GLAST Large Area Telescope Gamma-ray Large Area … Large Area Telescope ... SSD Ladder Assembly...
Transcript of GLAST Large Area Telescope Gamma-ray Large Area … Large Area Telescope ... SSD Ladder Assembly...
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 1
GLAST Large Area TelescopeGLAST Large Area Telescope
Lowell A. KlaisnerStanford Linear Accelerator CenterLAT Instrument Project Manager
GammaGamma--ray Large ray Large Area Space Area Space TelescopeTelescope
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 2
Status Status –– Transition from Design to Flight HardwareTransition from Design to Flight Hardware
• Design is mature – Instrument Architecture frozen– Some open engineering and manufacturing issues
• Costs reviewed – US budget for the Fabrication Phase is $133 M– DOE/NASA Joint Oversight Group approval– International Finance Committee
• Infrastructure is in place– Staff with experience in space instrumentation and
experience in HEP detectors– New integration and test facility at SLAC– Working relationships between the NASA Mission Office,
the LAT Project Office, Collaborators and foreign partners in place
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 3
•Objective: Larger field of view (FOV), higher sensitivity, and broader energy detection range than any previously flown gamma-ray mission.
•Mission Duration: 5 yrs (10 yr Goal)•Orbit: 565 km Circular, 28.5° Inclination•Launch Date: February 2007•Launch Vehicle: Delta 2920H-10•Launch Site: Kennedy Space Center
GLAST MISSION SUMMARYGLAST MISSION SUMMARY
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 4
LAT
GBM NaI Sensors
GBM BGO Sensors
+Z
+X +Y
LAT Radiators
GLAST Observatory
Solar Array
Spacecraft
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 5
Instrument StructureInstrument Structure
Anti Coincidence Detector
16 Tracker Modules
Grid
16 Calorimeter Modules
Electronics Modules
Radiators
Mass 3000 KgPower 650 Watts
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 6
LAT Organization ChartLAT Organization Chart
Principal InvestigatorP. Michelson
Instrument ScientistS. Ritz
Senior Science Advisory CommitteeN. Gehrels
Collaboration Science Team
Project ManagerL. Klaisner
D. Horn, DeputyJ. Martin, Deputy
Instrument Advisory CommitteeS. Kahn
Instrument Science PerformanceS. Ritz
AdministrationDebbie NicholsonProject Controls
T. BoysenQA & Mission Assurance
D. MarshManufacturing
J. Clinton
Chief EngineerL. Klaisner, Acting
System EngineeringD. Horn
TKRR. Johnson
Mechanical IntegrationM. Nordby
ACDD. Thompson
DAQ & FSWG. Haller
I&TE. Bloom
SASR. Dubois
MechanicalM. Campell
IOCD. Lung, Acting
CALN. Johnson
EPOL. Cominsky
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 7
2001 2002 2003 2004 2005 2006 2007 2011
Calendar Years
GLAST planned for launch in February 2007
CD-4 ApprovalCD-3 Approval
CD-2 Approval
CD-1 ApprovalCD-0 Approval
Grid Complete
Level 1Milestones
FABRICATION PHASE COMMISSIONINGPHASE
Build & TestFlight Units
ObservatoryI&T
Final DesignEngr’g Models
LAT I&TPrelim. & Sys. Design
EnviroTest
OPERATIONSPHASE
ScheduleFloat
Overall ScheduleOverall Schedule
Launch
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 8
LAT Rebaseline for US FundsLAT Rebaseline for US FundsBudget vs Actuals vs PerformanceDOE + NASA Project Expenditures
4.1 LAT
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S
CY 2000 CY 2001 CY 2004 CY 2005
$M
Actual Commitments
ACWP
RB BCWS+ Planned Commitments
RB FUND
Fund
BCWP
BCWS+ Planned Commitments
BCWS
CY 2003CY 2002
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 9
AntiAnti--Coincidence Detector Coincidence Detector -- David Thompson, GSFCDavid Thompson, GSFC
• ACD design is essentially complete– Some mechanical interference issues are being
resolved• Detector/Electronics End-to-End testing
– Required performance confirmed with flight-type scintillator Tile Detector Assembly (TDA), phototubes (PMT), High Voltage Bias Supply (HVBS), Front End Electronics (FREE) card
• Fabrication of mechanical structure is underway– Composite shell and aluminum base frame are in
fabrication
FREE Card
HVBS
Signals from TDAs, PMTs Full-size composite
panel for shell
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 10
Composite Panel & ConvertersItaly, SLAC
Tray Assembly and TestItaly
342
342
Tracker Tracker –– Robert Johnson, UCSCRobert Johnson, UCSC
SSD Ladder AssemblyItaly
2592
SSD Procurement, TestingJapan, Italy, SLAC
10,368
Electronics Design, Fabrication & Test
UCSC, SLAC648
Cable PlantUCSC
Tower StructureItaly, SLAC
Tower Assembly and Test (18)
Italy
18
16 flight modules + 2 spares
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 11
Calorimeter Calorimeter –– Neil Johnson, NRLNeil Johnson, NRL
CDE AssemblyNRL
PIN Diode(each end)
CsI Crystal
Optical Wrap
Twisted Pair Wires
Mechanical StructureFrance (IN2P3/Ecole Polytechnique)
Front-End ElectronicsNRL, SLAC
PEM AssemblyNRL
Module Assemblyand Test, NRL+collab
CsI CrystalsSweden (KTH)
16 flight modules + 2 spares
1728
18
18
72
18
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 12
Data Acquisition Data Acquisition –– GuntherGunther Haller, SLACHaller, SLAC
Empty boxes for heat conduction (5x)
Event Processing Unit (3x)
Power Distribution Unit
Global trigger ACD Signal Unit
Spacecraft Interface Unit (2x)
Tower Power Supply (16x)
Tower Electronics Module (16x)
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 13
Hole to accommodate solar array mast
Radiator
Cut-outs for solararray launch locks
VCHP reservoirs
Radiator Mount Bracket at 4 corners of Grid
Grid
Mechanical Mechanical –– Marc Campell, SLACMarc Campell, SLAC
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 14
1X4 Engineering Model under test1X4 Engineering Model under test
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 15
Flight Grid after rough machiningFlight Grid after rough machining
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 16
LAT I&T LAT I&T –– Elliott Bloom, SLACElliott Bloom, SLAC
I&T FacilitySLAC Bldg 33
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 17
Engineering ModelsEngineering Models
Calorimeter EM
1 X 4 Grid
Tracker Minitower
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 18
LAT Engineering ModelLAT Engineering Model
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 19
Cosmic Ray Tracks in the EMCosmic Ray Tracks in the EM
GLASTOnlineSingle Event Display
Preliminary Cosmic Ray
Data taken on Sept 3 !!!
CAL •Pedestal subtracted •Zero suppress off•4 range off
Preliminary data
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 20
Project IssuesProject Issues
1. Transition to flight hardware productiona. Closing design issuesb. Qualification testing
2. Aggressive cost and schedule plana. 9 weeks of schedule float and 25 % cost contingency
3. Communicationsa. Multi-disciplinesb. Work spread around the world
4. End to end performance assessmenta. Assuring that the instrument will meet science
requirementsb. PI has established a task force
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 21
StatusStatus
• Project cost and schedule reviewed– Strong sponsor support– Cost and schedule is still tight
• LAT Design is mature– Instrument configuration is well understood– Details need to be closed
• Transition to manufacture of flight hardware– Complete detailed design and analysis– Thorough testing
• Subsystem modules tests• System tests• Engineering model tests• Hardware qualification testing
• Next 6 months critical to closing issues and beginning fabrication
GLAST LAT Project Experimental Program Advisory Committee, November 14, 2003
rev. 2 22
SummarySummary
• A new capability is in place at SLAC– Managing, fabricating and operating a space instrument
• Draws on previous experience in particle detectors and space instruments
• New facility at SLAC for instrument integration and test• Specialists in space technology added to the staff• Working relationships in place
– NASA and DOE– NRL, GSFC, UCSC and collaborators– US, Italy, Sweden, Japan and France
– This staff and these facilities are an important resource for supporting further Astro-Physics projects
• GLAST will provide important opportunities for scientific discovery through 2017