Contracts for Difference Allocation Round 4: Application ...
Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company...
Transcript of Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company...
![Page 1: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/1.jpg)
Contracts for Difference
14 July 2015
![Page 2: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/2.jpg)
Contracts for Difference
Yasharn Smith EMR Delivery Manager
Overview
![Page 3: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/3.jpg)
Welcome, Timetable and Safety
3
![Page 4: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/4.jpg)
Today’s Agenda
4
Agenda 14th July 2015
09:30 - 10:00 Introduction, recent news and CfD process
overview
10:00 – 10:30 Company/Applicant Registration
10:30 – 11:00 Coffee and Networking Break
11:00 – 11:45 Application, Qualification & Disputes
11:45 – 12:00 Getting you ready for Round 2
12:00 – 12:30 Q&A
![Page 5: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/5.jpg)
Key Updates
CfD
Implementation
Indicative
Timeline
DECC response to
CfD Regs
Consultation
CfD Round -2
Kick Off Event
Removal of
Onshore from the
RO
Change to process
of planning consent
approval for
Onshore Wind
farms
CfD Timeline
&
Events
CfD
Consultations
Other
News
Final Modifications
to BSC for
Electricity
Intensive
Industries
![Page 6: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/6.jpg)
Low Carbon
Contracts Company
Delivery Partners
Setting Legislation &
Energy Policy
Signing and ongoing
management of CfD
contracts
Regulates Market
(inc EMR)
Delivery Body
EMR Settlement Agent
![Page 7: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/7.jpg)
CfD Process – End to End
5. Appeal 6. Valuation
7. Sealed Bids
8. Allocation & Independent Audit
9. Allocation Notification
1. 1. Pre-Application Activities
2. Application 3.
Qualification
4. Review
7
![Page 8: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/8.jpg)
Contracts for Difference
Nisar Ahmed Senior EMR Analyst
Registration
![Page 9: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/9.jpg)
CfD Process – End to End
9
5. Appeal 6. Valuation
7. Sealed Bids
8. Allocation & Independent
Audit
9. Allocation Notification
1. Pre-Application Activities
2. Application 3.
Qualification
4. Review
![Page 10: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/10.jpg)
Registration Overview
10
Why is Registration important?
Role of the Authorised Person and Main Admin
Registration Process
Registration Demo
Registration Guide
Registration plan for future events
![Page 11: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/11.jpg)
Registration – Why is it important?
11
All Companies / organisations that wish to
participate in the Contracts for Difference will
need to register with the Delivery Body.
Necessary to ensure a publically recognised
officer of the company / organisation has
approved the registration. Usually a Director /
Partner – the “Authorised Person”.
The Authorised Person can nominate a “Main Admin” to act on
their behalf to carry out activities.
The Main Admin can also be the same person as the
Authorised Person based on structure and governance.
![Page 12: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/12.jpg)
Registration Setup
12
Main Company
Sub Company 1
Sub Company 2
Main Admin
Deputy Main
Admin
Users Operator/Approver/Viewer
Authorised
Person
![Page 13: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/13.jpg)
Registration – Process
Delivery Body
Company
Registration Form
completed on
system
System
Notification
Applicant
Confirm registration
outcome via email
If successful
receive log in
details Verification
Delivery
confirmation
Applicant
1
5
3
7
System
Notification
Signed and
scanned
Company
Registration Form
uploaded
System
Notification
2
System
Notification
4
6
Delivery
confirmation
System
Notification
![Page 14: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/14.jpg)
14
Registration – Demo
Please do not use the form until advised by the Delivery
Body.
We will make an announcement on our Portal on the
commencement of Registration process for CfDs, when
other CfD Round dates are formalised by DECC.
DEMO
![Page 15: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/15.jpg)
15
Registration Guide
Comprehensive step by step
guide for CM and CfD
Registration with screen
shots.
Click on the cover page in
slide show mode to access
hyperlink for actual document
on the Delivery Body Portal.
![Page 16: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/16.jpg)
16
Registration – Plan for Future Events
Changes to Main Admin’s and Authorised Persons
Detailed User Management and Privileges
Creating sub-companies
Assigning Users to Companies
Activating / Deactivating Users
Password Management
![Page 17: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/17.jpg)
Contracts for Difference
Paul Mullen EMR Delivery Manager
Application and Qualification
![Page 18: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/18.jpg)
CfD Process – End to End
18
5. Appeal 6. Valuation
7. Sealed Bids
8. Allocation & Independent
Audit
9. Allocation Notification
1. Pre-Application Activities
2. Application 3.
Qualification
4. Review
![Page 19: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/19.jpg)
CfD Qualification
19
To be a qualifying applicant
Meet Eligibility Requirements
(General, additional & supplemental)
Provision of other
information/data
Not be an Excluded Applicant
![Page 20: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/20.jpg)
CfD Qualification Requirements
20
5.
Appeal 6. Valuation
7. Sealed Bids
8. Allocation &
Independent Audit
9. Allocation Notification
1. Pre-Application Activities
2. Application 3.
Qualification 4. Review
Not an Excluded Applicant
Non Delivery Disincentive Exemption Certificate
Connection Agreement(s) / Countersigned Offer(s)
signed by Applicant
Supplemental Requirements for phased Offshore
projects
Supply Chain Plan >=300MW
Planning Decision Notice
![Page 21: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/21.jpg)
Non Delivery Disincentive
Excluded
Site W
S
N
E
Applicant’s
CfD Unit W
S
N
E
Site Overlap –
Exemption
Certificate from
DECC required
Register of Temporary
Site Exclusion
![Page 22: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/22.jpg)
Non Delivery Disincentive
22
• DECC / Applicant approval process
• Full copy of exemption certificate to be provided with Application
• DB checks yet to be defined
Non Delivery
Disincentive Exemption Certificate
![Page 23: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/23.jpg)
Supply Chain Plan >=300MW
23
• DECC / Applicant approval process
• Full copy of approval certificate to be provided with Application
• DB verify name and validity during assessment
Supply Chain Plan
>=300MW
![Page 24: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/24.jpg)
Offshore Wind additional requirements
24
Offshore • Full copy of Crown Estate Lease/Agreement for Lease
OffshorePhased
• Phase 1 MW >= 25% of total MW of all phases
• <=1500MW across all phases
• Target Commissioning Date for last phase <=2 years from 1st Phase
![Page 25: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/25.jpg)
Excluded Applicants
25
CCS and Nuclear
AD, Hydro, Onshore Wind, Solar =< 5MW
Not to be in receipt of another subsidy (RO, CfD, CM, NFFO, RHI if
EfW with CHP) except:
RO accredited registering additional capacity >=5MW
RO accredited registering subsequent offshore phases
Biomass co-firer station can switch generating unit(s)
from RO to CfD as Biomass Conversions
Non GB
5.
Appeal
6. Valuation
7. Sealed Bids
8. Allocation &
Independent Audit
9. Allocation
Notification
1. Pre-Application Activities
2. Application 3.
Qualification 4. Review
![Page 26: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/26.jpg)
Excluded Applicants
26
• Provide statements that not in NFFO, CfD, RHI (if EfW with CHP), CM; and
• Provide statement whether accredited (in RO) – if accredited, provide type of Dual Scheme Plant
• Delivery Body checks
Subsidy Cross Check
![Page 27: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/27.jpg)
Connection Agreements
27
• Agreement(s) for connection with TSO and/or DNO for >=75% of capacity
Direct
Connection
• Agreement(s) between Private Wire Generator and Private Wire Network Operator
• Agreement(s) between Private Wire Network Operator and TSO/DNO
Partial
Connection
• Agreement(s) between Private Wire Generator and Private Wire Network Operator
• Confirmation that no connection agreement applies or is to apply
Islanded
CFD Unit
![Page 28: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/28.jpg)
Connection Agreement(s) – DB Checks
28
Parameter Direct Partial Islanded Evidence Requirements
Location x x x Consistent with Application
Transmission
Entry
Capacity
/Capacity
x Provides for >= 75% of capacity
requested on Application
Connection
Date
x Target Commissioning Date cannot
be earlier than Connection Date
Technology x x x Technology matches
For each of the above, Applicant asked to state parameter as
shown in connection agreement(s); state where found in
connection agreement(s); and provide further comments
![Page 29: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/29.jpg)
Applicable Planning Consents
29
Permissions must relate to CfD Unit and getting the power
to the transmission or distribution or private wire network
Section 36
Transport and Works Act
Order
Marine Licence Planning
Permission
Development Order
![Page 30: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/30.jpg)
Applicable Planning Consents – DB Checks
30
Parameter Evidence Requirements
Postcode / OS Map
Reference / Grid
Coordinates
Information in Application consistent with that specified in
Applicable Planning Consent(s)
Capacity >= capacity requested in Application
Validity Date Not expired at date of Application
Technology Technology matches
For each of the above, Applicant asked to state parameter as shown in
applicable planning consent(s); state where found in applicable planning
consent(s); and provide further comments
![Page 31: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/31.jpg)
31
Other Information/Data
5.
Appeal 6. Valuation
7. Sealed Bids
8. Allocation &
Independent Audit
9. Allocation Notification
1. Pre-Application Activities
2. Application 3.
Qualification 4. Review
Additional Information (inc.)
Name, address and contact
details of Applicant, Agent (if
non GB), Entity to enter into
CfD Contract, Entity
receiving notices under CfD
Contract
Project name and location
Capacity (MW)
Target Commissioning Date
and start of Target
Commissioning Window
Technology specific
questions
For LCCC to complete CfD
contract
Evidence of incorporation – i.e.
Certificate of Incorporation and
Tax Certificate
Valid
Incorporation
Identify type of CfD Contract
and whether on standard or
modified terms (+ for
modifications, date entered into
with LCCC)
Contract
terms
![Page 32: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/32.jpg)
Some common Qualification Questions
32
Can I still apply for the RO even if I have
applied for a CfD? My distribution offer has not been
countersigned by the DNO – what
evidence do I need to provide here?
What considerations do I need to make
when determining what my ”Initial
Installed Capacity Estimate” is? My planning decision notice does not
include a MW Limit? Do I need to provide
additional clarification?
My planning permission/connection
agreement is in the name of another
entity – what evidence do I need to
provide?
![Page 33: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/33.jpg)
Application creation and submission
33
System available Applicant can create, save, upload
documents, print, view
Application
Window
Applicant can create, save, upload
documents, print, view, submit and
withdraw
Application
Window Closed
Once closed, Applicant can print and
view only
Only Applications that are submitted by Application
Window closing date will progress to assessment stage
![Page 34: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/34.jpg)
CfD Qualification Assessment
34
1. Application
Closing Date
2. Assess application
3. Verification
checks
4. Take into account any contradictory
evidence
5. Issue determination to Applicant
6. Notify Applicant
via system
![Page 35: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/35.jpg)
Contracts for Difference
Qualification – Reviews and Appeals
![Page 36: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/36.jpg)
CfD Process – End to End
36
5. Appeal 6. Valuation
7. Sealed Bids
8. Allocation & Independent
Audit
9. Allocation Notification
1. Pre-Application Activities
2. Application 3.
Qualification
4. Review
![Page 37: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/37.jpg)
Reviews
37
Reviews
• Where Delivery Body (“DB”) determine that you are a non qualifying applicant:
• Applicant can raise non-qualification review via system within defined window
• Applicant can provide clarification but no new evidence
• Result communicated via system
![Page 38: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/38.jpg)
Reviews
38
Review Requirements
Concise statement identifying dispute
No new documentary evidence but can
clarify original evidence
Schedule listing the documents submitted
Succinct presentation of
arguments
Summary of grounds for dispute
![Page 39: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/39.jpg)
Appeals
39
Appeals
• Where Delivery Body (“DB”) determine that you are a non qualifying applicant after Reviews process:
• Applicant can raise Appeal to Ofgem (cc DB)
• Results communicated by Ofgem to Applicant and DB
• Allocation may proceed if overrunning
• Applicant can appeal to High Court where Ofgem uphold DB decision
![Page 40: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/40.jpg)
Round 1 Appeals
40
Delivery Body required to establish and
maintain an Appeals Register
Ofgem published details of Appeals from
Round 1
![Page 41: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/41.jpg)
Contracts for Difference
Getting you ready for Round 2
![Page 42: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/42.jpg)
CfD Stakeholder Events
42
CfD RD2
Inaugural Event
NG and LCCC
Company
Registration,
Application and
Qualification
processes
Detailed
Valuation and
Allocation
Rules
Qualification
Application
Form and
Demo
User
Management
Sealed Bids
submission
process and
Demo
18th June 2015 14th July 2015 TBC
Past Future
![Page 43: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/43.jpg)
Guidance Documents
43
Key:
Published for
Round 2
Not yet
published for
Round 2
![Page 44: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/44.jpg)
Get the latest CfD Information
44
Subscribe to the new National Grid EMR Portal (Please renew your even if
registered on old Portal)
![Page 45: Contracts for Difference - EMRDeliveryBody for Difference Document...Low Carbon Contracts Company Delivery Partners Setting Legislation & Energy Policy Signing and ongoing management](https://reader031.fdocuments.in/reader031/viewer/2022022423/5a9fcdaf7f8b9a7f178d4bf5/html5/thumbnails/45.jpg)
Contact us
45