMB; assigning Central Power Projects Management Board (CPPMB) to directly
manage the whole process of project implementation.
FS on Doc Soi - Quang Ngai 220kV transmission line 17
Resettlement Action Plan (RAP)
* Project Management Board (PMB)
Central Power Projects Management Board is assigned by EVN in directing the
whole project including the implementation of RAP from impact survey, inventory,
making plans for RAP implementation. Main tasks of PMB will be:
+ Making Master Plan, management and supervision of land clearance
implementation to ensure full determination of relating PAPs, set out satisfied
entitlements as per land clearance policy.
+ To ensure that all PAPs are announced of applied policies for RAP
preparation. Entitlements of PAPs, project information and RAP are popularized under
announcement form. This is considered the proof of their entitlement towards interests
of RAP work.
+ Disseminate project information to PCs of all levels
+ Send RAP to Resettlement Committees, explaining applied models and
entitlements in the project.
+ Supervision/monitoring for compensation payment, coordinate to implement
land acquisition and site clearance.
+ Independent monitoring for RAP implementation, assigning an experienced
and competent agency to do this.
+ Report the implementation process on land clearance work to EVN and WB.
To meet this responsibility, PMB needs to establish a department or a group
including experienced officers to monitor RAP and environment implementation.
*. Quang Ngai Provincial People's Committee (PPC)
PPC is the agency approving and directing matters concerning the RAP within
the provincial area. The Project PPC are responsible for:
* Directing departments, branches and local areas in province related to RAP
preparation and implementation such as Land Department, Construction Department,
Department of Finance and Goods Price and project affected DPCs.
* Approving the costs of compensation in provincial area.
* Approving dossiers of land delivery and recovery in provincial area.
* Establishing Provincial Resettlement and Compensation Committee and
directly manages the activities of this Board.
FS on Doe Soi - Quang Ngai 220kV transmission line 18
Resettlement Action Plan (RAP)
* Directing and managing the coordination between Branches and local
authorities in RAP implementation.
* Department of Finance and Goods Price of Quang Ngai Province
To be responsible for issuing detailed compensation unit prices applied in the
provincial area. During the implementation process, Department of Finance-Goods
Price needs to make cooperation with other departments such as Construction
Department, Land Department, Department of Agriculture and Rural Development
and People's Committee of Districts in order to establish the compensation unit price
for premises, land, trees and crops.
*: Compensation Committee of Quang Ngai province
This Committee is decided to be established by Chairman of Provincial
People's Committee in order to implement the duties regulated by the Provincial
People's Committee. When implementing the compensation, assistance and
resettlement (if any), it should have the participation of the Owner, representative of
leaders from the Commune People's Committee Provincial where the land was
recovered and representatives of households whose land was recovered.
* People's Committees of affected Districts.
Being responsible for guiding compensation and resettlement activities in
district responsible for:
+ Creating good conditions and coordinate with relating agencies in survey,
inventory of project impact; organize community consultation activities, information
dissemination on the project implementation policy and land acquisition plan to people
of district where project constructed.
+ Establishment of Resettlement Committee of District
+ Directing and monitoring RAP activities within areas managed by district
+ Solving relating matters during RAP implementation together with
Resettlement Committee of district.
*. Resettlement Committees of affected Districts
The provincial PC assigns the districts to implement the compensation,
assistance and resettlement. The Resettlement Committee of districts (Council of
FS on Doc Soi - Quang Ngai 220kV transmission line 19
Resettlement Action Plan (RAP)
compensation, assistance and resettlement) is decided to be established by the
Chairman of District PC and responsible for:
* Establishing the alternative of compensation, assistance and resettlement (if
any) within district area.
* Advising the district PC in approval of compensation, assistance and
resettlement alternatives. Checking the unit prices of compensation stated in RAP,
suggest adjustment to comply with market prices at the plan implementation period.
* Co-ordinating with PMB, consultant agency to organize RAP meetings in
local section and organize community consultation together with project owner.
* Directly make payment on compensation and allowances to PAPs in a timely
manner.
* Settling the complaints and grievances of PAPs, solving any difficulties
during the implementation period, and suggest the solutions for the outstanding issues
to Provincial Resettlement Committees and Owner.
* Making monthly report and send them to PRCs, Owner and Chairmen of
DPCs.
Resettlement Committee of district will be headed by leader of district PC and
consists of following members:
- Leader of Finance - Planning Department: Vice Head
- The Owner: standing member
- Representative of Natural Resources and Environment Department: member
- Representative of Industry and Commerce Department: member
- Representative of Leader of District Tax Department: member
- Representative of Leaders of affected Communes: member
- Representative of PAPs
and some other members decided by Head of the District Resettlement Board in order
*to comply with the real situation.
Staffs of Resettlement Boards of Districts will work concurrently and enjoy
allowances according to DPC's decision. Assistants work during the project
implementation and get salary during the work period.
FS on Doc Soi - Quang Ngai 220kV transmission line 20
Resettlement Action Plan (RAP)
*. People's Committees of affected communes
* Contributing to Overall Detailed Measurements Surveys.
* Co-ordinate with Resettlement Committees of districts for classifying
impacted assets, determine the legality and legibility of assets.
* Certify affected assets in general survey for compensation dossier of each
household (in the survey note).
* Assisting local people in overcoming the difficulties during the process of
construction or rehabilitation of damages caused by project implementation. Making
public information about the project and disseminating policies in RAP.
*: Project Affected Persons (PAPs)
* Directly participate in the general survey, consider thoroughly their
entitlement and responsibility policy. After getting full entitlements, PAPs should
transfer the construction surface on time.
* Propose expectation, requirement for the above mentioned institutions and
monitor their implementation.
2.3 STAFFING ORGANIZATION AND RESPONSIBLESTable 2.1: Responsibilities of RAP implementing Institutions
No. Activities Institutions
Organizing meetings with PAPs to Land Clearance Committee
1 disseminate information about RAPimplementationMonitoring and certifying impacted Project Management Board and
2 households and their assets Resettlement Committee of districtcoordinate with affected Commune
_ _____________________________ _ ^People's CommitteesProject Management Board coordinates
3 Detailed measurement survey with Commune People's Committee andrelevant Units of local authority.
4 Informing for PAPs Project Management Board
5 Decision on compensation problems Compensation Committee
6 Compensation payment Compensation Committee and ProjectManagement Board
7 Internal Monitoring Project Management BoardDepartment of Natural Resources and
. Independent MonitorEnvironment or provincial socio-science8 Independent Moitoring Units selected by Project Management
Board.
FS on Doc Soi - Quang Ngai 220kV transmission line 21
Resettlement Action Plan (RAP)
2.4 LEGAL FRAMEWORK
This is a project with loan from World Bank so the legal grounds applied will be
a combination of Vietnam and WB policies.
a. Legal documents of Vietnam:
* The Constitution of Vietnam, 1992 confirms the right of citizens to own a house
and to protect the ownership of the house.
* According to Vietnam Law on land passed by National Assembly Term XI,
Session IV on November 26th, 2003 and come into force from July Ist, 2004.
* Decree No.197/2004/ND-CP issued by GOV on December 3rd, 2004 regulates
compensation, resettlement support for recovered land by GOV.
* Circular No.1 16/2004/TT-BTC issued December 7th, 2004 by the Ministry of
Finance provides guidelines to implement Decree No.197/2004/ND-CP issued
by GOV on December 3rd, 2004 regulates compensation, resettlement support
for recovered land by GOV.
* Decree No 188/2004/ND-CP of November 16th, 2004 on the stipulation of
method to determine the land price and the frame for the price of land types.
* Circular No.1 14/2004/TT-BTC issued November 16th, 2004 by the Ministry of
Finance provides guidelines to implement Decree No 188/2004/ND-CP of
November 16th, 2004 on the stipulation of method to determine the land price
and the frame for the price of land types.
* Decree No.18 1/2004/ND-CP issued by the GOV concerning the
implementation of Land Law.
* Decree No.182/2004/ND-CP dated 29/10/2004 issued by the GOV concerning
the land price calculation method and the land price framework.
* Decree No.198/2004/ND-CP dated 03/12/2004 issued by the GOV concerning
the collection of land use charges.
* Decree No.17/2001/ND-CP issued by the GOV concerning the regulation on
management and using the ODA capital.
FS on Doc Soi - Quang Ngai 220kV transmission line 22
Resettlement Action Plan (RAP)
* Decree No.105/2005/ND-CP dated 17/8/2005 issued by the GOV concerning
the detailed regulations and guidelines on implementation of some articles in
the Electricity Law.
* Decree No.106/2005/ND-CP dated 17/8/2005 issued by the GOV concerning
the detailed regulations and guidelines on implementation of some articles in
the Electricity Law pertaining to the safe protection of high voltage network.
b. World Bank Policy on Involuntary Resettlement (OD 4.30)
* The primary objective of this policy is to ensure that PAPs who have lost
assets are compensated at replacement cost and are provided with recovery measures
to help them improve better or at least maintain their standard of life and their income
capacity as in pre-project conditions.
* The policy framework is established based on the principles and objectives,
selection criteria for PAPs, entitlements, legal framework and institutions, mode of
rehabilitation and compensation, the participation of people. Furthermore, procedures
of grievance will be guided in the process of compensation, resettlement and
rehabilitation for PAPs.
c. Comparison between Government of Vietnam and World Bank Approaches
There are a number of ways in which the approaches of the Vietnam Government -
both in policy and practice - are compatible with World Bank guidelines so that PAPs
can have legitimate entitlements. The most important compatibilities are:
* Vietnam has a process whereby most people without legal land rights may meet
conditions of legalization and receive compensation for losses.
* Permanent residents are provided with options that include relocation to an
improved site, or cash, or a combination of the two.
* Resettlement sites offer not only better-improved infrastructure and services but
also represent a higher standard of living.
* Allowances are provided to help the PAPs in the transition period and there is
an institutional structure through which people are informed, can negotiate
compensation, and can appeal.
Differences between the approaches and measures that need to be addressed within the
program also exist. However, in this context, procedures exist within national and
FS on Doc Soi - Quang Ngai 220kV transmission line 23
Resettlement Action Plan (RAP)
province governments that allow the granting of waivers of domestic law on specific
projects that may be in conflict with that of the funding agency.
d. Required Waivers
In order to meet the requirements of the World Bank OD4.30 on Involuntary
Resettlement a number of articles in various Vietnamese laws and regulations which
do not ensure compensation at replacement cost or set eligibility provisions which do
not extend the right to rehabilitation and or assistance to households without proper
land paper, will be waived.
The articles of law and regulations that will be waived are mentioned below:
* Price of Land for Calculation of Compensation
According to Vietnam regulations, the calculation of land price for
compensation will be based on Decree 188/2004/ND-CP, Decree 181/2004/ND-CP,
etc and Circulars No.1 16/2004/TT-BTC, No.1 14/2004/TT-BTC.
In order to ensure the objectives of project resettlement policies, the
compensation land unit price is established as per Decision No.19/2005/QD-UB dated
07/2/2005 issued by Quang Ngai Provincial People's Committee concerning the
regulations on compensation, assistance and resettlement when the State takes back the
land; Decision No.31/2005/QD-UB dated 07/3/2005 issued by Quang Ngai Provincial
People's Committee concerning the regulations on land price of all types, road
classifying, regions of agricultural land in Quang Ngai province and will be adjusted
so as to comply with the replacement costs.
In addition, when applying the compensation policies, it is necessary to comply
with regulations stated in Decree 17/2001/ND-CP dated 4/5/2001 concerning the
guidelines on ODA capital management. Item 4, Article 2 of this Decree stipulates that
"in case the international agreements on ODA have been signed between GOV and
sponsor stipulate different contents, then that international agreements will be
followed".
FS on Doc Soi - Quang Ngai 220kV transmission line 24
Resettlement Action Plan (RAP)
CHAPTER 3
ENTITLEMENT POLICY
3.1 DEFINITION OF ELIGIBILITY AND LIMITATION TO ELIGIBILITY
Project Affected Persons (PAPs) including people confirmed by data collected
from the survey and investigation process as follows:
- PAPs have houses which are partially or totally affected (temporarily or
permanently) by the project.
- PAPs with partial or total impacted residental land or agriculture land by the
project, temporarily or permanently.
- PAPs with businesses and related income which are partially or totally affected
(temporarily or permanently) by the project.
- PAPs have crops (annual and perennial) and trees which are partially or totally
affected by the project.
- Encroachers who settled into the proposed affected area after the cut-off date
(25/5/2004) will have no entitlement to compensation and resettlement. They will be
required to demolish their structure and cut the trees or harvest their crops for land
clearance to the project. In the case necessary, they will be forced to be removed out of
the proposed project area. Nevertheless, they do not have to pay any fine or sanction.
3.2 RESETTLEMENT AND COMPENSATION PRINCIPLES
The compensation and resettlement plan is established based on fundamental
principles, i.e conforming to laws, decrees, policies regulated by Vietnamese
Government and WB's guidelines consisting of:
1. Acquisition of land and other assets, and resettlement of people will be
minimized as much as possible.
2. All PAP's residing, working, doing business or cultivating land in right of
way (ROW) of transmission line (T/L), surrounding areas of tower
foundation, the substation areas, in the service roads under the project as of
the date of the baseline surveys are entitled to be provided with rehabilitation
measures sufficient to assist them to improve or at least maintain their pre-
FS on Doc Soi - Quang Ngai 220kV transmission line 25
Resettlement Action Plan (RAP)
project living standards, income earning capacity and production levels. Lack
of legal rights to the assets lost should not bar the PAP from entitlement to
such rehabilitation measures.
3. The rehabilitation measures to be provided are: (i) compensation at
replacement cost, without deduction for depreciation or salvage materials for
houses and other structures; (ii) agricultural land for land of equal productive
capacity acceptable to the PAPs or in cash at replacement cost according to
PAP's choice; (iii) replacement of residential/premise land of equal size
acceptable to the PAP or in cash at replacement cost according to PAP's
choice; and (iv) transfer and subsistence allowances.
4. Location of resettlement and relocation should be as close as possible to
existing residential area of PAPs.
5. The resettlement transition period will be minimized and the rehabilitation
means will be provided to the PAPs not over one month prior to the expected
start-up date of works in the respective Project site.
6. Plans for acquisition of land and other assets and provision of rehabilitation
measures will be carried out in consultation with the PAPs, to ensure minimal
disturbance. Entitlements will be provided to PAPs not over one month prior to
the expected start-up date of works in the respective Project site.
7. The standard of life, the infrastructure of community must be maintained or
improved better than their prior place.
8. Financial and physical resources for resettlement and rehabilitation will be
made available and as where and when required.
9. Institutional arrangements will ensure effective and timely design, planning,
consultation and implementation of RAP.
- 10. Effective and timely supervision, monitoring and evaluation of the
implementation of RAP will be carried out.
3.3 ELIGIBILITY TO COMPENSATION ENTITLEMENT
Legitimate PAPs are all the affected households and institutions included in the
inventory with or without legal title included in the RAP inventory or able to
FS on Doc Soi - Quang Ngai 220kV transmission line 26
Resettlement Action Plan (RAP)
demonstrate with other means that prior to RAP cut-off date they owned, rented or
used land, and properties associated with land as defined in 3.1 item.
3.4 ENTITLEMENT POLICY
PAP's will be entitled to the following types of rehabilitation and assistance
measures as per the policy framework OD 4.30:
* PAP's losing agricultural land and crops
(i) The general mechanism for compensation of lost agricultural land
will be through provision of "land for land" arrangements of equal
productive capacity, satisfactory to the PAP.
However, if the PAP prefers to receive cash compensation then the
following applies:
- if the portion of the land to be lost represents 25% or less than
25% of the total area of the landholding, and the remaining
land is still a viable economic holding, cash compensation, at
full replacement cost, may be provided to the PAP; or
- if more than 25% of a villager's agricultural land is acquired
and the remaining holding is not viable then the Project will
acquire the entire landholding and provide cash
compensation at full replacement cost.
(ii) PAP's will be compensated for the loss of standing crops and fruit or
industrial trees at market price. Productive trees will be compensated
at replacement cost. Fruit trees will be compensated for the
remaining harvests.
(iii) PAP's whose land is temporarily taken by the works under the each
sub-Project will be compensated for their loss of income, standing
crops and for the cost of soil restoration and damaged
infrastructure. Land will be rehabilitated after the project
construction by PMB.
* PAP's losing residential land and house/structure
(i) The mechanism for compensating loss of residential land and
structures will be: (1) the provision of replacement residential land
FS on Doc Soi - Quang Ngai 220kV transmission line 27
Resettlement Action Plan (RAP)
(house site and garden) of equivalent size, satisfactory to the PAP or
cash compensation at replacement cost according to PAPs' options;
and (2) cash compensation reflecting full replacement cost of the
house/structures, without deduction for depreciation or salvage
materials or compensate in kind according to PAPs' options.
(ii) If residential land is only partially being affected by the Project and
the remaining areas are not sufficient for reorganizing PAPs' then at
the request of the PAP, the entire residential land will be acquired at
full replacement cost.
(iii) If house/other structure is only partially being affected by the Project
and the remaining areas are not convenient to using, the house/
structure will be acquired at full replacement cost, without
depreciation.
* PAP's will also be provided compensation at full replacement cost, without
deduction for depreciation and salvage materials for any other fixed assets affected in
part or in total by the project, such as tombs and water wells, etc.
Pursuant to Decree 197/2004/ND-CP issued by the GOV concerning
compensation, resettlement support for recovered land by GOV, then PAPs will be
supported as follows:
- As per Article 27: Transportation allowance
Households getting land recovered by GOV must relocate within the province,
city are entitled to a maximum of 3 million VND, relocating out of the province are
entitled to a maximum of 5 million VND. The level of allowance in details will be
regulated by the Provincial People's Committee.
Entities getting fully conditions to be compensated on land and assets when
being recovered, however they must change the location then they will be supported
completely the actual displacement cost, dismantling and installation.
People who are recovered the residential land, having no other residential place then
within time waiting for rehabilitating the new place, will be arranged in the temporary
houses or supported with money for house renting; the time and the support level in
details are regulated by Provincial PC in accordance with the local reality.
FS on Doc Soi - Quang Ngai 220kV transmission line 28
Resettlement Action Plan (RAP)
- As per Article 28: Restoration allowance
Households, people directly make agricultural production, when being recovered more
than 30% area of assigned agricultural land, will be supported for stabilizing the life
within 3 months without relocation and within 6 months with relocation; in case
relocate in areas with difficult or especially difficult socio-economical conditions then
the support time is maximum of 12 months. The support level in cash for one person
per month equivalent to 30 kg of rice calculated as per the average price in local
region.
When the GOV recovers land of economical entities, registered business
households and causes business pausing, the maximum support level is 30% of an
annual income after tax, according to the average income of three subsequent years
before confirmed by the tax agency. The support level in details is regulated by
Provincial PC in accordance with the local reality.
Furthermore, PAPs are also entitled to other assistances as follows:
- As per Article 29: Support for changing the career and creating
employment.
- As per Article 30: Support for the hirer not belonging to the state
ownership
Households, people who are renting houses not belonging to the state
ownership, when being recovered the land by GOV and must dismantle the house and
relocate then will be supported with the displacement cost equivalent to the level
regulated at Item I Article 27 of this Decree. Pursuant to the local reality condition,
the Provincial PC regulates the support level to stabilize their life and production.
- As per Article 31: Support level when recovering the public land of
communes, wards or towns.
! - Other support such as beside the support regulated in Articles 27, 28, 29,
30- and 31 of Decree 197/2004/ND-CP, pursuant to the local actual
situation, the Chairman of Provincial PC decides the other support
measures to ensure the life and production stabilization for people who
were recovered the land; in special cases, this will be submitted to the
Prime Minister for decision.
FS on Doc Soi - Quang Ngai 220kV transmission line 29
Resettlement Action Plan (RAP)
Forms of subsidy and bonus for PAPs
Type of subsidy Amount
- Displacement subsidy Maximum of VND 3,000,000 for insideprovince and VND 5,000,000 for outsideprovince.
Supporting for the whole cost fordismantling, installation.
Supporting the house-renting money(regulated by the Provincial PC)
- Subsidy for life and production 30 kg of rice/month/person within 3
stabilization months if not displacing; within 6 monthsif displacing the accommodation andwithin 12 months if displacing to the
difficult accommodation.
Supporting 30% of the income in oneyear if affecting to the business.
- Subsidy for changing career and The impacted household losing over 30%
creating the employment area of the agricultural production landwill be supported for changing career.
- Other subsidy levels Due to the decision of the Chairman ofProvincial PC.
3.5 IMPACTED CATEGORIES
By the nature of the project impacts as described above and based on the survey
of the PAPs the impacted categories are classified into 7 categories.
Categorv 1: Temporary acquisition of productive land in ROW.
Category 2: Temporary acquisition of residential land and garden land in ROW
without houses or structures in ROW.
Category 3: Temporary impact on residential and garden land. Partial
house/building within ROW (the impacted area is less than 25% but not affect to the
common structure. Residential and garden land outside of ROW is sufficient for re-
organizing (over 60m2 in urban area and 1 OOm2 in rural area).
Category 4: Temporary impact on residential and garden land. Impact more
than 25% or less than 25% of total house/building area and impact to the common
FS on Doc Soi - Quang Ngai 220kV transmission line 30
Resettlement Action Plan (RAP)
structure. Land outside of ROW is sufficient for re-organizing (over 60m2 in urban
area and 100m2 in rural area).
Categorv 5: Temporary impact on residential or garden land in ROW.
House/structure is partially or totally affected. Land outside of ROW is not sufficient
for re-organizing (less than 60m2 in urban area and lOOm2 in rural area).
Category 6: Permanent land acquisition for tower foundation.
Category 7: PAP impacted on business or other services
Refer to Appendix 1 for details of impacted categories.
FS on Doc Soi - Quang Ngai 220kV transmission line 31
Resettlement Action Plan (RAP)
CHAPTER 4
SOCIO-ECONOMIC CONDITION OF PROJECT AREA &
PROJECT IMPACTS
4.1. Socio-economic condition of project area
The natural land surface of Quang Ngai province is 51,352km2, the population
counted to December 31, 2002 is of 1,244,814 people. For administrative organization,
there are 180 communes (wards, townlets), 13 districts and 01 town in the whole
province. Quang Ngai town is the political, socio-economical center of the province.
Transport: the National Road IA of 98km length runs from North to South of
the province together with traffic roads disposed evenly on the whole province,
connecting areas of materials, industrial zones, plane with the mountainous area
serving the transport, exchange goods between province with other regions in the
whole country. There is system of sea ports such as Dung Quat and Sa Ky, especially
Dung Quat deep water port, sooner and later, will be one of the important gates to the
sea of areas of the Central, Western Highlands provinces, Laos and Cambodia via the
National Road 24.
Infrastructure: In the future, Quang Ngai province will have Van Tuong city,
industrial zones such as Tinh Phong, Dung Quat contiguous with Chu Lai open
economical zone, etc...
Land use situation ofproject districts
Total natural area of project districts is 148,266.8 ha in which agricultural land
area is of 62,976.6 ha; forestry land area is of 24,136.7 ha; special use land area is of
15,141.6 ha; residential land area is of 3,969.3 ha; area of land not yet used is of
41,748.0 ha and rear & grow land area of 258.6 ha. Total land area of project districts
is summarized at table 4.1.
FS on Doc Soi - Quang Ngai 220kV transmission line 32
Resettlement Action Plan (RAP)
Table 4.1: Total land area of project districts
No. Place-name Total (ha)
1 Binh Son district 46,538.6
2 Son Tinh district 34,357.4
3 Tu Nghia district 22,729.7
4 Nghia Hanh district 23,418.1
5 Mo Duc district 21,223.0
TOTAL 148,266.8
Source: Statistical yearbook of project province and districts in 2002
Population ofproject districts
Total population of project districts in 2002 is 778,752 people, in which
377,640 males and 401,112 females. Population in the labor age of these districts gets
high percentage and this is the labor potential and the advantage of district industrial
zones. So it is necessary to have plan on training and development in the future.
Table 4.2: Current population situation of project districts
Total SexNo. Place-name
(people) Male Female
1 Binh Son district 176,286 84,525 91,761
2 Son Tinh district 191,335 93,166 98,169
3 Tu Nghia district 175,105 85,797 89,308
4 Nghia Hanh district 96,308 46,784 49,524
5 Mo Duc district 139,718 67,368 72,350
TOTAL 778,752 377,640 401,112
Source: Statistical yearbook of project province and districts in 2002
FS on Doc Soi - Quang Ngai 220kV transmission line 33
Resettlement Action Plan (RAP)
Main characteristics of major economical sectors:
+ Agriculture, forestry and fish-breeding: Life of people in these productive
sectors has much good change, agricultural production value increases compared with
the last year, and economical mechanism of agriculture and countryside has right
direction transfer (i.e decreasing agricultural rate, increasing rate of forestry, fish-
breeding and rear & grow).
Development direction of agriculture and countryside economical mechanism:
rapidly put technological science advances into agricultural and forestry production
(rehabilitation and upgrading the existing water reservancy system, apply
technological science in selecting breed for crop plants and rearing animals, put
machines into production, etc...). Especially in catching fishes and rear & grow
aquatic product, it needs investment in purchasing off-shore ships and boats and apply
strictly to process of rear & grow aquatic product as per industrial direction.
+ Industrial sector: the province has paid attention to develop some
advantageous industrial sector such as: the industry of processing agriculture, forestry,
aquiculture related to development of material zone, high development of construction
material industry beside many preferential policies for enterprises investing capital in
industrial zones.
The development direction in few years is to give priority to depth investment,
renovation of technology equipment, increase quality and decrease cost price of
products.
4.2 PROJECT IMPACTS
Project impact categories
Inventory of project impacts is implemented by PECC4 with coordination and
assistance of project local authorities. The ROW for line route is defined according to
Decree 106/2005/ND-CP dated 17/8/2005 of the Government concerning the detailed
regulations and implementation guideline of some articles in the Law on Electricity
pertaining to the safe protection of high voltage power grid. The survey work focuses
on:
FS on Doc Soi - Quang Ngai 220kV transmission line 34
Resettlement Action Plan (RAP)
+ Permanent land acquisition for tower foundation construction
+ Land area in ROW and in the process of pulling conductor, etc.. .This
impacted land area is intended to temporarily requisition about 01 to 12months.
+ Trees over 4m high in ROW of T/L must be cut.
+ All structures out of ROW but it is supposed to impact to the project such as
bomb and mine storage, gas station, stone mine, communication centers, etc will be
removed. The line route selection had tried to avoid these structures. If it can not be
done due to difficult topography, removal of these structures must be considered.
+ Permanently acquisition land for the project consists of:
Result of survey
The ending date of survey is 25/5/2004
Table 4.2.1: Inventory of affectedfor Doc Soi - Quang Ngai 220k TIE
No. Items Unit Quantity Remarks
1 Houses
Compensation on houses, construction parts mT 6,404
2 Treesa. Paddy + Crops (peanut, manioc ...) m 165,300
b. Eucalyptus tree 65,020
c. Cashew tree 1,590
3 Permanent land acquisition area m__ 29,500
FS on Doc Soi - Quang Ngai 220kV transmission line 35
Resettlement Action Plan (RAP)
CHAPTER 5
PUBLIC PARTICIPATION AND CONSULTATION
5.1 Objectives of information campaign and consultation program
Inforrnation dissemination to consultation with and participation of the affected
people and involved agencies (i) reduce the potential for conflicts (ii) minimize the
risk of project delays and (iii) enable the project to design the resettlement and
rehabilitation program as a comprehensive development program to fit the needs and
priorities of the affected people thereby maximizing the economic and social benefits
of the project investment.
The objectives of the Public Information Campaign and PAP Consultation
Program are as follows:
* To share fully information about the proposed project its components and its
activities with the affected people.
* To obtain the cooperation and participation of the affected people and
communities required to be undertaken for resettlement planning and implementation.
* To ensure transparency in all activities related to land recovering,
compensation, resettlement and rehabilitation for PAPs.
* To obtain information about the needs and priorities of the affected people as
well as information about their reaction/feedback to proposed policies and activities.
PAPs will be entitled to participate in different stages during the process of
investigation, survey, RAP preparation and implementation. They will be invited to
participate in meetings organized by the owner and local authorities in order to offer
opinions on replacement alternatives, entitlement policies, listening to procedures,
process of grievance implementation, responsibility of competent institutions and
responsibility of PAPs during the process of RAP implementation.
5.2. Information campaign, PAPs & agency consultation
There are two phases of the public information campaign and RAP
consultation:
FS on Doc Soi - Quang Ngai 220kV transmission line 36
Resettlement Action Plan (RAP)
Phase 1:
During RAP planning and survey, make interviews with PAPs for their
expectation and selection of compensation measures. During the process of
investigation, make coordination with local authorities for agreement on line route
selection.
Phase 2:
After RAP's approval, PMB and local authorities will organize meetings with
PAPs to announce information of project, compensation policy and entitlement,
replacement solutions, allowances, subsidy, guidelines on grievance procedures and
RAP implementation.
To ensure that PAPs, their representatives and local governments of the affected
areas fully understand on the details of RAP, PMB will also prepare briefly
information on compensation and rehabilitation policy applied in the project (RIB)
distributed to all PAPs before making compensation and resettlement payment for
PAPs.
The RIB will contain information on the followings:
Part I - Basic characteristics
- Project description.
- Project objectives
- Implementation schedule
- Project impacts
- Eligibility for PAPs
- Institutions responsible for resettlement
Part 2 - Specific entitlements of PAPs
- Description of the detailed impact of the project on PAPs
- Compensation rates for each type of impact
- Legality and Eligibility to compensation
- Resettlement and rehabilitation alternatives.
- Implementation schedule for compensation and resettlement
FS on Doc Soi - Quang Ngai 220kV transmission line 37
Resettlement Action Plan (RAP)
5.3. Information dissemination and PAPs' consultation
According to policy applied in this project, all PAPs are entitled to project
information, entitlement to compensation. All PAPs have the right to take part in the
process of determining the land acquisition and compensation area to ensure that they
enjoy proper compensation.
PAPs will be informed and consulted through the following stages:
+ Staffs of PMBs and Resettlement Committees of provinces, districts and
affected commune authority confirm the land acquisition part and make inventory of
all structures, land, crops and trees affected by the project with the help of PAPs as
well as the public structures affected.
+ PMP and Resettlement Committees of provinces, districts, comrnmune
authority will organize meetings with participants of land recovering process,
announce the project information to them. All PAPs are invited to participate in this
meeting.
The meetings schedule and participants are expected as follows:
The first time:
It is expected to organize after the project's approval with the above mentioned
content, but the project impacts and resettlement and compensation policy are pressed
in order to take advantage of PAP's participation in the inventory and survey work.
Participants are:
- Representative of PMB
- Representative of Provincial Resettlement Committee
- Representative of District PC, District Land Clearance Committee
- Representative of Commune level authority
- PAPs or representatives of PAPs
The second time:
It is expected to organize before resettlement and compensation payment, with
the same content of the 1st time but compensation policy and schedule are pressed to
ensure the fair and give favorable condition for site clearance work.
FS on Doc Soi - Quang Ngai 220kV transmission line 38
Resettlement Action Plan (RAP)
Participants are:
- Representative of PMB
- Representative of Provincial Resettlement Committee
- Representative of District PC, District Land Clearance Committee
- Representative of Commune level authority
- PAPs or representatives of PAPs
The Resettlement Committee (RC) in combination with the local authorities
announces information on multi-media such as the stages of project development,
information on RAP and project impact on the community in the project area.
The RAP report of Doc Soi - Quang Ngai 220kV transmission line will be
announced information at local area where the project is implemented.
FS on Doc Soi - Quang Ngai 220kV transmission line 39
Resettlement Action Plan (RAP)
CHAPTER 6
GRIEVANCE AND APPEALS
The main objective of RAP implementation is to ensure the fair and adequacy
during compensation payment for PAPs. The resettlement and compensation program
should be implemented in such a way that satisfies both partners: the owner and PAPs.
Grievance, complaint and solution are the process related to the owner and
PAPs during the process of RAP implementation. To solve them timely and
effectively, relevant institutions such as PMB, DRC, PRC need to respond to the
complaints of the PAPs speedily and sensibly.
All grievers within resettlement program pay no fees for their grievance.
To ensure that the PAPs have avenues for redressing'their grievances related to
any aspect of compensation and resettlement, detailed procedures of redresses of
grievances have been established for the project. The mechanism is designed to be
easy, transparent and fair.
The procedures are as follows:
Complaints and grievances related to any aspect of RAP, including the
determined area and price of the lost assets, will be handled as follows:
First step:
If any person is aggrieved by any aspect of the resettlement and rehabilitation
program, he/she can lodge an oral or written grievance with commune authorities.
Commune People's Committee will resolve the issue within fifteen days from the date
it receive the complaint.
Second step:
If any aggrieved person is not satisfied with the decision in stage 1, he/she can
bring the complaint to the District People's Committee (DPC) or District Resettlement
Committee (DRC) within fifteen days from the date of the receipt of the decision in
FS on Doc Soi - Quang Ngai 220kV transmission line 40
Resettlement Action Plan (RAP)
stage 1. The District People's Committee (DRC) or District Resettlement Committee
(DRC) will reach a decision on the complaint within fifteen days.
Third step:
If the PAP is still not satisfied with the decision at district level, he/she can
appeal to the Provincial People's Committee (PCC) or Provincial Resettlement
Committee (PRC) within 15 days of receiving the decision of the DPC or DRC. The
Provincial People's Committee (PRC) or Provincial Resettlement Committee (CRC)
will reach a decision on the complaint within fifteen days.
Fourth step:
If the PAP is not satisfied with the decision of the Provincial level, the case may
be submitted for consideration by the District Court within 15 days of receiving
the decision of the PPC or PRC.
PAP's will be exempted from all administrative and legal fees.
Coercion for site clearance can not be applied while PAPs are waiting for solving
the complaints.
In case an oral compliant is made, it will be written on paper by the commune
and processed. Commune People's Committee will resolve the issue within 02 weeks.
In case of PAPs are illiterate persons, they can make an oral complaint with the
representatives of affected households and their representatives will record all queries
to submit to authority levels. Every authority level will resolve the complaints as per
the time regulated above.
The disputes are organized publicly and implemented in accordance with law.
Detailed procedures for redress of grievances and appeal process shown publicized
among the PAPs during participation meetings and also in the offices of RBs.
FS on Doc Soi - Quang Ngai 220kV transmission line 41
Resettlement Action Plan (RAP)
CHAPTER 7
MONITORING & SUPERVISION
Implementation of RAPs will be regularly supervised and monitored by the
respective PCs/PMB in coordination with the respective District and Commune Peoples'
Committees. The findings will be recorded in quarterly reports to be furnished to EVN
or MOI.
7.1. INTERNAL MONITORING & SUPERVISION
Internal supervision and monitoring include the following activities:
-Verify that the baseline information of all PAP's has been carried out and
that the valuation of assets lost or damaged, and the provision of compensation,
resettlement and other rehabilitation entitlements has been carried out in
accordance with the provisions of this Policy Framework and the respective
RAP.
- Oversee that the Inventories and RAP are implemented as designed and
approved.
- Verify that funds for implementing the Inventories and RAP are
provided to the respective PMBs at local level (provincial/district) in a timely
manner and in amounts sufficient for their purposes, and that such funds are used
by the respective PMB's in accordance with the provisions of RAP.
- Record all grievances and their resolution and ensure that complaints are
dealt with in a timely manner.
7.2. Independent monitoring
An independent agency or individual consultant will be retained by PMB of the
MOI and EVN to periodically carry out external monitoring and evaluation of the
implementation of RAP. The independent agencies will be academic or research
institutions, non-Governmental Organizations (NGO) or independent consulting firms,
all with qualified and experienced staff and terms of reference acceptable to the World
Bank.
FS on Doc Soi - Quang Ngai 220kV transmission line 42
Resettlement Action Plan (RAP)
In addition to verifying the information furnished in the internal supervision and
monitoring reports of the respective PMBs, the external monitoring agency will visit a
sample of 20% of household PAPs in each relevant province six months after each RAP
implementation to:
- Determine whether the procedures for PAPs participation and delivery of
compensation and other rehabilitation entitlements has been done in accordance with
this Policy Framework and RAP.
- Assess if the Policy Framework objective of enhancement or at least restoration
of living standards and income levels of PAPs have been met.
- Gather qualitative indications of the social and economic impact of Project
implementation on the PAPs.
- Suggest modification in the implementation procedures of RAPs, as the case may
be, to achieve the principles and objectives of this Policy Framework.
FS on Doc Soi - Quang Ngai 220kV transmission line 43
Resettlement Action Plan (RAP)
CHAPTER 8
IMPLEMENTATION ORGANIZATION ON
COMPENSATION AND RESETTLEMENT PLAN
8.1. MEASURES FOR THE PROJECT IMPLEMENTATION
8.1.1. Announcement to PAPs
All PAPs shall be thorough informed about the rights and policies of RAP
including entitlement policies, rate of compensation for every type of impact, the
active participation right in land acquisition process, complaint and grievance. RAP
information will be prepared by PMB and announced to all PAPs or informed at the
meetings in province, district and commune levels; on television, radio, newspaper,
hung in public places such as administrative quarters of communes.
Public announcement tasks shall be implemented irmmediately after EVN and
WB's approval of project is obtained. The information announced consists of:
+ Schedule of project implementation
+ Eligibility and non-eligibility to compensation and resettlement
+ The compensation principle: only make compensation for households using
land before inventory making and the official announcement about land acquisition of
State.
8.1.2. Compensation deadlines
The project impacts conclude households with areas of residential land,
agricultural land, forestry land, etc... affected pernanently or temporarily. PAPs
agreed to receive compensation amount so the RAP is carried out in package to PAPs.
Compensation payment for land, assets, paddy and crops; land delivery for
resettlement should be done at least 02 months before the project land acquisition.
PAPs will receive subsidies at the beginning of months and after their
receiving, they will have to transfer land for Site Clearance Board at least one month
before construction time.
8.2. RAP implementation process
Basic actions of the proiect
FS on Doc Soi - Quang Ngai 220kV transmission line 44
Resettlement Action Plan (RAP)
Action 1:
After RAP approved, PMB hires qualified agency for independent monitoring,
this agency must be approved by EVN and WB
Action 2:
Provincial authorities and PMB are required to supply the Town Resettlement
Committee with fully costs and declare the tasks for RAP implementation.
Action 3:
Town Resettlement Committees carry out the Detail Measurement Survey of
affected assets and socio-economic conditions, determining the compensation unit
price and if necessary, checking and readjusting it in order to make compensation at
market price and conversion price.
Action 4:
Immediately the ends of final inventory survey, Resettlement Committees of
Town will inspect and define the official number of PAPs, impacted properties and
total compensation amount for PAPs.
Action 5:
Resettlement Committees will officially announce the RAP policy, schedule of
project implementation and information for RAP to PAPs at public meetings including
issues related to compensation, resettlement and land clearance.
Action 6:
It is suggested to give priority to compensation payment for households with
permanent impacts, assisting them in transferring the production mode and mechanism
or with land for resettlement and life stabilizing. After that, making compensation
payment for PAPs affected on other properties.
Action 7:
During the project implementation, Independent and Intemal Monitoring
Institutions will supervise/ monitor all actions of RAP implementation, at the same
time giving proposals, discussions or report the changes during project implementation
as well as suggest solutions.
FS on Doc Soi - Quang Ngai 220kV transmission line 45
Resettlement Action Plan (RAP)
8.3. RAP implementation schedule
RAP will be implemented as per the schedule established to ensure the site
clearance work and schedule on project construction.
Payment of rehabilitation and furnishing of other restoration/assistance
entitlements is made in cash.
Organizational arrangement
Power companies and provincial area where the project goes by will arrange
full experienced staffs to ensure that RAP will be implemented smoothly as per the
accepted schedule.
FS on Doc Soi - Quang Ngai 220kV transmission line 46
Resettlement Action Plan (RAP)
CHAPTER 9
COST AND BUDGETS
9.1. Budgets
Budget for RAP implementation will be from the self-financed capital and
loans from WB. EVN entrusted Central Power Projects Management Board (CPPMB)
with management and directing project 's activities as well as project finance
management.
CPPMB has coordinated with Quang Ngai province, districts, departments of
Finance and Goods Price, Resettlement Committees at all levels to implement
compensation payment for PAPs.
9.2. Determining the compensation price
Compensation price for temporary and permanent impacted cultivated land,
trees and crops based on:
- The Government Decree No 197/2004/ND-CP of December 3, 2004
concerning the compensation and resettlement assistance when the State
takes back the land.
- The Government Decree No 188/2004/ND-CP of November 16t, 2004 on
the stipulation of the frame for the price of land types.
- Decision No.19/2005/QD-UB dated 07/2/2005 issued by Quang Ngai
Provincial People's Committee concerning the regulations on compensation,
assistance and resettlement when the State takes back the land.
- Decision No.31/2005/QD-UB dated 07/3/2005 issued by Quang Ngai
Provincial People's Committee concerning the regulations on land price of
all types, road classifying, regions of agricultural land in Quang Ngai
province.
9.2.1. Project
Types of compensation unit price in this project is suggested as follows:
FS on Doc Soi - Quang Ngai 220kV transmission line 47
Resettlement Action Plan (RAP)
Table 9.1. Compensation unit price for project
No. Item of compensation Unit price Remarks
1 Houses class IV with concreteroof, brick wall, cement 593,000VND/m2
foundation
2 Houses class IV with tile roof, 380,000 VND/m2
land wall, land foundation
3 Houses class IV with tile roof, 593,000 VND/M2
brick wall, cement foundation
4 2 storey houses with tile roof, 987,000 VND/m2
brick wall, cement foundation
5 Houses class IV with tile roof,wall by other materials, cement 399,000 VND/m2
foundation
6 Houses class IV with tole roof, 593,000 VND/m2
brick wall, cement foundation
7 2 storey houses with tole roof, 9700VDmbrick wall, cement foundation 987,000 VND/m2
8 Houses class IV with thatchedroof, brick wall, cement 525,000 VND/m2
foundation
9 Houses class IV with tole roof,wall by other materials, cement 202,000 VND/m2
foundation
10 Houses with thatched roof, wallby other materials, land 399,000 VND/m2
foundation
9.2.2 Land
Compensation unit price for permanent acquisition land is determined as per
Decision No.31/2005/QD-UB dated 07/3/2005 issued by Quang Ngai Provincial
People's Committee concerning the regulations on land price of all types, road
classifying, regions of agricultural land in Quang Ngai province. The unit price for
every land kind is as follows:
Residential land: 250,000VND/m 2
Agricultural land: 14,000VND/m 2
FS on Doc Soi - Quang Ngai 220kV transmission line 48
Resettlement Action Plan (RAP)
9.2.3 Trees and crops
Compensation unit price for trees and crops on the whole ROW as per Decision
No.19/2005/QD-UB dated 07/2/2005 issued by Quang Ngai Provincial People's
Committee concerning the regulations on compensation, assistance and resettlement
when the State takes back the land.
Price of trees, crops of this project is agreed as per table 9.2.
Table 9.2: Compensation unit price for trees and crops
No. Type Unit price Remarks
1 Eucalyptus 10,000 VND/tree
2 Cashew 60,000 VND/tree
3 Rice, crops 2,000 VND/m2
9.3 IMPLEMENTATION COST
9.3.1 Compensation cost
Based on the type and extent of impacts (described in the previous chapters),
compensation costs of the project including of:
- Compensation for permanent land acquisition for construction of tower
foundation and residential of displaced households within ROW.
- Compensation for trees and crops
- Compensation for houses, other auxiliary works for PAHs
- Cost for compensation board.
Table 9.3: Summary table of compensation cost
Doc Soi - Quang Ngai 220kV transmission line
No. Type of compensation Amount (VND)
I Compensation cost for houses 4,961,267,000
1 Houses class IV with concrete roof, brick wall, cement 29,650,000
foundation: 50 m2 x 564,000 VND/m 2
FS on Doc Soi - Quang Ngai 220kV transmission line 49
Resettlement Action Plan (RAP)
2 Houses class IV with tile roof, land wall, land foundation: 19,000,000
50 m2 x 200,000 VND/m2
3 Houses class IV with tile roof, brick wall, cement 1,464,117,000
foundation:
2,469 m2 x 492,000 VND/m2
4 2 storey houses with tile roof, brick wall, cement 2,556,330,000
foundation:
2,950 m2 x 845,000 VND/m2
5 Houses class IV with tile roof, wall by other materials, 37,905,000
cement foundation:
95 mr x 420,000 d/m2
6 Houses class IV with tole roof, brick wall, cement 308,360,000
foundation
520 m2 x 492,000 VND/m 2
7 2-storey houses with tole roof, brick wall, cement 483,630,000
foundation
490 m2 x 845,000 VND/m2
8 Houses class IV with thatched roof, brick wall, cement 47,250,000
foundation
90 m2 x 423,000 VND/m 2
9 Houses class IV with bamboo roof, wall by other materials, 5,050,000
land foundation:
25 m2 x 200,000 d/m2
10 Houses class IV with tole roof, wall by other materials, 9,975,000
cement foundation: 25 m2 x 420,000 VND/m2
II Compensation cost for permanent land acquisition 2,014,000,000
1 Compensation on land for households within ROW 1,601,000,000
6,404 m2 x 200,000d/m2
2 Compensation on permanent land acquisition for tower
foundation (agriculture land):
29,500 m2 x 21,OOOVND/m2 413,000,000
III Compensation cost for trees 1,076,200,000
1 Crops 165,300 m2 x 2,000 VND/m2 330,600,000
FS on Doc Soi - Quang Ngai 220kV transmission line 50
Resettlement Action Plan (RAP)
2 Cashew 1,590 trees x 85,000 VND/tree 95,400,000
3 Eucalyptus 65,020 trees x 10,000 VND/tree 650,200,000
IV Cost for relocation 850,615,000
I Subsidy for production stabilizationi:
420 people x 90,OOOVND x 6 months 210,000,000
2 Displacement 3,000,000 VND x 70 households 220,500,000
3 Relocation bonus 5,000,000 VND x 70 households 320,200,000
4 Cost for dismantling houses:
70 houses x 400,000 VND/house 99,915,000
_ Total - 8,902,082,000
9.3.2 Cost for RAP establishment
Cost for RAP establishment consists of:
- Preparation work: cost for document study, translation, preparation of
forms for socio-economic survey and PAPs 'inventory.
- Site survey work: work with local authority for detailed measurement
survey (DMS) of PAPs and collecting compensation price list.
- Summarize data for establishment of report and RAP report.
Survey work is carried out in two stages: Preliminary stage and Detailed
Measurement Survey.
9.3.3. Management cost
Management cost consists of cost for activities of PMB and local PRCs
including: material base, salary and other allowances for administrative apparatus. For
organizational mechanism of these RCs, staffs often work concurrently during project
construction period, only several members work permanently by labor contracts.
- Cost for meetings, announce with PAPs or their representatives.
- This total cost is temporarily calculated 1% of total compensation cost for
project impacts stated in item 9.3.1.
FS on Doc Soi - Quang Ngai 220kV transmission line 51
Resettlement Action Plan (RAP)
9.3.4 Monitoring cost
- When implementing the project, PUB will sign contract with independent
supervision organizations. Total cost for supervision is temporarily
calculated as 2% of total compensation cost for project impacts and cost for
RAP establishment stated in item 9.3.1 and 9.3.2.
9.3.5. Reserved cost
Reserved cost for unpredictable problems is calculated as 10% of total
compensation cost for project impacts and cost for RAP establishment stated in item
9.3.1 and 9.3.2.
9.4. Total cost for RAP implementation
Total cost for RAP implementation of Doc Soi - Quang Ngai 220kV
transmission line
No. Content Amount (VND)
1 Total compensation cost (a) 8,902,082,000
2 Cost for RAP establishment (b) 185,202,000
3 Management cost: 1% (a) 89,020,820
4 Monitoring cost: 2%(a+b) 181,745,680
5 Reserved cost: 10%(a+b) 908,728,400
Total 10,266,778,900
FS on Doc Soi - Quang Ngai 220kV transmission line 52
Resettlement Action Plan (RAP)
CHAPTER 10
CONCLUSION AND PROPOSALS
10.1. Conclusion
After investigation, summing up data on damages in the ROW, consulting
opinions of the relevant local authorities and community of affected households.
Through the making of RAP, we have the following conclusions:
* Investment for work construction is necessary in order to in order to perfect
the power grid, increase the transmission capacity on the line and the reliability, safety
and continuity in power supply for Quang Ngai province and adjacent areas and
furthermore, increasing the economical nature in operation.
* As the secure corridor of route line and construction site of substation
spreading on the area of 5 district of Quang Ngai province, at development of
compensation and making land clearance works of the project, the relevant local
committees and services have to work in combination to ensure favorable results.
* Report on determination of land surface, trees and agricultural crops being
affected by the project.
* Summing up report and calculation on damages due to the project, then
bringing up common compensation price.
* Study and submission of RAP planning for community of affected inhabitants.
10.2. Proposals
Based on problems considered in feasibility stage, propose to carry out following
works so that RAP implementation of this project will have high feasibility.
* The CPPMB will progagate the deep and broad information on the project by multi-
media system, etc... to the habitants in order to minimize the negative impact of individuals
profiting of the standpoint, investment policy of the government.
* The CPPMB, Resettlement Committee and Compensation Committee have to inspect
closely the execution of compensation and land clearance works in preparation of work
execution.
* Appointment of a standing team to solve in a timely way the complaints and claims of
affected households.
* To implement compensation and resettlement on schedule and monitoring strictly the
implementation. To ensure that life quality of PAHs will be better than pre-project.
FS on Doc Soi - Quang Ngai 220kV transmission line 53
Resettlement Action Plan (RAP)
APPENDICES
FS on Doc Soi - Quang Ngai 220kV transmission line 54
Resettlement Action Plan (RAP)
ANNEX 1: ENTITLEMENT MATRIX
No Type of loss Applicati Definition of Compensation Policy Implementation Issues
on entitled PAPs
I Temporary All PAPs PAPs - Cash compensation for affected - Trees have to be cut are regulated by Article 5 of
acquisition of have trees, with/without trees at the replacement cost plus Decree 106/2005/ND-CP dated 17/8/2005 of the
productive land in crops, land cost for cutting trees, crops at market Government concerning the guideline on
ROW other certificate price. Number of crop patterns to be implementation of some articles of Electricity Law
assets in included in compensated based on the time of pertaining to the safe protection of high voltage
ROW the inventory temporarily acquired of land. power network.
or able to - No compensation for land on the protection of the high voltage networks.
prove land - Rehabilitate land after the project - PMB and local authorities determine and ensure
ocupriontcut- construction. that compensation for trees will be at the
o replacement cost and for crops at the market price.
If PAP is requested for cutting affected trees, PMB
will pay money for this work. PAP has right for
using salvageable trees.
- Full compensation at least 01 month before land
clearance. Payment to PAPs will be delivered by
PMB and Resettlement Committees (RCs).
- Affected land in ROW will be rehabilitated by
contractors after the project construction and land
could be used with the restricted purposes.
- Finance available for compensation and well
information disclose/ disseminate
2 Temporary All PAPs -do- - Cash compensation for affected - Trees have to be cut are regulated by Article 5 of
acquisition of with fruit trees and trees at replacement Decree 106/2005/ND-CP dated 17/8/2005 of the
residential and orchards cost. Government concerning the guideline on
garden land in or trees in implementation of some articles of Electricity Law
FS on Doc Soi - Quang Ngai 220kV transmission line 55
Resettlement Action Plan (RAP)
No Type of loss Applicati Defmition of Compensation Policy Implementation Issues
on entitled PAPs
ROW without ROW - No compensation for land pertaining to the safe protection of high voltage
house or structures - Rehabilitate land after the project power network.
in ROW construction.
- PMB and local authorities determine and ensure
that compensation for trees will be at the
replacement cost. If PAP is requested for cutting
affected trees, PMB will pay money for this work.
PAP has right for using salvageable trees.
- Full compensation to PAPs at least 01 month
before land clearance. Affected land in ROW will
be rehabilitated by contractors after the project
construction
- Payment to PAPs will be delivered by PMB and
RCs- Finance available for compensation and well
information disclose/ disseminate
3 Temporary impact All PAPs -do- House/ building: - House and building have to be demolished or
on residential and have - PAP can opt for: i) Remain their could be existed are regulated by Article S of
garden land. Partial house/buil houses or building in ROW with the Decree 106/2005/ND-CP dated 17/8/2005 of the
house/building ding and conditions regulated by - Trees have Government concerning the guideline on
within ROW (area trees/fruit to be cut are regulated by Article 5 implementation of some articles of Electricity Law
in ROW less than trees in of Decree 106/2005/ND-CP dated pertaining to the safe protection of high voltage
25% of total area) ROW 17/8/2005 of the Government power network.
and the demolished concerning the guideline on - Consultation for PAP's options on remain their
area does not implementation of some articles of house in ROW or move out of ROW.
impact to the Electricity Law pertaining to the safe - PMB and local authorities determine and ensure
remaining protection of high voltage power that compensation will be at the replacement cost,
_ house/building, network.
without deduction for salvageable materials
FS on Doc Soi - Quang Ngai 220kV transmission line
56
Resettlement Action Plan (RAP)
No Type of loss Applicati Definition of Compensation Policy Implementation Issues
on entitled PAPs
Residential land Subsidy allowance for fireproof - PAPs will demolish the impacted part/ room and
and garden land materials and lightning arrestors for reconstruct/or improve their houses themselves.
outside of ROW is the existing house/building; or ii) - Full compensation for trees and fruit trees at least
sufficient for re- Cash compensation for the directly 01 month before land clearance. If PAP is requested
organizing (more affected rooms at the replacement for cutting affected trees, PMB will pay money for
than 60 m in the cost and cost for demolishing an this work. PAP has right for using salvageable
urban area and 100 affected room. trees
m2 in the rural - No compensation for land.
area).-Reaiiaelnafethprjc Full entitlement to PAPs impacted. on
,- ~~~~~~~~~~~~- Rehabilitate land after the project -os/uligbfr adcerne
construction by contractors. house/building before land clearance.
Tree and fruit tree - Payment to PAPs will be delivered by PMB and
- Compensation for affected trees RCs
and fruit trees at the replacement - Land in ROW could be used with restricted
cost. purposes.
Allowances: - Finance available for compensation and well
.* s r ^n a r ~~~~~~~~~~~~information disclose/ disseminate
- Relocating allowance of 30 kg of
rice equivalent per person per month
in six months.
4 Temporary impact All PAPs -do- House/ building: - House and building have to be demolished or
on residential and have - PAP can opt for: i) Remain their could be existed are regulated by by Article 5 of
or garden land. house/buil houses or building in ROW with the Decree 106/2005/ND-CP dated 17/8/2005 of the
Impact more than ding and conditions regulated by - Trees have Government concerning the guideline on
25% or less than trees/fruit to be cut are regulated by Article 5 implementation of some articles of Electricity Law
25% of total trees in of Decree 106/2005/ND-CP dated pertaining to the safe protection of high voltage
house/building ROW 17/8/2005 of the Government power network.
area but the concerning the guideline on - Consultation for PAP's options on remain their
demolished area implementation of some articles of house in ROW or move out of ROW
_ _L_will impact to the _ ___
FS on Doc Soi - Quang Ngai 220kV transmission line 57
Resettlement Action Plan (RAP)
No Type of loss Applicati Definition of Compensation Policy Implementation Issues
on entitled PAPs
remaining of Electricity Law pertaining to the safe - PMB and local authorities determine and ensure
house/structure, protection of high voltage power that compensation will be replacement cost at the
Land outside of network. Subsidy allowance for time of payment.
ROW is sufficient fireproof materials and lightning - PAPs will demolish the impacted areas and
for reorganizing ( arrestors for the existing reconstruct/or improve their houses themselves.
more than 60 m2 in house/building; or ii) Cash
the urban area and compensation at replacement cost - Full compensation for trees and fruit trees to PAPs
100 m2 in the rural for full areas of impacted at least 01 month before land clearance. If PAP is
area). house/building.
requested for cutting affected trees, PMB will pay
money for this work. PAP has right for using
- No compensation for land.slaebete.- Rehabilitate land after the project salvageable trees.
construction by contractors. - Full compensation for impacted house and
allowances to PAPs at least 01 months before land
Tree and fruit tree clearance.
- Compensation for affected trees - Payment to PAPs will be delivered by PMB and
and fruit trees at the replacement RCs
cost. - Cleared residential could be reused with restricted
Allowances: purposes.
- relocating allowance of 30 kg of - Finance available for compensation! rehabilitation
rice equivalent per person per month and well information disclose/ disseminate
in six months.
5 Temporary impact All PAPs -do- PAPs can opt for one of the - House and building have to be demolished or
on residential and have followings: could be existed are regulated by Article 5 of
or garden land in house/build i) Remain their houses or building Decree 106/2005/ND-CP dated 17/8/2005 of the
ROW. Full or ing and in ROW with the conditions Government concerning the guideline on
partial trees, fruit regulated by Article 5 of Decree implementation of some articles of Electricity Law
FS on Doc Soi - Quang Ngai 220kV transmission line
58
Resettlement Action Plan (RAP)
No Type of loss Applicati Definition of Compensation Policy Implementation Issues
on entitled PAPs
house/building trees in 106/2005/ND-CP dated 17/8/2005 pertaining to the safe protection of high voltage
impacted and land ROW of the Government concerning the power network.
outside of is not guideline on implementation of
sufficient for some articles of Electricity Law - Consultation for PAP's options on remain their
reorganizing (less pertaining to the safe protection of house in ROW or move out of ROW
than high voltage power network.
60 m2 in the urban Subsidy allowance for fireproof - PMB and local authorities determine and ensure
area and 100 m2 in materials and lightning arrestors for that compensation will be at replacement cost at the
the rural area) the existing house/building; or ii) time of payment.
Cash compensation for the whole - Replacement land, and resettlement sites
residential area which PAP occupied development.
(not only for the impacted areas) and - PAPs receiving compensation will demolish the
properties associated with occupied impacted areas and reconstruct/or improve their
land at replacement cost. Impacted houses themselves.
land will be obtained by localauthorities; or ii) "Land for lan" Full compensation for trees and fruit trees to
authorities; or ii) "Land for land" PAPs at least 01 month before land clearance. If
with the samne area PAP occupied PAP is requested for cutting affected trees, PMB
and cash at replacement cost for the willpymnyfrtiwokPA hargtfr
affected assets associated with land. i pay money for this work. PAP has right for
Land occupied by PAP will be ng salvageable trees.
obtained by local authorities. - Payment to PAPs will be delivered by PMB and
- Compensation for affected trees RCs
and fruit trees at the replacement - Cleared residential could be used with restricted
cost. purposes.- Finance/ land available for compensation/
Allowances: rehabilitation and well information disclose/
- Relocating allowance of 30 kg of disseminate.
rice equivalent per person per month - PMB consult with PAP who are eligible to
in six months
FS on Doc Soi - Quang Ngai 220OkV transmission line
59
Resettlement Action Plan (RAP)
No Type of loss Applicati Definition of Compensation Policy Implementation Issues
on entitled PAPs
- Transportation allowance for rehabilitation for their options and prepare proposal
relocating PAP according to the for rehabilitation programs in the period of RAP
Decree 197/2004/ND-CP dated implementation.
03/12/2004 of GOV.
- Rehabilitation assistance if PAPs
permanently losing business or more
than 25% of their incomes.
- Incentive for relocating in a timely
manner: 5,000,000 VND/HH
6 Permanent All PAPs -do- For PAP losing productive land: - Consultation for PAP's options on land
acquisition of land occupied a Land loss less than 25% of their compensation.
for tower land and total landholdings - PMB and local authorities determine and ensure
foundations, properties - Cash compensation for the lost area that compensation will be at replacement cost at the
substation and associated if the remaining plot is still time of payment.
access roads etc. with land economically viable. - Replacement land, and resettlement sites
y impacted - Cash compensation for the whole development.
by towers impacted plot if the remaining plot is - PAPs receiving compensation will demolish the
foundations not economically viable. impacted areas and reconstruct/or improve their
, substation - Cash compensation for properties houses themselves.
and access associated with land - Full compensation for trees and fruit trees to
roads etc. b. Land loss equal or more than PAPs at least 01 month before land clearance. If
25% of their total landholdings: PAP is requested for cutting affected trees, PMBwill pay money for this work. PAP has right for
followings: using salvageable trees.
- No award civil work contract before completion
i)"Land for land" with the same area of compensation and reorganizing houses or
FS ________on_______Doc_____ ____Soi_____ and productive of impacted area if
FS on Doc Soi - Quang Ngai 220kV transmission line 60
Resettlement Action Plan (RAP)
No Type of loss Applicati Definition of Compensation Policy Implementation Issues
on entitled PAPsthe remaining plots are still relocation.
economicviable and for the whole - Payment to PAPs will be delivered by PMB and
impacted plots if the remaining RCs
plots are not economicviable. - Finance/ land available for compensation/
ii) Cash for land at the replacement rehabilitation and well information disclose/
cost. disseminate.
- Compensation for trees and affected - PMB consult with PAP who are eligible to
fruit trees at the replacement cost. rehabilitation for their options and prepare proposal
- Rehabilitation assistance. for rehabilitation programs in the period of RAP
. implementation.For PAP losing Residential and - PAPs will be granted with Land Use Right
garden land: ~~~~Certificate- If remaining land is sufficient forCetfce
freoganizing (mor ta 60 for without payment of administrative fees.reorganizing (more than 60 m2 mi.
the urban area and 100 m2 in the
rural area): Cash compensation for
lost area and assets associated with
land.
- If remaining land is not sufficientfor reorganizing:
PAP can opt for i) cash compensation
at replacement cost for land and
assets on land, or ii) "land for land"
compensation for the whole
residential area which PAP occupied
(not only for the impacted areas) and
properties associated with occupied
land. For affected house and building,
FS on Doc Soi - Quang Ngai 220k V transmission line 61
Resettlement Action Plan (RAP)
N- Type of loss Applicati Definition of Compensation Policy Implementation Issues
on entitled PAPs
the same entitlement to PAP ofcategories 3 or 4 or 5.
7 PAP impacted on All PAPs -do- (a) Temporary impact on business or - Full compensation for incomes lost to PAPs at
business or other impacted other services. least 01 month before land clearance.
services on business - PMB consult with PAP who are eligible to
and other Compensation for income lost in the rehabilitation for their options and prepare proposal
services affected time for rehabilitation programs in the period of RAP
(b) Permanent impact on business or implementation.other services.
Rehabilitation assistance.
FS on Doc Soi - Quang Ngai 220kV transmission line 62
Resettlement Action Plan (RAP)
Annex 2: Inventory of Project Affected People
_oss of Othe
Loss of Assets Loss of Crops assets Eg., Other Losses
Total Land to be umber an Structure itructure Area of Number Structures Structures etc. 4umber an, Structure Structure Losses
Survey Name of Head of No. of nandholdin Acquired ss as ype of los ermanen empora esidentia and type permanent emporary (No. &type :ype of los ermane empor (specify)
No. Household persons Of Hhold in M by of structures (Mv) (M2 ) land lost of lost (M2 ) (M2 ) Area of structures (M2) (M2 ) umbe and
in Hhl(ttlM2)) yeofls
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ jJ j _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ la n d lo st _ _ _ _ j { _ _ _ _ str u ctu r e
Binh Son district
Binh Nguy8n commune
1 PhingThiMai S 1000 = = |
2 Nguyen Chung Cu 3 800 _ _ _ _ _ _ _ _
3 Huynh Thi Vinh 5 500 _ _ _ _ _ _ _ _ .
4 uynh C6ng . _4 1000 _ _ _ _ _ ____
Binh Trung commune
5 PhanThiNhAn 6 1500 | ____
6 CaoVanS S| 5 800 | _ _ _ ____
7 |V Van Thanh 5 1500 | _ ____
8 aoThi | 4 2000 | ___ ___ _ _ _____
9 |ao Van Kim 5 1000 | _ _ _ _ _ _ _ _ | |_._|
Binh Minh commune
10 |NguynVinDfrc 6 500 250 |50 House| 50 | |50
11 Dinh Vn ThuS' 5 800 300 37,5 House 49,5 49,5 | _ _ _ _ _ _
12 MmtmTai 4 300 150 50 House 25 | | 25 |
Binh Chitng commune
13 |Nguyen Thbi 3 200 | _ _ 1 I I 1 1-14 NguynAn | 2 2500 | | | |
FS on Doc Soi - Quang Ngai 220kV transmission line 63
Resettlement Action Plan (RAP)
15 |Nguy8nPhui KS 5 150 _ _
16 jPh4mThiY "n | 4 150 | _ _ _ _
Son Tinh district
Tinh Tra commune
17 DoAn NgQc Linh 5 800 200 25 House 140 140 ___= =
18 Doin Thj Quyen 1 1000 600 60 House 50 _ 50 _
19 Eng Va.n Thanh 4 1000 400 40 House 49,5 49,5
20 E3angNgoc Tha 5 1500 200 13,3 House 160 160 .
21 Nguy8n Chuing Trinh 2 140 _ 100 71,4 House 50 50 .
Tinh Binh commune
22 Tran Thanh Phong 5 1000 100 10 = = =- = _ _ _ _
23 Truong Thi PhuM c 3 200 84 42 House 84 84
24 L8 Am 2 2500 _ House 50 50 |
25 L8 Van Thanh 5 150 80 53,3
26 D3 Van Lap 4 150 70 46,7 House 60 _ 60
27 D6 Van DOng 4 150 90 60 House 60 60 .
28 L ThQ 9 4000 500 12,5 House 250 250
29 Nha mau giao 30 30 100 _ .
30 Tran Thi Cuic 7 2000 800 40 _ .
31 TruangVan San 9 1000 200 20 House 100 100
Tinh Son commune
32 PhiingXuanAnh 5 1500 500 33,3 House 120 120 |
33 Dox Tuan Sfru 5 1500 500 33,3 House 60 |_|_60 | _ _ _
34 TrAn Thanh Thuy 4 2000 | 500 25 House | 80 |_|_80 |
35 08TAnThi 4 1200 | 200 16,7 House 80 80 |
Tr Nghla district
FS on Doc Soi - Quang Ngai 220kV transmission line 64
Resettlement Action Plan (RAP)
Nghia Thang commune
36 |guyenR6 | 6 1000 80 8 House 80 |_ 80 | |
37 |NguyenThjThi 2 1500 90 6 House go _ | 90 |
ghia Thuan commune
38 Vo Thinh Tien 6 2000 64 3,2 House 64 = 64
39 Nguy8n Thanh Hai 4 600 60 10 House 60 60
40 Nguy8n Thi Thur 3 1500 42 2,8 House 42 42
41 Le Van Tan 4 1500 150 10 House 150 150
42 L8 Thanh Long 7 1500 90 6 House 90 90 o _ _
43 Vo Vnin Dng 3 1500 30 2 House 30 30 = =
44 L8 Van Kim 4 2000 200 10 House 200 200 _
45 ran TieI 5 3000 300 10 House 300 300
46 Nguyn Thanh Tarm 5 1500 500 33,3 House 80 80 = = =
47 Nguyen Hong Du 7 8000 200 2,5 House 120 120 . .
NghTa Kr commune
48 Nguyen Thi Meo 8 4500 80 1,8 _ _
49 Truang Phi Khanh 2 8000 200 2,5 House 200 200 =
50 Nguy&nBien 6 2000 150 7,5 House 150 150
51 NguyenTh6ng 7 8000 90 1,l .
52 VoThiLan 5 2000 100 5 _ _ | |
53 V6 Van ThiQn 4 2500 50 2 House 50 50 _ _ _ _ _
54 LThiXua.n Dirgc 3 500 50 10 House 50 50 _____ ______
55 |L Van Phu 8 600 70 11,7 House 70 70 = -___
56 NguyenThoa 6 500 70 14 House 70 70 | | |
57 guyen Thi Tubng 4 700 40 5,7 House 40 40
58 Nguyn Van Hue 3 1000 300 30 _ _ ____
FS on Doc Soi - Quang Ngai 220kV transmission line 65
Resettlement Action Plan (RAP)
59 NguyenLQng 7 |6000 150 |2,5 |
Ngh1a Hanh district
Uanh Dung commune
60 TrAn Vn 4 1000 = === =
61 TrAn Thanh Xuan 4 500 _ _
62 Tran VAn Mn 6 1000 _
63 Nguyen Thi Nhi 5 1000 _ _
64 Tran An 8 500
65 Tran Lap 7 1500 . _
HInh Minh commune
66 Pham Van Le 4 1500 350 23,3 House 80 80
67 Pham Yen 4 1000 400 40 House 152 152
68 Tran On 4 1000 500 50 House 30 30 =
69 L Thi Thuan 6 500 200 40 House 70 70
70 Ho Van Luat 5 1000 300 30 House 120 120
71 Tran Thi Mai Khanh 8 1000 500 50 House 100 100
72 Le Thi Em 2 500 100 20 House 50 50
73 Luong ChAu 6 1500 700 46,7 House ioo 100
74 Nguy8nVnKhiem 2 2000 200 10 House 100 100 .
75 Liru Thi Hao 3 600 go 90 15 House 80 80
76 Luu ThiDgi 5 100 50 50 House 80 80
77 Vo Thi Quang 13 1200 300 25 House 150 150
78 Ho Van Doan 5 300 40 13,3 House 40 40
79 Tran Thanh 10 150 50 33,3 House 50 50
80 rrAn Bang 5 180 80 44,4 House 120 120
1 81 rAn Nong 4 365 80 21,9 House 60 60 ._ _ _ _ _
FS on Doc Soi - Quang Ngai 220k V transmission line 66
Resettlement Action Plan (RAP)
82 TrAn Dfing 6 600 100 16,7 House 20 20 ______
83 Tran Minh Dfrc 3 150 50 33,3 House 50 _ 50
84 Tran Quang 6 150 80 53,3 House 70 70
85 Tu Phuac 4 180 70 38,9 House 50 50
86 Tr Van Hien 7 3500 500 14,3 House 70 70
87 Ho Thi Kim Anh 6 1000 100 10 House 80 80
88 Tir Loan 6 3000 100 3,3 House 60 60 _ _
89 Tu Phutang 4 365 100 27,4 _ _ _
90 Tran Giang 4 365 100 27,4
Hhnh Thien commune
91 Truang Bich 5 1000 500 50 House 501 50 |
92 U VVan Tu| 4 | 0 | 0 |o 10 House| 25 | |25|
HAnh Thinh commune
93 Huynh Thai My 4 640 300 46,9 House 60 |_ |_60 |
94 jDo Thi Thu 5 1300 500 38,5 House 70 | | 70 |
95 Nguyen Mau Thai 3 600 300 50 House 25 | | 25 | _ _
i rue district
Duc Phu commune
96 TrAn D6ng Ba | 4 500 j 300 60 House 40 |_ |_40 |
97 |Tran Duc Ng(c |4 | l00 |700 |46,7 Housel 25 r |25
D(c Phong commune
98 Hu'nhThiKy |6 365 |
99 |NguyenVanTh6ng 6 600 | _ _ _ _ _ _ _ .
100 Pham Hir6ng 4 150 | _ _ _ _ _ _ _ _ _ _____
FS on Doc Soi - Quang Ngai 220kV transmission line 67
Resettlement Action Plan (RAP)
Annex 3: Entitlements of Project Affected People
Compensation for Land Compensation for Structures Compensation for Crops & Compensation for Other Assets
Survey Name of Head of .Toal in DongNo. Household_Toa nDg
Quantity Unit Price Entitlement in Quantity Unit Price Quantity Unit Price Entitlemen Quantity Unit PriceSq. Sq. Meters Dong Sq. Meters Sq. Meters Sq. Sq. Meters in Dong q. Meter Sq. Meters
Meters I Meters I
Binh Son district
Binh Nguyen commune
1 Phung Thi Mai = = = __
2 Nguyen Chung Cur
3 Huynh Thi Vinh _
4 Huynh Cong _
Binh Trung commune
5 Phan Thi Nhan
6 Cao Van Su _ _____|_
7 V6 Van Thanh _ . .. ____
8 CaoThi____
9 Cao Van Kim _ _ r _ _ _
Binh Minh commune
10 |Nguyen Van DOrc 50 250.000 12.500.000 50 593.000 29.650.000 _ _ _ _ T 42.150.000
11 )inhVanThuy | 49,5 250.000 12.375.000 49,5 987.000 48.856.500 _ J | 61.231.500
12 |Pham Tai 25 250.000 6.250.000 25 399.000 9.975.000 _ _ _ I | 1 16.225.000
[inh Chirog commune
13 guy6n ThMi
FS on Doc Soi - Quang Ngai 220kV transmission line 68
Resettlement Action Plan (RAP)
14 NguynAn =_ = =
15 Nguyen Phu_ Ky
16 Pham Thi Yen _
Son Tinh district
Tinh Tra commune
17 Ooan Ng9e Linh 140 250.000 35.000.000 140 987.000 138.180.000 _ 173.180.000
18 Doan Thi Quyen 50 250.000 12.500.000 50 987.000 49.350.000 _ 61.850.000
19 D4ng Van Thanh 49,5 250.000 12.375.000 49,5 987.000 48.856.500 _ 61.231.500
20 D)ng Ng.c Tho 160 250.00 40.000.000 160 987.000 157.920.00C 197.920.000
guyen Chuang21 rinh 50 250.00 12.500.000 50 987.00 49.350.00Al 61.850.00C
rinh Binh commune
22 TranThanhPhong 150 250.000 37.500.000 150 987.000 148.050.000 ______ _ |_| 185.550.000
23 Trrang Thi Phu6c 84 250.000 21.000.000 84 987.000 82.908.000 103.908.000
24 Le Am 50 250.000 12.500.000 50 380.000 19.000.000 31.500.000
25 L Van Thanh 105 250.000 26.250.000 105 987.000 103.635.000 _ _ _ _____ 129.885,000
26 Do Van Lap 60 250.000 15.000.000 60 987.000 59.220.000 74.220.000
27 EO Van D6ng 60 250.000 15.000.000 60 987.000 59.220.000 74.220.000
28 Le Th9 250 250.000 62.500.000 250 987.000 246.750.000 309.250.000
29 6p mau giIo 30 250.000 7.500000 30 987.000 29.610.000 37.110.000
30 TrAn Thi Cuic 70 250.00 17.500.000 70 987.000 69.090.000 _ _ ____| | 86.590.000
31 TrircngVan San 100 25.00 25.000 .0001 700 98.700.000 _ _ _ _____ 123.700.000
jnh Son commune
32 hung Xuan Anh 120 250.000 30.000.000 120 987.000 118.440.00| 148.440.000
FS on Doc Soi - Quang Ngai 220kV transmission line 69
Resettlement Action Plan (RAP)
33 Do Tuan Sru 60 250.000 15.000.000 60 987.000 59.220.004 = = = _ 74.220.000
34 Tran Thanh Thuy 80 250.000 20.000.000 80 987.000 78.960.00 _ 98.960.000
35 D0 TAn Tai 80 250.000 20.000.000 80 987.000 78.960.000 98.960.000
Tv NghTa district
Nga Thing commune
36 Nguyen Ro 80 250.004 20.000.000 80 593.0001 47.440.000 67.440.00
37 JNguyAn Thi Thi 90 | 250.0001 22.500.0001 90 593.0001 53.370.0001 _ _ 1 _ | | 75.870.000
Nga Thuan commune _
38 W Thanh Tien 64 250.000 16.000.000 64 593.000 37.952.000 = = | 53.952.000
39 Nguy&n Thanh Hai 60 250.000 15.000.000 60 593.000 35.580.000 __ | 50.580.000
40 Nguy8n Thi Thur 42 250.000 10.500.000 42 593.000 24.906.000 | 35.406.000
41 LVan Tan 150 250.000 37.500.000 150 593.000 88.950.000 | 126.450.000
42 Le Thanh Long 90 250.000 22.500.000 90 525.000 47.250.000 | 69.750.000
43 V Van Diing 30 250.000 7.500.000 30 593.000 17.790.000 __| 25.290.000
44 Le Van Kim 200 250.000 50.000.000 200 593.000 118.600.000 _ 168.600.000
45 ran Tien 300 250.000 75.000.000 300 593.000 177.900.000 |252.900.000
46 Nguy8n Thanh Tam 80 250.000 20.000.000 80 987.000 78.960.000 | 98.960.000
47 Nguy8n Hong DVu 120 250.000 30.000.000 120 987.000 118.440.000 _ | 148.440.000
Nghia Ky commune I
48 |Nguy&n Thi Mqo | 80 250.000 20.000.000 80 593 .000 47.440.000 67.440.000
49 |Trunang Phi Khanh 200 250.0o0 50.000.00o 200 593.000 118.600.0001 _ _ _ _ | | 168.600.000
50 Nguy9n Bien 150 250.0001 37.500.00 150 593.000 88.950.00ol _ _ _ _ | | 126.450.000
51 __Nguygn Thong 90 250.0001 22.500.000 90 593.000 53.370.0001 | | _ _ _ | 75.870-oo
FS on Doc Soi - Quang Ngai 220kV transmission line 70
Resettlement Action Plan (RAP)
52 V6 Thi Lan 100 250.00( 25.000.000 100 593.000 59.300.000 = = _ = 84.300.000
53 V6 Van Thien 50 250.000 12.500.000 50 593.000 29.650.000 42.150.000
54 Le Thi Xuan DiOcre 50 250.000 12.500.000 50 593.000 29.650.000 42.150.000
55 Le Van Phu 70 250.00 17.500.000 70 593.000 41.510.000 1 59.010.000
56 Nguyen Thoa 70 250.00 17.500.000 70 593.000 41.510.000 59.010.000
57 Nguyen Thj Tuang 40 250.00 10.000.00C 40 593.000 23.720.000 33.720.000
58 Nguyen Van Hu8 48 250.00( 12.000.00C 48 593.00 28.464.000 _ 40.464.000
59 Nguyen LQng 80 250.001 20.000.00 80 987.00 78.960.00 f__
_98.960.000
Nghia Hanh district
Hanh Dung commune
60 Tran Van
61 Tran Thanh Xuan
62 Tran Van Min
_ __
63 Nguyen Thi Nhi
64 TrAn An _
65 Tran L^p _ |
Hanh Minh commune
66 Pham Van Le 80 250.000 20.000.000 80 987.000 78.960.000 _ 98.960.000
67 Pham Yen 152 250.000 38.000.000 152 987.000 150.024.000 1 88.024.000
68 iTrAn On 30 250.000 7.500.000 30 399.000 11.970.000 ____ 19.470.000
69 L6 Thi Thuan 70 250.000 17.500.000 70 593.000 41.510.000 __|
59.010.000
70 HVanLuat 120 250.000 30.000.000 120 987.000 118.440.000 _ _ _ _ | | 148.440.000
71 Tran Thi Mai Khanh | 100 250.000 25.000.00 100 987.000 98.700.0001 _ _ _ _ _ | 123.700.000
FS on Doc Soi - Quang Ngai 220kV transmission line 71
Resettlement Action Plan (RAP)
72 L6 Thi Em 50 250.000 12.500.000 50 593.000 29.650.000 =_== 42.150.000
73 Lucng Chau 100 250.000 25.000.000 100 987.000 98.700.000 123.700.000
74 Nguyen Vani Khiem 100 250.000 25.000.000 100 987.000 98.700.000 _ 123.700.000
75 Luu Thi Hao 80 250.000 20.000.000 80 987.000 78.960.000 _ 98.960.000
76 tru Thi Dgri 80 250.000 20.000.000 80 593.00 47.440.000 67.440.000
77 Vo Thi QuAng 150 250.000 37.500.000 150 987.000 148.050.000 185.550.000
78 Ho Van Doan 40 250.000 10.000.000 40 399.00C 15.960.000 25.960.000
79 Iran Thanh 50 250.000 12.500.000 50 593.000 29.650.000 42.150.000
80 TrAn Bang 120 250.000 30.000.000 120 987.000 118.440.000 _ 148.440.000
81 rran Nong 60 250.000 15.000.000 60 593.000 35.580.000 _ 50.580.000
82 rAn Diing 20 250.000 5.000.000 20 593.000 11.860.000 16.860.000
83 rAn Minh DMc 50 250.000 12.500.000 50 593.000 29.650.000 42.150.000
84 Tran Quang 70 250.000 17.500.000 70 593.00 41.510.000 59.010.000
85 ir Phi.r6c 50 250.000 12.500.000 50 593.000 29.650.000 42.150.000
86 Tr Van Hien 70 250.000 17.500.000 70 593.000 41.510.000 59.010.000
87 Ho Thi Kim Anh 80 250.000 20.000.000 80 593.000 47.440.000 67.440.000
88 T Loan 60 250.000 15.000.000 60 593.000 35.580.000 50.580.000
89 Tr Phuang 70 250.000 17.500.000 70 593.000 41.510.000 _ 59.010.000
90 ran Giang 50 250.000 12.500.00 50 593.000 29.650.000 _ 42.150.000
Hanh Thien commune
91 lTrlang Bich 50 250.000 12.500.000 50 | 987.000 49.350.000 | 61.850.000
92 JL Van Tu | 25 250.000 6.250.0001 25 | 202.000| 5.050.001 _ _ 1 _ | | 11.300.000
Hanh Thinh commune
FS on Doc Soi - Quang Ngai 220kV transmission line 72
Resettlement Action Plan (RAP)
93 Huynh Thai My 60 250.000 15.000.00( 60 593.000 35.580.000= 50.580.000
94 DAo Thi Thiu 70 250.000 17.500.000 70 593.000 41.510.000 59.010.000
95 Nguyen Mau Thai 25 250.000 6.250.000 25 399.000 9.975.000 16.225.000
o6 DOc district
Dirc Phu commune
96 TrAn DOng Ba 40 250.00 10.000.000 40 593.000 23.720.000 =_=_= 33.720.000
97 1Tran DEuc Ngoc 25 250.000 6.250.000 25 593.000 14.825.000 _ 21.075.000
irc ]hong commune
98 Huynh Thi Ky
99 Nguyen Van Th6ng
100 Pharn Hr6ng
FS on Doc Soi - Quang Ngai 220kV transmission line 73
Resettlement Action Plan (RAP)
Annex 4: Socio-Economic Household Data Sheet of Project Affected People
Ethnic Occupation and Sources of ~~Estimated TotalNo, Address of Household Name of Household Member Sex Age Group Educationti dSourcesof Em I Income aprYa
secondary Agriculture1 Phung Thi Mai Female Kinh school 12.000.000
Male secondary Agriculture
2 Nam Binh village - Binh Nguuyen Nguyen Chung Cu Kinh school 13.000.000
commune - Binh San district secondary Agriculture
3 Huynh Thi Vinh Female Kinh school 20.000.000
Male secondary griculture4 Hu'nh Cong Kinh school 11.000.000
secondary Agriculture5 Phan Thi Nhan Female, Kinh school 22.000.000
Male secondary Agriculture6 Cao Van Sur Kinh school 15.000.000
Phu Le village- Binh Trung commune - Male secondary Agriculture7 Binh San district Vo Van Thanh Kinh school 10.000.000
Male secondary Agriculture8 Cao Thi Kinh school 15.000.000
secondary Agriculture9 Cao Van Kim Male Kinh school 20.000.000
secondary Agriculture10 Nguyen Van D(rc Male Kinh school 12,000,000
Tay Phir6c village- Binh Minh commune- Male secondary Agriculture
1 Binh Son district Dinh Van Thuy Kinh school 13,000,000
Male secondary Agriculture12 Pham Tai Kinh school 11,000,000
NgQc Tri village - Binh Chirang secondary Agriculture
13 commune - Binh San district Nguyen Thai Male Kinh school 12.000.000
Male secondary Agriculture14 Nguyen An Kinh school 13.000.000
FS on Doc Soi - Quang Ngai 220kV transmission line 74
Resettlement Action Plan (RAP)
Male secondary Agriculture15 N guyen Phui Ky Kinh school 11.000.000
secondary Agriculture16 . Pham Thj Yen Female Kinh school 12.000.000
secondary Agriculture17 Doan Nggc Linh Female Kinh school 25,000,000
18 Doan Thi Quyen Female Kinh primary school Agriculture 6,000,000
Tra Binh village- Tjnh Trai commune- Male secondary Agriculture19 San Tinh district cE)ng Van Thanh Kinh school 20,000,000Son Tinh district Male secondary Agriculture20 .4ng Ng9c Thor Kinh school 11,000,000
Male secondary Agriculture + Service21 Nguyen Chuang Trinh Kinh school 30,000,000
Male secondary Agriculture22 Tran Thanh Phong _ Kinh school 18,000,000
23 Truang Thi Phu6c Female Kinh primary school Agriculture 15,000,000
24 Le Am Male Kinh primary school Agriculture 10,000,000
Binh Bac village- Tjnh B'mhi commune- 0Male secondary Agriculture25 San Tinh district Le Van Thanh Kinh school 15,000,000
26 670B Van Lap Male Kinh primary school rade 20,000,000
Male secondary Agriculture + Trade27 .6 Van DOng Kinh school
Male secondary Agriculture28 . _________.._____._____ ...._____ L8 Th_ Kinh school 20,000,000
29 Nha mau giAo
Binh Nam village- Tinh Binh commune- _ secondary Agriculture + Trade30 San Tinh district Tran Thi Cuc Female Kinh school 30,000,000
Male secondary Agriculture31 TrLrrang Van San Kinh school 15,000,000
32 An ThQ village - Tinh Son commune - Phng Xuan Anh Male Kinh high school Agriculture 13,000,000
33 San Tinh district O Tuan Sru Male Kinh college Agriculture 20,000,000
FS on Doc Soi - Quang Ngai 220kV transmission line 75
Resettlement Action Plan (RAP)
Male secondary Agriculture
34 . Tran Thanh Thuy Kinh school . 20,000,000
Male secondary Agriculture
35 . Oo Tan Tai Kinh school 15,000,000
secondary Agriculture
36 D6ng Thang village- NghIa Thang Nguyen Ro Male Kinh school
commune - Tu Nghia district Agriculture37 N________________ guyen Thj Thi Female ____ Kinh giutr
Male secondary Agriculture
38 Vo Thanh Tien Kinh schoolMale secondary Agriculture+ bricklayer
39 Nguyen Thanh Hai Kinh school 15,000,000
secondary Agriculture
40 Nguyen Thj Thur Female Kinh school _
41 Le Van Tan Male Kinh high school Agriculture 23,000,000
Male secondary Agriculture
42 Le Thanh Long Kinh school .
Male Kinh secondary Agriculture
43 o6 Van Dung school 21,000,000
My Phui village- NghTa Thuan commune- Male Kinh secondary Agriculture
44 Tu Nghia district Le Van Kim school 20,000,000
45 Tran Tien Male Kinh high school Agriculture 20,000,000
46 guyen Thanh Tam Male Kinh high school Agriculture 23,000,000
47 Nguyen Hong Du Male Kinh griculture 25,000,000
Phu San village- Nghlia Ky commune- Kinh secondary Agriculture
48 Tu NghTa district Nguyen Thi Meo Female school 20,000,000
Male Kinh secondary Agriculture
49 Trtrang Phi Khanh school 10,000,000Male Kinh secondary Agriculture
50 Nguyen Bien school 47,000,000
Male Kinh secondary Agriculture
51 Nguyen Thong school 40,000,000
FS on Doc Soi - Quang Ngai 220kV transmission line 76
Resettlement Action Plan (RAP)
Kinh secondary Agriculture
52 Vo Thi Lan Female _ school 22,000,000
Kinh secondary Agriculture
53 Vo Van Thien Male school 15,000,000
Kinh secondary Agriculture
54 Le Thi Xuan Diunc Female _ school 10,000,000
55 L8 Van Phu Male Kinh primary school Agriculture 15,000,000
56 Nguyen Thoa Male Kinh primary school Agriculture 20,000,000
57 Nguyen Thi Thbng Female Kinh primary school Agriculture 15,000,000
secondary Agriculture
58 Nguyen Van Hue Male Kinh school 7,000,000
secondary Agriculture
59 Nguyen L,ng Male Kinh school 25,000,000
secondary Agriculture
60 Tran Van Male Kinh school 18.000.000
61 TrAn Thanh Xuan Male Kinh High school Agriculture 8.000.000
Hanh Dung commune - Nghia Hanh secondary Agriculture
62 district ran Van Man Male Kinh school 16.000.000
63 Nguyen Thi Nhi Female Kinh High school Agriculture - 15.000.000
64 Tran An Male Kinh primary school Agriculture 10.000.00o
65 _________________________________ Tran Lap Male Kinh High school griculture 12.000.000
66 Phii Binh village- HAnh Minh commune- h,m Van Le Male Kinh high school Agriculture 27,000,000
67 NghTa Hanh district Ph,m Yen Female Kinh college Agriculture 25,000,000
secondary griculture
68 Trran On Male Kinh school 8,000,000
69 Long Bin Bac village- Hanh Minh L8 Thi Thuan Female Kinh high school griculture 15,000,000
commune- NghTa Hanh district secondary Agriculture
70 Ho Van Luat Male Kinh school 17,000,000
71 Tr_an Thi Mai Khanh Female Kinh high school Agriculture 18,000,000
72 Long Bin Bac village- Hanh Minh L Thi Em Female I Kinh primary school Agriculture 8,000,000
ES on Doc Soi - Quang Ngai 220kV transmission line 77
Resettlement Action Plan (RAP)
73 commune - Nghia HAnh district Luang Chau Male Kinh high school Agriculture 16,000,000
74 Nguyen Van Khiem Male Kinh college Agriculture + state officer 15,000,000
75 .Liu Thi Hao Female Kinh college Agriculture + state officer 10,000,000
76 Luu Thj DOi Female Kinh high school griculture 12,000,000
77 Vo Thi QuAng Female _ Kinh primary school Agriculture 35,000,000
Male secondary Agriculture
78 Ho Van Doan Kinh school _ 17,000,000
79 Tran Thanh Male Kinh high school Agriculture + carpenter 20,000,000
80 TrAn Bang Male Kinh high school Agriculture + tailor 20,000,000
81 Tran Nang Male Kinh high school Agriculture 30,000,000
Male secondary Agriculture + Trade
82 Tran Dung Kinh school 25,000,000
83 Tran Minh Dfic Male Kinh high school Agriculture + Tailor 18,000,000
84 Tran Quang Male Kinh high school Agriculture 30,000,000
Male secondary Agriculture
85 Tur Phtx6c Kinh school 20,000,000
86 Tu Van Hien Male Kinh high school griculture 18,000,000
87 .Ho Thi Kim Anh Female Kinh college Agriculture 20,000,000
88 Long Ban Nam village- Hanh Minh Tu Loan Male Kinh high school Agriculture 23,000,000
commune -NghYa Hanh district Male secondary griculture
89 .Tr Phucang Kinh school . 20,000,000
Male secondary Agriculture + Tailor
90 Tran Giang Kinh school 20,000,000
91 Phui Lam village - Hanh Thi8n Truang Bich Male Kinh primary school Agriculture 23,000,000
92 commune- NghTa Hanh district Le Vin Tir Male Kinh primary school Agriculture 8,000,000
Male secondary Agriculture
93 Hoa iuan village- Hanh Thinh commune Huynh Thai My Kinh school 15,000,000
94 - NghIa HAnh district DAo Thi Thu Female Kinh secondary school griculture 15,000,000
95 Nguy8n Mau ThAi Male Kinh secondary school Agriculture 13,000,000
FS on Doc Soi - Quang Ngai 220kV transmission line 78
Resettlement Action Plan (RAP)
96 Phtnc Hoa village - D(rc Phu commune -Tran D8ng Ba Male Kinh primary school Agriculture
97 Mo DOic district Tran Dirc Nggc Male Kinh primary school Agriculture 15,000,000
secondary Agriculture
98 Huynh Thi Ky Female Kinh school 23.000.000
Chau Me village - DOrc Phong commune - secondary Agriculture
99 MO DOrc district Nguyen Van Thong Male Kinh school 14.000.000
secondary Agriculture
100 ._____________________________ Ph.m Hu6ng Male Kinh school 15.000.00
FS on Doc Soi - Quang Ngai 220kV transmission line 79
Resettlement Action Plan (RAP)
APPENDIX 5. MINUTES OF PUBLIC CONSULTATION
FS on Doc Soi - Quang Ngai 220kV transmission line
CONG HOE k XX HQI CHIJ NGHIA VI$T NAMDoc lp - TV do - H?nh phiic
£,-.-.C4ng6y .. thdng..O..ndm 200.5.
BItN BAN THAM VAN CQNG D(6NG
V* KX HOACH DEN Bt VA TAI DINH CU
Thanh phan tham dV-.
1. Di diOnUBND ...... ..... ke . .& .......
2. Nhmgngxubi Anh hu6ng: . Nam ...... . fi Nr .
3. Dai dion Cty TVXD Din 4: ........ .......
Cac van di tham vAn cQng ding:
1. Pho bitn nhirng chinh sich lien quan dtn dAn bit, t£i djnh cwr.
- Nhfng khu vrc tnmg dung dAt cho dy in.
- DII kidn th&i gian ti6n hinh cho d, an.
- Pho bitn cic chinh sach cfia ViEt Nam vA WB.
- Cic quy djnh phap luit ViEt Nam vi chinh sach WB c6 li8n quan.
- Cac chfnh sach dEn bA cho Dv an.
- CUc khu tai dnh cu (n6u c6).
2. 't kidn cfia dia phumng v& k6 ho#ch dn bii va tai djnh cwr
- Kh4 natng4xy ra Anh hw&ng bAt Ii cfia d dn
+ D& v6i nha c*a: ............ </Z~~~~~~~~~~~~~~~~~~~~~~~..............................................;
...................................... i.............................................................
+ D36i vri dt dai: ...... c ... ... . ...... 4: .... ....................................................................................................................................
.............................................................................................................................
+ DWi v6ri edy A F ...... ... ds. A. .;0 ...................
.................. ...... *^ M ;....... y...................................................
+ D6i v6i m8i tnrung tkr nhi6n, xi h8i: .
' Cdc bip gidm thi: 1.z@................~~~~~~~~~~~~~~~~~~~~~~~~~~...... <;. s.. <L. a z.. @C...........
! ~~~~Cdc bign php gifm thlb.:
Il
+ Trong giai doan ~itti ~~~F__
I~~~~~~~~~~~~~~~~~~~~~~i ........ ............ .........
+ Trong giai dopn thi c8ng: ....
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ .. ~~~~~~~~~~~~~~~~~~~~~~~~~~~~
...... ........... . .. .. .
.......... ......... ..... .................. ...............................
+Trong galdo n v hinh Z. 64~L~ ............. ........ ...
+ rn iidv ditk:................ .ff. ..... .. 5... 4.. e-.;... . . . . . . . . . . . . . . . . .. . . . . . .. . . . . . . . . . . . . . . . . . . . . .. . . .
- Cdcphtrung dnc~n biiquy trinh,chiitrd &i.ze bzt: 5
+ Gia' d-n bi' hinh th'c' den b .1':.......... . ..-... .
..... v , ................... i........
+Togga onicn:.................n ... .. .............
+ Th?,i gian thvrc hie-n chi trA den U:.* s aX' ........... ... '
. .Q . . . . . . . w....... . . . . ....................--.-.-!---.---'---.--------.............'---.-'--.--.-.-
+ uy ch4 ki6u n~Li giam slit: .....
........... ....................................... ....................................... ........................................... .
X-ac nh4n cnia dii di' i XAc nhr inia nguni 'anh hb-.ng
Cng ty Tir van Xfiy dhhng Dic n 4
Xi'.tij.h aa.lii h quy"n dca phiro'ngX#~~~~-
................. .................................................................................
+~~~L Qu ch iun ii ft .......... ;
I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~CONG HOXA XA H6I CHtU NGHIA VI3T NAM
DQc Ip - Tvr do - H anh phiic
BI1EN BAN THAM VAN CONG DONG
Vt KF HO4CH DPN BU VA TAl DINH CLY
, .i,, ngay ~tt ............ thdng m9'.nQm 20Oc7
Th?anh phan tham du:1. idi n I UBND: .............. ....... ..............
2. Nhttng ngtri bj Anh htr&ng: .............. Na.. .... Na .fN....
3.Dai dien C6ng ty TVXD Diein 4: .... r', .......A~~~~
Ca cc van di tham va n:1. Pli bien cdc chin!h sach lien quan idn -een bii - tdi SinIi cu:
-Nhn khuvgctnxngdingdatcho du an.- Du kien ti gian ti8n hanh cho dr an.
- Phc biEn cac chinh sch cuia ViWt Nam va WB.
- Cac quy dinh phap lu.t Viet Narn va chinh sdch WB co li8n quan.
- Cac chinh sach den biu cho du an.- Cac khu tai dinh cu (neu c6).
2. kit4n cfa dia ph wong vi kl hogchl een biA vil idi dinh cit
- Khd ndngxdy ra nhrmg anh hrt6ng bdt li cta dVa an:. -
+ D6i v6i nha cira:................................................................................................................................................................................................................................................... ................................. ...
~~~~~~~~. .... ............................................................ ................... ..... .+ DOi v6i dat dai: .... . .... ..........
.................................................... .. .............. .......... ............ .......................... .--'----!-----------------
....... ....... ....... ....... ....... ........
... . . . . .. . . . .. ... .
+ O..............c........i.... .w*...................J.C ;.s.c2,.... **..,...................
+ D6i v6i cfy c&i ... C/
........ A 3ivV itlI urlEn- xa h i .............................................
+ 'i v6i m6i tr-6ng t- -hien - x-- h. .......................i
~~~~~~~~~~~~~~~~~~~~~~~............ ..... .'.. ./.<
.
. ..~~............................ ............................................................................- C&c bien phap ;idin thieu:+ Trong iai doan thief ke: ........... .. .............
.......... .
. . . .+ .. . . . . .. . . . . . .. . . .......... ......
+Tongga "a ico :................. ............................. ...................................
+ r n iid P tl '........... .. A... . 4. . '............................ g................. ....................................................................................
+Trng ai oa 3ihuh ................ -.................. ........ ... ...............+Trong giai doan vbn h?tih: ............ .......,. .G.'...... -M ~~~~~~~~.. 1~~~~~~~~~~7 "0~~~~~~~~
.................... .................. ....................... hi- C gciphtrong a n ibu, uy trinh chi .rd . n bic:
.... . .............. ..t7.................................. u......................................................................... .............................+ u h h t n t,g i d :............................ . ... . ....................
........................................................ .................................................
........................................................ .. . . . . . . . . . . . . . . . . . ... .. ..
X|ic nh#an ciua C8ng ty TVXD Dion 4 XiYc nh4n cfia n gr&i bi anh hiru6ng
X 2c nhfin cfia chin h qay Fn d' phiromng
cYX,
CQNG boA XX H(I CHU NGHIA V]LtT NAMDQc 1Ip - TV do - Hanh phfuc
7 ... , , ng&y. %4th4ng. .... 'ndm 2005OBItN BAN THAM VAN CONG D6NG
Vt Kt H04CH DtN BJ VA TMI DI.~~~~~~~~~~~~~A NH.'Thuanh phin tham dtr:
1. i).ai dign UBND~~~~~~~~ .............. P . ... .4t.. -.N4--.......--...t;.1. DOi din UBND A4e1 A ... . 1.
2. Nhiing ntr?y inh hi6ng: ..................... . ... Nam .; .. Nit :
3. DOidi8n Cty TVXD Di8n 4 .. ....................... t,¢..
Cac van de tham van c-ng dIng:
1. Pho bien nh*ng.chinh saich liEn quan den den buz,taii dinh cir.
- Nhuing khu wc trmg dung dAt cho dy in.
- Dv kien thbi gian ti4n hinh cho dy an.
- Pho bi6n cac chinh sach ceua Vi8t Nam va WB. -.
- Cac quy dinh phaip lu4.t Vi.t Nam va chinh sich WB c6 lien quan.
- Cie chfnhsach dan bui cho DV in.
- Cic khu tai djnh ct (n4 u c6).
2.4 kien cu.a dja phxrong ve kA hoach den bui va tai dinh car:
- Kiht naitg xdy. ra dnh' hw,&ng b1t ISi cuia dw adn
+ Doi vai nha era: ............. .
................. ... ,... ...... f;.. g.
................
+ Oi vi dat daiy ..........z..s... .... .
... ... ......... ..... ... ........ .... t. ........ .... .. .......... w...... . ....... .... .. .... .. ..... ... .v... ..... .. .... .... ..... .. .........
+Oivicyci................ .fi .. o 4/ : ..-....
+ ^ 6 i 6 :......... ;............................ ..........................
+ D Oi i 6 trr g t% nh n,x H i:....................................I............. .......... ,............:+ E)oi v6i moi tnrbng ty nhien, xa Hoi:.*
~~~~~~el 4 ....... ...... .... '. '....zk.......................................................................................................................................
-Cdc bi?n ph ap giam thiiSu:
~~~~~~~~~~~~~~~~~2.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
+ Trong giai doan thiet c :....
... ~ A1 .. ............................................................................. ..........................................................................+ Trong giai dop thi c6ng: .... cwr-g:---x ...$V.;4 .. /A4.g-gr--- w:C./ - - i;-
............................................................................... ................................................................................................-
+ Trong giai doen v#n hinh: ......
~~~~~~~~~~~~~~~~.... J8. 7. ~~~~~~~~~~~................... ....................... ............................................-..-
- Cdcphwang an den bi, quy trinh chi tra An bit:+ Gia den b?i, hinh th*c d&n ba: ...... 2!* . -. I4.i-
...... ~~~~~~~~~~~~~~~~~~~~~~r . <.g?......... r--&-a-................ ... .. L.. .
.......................................................................................................................................
+ Thbi gian thyc hi,n chi tra d&en bu: ...... a ' ................ ,d -,: .... 4 L:,~ .. 104 . .............. ;s........e ........../~~.......................................................................................................................................
+ Quy che kieu nai giam sat: .......... ................................................................................................................... ...................................................................................................
......................................................................................................................................
Xac nhan cfia dai dion MXac nhan cuia ngtr&i Anh hir6ngC6ng ty Tir van Xfiy dyng Di?n 4
7L~~~XC u x
C?NG HOA XI HQI CHU NGBIA VE$T NAMD§c I4p - Ty do - Hanh phuc
lf,6U-7%2 ngay q..thing .. q..n&n 200L..
*BIN BAN THAM VAN CQNG D6NG
Vt Kt HO4CH DtN BLU VI TAI BINH CU'
Thinh ph&n tham dy:.
i. Dai dit n UBND :.4 :d .... ......... sfi. .......... ................2. Nhttg ngubi inh huig. .................. Nam .... Nil
3. Dai di8n CTVXD Dien 4:.& ......................... ....7....
Cic van de tham van cong ding:
1. Ph6 bien nhfrng chinh sich lien quan dtn den biu, tii djnh 'cr.
- Nhitng khu vuc trnmg dug dt cho dr n.
- Dv ki&n thbi gian ti6n hAnh cho d fin.
- Pho bien cic chinh sdch cila ViOt Nam vi WB. -
- Cic quy djnh phUp 1u0t ViOt Nam vi chfnh sich WB c6 li&n quan.
- Cic chlnh sich d&n bit cho Dy in.
- CAc khu tAi dnh cu (nuco).
2. Y kien cfia dia phung vt kg hoqich din bi via ti dinh cr:
-Khd ndngxy radnh hz g bdtlg cia dwdn
+ DOi vWi nhA cfa ... ... e..f ... I, a ....
.aac;. ........... ................................................ i...... ...................................................
....... ........... - ...................................................... .................... &+ v6i dt dai: ......le$.... .. e.. ....
.................................................................................................................................
...................................................................... ...........................................................
+ DOi v6i cay A.: ..................... .
.................................................................................................................................
............................................................................................................... ...........
+ DOi vri m6i tnrung tV nhien, hOi: ;..
W p
-* ' Cdc pha guim thien......................
- Cdc bi?nphgp gidm thlzu:-
+T.rong giai ioan- thiet ke: ....
*+ Trong giai dopn thi c6ng: ......... /Ay
-7.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
+ Trong giai dopi v An hbhL.V.,..A 1..4"A
+Tronggiaidoan^iftke ~~~~~~................ X. 2... .. .;.7s.......... ....7. ;.. .............
~~~~~~~~~~~~~.. 2.. .te.. S... 4. ft,aW.ah .2/....... ... ~~~~ gy/ 9~ . g. ;k,,s.(
+ Trong giai ......................... ......... o..n...................... s /. G .gz.7A ............ .. ..N....
....................................... ............. I..................................................................................
+......... T............................................X....i...s ....A...........o..~~~~~~~~~~~~~~~~~~~~~~~~~~~~. ... sA.. z .... ..... .. .. .- Cdc pinning ani deAn bfi, quy trinh clii tradjtn bi:
+ Gia den bui, hinh thu~c den u .......... ^ . w. ; .:
......................................................................................................
..........................
............................................................... ............................................................................
......................................--+ ThbixgianA thurc hi8n chii tii den bu ........... o. '.PHs.. :
+ Quy che kieL nai giam sat: ...... C ., la /4
...4'a7i...AL..+....,+.. U.. j o.... * r-........................................ ........................................................ ....................................................................................................................
Xfc nh.an chia da; di8n Xac nh4n ciua ngzr6i inh hur&ng
C8ng ty Tvr vin Xfiy dyng Dion 4
Xficnhban ciua chinh quyen lia phriong
-/ UE D X .t'i Tc
MI,
C Q NG HOA Xi HQI CHU NGHIA VI.T NAMDc l4p - TXr do - Hanh phfic
BtIN BAN THAM VAN CQNG D6NG
VE Kd HOACH DtN BU VA TI DINH CIU
MhA .7Z4, ng&y ......... thdng ... .. neam 200$
Thanh phkn tharm dir: ' '
1. D)i di4n IJ13ND1: ............. e K 7-ao............. ; .... ... ..........
2. Nhlg ngtxbi bi tnh hu6ng: ................... A .. . .Nam . . NCl.d,
3.Dii di8n C ng ty TVXD Diin 4: .......................
Cic van di tham van:1. Phg bien cdc chfnh sdch BiEn quan din dn bAi - idi djnh ci':
- NhAng khu vvc trimng dpmgd&t cho dy an.
- Dth?i gianti&ihhnh cho dg fLn.- Pho bi& cAc chfnh sich c-ia Viet Nam va WB.
- CAc quy dinh phip luSt Viet Nam vi chinh sAch WB c6 li8n quan.
- Cic chinh sach d6n biL cho dlr an.
- Cic khu tdi djnh cu (niu c6).
2. J lkien cia aTa phweng vi ki ho ckh dn bit va' idi dlnh cwr
-Khdnangxayranhirnganhhwngbadtlicuaad4dan: -
+ D6i v6i nhA cra: ..........................................................................
......................................................................................... ;.................
.........................................................................................................+ D&6 v 6i dhit dlai: ....4gSc.. u0ji Z.A.. ... 444..-7AlH .............................
............................................................... :.................... I......................
................................................. ............................................................................ . ..............
.. .. . .. .. . .. ...
+ D i v6i cay c6i: ......... ... .......................
..................................... .. . . . . .. ... . . . . .. . . . . . . . . . . . . .
.................................... .....................................................................
.........................................................................................................+ D6 i v6im8i trut g tW nhien - xie hoi:................................................
...... ... iZ .. e8< .<^i ... C;; afU .a64 .lZ.' . Ey.#F
........... . a"' , ... ................... -, ~~~..........................................I....................................... ........................
- Cdc biOn phdp giam thieu:+ Trong giai doan thi& k :/ .....k.............. .....................
......... .. _.' ~. ................* - -- - - -- * - - ;-/g* -r-/4 / - * - o- -*Z *- q to,................
+ Trong giai doog .tb..c.ng' . -................................. :..
............. jA 1....... .. . .. .. .
.................. 7 ................................... ... ...................................................+ Tron g oa v 2 bira:...<;;g;7...Sit''c8X .................. .. ...b#>2..........
+Trong giai doan van hhnh: .. j; ` *.
.......... .. L.. .....
.~~~~~~~~~ . . . . . . .. . . . . . . . . . . . . . . . . .
........ ............ vvo. .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
::c jhn c acphCrong atn Xdn bu, uy trinh4chi tra d nn bu: g b; bi hn tc den biha: ......c h quy.n .. phiri
,...................... w.................. ........................................ ........................
. . ......~~~......... .............................................................................................. Q. uy.. che.. kdhi.u.. nai,.. gia.m.. sat:........................................... ..
. .. ... .
........ ... ... ......................................... ........................................
....... ........ ----- '-------------------- ......................................... ................................ .. . . . .
X ac n hft n c'ua C 8n g tOy TVXD%El DiV^n 4 X fic n h an'cfi a n guri bi, i nh htrkn g
;~ ~ ~ ~~fcng facihqyndapw-7bE_- *~~~~~~~
T/CHi', '~~~~~~~~~~H X Sr'ilz .' , , sX~~~~~~~~~~(a
!~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
CQNG HOA XX HQI CHt NGILA VWtT NAM
DUc14p -Tir do -H#nhphfici
Lc6l.~2, nghy:tL4th6.ng. ... nrun 2005.
GakY XAC NHA4N
* ~~~~V/v "X&~ nh4n c6ng bo' th6ng tin kd hoq(Whd& bi tt6i dinh cw' (RAP)
cho du 6n: Dza3ng ddy 22 OkVD6c S6i - Qucing Ngdi"
Dai diEn UBNDxa ..... .. a ez. .............................
Dai dien C6ong t.y Tu vAin X-ay d1rng Di8n 4
Nay C6ong ty Tir vin XMy dVrng DiEn 4 da c6ng b6 th6ng tin ve' k6 hoach de^n
bfi tAi dinh cir cho dir An: Dir&ng dai y 220kV D&c S6 - Qu'ang Ngli
Trong th6i gian.•......................+ 1i212( ~
V4y kfnh d& nghi UBND xa . .hL$ . J~),.xdc nh,~n C -ng ty Tir vAnX&y d~rng
Di8n 4 da c6ng b6th6ng tin tr6n.
Daii dion do in c'ong tic D#i di~n chinh quyin dia phro-ng
.~~j~•7. . .~X?.
~.k
CQNG HOX Xi HOI CHJ NGHIA VItT NAMDQc lap - Tu do - Hanh phuc
----------o0o0--------flk)nt.NaW ' ngyy..tl ing..T narn 2005.
GIXY XAC NHANV/v "Xac nhadn c6ng bo' th6ng tin ke hooch d&n biu tai dinh ct (RAP)
cho dw an: DOcung ddy 22OkVD6oc S6i - Quang Ngai"
Dai di8n TJBND xa ... ECoh. Nqu ....................................................Ong ...). ........... .. .....Dai dien C8ng ty Tu vin Xay dyng Dien 4
Ong (ba) ...... r .IkA. . 1 xn h ................. ;
Nay Cong ty Tu van Xay dung Dien 4 da c6ng bo th6ng tin ve ke hoach den
biu tai dinh cu cho du an: Dtr&ng day 220kV Doc Soi - Quing Ngai
Tai .... AU1 2.X~ .................. ............... ' ;.............
Trong thbi gian ...... ... & . .......J.JQ./.......
Vay kinh d nghi UBND xa &;ch. li . ..... xdc nhOn CUng ty Tu van Xay durng
DiWn 4 d cong b6 th6ng tin tren.
Dai diEn doan c8ng tAc D)ti divn chinh quyen dia phirong
/ li !' -1< \P'0 YCAO QH TICEk
TrudngWb7haczfJM 2l/'-'
* 5
...... ph'tt
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~......
CONG HOA XX H(I CH[J NGHLA VIET NAM
DQc lap - Tiy do - Hanh phfic-oOo---
-.0 AI I ngy.1 ilth-ng. B.. nam 2005.
GLY XAC NHANV/v "Xac'nhan cong bo thong tin ke hoach den bu ta dinh cw (RAP)
cho dut an: Dw&ng ddy 22OkVDoc S6i - Qu6ng Ngai"
Dai dien UBND xq ........... . ... . . . .
Ong (d) ............... 1 .. It6 .... .
Dai dien Cong ty Tu van Xay durng DiEn 4
6ng 9 fa) ....... V- u ..
Nay Cong ty Tu van Xay dung Di6n 4 da c6ng b6 th6ng tin ve ke hoach den
bui tAi dinh cir cho di ain: D)wrng day 220kV Doc Soi - Quang Ngai
Tai .... i AD,, ... X ct^2 ........... ............... .............
Trong th&i gian .... I. .. .. .4.. b..... ... .....&.. ..
V^y kinh de nghi UBND xa .. .Xt.L ...xac nhan COng ty Tu van Xay duxng
Di3' ;n 4 da c6ng b6 th6ng tin tren.
Diii dion doan cong tic air g
Vlt~~~~~~~~ JA,- ~ ~ ~ ~ ~ ~ IA71~
, tG&*tL-
-1' W a ai. .>v.d: ~~~~
/ ~ ~ ~ ;Gg.~~~~/~~~~~~~~~~~~~~~~
-� - - � t � r�trrr �; itt; qr